SYSTEM IMPACT STUDY FINAL REPORT

Similar documents
Standard TPL Transmission System Planning Performance Requirements

WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY

Standard Development Timeline

Case Metrics 2015 Summer Base Case Quality Assessment Phase I Powerflow and Dynamics Case Quality Metrics FINAL

Investigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection

Information Document Protection System Information ID# R

POTOMAC ELECTRIC POWER COMPANY

Impacts of the Decentralized Wind Energy Resources on the Grid

Connection of generation plant to distribution networks. Guidance on completing the application form

Standard PRC-002-NPCC-01 Disturbance Monitoring

Technical considerations for integration of distributed renewables on the grid

LARGE WIND FARM AGGREGATION AND MODEL VALIDATION MULUMBA PROSPER PANUMPABI THESIS

Public Utility District Number 1 of Snohomish County

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System

Mitigation of Voltage Fluctuations in Power System Using STATCOM

SMALL GENERATOR INTERCONNECTION REQUEST (Application Form)

Grid Interconnection Issues for Wind Generation

POWER SYSTEM STABILITY GUIDELINES

Coordination of Multiple Voltage Controllers of Adjacent Wind Plants Connected to João Câmara II with Droop Function

Power Quality Assessment of Large Motor Starting and Loading for the Integrated Steel-Making Cogeneration Facility

8 th Annual Electric Power Industry Conference

Integration issues and simulation challenges of high penetration PV

ELECTRIC ARC FURNACE WITH STATIC VAR COMPENSATOR PLANNING AND OPERATIONAL EXPERIENCE

Distribution Information Exchange Code

International ejournals

The Effect of the Volt/Var Control of Photovoltaic Systems on the Time-Series Steady-State Analysis of a Distribution Network

The Impact of Grid Connected Photovoltaic Generation System to Voltage Rise in Low Voltage Network

Public Utility District Number 1 of Snohomish County. Facility Connection Requirements February 9, 2018

WIND TURBINE PLANT CAPABILITIES REPORT

Large-scale Wind Power Integration and Voltage Stability Limits in Regional Networks

Transient Stability Analysis of an Industrial Cogeneration System

Transient Overvoltages and Distance Protection: Problems and Solutions

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014

Consequence and Impact of Electric Utility Industry Restructuring on Transient Stability and Small-Signal Stability Analysis

Impact study of PV integration in Bornholm power system

SOUTH AUSTRALIA SYSTEM STRENGTH ASSESSMENT

Technical Requirements for Distributed Generation Connection

Grid Power Quality Improvement and Battery Energy Storage in Wind Energy System by PI and Fuzzy Based STATCOM Controller

ETAP PowerStation 4.0

Operating Procedure PURPOSE... 2

Grid Connection and Power Quality Optimization of Wind Power Plants

R2 TESTING GUIDELINE. PREPARED BY: Network Models Systems Capability VERSION: Final RELEASE DATE: 28 June 2013

Facility Interconnection Requirements

WIND ENERGY INTEGRATION IMPACT ON POWER QUALITY IN ESTONIA

Session 9: Photovoltaic System Case Studies And Electric Distribution Planning for DER October 21, 2015 Santiago, Chile

BULK ELECTRIC SYSTEM PLANNING CRITERIA

Full electrical LNG-plant: Highest availability and energy efficiency trough overall system design

Phasor measurement units gain credibility through improved test and calibration standards

UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES

Refinement of Hydel power by implementing FACTS at Narangwal hydroelectric power plant

Power Flow Control Scheme for Wind Energy Conversion System

RESEARCH ON THE VIRTUAL SYNCHRONOUS GENERATOR CONTROL STRATEGY OF GRID-CONNECTED PERMANENT-MAGNET DIRECT-DRIVEN WIND POWER SYSTEM

GRID CODE FOR ISOLATED SYSTEMS

H AND REPETITIVE CONTROL

THE GRID CODE FOR THE NIGERIA ELECTRICITY TRANSMISSION SYSTEM

Power System Economics and Market Modeling

California Independent System Operator Corporation Fifth Replacement Tariff

DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA

Proposed Facility Study Report. Project: A380_A383_A415_A414_A413 MISO # F088. Prepared for Midwest ISO

ENABLING FREQUENCY AND VOLTAGE REGULATION IN MICROGRIDS USING WIND POWER PLANTS

ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM

An Assessment of Distributed Generation Impacts on Distribution Networks using Global Performance Index

Schedule 2 TECHNICAL INFORMATION

Requirements for Transmission System Interconnections to Generation, Transmission and End-User Facilities Revised June 10, 2014

INITIAL ASSESSMENT OF REACTIVE POWER EXCHANGES AT UK GRID SUPPLY POINTS

H REPETITIVE CURRENT CONTROLLER FOR

TPL Transmission System Planned Performance for Geomagnetic Disturbance Events

Centralized wind power plant voltage control with optimal power flow algorithm

Modeling and Operation Analysis of Meshed Distribution Systems with Distributed Generation

