Developing a Cost Estimation Probability Model of a Large Multi-Year System An Experience Report

Similar documents
3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3)

This resource is associated with the following paper: Assessing the maturity of software testing services using CMMI-SVC: an industrial case study

BAE Systems Insyte Software Estimation

Independent Verification and Validation (IV&V)

Command and Control Software Development Lessons Learned. Lt Col Michael D. Sarchet Deputy Director, Space Systems Command and Control Division

Systems Engineering, Program Management conjoined Disciplines over the Project Life Cycle

System Engineering Process Improvement using the CMMI in Large Space Programs

Software Acquisition Best Practices for Ground Systems

Complex Systems (Systems of Systems) Technology and What s Next!

Life Cycle Cost Estimate (LCCE)

Systems Engineering Challenges for an Army Life Cycle Software Engineering Center

Measures and Risk Indicators for Early Insight Into Software Safety

PMI Scheduling Professional (PMI-SP)

Project Managers Guide to Systems Engineering Measurement for Project Success

PLANNING AND ESTIMATING

Need for Affordability Analysis in Systems Engineering

Program Management Professional (PgMP)

System Engineering. Instructor: Dr. Jerry Gao

The Internal Consistency of the ISO/IEC Software Process Capability Scale

AGI Software for Space Mission Design, Analysis and Engineering

IT Service-Based Costing: Standardizing Provisioning and Servicing IT Resources

Highlights of CMMI and SCAMPI 1.2 Changes

Safety Management Center. DNV IT Global Services Safety Engineering / Management in the automotive industry. Content

Section M: Evaluation Factors for Award HQ R LRDR Section M: Evaluation Factors for Award For HQ R-0002

USING PILOTS TO ASSESS THE VALUE AND APPROACH OF CMMI IMPLEMENTATION. Goddard Space Flight Center (GSFC)

WORK PLAN AND IV&V METHODOLOGY Information Technology - Independent Verification and Validation RFP No IVV-B

CMMI-DEV V1.3 CMMI for Development Version 1.3 Quick Reference Guide

Sample Reliability Language for DoD Acquisition Contracts

DRAFT. Effort = A * Size B * EM. (1) Effort in person-months A - calibrated constant B - scale factor EM - effort multiplier from cost factors

Project Management Session 6.2. Project Initiation Phase Integration Management

Leveraging Best Practices in Risk Management For Strategic Outcomes. Peter Schmidt Director ESI International

Replacing Risk with Knowledge to Deliver Better Acquisition Outcomes

System Cost Modeling Using Proxy Estimation and COSYSMO

GAIA. GAIA Software Product Assurance Requirements for Subcontractors. Name and Function Date Signature 15/09/05 15/09/05 15/09/05 15/09/05 15/09/05

DATA ITEM DESCRIPTION

New Reliability Prediction Methodology Aimed at Space Applications. Briefing Meeting with Industry

How Cisco IT Manages IT Service Costs

CMMI Project Management Refresher Training

Addressing the Challenges of Systems Engineering Estimation

Identify Risks. 3. Emergent Identification: There should be provision to identify risks at any time during the project.

Introduction of RUP - The Rational Unified Process

SYSTEM MODERNIZATION BEST PRACTICES

Successful Cost Estimation with T1 Equivalents

PMP MOCK EXAMS BASED ON PMBOK 5TH EDITION

Software Cost Metrics Manual

SECTION C - DESCRIPTION / SPECIFICATIONS / STATEMENT OF WORK

CENTURYLINK DRAFT SUPPLY CHAIN RISK MANAGEMENT (SCRM) PLAN

Enterprise Software License Agreements - Best Practices - Lessons Learned 9/8/2009 1

Leveraging Your Service Quality Using ITIL V3, ISO and CMMI-SVC. Monday Half-Day Tutorial

Colorado Springs PMI Risk Management in Five Easy Pieces Colorado Springs, Colorado May 8 th, 2008

Evolutionary Differences Between CMM for Software and the CMMI

Information Technology Services Project Management Office Operations Guide

Manager Strategy, City Shaping and Policy

Deriving Software Sustainment Cost Estimating Relationships in a Diverse Army Execution Environment

Oracle Prime Projects Cloud Service

Work Plan and IV&V Methodology

PMP Sample Questions. 1. In face-to-face interactions, how is most information conveyed?

Top 10 Signs You're Ready (or Not)

Project Controls Expo

Systems Integration: Effective DOD Test & Evaluation

FAA s Experience with Process Improvement & Measurements

Summary of TL 9000 R4.0 Requirements Beyond ISO 9001:2000

SWE 211 Software Processes

CHAPTER 2 Analyzing the Business Case (Phase 1: System Planning)

PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3)

7. Model based software architecture

A Model for CAS Self Assessment

Performance-Based Earned Value

Job Titles and Skill Categories

Principles of Schedule Contingency Management

UPGRADE CONSIDERATIONS Appian Platform

ISO INTERNATIONAL STANDARD. Risk management Principles and guidelines. Management du risque Principes et lignes directrices

Mergers and Acquisitions in the Biotechnology Industry

CMMI-SVC V1.3 CMMI for Services Version 1.3 Quick Reference Guide

Joel Castaneda. January Tecolote Research, Inc.

