Reliability Analysis using PLEXOS

Similar documents
Calculation of system index - Basic idea. Load model Alternative 2. Thermal power station model. Equivalent load. Example 6.8:

APRIL 23, Capacity Value of Wind Assumptions and Planning Reserve Margin

AUSTRALIAN ENERGY MARKET OPERATOR

PowrSym4. A Presentation by. Operation Simulation Associates, Inc. February, 2012

Estimating the Economically Optimal Reserve Margin in ERCOT

Flexible power generation and interconnection capacity needs of the Italian power system using PLEXOS LT plan.

ICA Demand Curve Development:

TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY

Eastern Wind Integration and Transmission Study

Phase 2 of 2015 General Rate Case Marginal Cost and Sales Forecast Proposals

Methodology to Perform Long Term Assessments

PJM PROMOD Overview. August 1, PJM

Contents. What is PLEXOS? Why use PLEXOS? Who uses PLEXOS? Services. Support. Training. Implementation. Datasets. Customisations.

LMP Calculation and Uplift

The Confluence Model. Presentation to Modeling and Forecasting Working Group January 21, 2015

LOLE Fundamentals Loss of Load Expectation (LOLE) Fundamentals

Summary of 2016 MISO State of the Market Report

Demand Dispatch and Probabilistic Wind Power Forecasting in Unit Commitment and Economic Dispatch: A Case Study of Illinois

2017 IRP Advisory Group. July 21, 2017 IRPAG

Integrated Grid Planning Symposium

PACIFIC POWER A DIVISION OF PACIFICORP

Duration-Limited Storage De-Rating. Factor Assessment Final Report

Mid-term Adequacy Forecast of the Czech Republic ČEPS 08/2016

Net Demand Variability (NDV) Summary

Evolution of the Grid in MISO Region. Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017

FERC Order 764 Settlements

NPCC 2016 MARITIMES AREA COMPREHENSIVE REVIEW OF RESOURCE ADEQUACY Approved by RCC December 6, 2016

3. DATA INPUT PREPARATION...

Assessing the Potential Value of Utility-Scale Energy Storage Arbitrage in the Australian National Electricity Market

Locational Based Marginal Pricing

Including Advanced Energy Storage in Integrated Resource Planning: Cost Inputs and Modeling Approaches

RISK OF A CAPACITY SHORTAGE IN THE POLISH ELECTRICITY SYSTEM UP TO 2020

Capacity Revenues for Existing, Base Load Generation in the PJM Interconnection

MISO Hourly Scheduling Rules. PJM Interconnection - Generator Offer Flexibility Senior Task Force June 19, 2015

Dispatch Signal & Locational Marginal Pricing (LMP)

RESOURCE PLAN DECISIONS

MAY 1, Variable Generation Integration Costs

Best Practices in Conducting Grid Integration Studies

DATA ASSUMPTIONS AND DESCRIPTION OF STUDIES TO BE PERFORMED 2014 EGSL & ELL Integrated Resource Plans

Reduced Network Modeling of WECC as a Market Design Prototype

NPCC 2013 MARITIMES AREA COMPREHENSIVE REVIEW OF RESOURCE ADEQUACY

Integrated Resource Plan

Report to the Texas Senate Committee on Business & Commerce

January 3, 2018 MEMORANDUM. Council Members. John Ollis, Power System Analyst. SUBJECT: Marginal Carbon Emissions Rate Study Draft BACKGROUND:

Shortage Pricing Penalty Factors and the Offer Cap (Corrected September 9, 2015)

Entergy New Orleans, Inc.