ANALYSIS OF THE BEHAVIOR FOR REACTIVE POWER COMPENSATION USING SVC CONTROLLED HYBRID SOLAR/WIND POWER GENERATING SYSTEMS

Member Service Electric Wiring Guidelines

Distribution System Design General Requirements

A JOINT DSO-TSO REACTIVE POWER MANAGEMENT FOR AN HV SYSTEM CONSIDERING MV SYSTEMS SUPPORT

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES

Comparison of Variable Speed Wind Turbine Control Strategies

safe reliable affordable GENERATOR COMPLIANCE MONITORING PROGRAM REQUIREMENTS 1 21 September 2015 TITLE: PREPARED BY: SYSTEM ANALYSIS & SOLUTIONS

Modeling of the Dynamic Behavior of the Island Power System of Cyprus

Network Interconnection Studies of Distributed Generation

DEW-ISM Implementation at PEPCO: A Model and Data Driven Approach to Automating PV Interconnection Studies

THE DYNAMIC ASPECTS OF WIND FARM OPERATION MEASUREMENTS AND ANALYSIS

ESP ENERGY SYSTEM PLANNING (PTY) LTD COMPANY EXPERIENCE (PROJECTS) Cons ulting Group

MOD Data for Power System Modeling and Analysis

Primary Frequency Response Stakeholder Education Part 1 of 2

Validation of dynamic models of wind farms (Erao-3)

Integrating Building Automation Systems with Microgrid Controls. Mingguo Hong, Associate Professor Case Western Reserve University Cleveland, OH

IMP/001/914 Code of Practice for the Economic Development of the 132kV System

Operational, economic and environmental benefits of electrically driven LNG with a combined cycle power plant

Indian Wind Grid Code

XXXX. Bremner Trio Small Hydro Project. Interconnection System Impact Study

Power Quality Measurement and Evaluation of a Wind Farm Connected to Distribution Grid

Power-Flow Analysis of Large Wind Power Plant Collector Systems With Remote Voltage Control Capability

Power quality improvement by using STATCOM control scheme in wind energy generation interface to grid

2018 PRICE LIST POWER*TOOLS. The Leader in Electrical Engineering Software Chosen by the top 40 Electrical Engineering firms in the world.

TABLE OF CONTENTS. LIST OF FIGURES Figure 4-1: Alternative 1 System Overview Figure 4-2: Alternative 3 System Overview...

Methodology PLG-METH-0002-V4

Trico Electric Cooperative, Inc. Interconnection Requirements. For. Distributed Generation

Analysis of Three Recent Blackouts

Custom Power Interfaces for Renewable Energy Sources

Ancillary Service for Transmission Systems By Tap Stagger Operation in Distribution Networks

Research Co-design Activity

Transcription:

SYSTEM IMPACT STUDY FINAL REPORT Prepared for Tri-State Generation & Transmission Association, Inc. By Dennis Woodford, Garth Irwin, and Andrew Isaacs. Electranix Corporation 107 865 Waverley St., Winnipeg, MB R3T 5P4 Phone: +1 204 953 1832 Fax: +1 204 953 1839 e-mail: daw@electranix.com i

SUMMARY A system impact study for the Owaissa Wind Ranch has been commission by Tri- State Generation and Transmission Association (Tri-State). A previous report [1] examined power flow, dynamic and short circuit studies for the Owaissa Wind Ranch rated at 40 MW, without the proposed Tri-State s Gladstone to Walsenburg 230 kv transmission line. This second study includes the Gladstone to Walsenburg 230 kv line 1, and investigates the Owaissa Wind Ranch at the same interconnection point, but with 80 and 120 MW injections in addition to the original 40 MW output level. If power from the wind ranch supplies its designated load by backing off an equivalent amount of power at San Juan generating station, acceptable steady state performance during contingencies for the three acceptance criteria of line/transformer overload, undervoltage deviations and maximum/minimum bus voltage limits was generally achieved in the North East Area of New Mexico (also known as the NEA) for the operation of the Owaissa Wind Ranch up to 120 MW. Marginal voltage deviations exceeding 5% were observed on some of Tri- State s 115 kv buses for the following contingencies: Ojo-Taos 345kV line (or 345/115kV Taos transformer), Colinas-Rowe Tap 115kV line, and the Black Lake-Taos 115kV line. The list of contingencies studied is in Appendix I. If designated load at or around Hernandez substation is additional to the normal projected loads for the area, and is to be supplied from the wind ranch without backing off scheduled generation, then major additional facilities are required in the Taos Ojo Hernandez triangle for a rating of the Owaissa Wind Ranch exceeding approximately 40 MW. An increase in wind ranch rating above 40 MW would be possible with increased investment in facilities that have yet to be defined in order to comply with acceptable steady state performance during contingencies. Acceptable performance during stability analysis was generally achieved. A preexisting problem in this part of the system was identified for a three-phase fault on the Gladstone to Walsenburg 230 kv line 2. This fault causes the Bravo Dome compressor motors to trip on under frequency. When wind generation at Owaissa is added at levels of 80 MW or higher, the load at Bravo Dome is able to remain in service 3. 1 At this time, the proposed Gladstone Walsenburg 230 kv line is projected to be in service in December 2006. 2 Although the Gladstone Walsenburg 230 kv line does not currently exist, in terms of the Owaissa Wind Ranch, the potential to trip Bravo Dome load for underfrequency conditions exists today and was confirmed to be possible after the addition of the Gladstone Walsenburg 230 kv line. 3 The Tri-State transmission system serving the Bravo Dome load is intentionally operated up to a steady state stability limit with all transmission lines in service. i