Implementing a Data Collection Tool to Estimate and Analyze Spending ICEAA Conference June 2013

CERTIFIED RELIABILITY ENGINEER (CRE) BODY OF KNOWLEDGE MAP 2018

Report of the Reliability Improvement Working Group (RIWG) Volume II - Appendices

Number: DI-IPSC-81427B Approval Date:

CMMI ACQUISITION MODEL (CMMI-ACQ):

Available online at ScienceDirect. Procedia Computer Science 61 (2015 )

DEPARTMENT OF DEFENSE HANDBOOK ACQUISITION OF SOFTWARE ENVIRONMENTS AND SUPPORT SOFTWARE

Part Work plan and IV&V methodology

Der virtuelle Entwurfsprozess (Virtual Spacecraft Design VSD)

Chapter 4 Software Process and Project Metrics

Performance Outcomes of CMMI -Based Process Improvements

Business Value and Customer Benefits Derived from High Maturity

Modernize Your Device Management Practices Using The Cloud

The Effectiveness of Risk Management Within the DoD

PAYIQ METHODOLOGY RELEASE INTRODUCTION TO QA & SOFTWARE TESTING GUIDE. iq Payments Oy

Business Management System Manual Conforms to ISO 9001:2015 Table of Contents

Research on software systems dependability at the OECD Halden Reactor Project

Copyright 2012, Oracle and/or its affiliates. All rights reserved.

SOLUTION BRIEF RSA ARCHER PUBLIC SECTOR SOLUTIONS

RISK MANAGEMENT SUPPLEMENT TO IEEE

IT PROJECT ANALYST/MANAGER

``Overview. ``The Impact of Software. ``What are Virtual Prototypes? ``Competitive Electronic Products Faster

Vol. 2 Management RFP No. QTA0015THA A2-2

ES. EXECUTIVE SUMMARY FOR RESIDENTIAL MULTI-FAMILY PROGRAM AREA (R5)

Transcription:

Developing a Cost Estimation Probability Model of a Large Multi-Year System An Experience Report NDIA 2012 Kathleen Dangle, Madeline Diep, and Forrest Shull Fraunhofer

Context of Our Experience Program characteristics: Aerospace domain Large and mission-critical system Prime contractor with many partners and subcontractors Distributed development Government oversight Software-intensive and COTS heavy Cost estimation in preparation for Key Decision Point (KDP) to enter Concept & Technology Development 2

Why A Probability Distribution Model Cost estimation is an important part of program planning and tracking But it can be very difficult to do accurately Single-point estimation does not account for uncertainties in the estimation sources and errors in the model Probability distribution model helps to understand the likelihood of achieving the point estimate Required to budget the cost estimate at the 70% confidence level. 3

GAO Guidelines on Cost Estimation Include probability distributions...as outlined in the GAO Publication* 1. Determine the program cost drivers and associated risks; 2. Develop probability distributions to model various types of uncertainty (for example, program, technical, external, organizational, program management including cost estimating and scheduling); 3. Account for correlation between cost elements to properly capture risk; 4. Perform the uncertainty analysis using a Monte Carlo simulation model; 5. Identify the probability level associated with the point estimate; 6. Recommend sufficient contingency reserves to achieve levels of confidence acceptable to the organization; and 7. Allocate, phase, and convert a risk-adjusted cost estimate to then-year dollars and identify high-risk elements to help in risk mitigation efforts. *GAO Cost Estimating and Assessment Guide, GAO-09-3SP, March 2009 4

About Probability Distribution Models P(X>1) Usually represented in two views: Probability Density Function (PDF) Cumulative Density Function (CDF or S-curve) ~81% likelihood that X will not exceeds 1 Describe the probability that a variable have a value less than or equal to x 5

Building the Model Select Probability Model Derive Bases of Estimates Generate Model Profiles Consolidate Model Profiles 6

Step 1: Select Probability Model A number of probability distribution models are available to represent cost risks for the different cost elements. We selected the Weibull probability distribution Traditionally used for reliability models Flexible -- its three parameters can be adjusted to represent distribution curves such as the normal, logarithmic, Rayleigh, and exponential A single model with the ability to accommodate multiple cost model profiles 7

Effect of increasing the value of scale parameter On the Weibull Distribution Three parameters of Weibull model: Shape: Affects the shape of the model, as well as slope of the model Scale: Increasing its value while holding Shape variable constant has the effect of stretching out the probability model Location: Provides an offset for the starting value of the (cost) variable Effect of increasing the value of shape parameter 8