Gas Prices and Offer Price Flexibility in Other ISO/RTO Markets

Mid-term Adequacy a glance

Technical Bulletin Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations

Capacity Market. as means to avoid blackouts. Assessment of the impact of implementation of a comprehensive capacity market mechanism in Poland

Long-term capacity expansion planning with variable renewable power. Daniel Russo April 27, 2017, IITC

New England States Committee on Electricity

ANNUAL REPORT ON MARKET ISSUES & PERFORMANCE

LMP Implementation in New England

SPP at a Glance. Located in Little Rock. Approximately 600 employees

to Multi-Area Reliability Evaluations

2015 ISO/RTO Metrics Report. Summary. November 2015

Simulation of the Central European Market for Electrical Energy

2016 ANNUAL VRL ANALYSIS

The OTC Emission Reduction Workbook 2.1: Description and User s Manual

Locational Marginal Pricing II: Unlocking the Mystery

PEAK DEMAND REDUCTION STRATEGY

A Case Study: Optimal Wholesale Power Buying in ERCOT

PJM Renewable Integration Study

Course notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing

Market Mechanics Review of Net Demand Variability from the E&AS Design Stream Working Group Meeting 6&8

1.818J/2.65J/3.564J/10.391J/11.371J/22.811J/ESD166J SUSTAINABLE ENERGY. Prof. Michael W. Golay Nuclear Engineering Dept.

POWER SYSTEM OPTIMIZATION BY INCREASED FLEXIBILITY

Power Generation Asset Optimization: Optimal Generating Strategies in Volatile Markets (Case Study) Presented at POWER-GEN 2001 Las Vegas, Nevada

Release Notes OASIS April 18, Version 1.1

LOAD SERVING ENTITIES PJM REGION

Economic Viability of Combined Heat and Power in ERCOT

New England Wind Integration Study Executive Summary

The challenge of integrating offshore wind power in the U.S. electric grid. Part II: Simulation of electricity market operations.

Applying PROBE for Congestion Analysis and Grid Planning

Generation adequacy and transmission interconnection in regional electricity markets

Investigating Power System Primary and Secondary Reserve Interaction under High Wind Power Penetration Using Frequency Response Model

IRP Advisory Group 2017 IRP Kick Off

Executive Summary MQRI-OPS 2

Impact of small solar PV on the NSW wholesale electricity market. Approved for Public Release 12 October 2017

Introduction to Efficient Pricing

THERMAL ENERGY STORAGE AS AN ENABLING TECHNOLOGY FOR RENEWABLE ENERGY

PJM Interconnection Economic Analysis of the EPA Clean Power Plan Proposal

Survey of Modeling Capabilities and Needs for the Stationary Energy Storage Industry

Integrating Variable Renewable Electric Power Generators and the Natural Gas Infrastructure November 2011

2015/16 Margin Peak and Margin Off-peak Review

Further Analyses of the Exercise and Cost Impacts of Market Power In California s Wholesale Energy Market

Energy Efficiency in Wholesale Markets

Load Granularity Refinements Pricing Analysis Study

TRANSMISSION INVESTMENT BENEFIT-COST EVALUATION: REASONABLENESS ASSESSMENT OF TRANSMISSION INVESTMENT COST ALLOCATION IN SPP.

Demand Curve Analysis

Review: Simple schedule risk modelling with Safran Risk

Energy Imbalance Market Overview

NCSL Transmission Policy Institute Denver, CO

APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST

Appendices. New York Control Area Installed Capacity Requirement. December 2, For the Period May 2017 To April 2018

Integrating DER in PJM Transmission Operations and Planning

Methodology for Calculating Operating Limits for Generators

California ISO. Q Report on Market Issues and Performance. July 10, Prepared by: Department of Market Monitoring

ICAP Reform Proposals In New England and PJM

Transcription:

Reliability Analysis using PLEXOS Published by: Randell Johnson Energy Exemplar LLC, East Coast USA Office. 1 P a g e