Studies using PSCAD (a 3-phase instantaneous solution simulation program [3]) were performed to determine short circuit current levels, determine the level of negative sequence imbalance, study wind turbine and SVC interactions, determine the effect of the pulsations from compressor motors on the wind turbines, look for amplification of wind turbine harmonics and to study the transient impact of closing the breaker on the Gladstone to Walsenburg 230 kv line. From steady state, short circuit, electromagnetic transients and also transient stability analysis considerations, the operation of the Owaissa Wind Ranch up to 120 MW still appears a realistic objective for the operating condition where San Juan generation can be backed off against wind power generated by the wind ranch. The facilities required to achieve operation of the wind ranch at 120 MW are minimal providing generation can be backed off at San Juan. These include replacing the current transformers on the 115 kv transmission lines that are presently limiting and to identify if conductors on the 115 kv transmission lines have to be raised. The 115 kv transmission line section between the Owaissa interconnect point and the proposed Gladstone substation is of concern at this stage. If load is added in the area of the Hernandez substation that is supplied with power from the Owaissa Wind Ranch so that no scheduled generation can be backed off, then major facilities will be required in the area to accommodate load and wind ranch capacity above about 40 MW. The Facilities Study will address these issues provided the load sink can be defined. The Owaissa project is modeled as an interconnecting bus and radial facilities to the wind ranch. Although the System Impact Study does not detail the interconnection facilities required, full sectionalizing will be required at the point of interconnection via a 115 kv substation. ELECTRANIX ii

CONTENTS 1 INTRODUCTION... 1 2 BASIC ASSUMPTIONS... 2 2.1 Originating Case for Study...2 2.2 Owaissa Wind Ranch Representation...2 2.3 SVC at Clapham...7 2.4 Thermal Capacity of the Springer to Rosebud 115 kv Line...7 2.5 Power Flow Acceptance Criteria...8 2.6 Transient Stability Acceptance Criteria...8 2.7 Simulation Software...8 2.8 Load Sink...9 3 LOAD FLOW STUDY METHODOLOGY... 9 4 RESULTS (STEADY STATE)... 9 4.1 Summary of Power Flow Results...9 4.2 Discussion of Power Flow Results...11 5 STABILITY STUDY METHODOLOGY... 11 6 RESULTS (TRANSIENT STABILITY)... 12 6.1 Summary of Transient Stability Results...12 6.2 Discussion of Bravo Dome Compressor Motor Tripping...12 6.3 Discussion of Tripping of Owaissa Wind Ranch...13 6.4 Sympathetic Tripping...13 7 SHORT CIRCUIT AND TRANSIENTS STUDY... 14 7.1 Model Development...14 7.2 Short Circuit Current Calculations...15 7.3 Measurement of Negative (-ve) Sequence Voltage Levels...18 7.4 Interactions between the Clapham SVC and the Wind Turbines...19 7.5 Impact of Pulsating Bravo Dome Compressor Motors on the Wind Turbines...19 7.6 Harmonic Studies...20 7.7 Impact of Closing the Gladstone to Walsenburg 230 kv line...22 8 CONCLUSIONS... 24 9 REFERENCES... 25 10 ACKNOWLEDGEMENTS... 25 APPENDICES Appendix I. Power flow case list Appendix II.Power flow analysis with generation backed off at San Juan to accommodate the power from the Owaissa Wind Ranch Appendix III Transient stability analysis results with generation backed off at San Juan to accommodate the power from the Owaissa Wind Ranch ELECTRANIX iii

Appendix IV NERC/WECC Performance Standard Appendix V.Transient stability analysis results with load added at Hernandez to accommodate the power from the Owaissa Wind Ranch Appendix VI.. Power flow analysis with load added at Hernandez to accommodate the power from the Owaissa Wind Ranch Appendix VII..GE Wind turbine generator model parameters Appendix VIII..Sympathetic tripping report Appendix IX..Power flow single line diagrams Appendix X Single line diagrams for the Owaissa Wind Ranch. ELECTRANIX iv