Building the Model Select Probability Model Derive Bases of Estimates Generate Model Profiles Consolidate Model Profiles 9

Step 2: Derive Bases of Estimates Large Program = Large and deeply nested WBS Impractical to create a cost model for each item in the Work Break-down Structure (WBS) Created buckets for the WBS items and generated a cost model for each bucket Items in a bucket should, intuitively, have similar types of uncertainty or risks Buckets should be general enough to contain all items under Level 3 or 4 WBS elements 10

Buckets of Cost Elements Program Management & Other cross cutting cost Sub-systems Sub-systems Development Development Software Dev Effort Non-Software Labor HW/SW Cost (Mats & license) System Eng I&T Deployment SW development effort includes COTS labor, VHDL development effort, maintenance, support (documentation) Non-SW Labor includes sub-system engineering labor, I&T, COTS and HW operational related labor (handling, shipping) 11

Building the Model Select Probability Model Derive Bases of Estimates Generate Model Profiles Consolidate Model Profiles 12

Step 3: Generate Model Profiles Create preliminary model for each cost bucket Meet with element SME and obtain feedback Known technology readiness issues SW size CCRs Supplier performance history etc. Send Models to SMEs for review Adjust Models based on SMEs feedback and other known risks Known adjustments to IBR data Expected model profile and range based on expert judgment COCOMO output Etc. 13

Preliminary Model For all buckets, set the location variable to be the original Initial Baseline Review (IBR) estimation Criteria for setting the scale and shape parameters: For sub-systems software cost bucket Software labor cost tends to have larger uncertainty and to be prone to underestimations the model is skewed to the left (median value >> IBR estimates) Used variability in SW sizes (likely and high estimates) to adjust the skewness the higher the variability, the more skewed the model For sub-systems hardware/software cost bucket HW/SW material and licensing cost is generally stable where variability comes from amount of equipment to acquire the model was skewed to the right (median value > IBR estimates) For sub-systems non-sw labor & program management (cross cutting concerns), I&T, and Deployment bucket Some variability is expected used normal distribution model 14

Getting Subject Matter Expert Input Talked to 1-2 SMEs from each major sub-components Presented the preliminary model To facilitate the discussion, provided reference model of a set of Weibull distribution profiles Captured feedback: The range and skewness of the model Justification for the profile: Known issues, other estimation analyses, perceived risks 15

Adjusting the Model Incorporated feedback from the SMEs and any known estimate adjustments thus far, as well as the dollar value of risk exposure Performed sanity check: Use COCOMO analysis to estimate software development effort/cost based on estimated software size Ensure that the model includes the COCOMO output 16

Building the Model Select Probability Model Derive Bases of Estimates Generate Model Profiles Consolidate Model Profiles 17

Step 4: Consolidate Model Profiles Generate a cost model for each subsystem by summing SW effort, HW/SW cost, and non-sw labor Correlate costmodels of the subsystems Generate the Program cost model by summing all the cost-models SW Effort Model HW/SW Cost Model Non-SW Model + + = A sub-system cost model Subsystem 1 Model Subsystem 2 Model Program Management Cost + + + = The Program cost model 18

Summing the Models Used Monte Carlo simulations to sum the models Repeatedly generated a random value following the defined distribution model For each sampling, summed the generated value across all the distribution models Created histograms of the sum generated from all the samplings Note: The number of iterations/samples can significantly affect the range of the model We used 10,000 iterations/samples, and still observed some sensitivity in the produced models 19

Parting Thoughts We described our approach for generating costestimation probability distribution models Some lessons learned: A WBS that makes key cost drivers visible makes it easier to bucket cost items in a manageable way. Weibull is a flexible model, but may not be as popular as other models lack of accessible statistical tool support for performing more sophisticated activities, such as model correlation. Program is still ongoing The cost model have been vetted by a separate cost policy team We are collecting the data now for the quantitative validation 20

List of Abbreviations CCR: Contractor Cost Report I&T: integration and Test IBR: Initial Baseline Review SME: Subject Matter Expertise VHDL: VHSIC (Very High Speed Integrated Circuit) Hardware Description Language 21

Questions? Contact Information Madeline Diep mdiep@fc-md.umd.edu 240-487-2937

Backup 23

Fraunhofer Center Maryland A not-for-profit applied research & technology transfer organization Mission: Advance real-world software practices via empirically validated research into softwareengineering technologies and processes Work closely with the customer to develop unique, innovative solutions within their business context Purveyor of best practices to organizations inside and outside of the software industry Affiliated with Fraunhofer-Gesellschaft in Germany and University of Maryland at College Park

Fraunhofer Center Maryland Competences Security, reliability & safety analysis Software design & architecture analysis Software testing, verification & validation Technology evaluation Software product & process evaluation CMMI training & coaching Program, project, and risk management Deep expertise in Goal-driven, measurement-based process and product improvement Software defect causal analysis and resolution Process improvement and best practices 25