Introduction The PLEXOS simulator is a powerful tool for performing reliability studies on electric power systems. The simulator can calculate the standard metrics of LOLP, LOLE, EDNS and EENS from the PASA simulation phase using convolution. However, PLEXOS can also use the detailed chronological simulation of ST Schedule to produce the same metrics via Monte Carlo. Energy Exemplar adopted this approach in the valuation of Loss of Load Expectation (LOLE) for the market operated by ISO-New England, which covers the six states of New England in the northeastern US. The following describes this approach we used with PLEXOS. How to setup PLEXOS for Reliability via Monte Carlo In a reliability study we are only interested in whether or not the system can meet the electric load, and possibly ancillary services requirements, given all generation technical, transmission, fuel availability and other user-defined constraints. The dispatch order of generators and the system marginal price is not useful and thus we can simplify the simulation by removing all costs apart from the pseudo cost of unserved energy (Value of Lost Load or VoLL). To do so, simply mark all cost information with a Scenario and exclude that Scenario from your reliability Model run. Example of cost parameters include: Generator [Heat Rate] and [Load Point] Generator [VO&M Charge] Fuel [Price] Generator [Offer Price] Having done this, the simulation will be less complex, with the objective function containing only costs of unserved energy, dump energy and perhaps reserve shortage. Loss of Load Expectation (LOLE) Normally we compute the Loss of load probability (LOLP) as a reliability metric. This is a measure of the probability that demand will exceed the capacity of the system in a given period and is expressed as a percentage. As noted above, the periods when demand exceeds supply is a shortage event. An alternative metric is the Loss of Load Expectation (LOLE), which is the number of days of outage or the number of times in a given period that the load will be greater than the demand. This can be expressed as LOLE = LOLP * N/24. A value of 1.0 LOLE over a single year signifies multiple periods or hours over the year in which there were shortages. It is unlikely these shortages occurred in a single day but likely over multiple hours over several or more days. 2 P a g e

Load Risk We used the Monte Carlo feature in PLEXOS to calculate the probability of the LOLE for each load probability forecast in the New England. The first calculation was to benchmark the ISO-New England Installed Capacity Requirement ( ICR ) calculation for the study period, or in this case the 2017 Peak Load Forecast. The following demand forecast from ISO-NE s ICR report (see Table 1 below) was used for this analysis. Forecast Probability Table 1 10/90 20/90 30/70 40/60 50/50 60/40 70/30 80/20 90/10 95/5 2017 Peak Load Forecast 28,325 28,590 28,940 29,340 29,790 30,265 30,750 31,445 32,210 32,900 We then performed a LOLE calculation with an average load-weighted risk approach. We prepared a range of 16 different installed capacity levels in the ISO-NE control area and for each capacity level evaluated the average load weighted LOLE at each of the above 10 load probabilities in Table 1. The following figure, shows the demand distribution on the y-axis and the capacity distribution on the x-axis. There are a total of 160 capacity and demand pairs in the following chart for which we computed the average load weighted LOLE for using PLEXOS. Figure 1 Weighted-Average LOLE Load Risk Calculations 32900 32210 31445 30750 30265 29790 29340 28940 28590 28325 32000 33000 34000 35000 36000 37000 38000 Installed Capacity Then we prepared an average load weighted LOLE calculation for the 10 load probabilities for each capacity point and derived 16 average load weighted LOLE s as a function of installed capacity for the 3 P a g e

ISO-NE control area. We derived a value of LOLE at the ISO-NE Net Installed Capacity Requirement (NICR) value of 0.1 day per year which is consistent with reliability criteria for NICR. With the 16 LOLE calculations we were also able to compute the cost of lost load at each installed capacity level using the PLEXOS 8,760 hour time series simulation. PLEXOS estimates Unserved Energy (USE) at each hourly interval if demand is greater than generation, or a shortage event. This can happen primarily in summer months with reduced thermal generator capacities in combination with load risk and forced generator outages. We then approximated the Value of Lost Load (VoLL). For this analysis, we assumed a VoLL $20,000/MWh. Figure 2, below, displays an example time series path of one of the load weighted risk replications for the 8760 hour simulation performed. We charted the cost of lost load in millions of dollars, which is the result of multiplication of the USE at each interval as described above by the value of VoLL selected above. Figure 2 In Figure 2, the show an example of the 8760-hour simulation path for the peak demand and installed capacity pair with the cost of unserved energy is displayed on an hour by hour basis in millions of dollars. We ran 160 of these paths using Monte Carlo simulation and then took an average load weighted cost of lost load across the demand risk for each of the 16 installed capacity values. 4 P a g e

Figure 3, below displays a curve of the LOLE calculations as a function of percent of Net Installed capacity Requirement ( NICR ) for the New England Control Area as well as the cost of lost load as a function of percent NICR. Figure 3 Figure 3 shows that the system LOLE reliability metric degrades rapidly for installed capacity values below NICR. Also, the cost of lost load increases rapidly below NICR. 5 P a g e