1 INTRODUCTION A system impact study for the Owaissa Wind Ranch has been commissioned by Tri- State for the requestor; Owaissa Wind Ranch, LLC. The wind ranch will be located in the North East area of New Mexico (also known as the NEA) and will interconnect onto the existing 115 kv transmission line that extends from Springer substation to Rosebud substation. The interconnection point will be approximately half way between Clapham and Rosebud substations or 11.5 miles each way (see Figure 1). A previous report [1] examined power flow, dynamic and short circuit studies for the Owaissa Wind Ranch rated at 40 MW, and without the proposed Gladstone to Walsenburg 230 kv transmission line. This second study investigates the Owaissa Wind Ranch at the same interconnection point with the Gladstone to Walsenburg line in service, with 80 and 120 MW injections in addition to the original 40 MW output. Walsenburg Colorado York Canyon New Mexico 230 kv New 230 kv transmission line To San Juan 345 kv Ojo Taos Black Lake Springer Gladstone 115 kv Foresight (new) Clapham location of existing and replacement SVC Hernandez 115 kv 34.5 kv To Norton Owaissa Wind Ranch To Arriba_T Storrie Rosebud (Bravo Dome) Figure 1: Single line diagram of the area under study showing the location of the proposed Owaissa Wind Ranch. ELECTRANIX 1

This is a final report of the power flow, transient stability and PSCAD electromagnetic transients study results. Two operating conditions were examined, which were based on where the power generated by the Owaissa Wind Ranch was delivered. The first operating condition accommodated the power from the Owaissa Wind Ranch by backing off an equivalent amount of generation at San Juan. The second operating condition was to lump a load at Hernandez that was equivalent to the power being generated from the wind ranch at Owaissa. The cases run are summarized in Appendix I. The steady state power flow results are summarized in Appendix II (with power backed off at San Juan) and Appendix VI (with load added at Hernandez). The transient stability results are shown in Appendix III with generation backed off at San Juan to accommodate the wind power, and in Appendix V with load added at Hernandez to accommodate the wind power generated. Due to the GE Wind turbine/generator proposed for Owaissa that uses doubly fed generators, it was necessary to undertake the following studies using PSCAD, which are discussed in Section 7 below: - Short circuit current calculations - Measurement of ve sequence voltage phase unbalance - Interactions between the Clapham SVC and the wind turbines - Impact of pulsating Bravo Dome compressor motors on the wind turbines - Harmonic studies - Impact of closing the Gladstone to Walsenburg 230 kv line. 2 BASIC ASSUMPTIONS The assumptions that apply for the power flow study are summarized as follows: 2.1 Originating Case for Study The originating case for this study is the 2008 hs2-sa (summer peak load) case prepared by member organizations of the Western Electricity Coordinating Council (WECC). This case included the proposed Gladstone to Walsenburg 230 kv transmission line. 2.2 Owaissa Wind Ranch Representation Significant detail was included in the representation of the wind ranch to include the main substation transformer, and an equivalent 34.5 kv feeder to each cluster of wind turbine generators (WTGs) connected to that feeder. The detail of the layout and information of the feeder was taken from single line diagrams SE-1, for the 40, 80 and 120 MW wind ranch options (see Appendix X). ELECTRANIX 2

Each cluster of 12 to 15 WTGs was represented as a single WTG in the studies. There were 2 clusters and consequently 2 equivalent WTGs represented in the 40 MW option. The 80 MW injection was represented by 4 lumped WTGs for its 4 clusters, and the 120 MW injection by 6 lumped WTGs for 6 clusters. This information is shown in Figures 2, 3 and 4. The underground 34.5 kv cables applied for each feeder to its single equivalent lumped WTG consisted of two types of cables: 1000 MCM Aluminum between the main substation and the cluster. 4/0 Aluminum within each cluster. The parameters applied for each type of cable for the power flow program in per unit of 100 MVA base for 1000 feet length were: Table 1: Parameters for Wind Ranch 33 kv collector system cables. Cable R/1000 X/1000 B/1000 1000 MCM Al 0.0034 0.005 0.00072 4/0 Al 0.01 0.007 0.00026 ELECTRANIX 3

Clapham 115kV Foresight 115kV Rosebud 115kV TMVA 27/36/45 X = 8.5% (0.3148pu) R = 0.0315 X = 0.0338 B = 0.007 1.68 mi. Foresight 34.5kV R = 0.0265 X = 0.0189 B = 0.006 1.5 mi. 34.5kV 34.5kV 22 MVA X = 0.2760 23 MVA X = 0.257 0.575kV 0.575kV P max = 19.5MW MVA = 21.71 Q max = 6.4MVAr Q min = -9.5MVAr 13 Turbines P max = 21MW MVA = 23.38 Q max = 6.9MVAr Q min = -10MVAr 14 Turbines Figure 2: Foresight 2 Feeder Equivalent Model For 40 MW Wind Ranch used in Cases 1,2,5 and 6 of system impact study. All impedances on 100 MVA base. ELECTRANIX 4

Clapham 115kV Foresight 115kV Rosebud 115kV TMVA 54/72/90 X = 8.5% (0.1574pu) Foresight 34.5kV R = 0.0369 X = 0.0409 B = 0.0082 R = 0.0259 X = 0.0238 B = 0.0059 R = 0.0548 X = 0.0597 B = 0.0122 R = 0.0361 X = 0.0257 B = 0.0084 2.05 mi. 1.44 mi. 3.08 mi. 2.05 mi. 34.5kV 34.5kV 34.5kV 34.5kV 25 MVA X = 0.24 20 MVA X = 0.3 25 MVA X = 0.24 20 MVA X = 0.3 0.575kV 0.575kV 0.575kV 0.575kV P max = 22.5MW MVA = 25.05 Q max = 7.4MVAr Q min = -11MVAr P max = 18MW MVA = 20 Q max = 5.9MVAr Q min = -8.8MVAr P max = 22.5MW MVA = 25.05 Q max = 7.4MVAr Q min = -11MVAr P max = 18MW MVA = 20 Q max = 5.9MVAr Q min = -8.8MVAr 15 Turbines 12 Turbines 15 Turbines 12 Turbines Figure 3: Foresight 4 Feeder Equivalent Model For 80 MW Wind Ranch used in Case 3 and Case 7 of system impact study. All impedances on 100 MVA base. ELECTRANIX 5

Clapham 115kV Foresight 115kV Rosebud 115kV TMVA 81/108/135 X = 8.5% (0.1049pu) Foresight 34.5kV R = 0.0369 X = 0.0409 B = 0.0082 R = 0.05 X = 0.0639 B = 0.0109 R = 0.013 X = 0.0111 B = 0.003 R = 0.0884 X = 0.1127 B = 0.0192 R = 0.0429 X = 0.0511 B = 0.0094 2.07 mi. 2.79 mi. 0.74 mi. 4.95 mi. 2.41 mi. R = 0.1302 X = 0.1807 B = 0.0279 7.27 mi. 34.5kV 34.5kV 34.5kV 34.5kV 34.5kV 25 MVA X = 0.24 22 MVA X = 0.2764 20 MVA X = 0.3 22 MVA X = 0.2764 22 MVA X = 0.2764 25 MVA X = 0.24 0.575kV 0.575kV 0.575kV 0.575kV 0.575kV P max = 22.5MW MVA = 25.05 Q max = 7.4MVAr Q min = -11MVAr P max = 19.5MW MVA = 21.71 Q max = 6.4MVAr Q min = -9.5MVAr P max = 18MW MVA = 20 Q max = 5.9MVAr Q min = -8.8MVAr P max = 19.5MW MVA = 21.71 Q max = 6.4MVAr Q min = -9.5MVAr P max = 19.5MW MVA = 21.71 Q max = 6.4MVAr Q min = -9.5MVAr P max = 22.5MW MVA = 25.05 Q max = 7.4MVAr Q min = -11MVAr 15 Turbines 13 Turbines 12 Turbines 13 Turbines 13 Turbines 15 Turbines Figure 4: Foresight 6 Feeder Equivalent Model For 120 MW Wind Ranch, used in Case 4 and Case 8 of system impact study. All impedances on 100 MVA base. ELECTRANIX 6

For each wind ranch rating option, the 34.5 kv cable feeders to the equivalent lumped WTG is summarized as follows: Table 2: Wind Ranch 33 kv feeder cable and unit transformer impedances Cluster Feeder Length R (pu) X (pu) B (pu) Unit Tfr Impedance No. WTGs (miles) (pu) 40 MW Feeder #1 1.68 0.0315 0.0338 0.007 0.276 13 Feeder #2 1.50 0.0265 0.0190 0.006 0.257 14 80 MW Feeder #1 2.05 0.0368 0.0409 0.0082 0.2395 15 Feeder #2 1.44 0.0259 0.0238 0.0059 0.3 12 Feeder #3 3.08 0.0548 0.0597 0.0122 0.2395 15 Feeder #4 2.05 0.0361 0.0257 0.0084 0.3 12 120 MW Feeder #1 2.07 0.0369 0.0409 0.0082 0.2395 15 Feeder #2 2.79 0.05 0.0639 0.0109 0.276 13 Feeder #3 0.74 0.013 0.0111 0.003 0.3 12 Feeder #4 4.95 0.0884 0.1127 0.0192 0.2876 13 Feeder #5 2.41 0.0429 0.0511 0.0094 0.2764 13 Feeder #6 7.27 0.1302 0.1807 0.0278 0.2395 15 Each individual WTG is a GE Wind-VAR unit rated at 1.5 MW, and the reactive power range that can be applied for ac voltage control is +0.49 MVAR, and 0.73 MVAR. 2.3 SVC at Clapham Only one ±25 MVAR is modelled as in service at Clapham. Although a second ±25 MVAR is being planned at the same location, it was not considered in these studies. 2.4 Thermal Capacity of the Springer to Rosebud 115 kv Line The thermal capacity of the 115 kv transmission line conductor from Springer to Rosebud is applied at 146.6 MVA instead of the 119.9 MVA as it is presently rated. The 146.6 MVA rating was determined through the utilization of a statistical static thermal conductor rating, based on the weather conditions recorded in New Mexico and the surrounding region 4 4 McElvain, F.R. and Mulnix, S.S, Statistically Determined Static Thermal Ratings of Overhead High Voltage Transmission Lines in the Rocky Mountain Region, IEEE Transactions on Power Systems, May 2000, p. 899. ELECTRANIX 7

2.5 Power Flow Acceptance Criteria For each of the power flow cases and each contingency, bus voltages and equipment ratings are to fall within the WECC and Tri-State system operation criteria. Tri-State criteria that differ from WECC criteria are identified below. These include: Bus Voltages: 0.95 < V steady state < 1.05 during normal system conditions, and must be between 0.90 < Vsteady state < 1.10 during single contingency outage conditions. Steady state voltage deviations during contingencies must be less than 5%. Although this is not a substitute for voltage collapse studies, this criterion is a screening test for potential voltage collapse, where voltages that drop by more than 5% are flagged for further review. Past P-V analyses in the area have determined that the region is operating near its point of collapse for contingencies to the west of Springer substation. Additional generation to the east of Springer substation improves the voltage stability of the region. Line and Transformer Ratings in normal steady state conditions must not exceed 80% of the full load rating. Line and Transformer Ratings during contingencies must be within 100% of the continuous rating. Load tap changers, phase shifters, and switched shunt devices can operate during contingencies. This is a variation from the WECC criteria since Tri- State s system is primarily rural with very low consumer density. Fixed area power flow interchanges are enforced during all contingencies. The slack bus was a unit at San Juan. 2.6 Transient Stability Acceptance Criteria For each of the base cases and each contingency, transient bus voltages and frequency deviations are to fall within the WECC and Tri-State system operation criteria. These criteria are summarized in Appendix IV, and include: Bus frequencies at a load bus must not fall below 59.6Hz for longer than 6 cycles. Voltage dip at a load bus must not exceed 25% at load busses, or 30% a non-load busses. Voltage dip at a load bus must not exceed 20% for longer than 20 cycles. Mechanical oscillations must be damped after 20 seconds. 2.7 Simulation Software The simulation software used for this study is the GE PSLF V14.1 program. This version of the program includes the latest GE PSLF wind turbine dynamics models. The data for the parameters for the PSLF wind turbine model are included in Appendix VII along with the results of the stability study (Appendices III and V). ELECTRANIX 8

2.8 Load Sink The power balance when wind power from Owaissa was being generated was achieved with two operating conditions. Firstly, power generated by San Juan was reduced by an equivalent amount. Secondly, load was added at Hernandez by an equivalent amount. Results for each method are included in the Appendices II and VI and are summarized in this report. 3 LOAD FLOW STUDY METHODOLOGY This interim report considers the steady state system impact of the power flow during single contingencies. In this particular study, outages within the NEA were simulated as listed in Appendix I. For each contingency, Cases 1 to 4 are with the Bravo Dome compressor motors all in-service and fully loaded at 43.8 MW total. Case 1 is the base case with no wind power being generated. Case 2 is with 40 MW of WTG capacity in place and fully loaded. Case 3 is with 80 MW of WTG capacity in place and fully loaded. Case 4 is with 120 MW of WTG capacity in place and fully loaded. Cases 5 to 8 are for the Bravo Dome compressor motors all out of service. Case 5 is the base case with no wind power being generated. Case 6 is with 40 MW of WTG capacity in place and fully loaded. Case 7 is with 80 MW of WTG capacity in place and fully loaded. Case 8 is with 120 MW of WTG capacity in place and fully loaded. A summary of the results for each case studied is included in Appendix II for the load sink at San Juan, and in Appendix VI for the load sink at Hernandez. 4 RESULTS (Steady State) 4.1 Summary of Power Flow Results The results of the power flow study in Appendix II consider the power flow acceptance criteria (Section 3.5 above) for the NEA area of interest (Zone 121 in the WECC base case). Output results are only shown if the power flow approaches violation conditions. The conclusions for the operating condition when the load sink is at San Juan are: There were no overload violations as a consequence of the Owaissa wind farm, for any power level up to 120MW. The transformer at the Rowe Tap was overloaded in the base case and throughout the contingency cases at 0.84 per unit. ELECTRANIX 9

Undervoltage deviation violations greater than 5% were observed when the wind power from Owaissa was both 80 and 120 MW for Contingency No. 5 (outage of the Black Lake -Taos 115 kv line), and for Contingency No. 8 (outage of the Colinas Rowe Tap 115 kv line). Additional undervoltage deviations exceeding 5% were observed at the Taos 115 kv busbar for outage of the Ojo Taos 345 kv line (Contingency 12) and for the outage of the Taos 345/115 kv transformer (Contingency 15) when the Owaissa wind farm was generating at 120 MW and the compressor motors at Bravo Dome were out of service. There were no bus voltage violations for contingency conditions. The ±25 MVAR SVC at Clapham remained operational for the cases studied, and was sized sufficiently to prevent any voltage violations. The switching of the shunt capacitor banks at Clapham and Springer substations was checked to ensure the SVC was operating with sufficient range. Results for the operating condition when the load sink is a load at Hernandez are found in Appendix VI, and are summarized as follows: Outage of the Taos Hernandez 115 kv line causes severe overload of the Ojo 115/345 kv transformer and the Ojo Hernandez 115 kv transmission line. Outage of the Ojo Taos 345 kv transmission line causes severe overload of the Ojo 115/345 kv transformer and the Ojo Hernandez 115 kv transmission line. There is a similar performance observed for the outage of the 115/345 kv transformer (as would be expected). There are also significant voltage drops on the 115 kv transmission system from Hernandez to Springer. There are cases where PSLF failed to converge, particularly when the wind ranch is generating 80 to 120 MW. The system impact around Taos Ojo Hernandez with the Bravo Dome compressor motor load out of service is slightly more severe compared with the compressor motor load being in service. There is a difference in system impact between having the load sink being accommodated by backing off San Juan generation compared to a lumped load at Hernandez. When the San Juan generation is backed off, a 120 MW rated wind ranch for Owaissa is possible with minor additional facilities required. With the load sink lumped as a single load at Hernandez, major additional facilities are required in the Taos Ojo Hernandez triangle for a rating of the Owaissa Wind Ranch exceeding 40 MW. An increase in wind ranch rating above 40 MW would be possible with increased investment in facilities that have yet to be defined. ELECTRANIX 10

4.2 Discussion of Power Flow Results The results of the power flow study highlight how the definition of the load sink impacts system performance. If the load sink is not additional load to what is built into the WECC 2008 hs2-sa (summer peak load) base case used for this study, then the load sink is achieved by backing off scheduled generation. If San Juan generating station is backed off, then the results in Appendix II are valid and little in the way of additional transmission facilities are required, based on the results from this System Impact Study. If the loads being targeted from Owaissa Wind Ranch have all or part of their generation requirements normally scheduled from a generating station other than San Juan, then those generating stations need to be identified. If new load at or near Hernandez is being supplied from Owaissa so that no scheduled generation needs to be backed off, then the results in Appendix VI are valid, and additional transmission facilities will be required in the Taos Ojo Hernandez triangle. 5 STABILITY STUDY METHODOLOGY Stability studies were performed with the goal of evaluating the voltage stability response of the NEA 115 kv power system, and dynamic stability of the Bravo Dome synchronous compressor motors. Load flow base cases 1 to 4 (Appendix I) have the Bravo Dome compressor motors operating. These base cases were run with the disturbances listed in Table 3. These cases are not exhaustive, but have been selected to represent severe disturbances. Since disturbance S2 was not applicable to Case 1, a total of 19 simulations were run. For this study, results of the disturbance simulations were examined relative to the April 2003 NERC/WECC Planning Standards. These simulations represent disturbances based on the WECC 2008 heavy-summer configuration. It is noteworthy to mention that the transient stability representation of the compressor motors does not include the pulsating torque effect on the compressor motors due to piston action. This effect was included in PSCAD models, but only for breaker energization studies (Section 7). The Bravo Dome Compressor motors were modeled in both PSCAD and PSLF as two synchronous motors. One motor represents six 8000 hp motors and one to represent three 6000 hp motors. Exciter models were provided from an earlier study [2]. Impedance relays were represented on the 115 kv transmission line sections Springer to Gladstone, and Gladstone to Clapham. The settings on each based on the impedance Z of the transmission line section were: ELECTRANIX 11

Zone 1: 80% of Z, no delay Zone 2: 125% of Z, with 20 cycles delay Zone 3: 150% of Z, with 60 cycles delay. The cases were undertaken with the GE Wind -VAR wind turbine and generator model included in the PSLF program and with specific parameters provided by GE Wind, which contain the undervoltage settings and ride-through capability they expect to provide for Owaissa Wind Project. This model also includes the reactive power control capability of the wind turbine. Test S1 S2 S3 S4 S5 Table 3: Transient Stability Disturbance List Stability Disturbance Descriptions 3Ø permanent fault on the Foresight 34.5 kv Transformer bus, transformer clears after 6 cycles Sudden loss of Power from the Wind Ranch due to wind gust 3Ø permanent fault on the Gladstone-Walsenburg 230kV line, clears after 6 cycles 3Ø permanent fault on the Springer-Black Lake 115kV line, clears after 6 cycles 3Ø permanent on the Ojo-Taos 345kV line, clears after 6 cycles. 6 RESULTS (Transient Stability) 6.1 Summary of Transient Stability Results Results for all of the 19 disturbance simulations are shown in Appendix III, and met or exceeded the specified category of the NERC/WECC Performance Standards (See Appendix IV). For the condition where the load sink was lumped at Hernandez, the simulation results are assembled in Appendix V. 6.2 Discussion of Bravo Dome Compressor Motor Tripping Although the monitored system busses met the required stability criteria, several of the disturbance cases caused load tripping of the Bravo Dome compressor motors. During a three-phase fault applied to the middle of the Gladstone-Walsenburg 230 kv line (Test S3), Bravo Dome compressor motors tripped due to under-frequency for Cases 1 and 2 (0 MW and 40 MW of wind, respectively). As more wind generation was added in Cases 3 and 4 (80 MW and 120 MW respectively), the compressor motors at Bravo Dome were able to remain on through the disturbance. For Case 2 the 40MW Owaissa wind ranch also tripped due to undervoltage. If the 3-phase fault on the Gladstone-Walsenburg line is cleared after 4 cycles instead of 6 (a realistic scenario), the Bravo Dome motors do not trip in Case 2, ELECTRANIX 12

which has 40 MW of wind generation. Additionally, the faster fault removal is sufficient to prevent the wind ranch from tripping during this disturbance. The reduced fault clearing time is not sufficient to prevent the Bravo Dome compressor motors from tripping during Case 1, where no power is available from wind. Further tests with simulated 1 phase faults instead of three phase faults with 6 cycle clearing time show there is no tripping of the Bravo Dome compressor motors. It is worth noting that the under-frequency resulting from the Gladstone- Walsenburg 230kV line fault was reported in the WECC 2003 Study Program Annual Report Case D0310, published Feb. 2004. This is an indication that the addition of larger amounts of wind generation in the immediate vicinity of the Bravo Dome compressor motors provides system support including offsetting the required power flow through the radial lines to the motors. 6.3 Discussion of Tripping of Owaissa Wind Ranch During the 3 phase fault on the Walsenburg-Gladstone 230kV line, the turbines at the Owaissa wind ranch also trip off for the 40 MW case. As discussed in Section 6.2, this condition may be alleviated by reducing the fault clearing time to 4 cycles from 6. Additionally, a fault on the main substation transformer at the wind farm site causes the wind ranch to be islanded from the network, and the wind turbines to trip. 6.4 Sympathetic Tripping The outage determined to be the most likely to cause sympathetic tripping on the Springer Rosebud transmission system was the loss of the Gladstone Walsenburg 230 kv line. This disturbance was studied for the following four loadings of Owaissa Wind Ranch: 1. 0 MW wind generation 2. 40 MW wind generation 3. 80 MW wind generation 4. 120 MW wind generation For case 4 with 120 MW wind generation, additional 3 phase faults were placed on nearby 115 kv transmission lines to see if sympathetic tripping occurred. These disturbances were located on: 1. Springer York Canyon 115 kv transmission line 2. Springer Storrie 115 kv line 3. Springer Black Lake 115 kv line. All faults were cleared after 6 cycles. The results of the stability study showed that for the 4 cases studied, the impedance characteristic entered the 3 rd zone of protection for the distance relay located on the ELECTRANIX 13

Springer Gladstone transmission line section for a very short time following a Gladstone Walsenburg line fault. With the load sink located at Hernandez, the impedance characteristic entered the 3 rd zone only for case 4, with 120 MW of generation. None of these cases resulted in sympathetic line tripping. 7 SHORT CIRCUIT AND TRANSIENTS STUDY The following studies were performed with PSCAD: - Short Circuit Current Calculations - Measurement of ve sequence voltage phase unbalance - Interactions between the Clapham SVC and the Wind Turbines - Impact of pulsating Bravo Dome compressor motors on the wind turbines - Harmonic Studies - Impact of Closing the Gladstone to Walsenburg 230 kv line 7.1 Model Development All models were developed in PSCAD V4.0.3 (the latest release at the time of this study). The system representation is shown in Figure 5 (most objects in the single line diagram (SLD) in Figure 5 are page components, with detailed models on subpages). The E-TRAN program is used to translate loadflow information into PSCAD and to initialize loads, transformer tap settings and to set machine initial conditions. Most of the system 3 or 4 busses away from the study area is represented in detail, with multi-port system equivalents being calculated at San Juan 345 kv, Comanche 230 kv, Storrie, Walsenburg and Hernandez 115 kv busses. E-TRAN calculates system equivalents by re-creating the admittance matrix from the loadflow information and uses network reduction techniques to reduce the network to a size manageable in PSCAD. Data from the dynamics file (machine reactances) was imported and used to update the loadflow generator impedances so that accurate system equivalents can be created. In addition: - All transformers are represented using detailed 2 or 3 winding transformer models, including wye-delta transformations, neutral grounding, tap settings and non-linear saturation. - The 115 kv transmission system from Rosebud back to Springer is represented with detailed phase-domain frequency dependent line models, whereas remaining transmission lines are represented based on loadflow RXB data (traveling wave Bergeron models for longer lines and pi-sections for short lines). - The SVC at Clapham is modeled with a thyristor switching model of the TCR. The model was developed for a different project [2]. Although in the ELECTRANIX 14

future there will be 2-25 MVAR SVC units, only a 25 MVAR single unit was included in this study. - The compressor motors at Rosebud and York Canyon were also modeled in a previous study [2] and re-used here. They are represented with DQ0 machines, and include the multi-mass and piston torsional effects. The models were validated against site measurements. - The wind farm units are modeled using the latest PSCAD model from GE Wind, with a recommended number of units lumped together as per Section 2.2. SAN_JUAN N10292 E_10292_10232_1 I OJO N10232 345 115 T_10232_12050_1 OJO 345/13.8/115 E_10232_12082_1 OJO N12050 E_12050_12038_1 HERNANDZ N12038 E_12038_12081_1 TAOS N12081 E_12081_12011_1 115 69 T_12081_12080_1 Taos 115/69 115 345 T_12082_12081_1 Taos 345/13.8/115 BLACKLAK N12011 TAOS N12080 TAOS N12082 115 69 T_12011_12010_1 Blacklak 115/69 E_12011_12077_1 28.75 9.45 E P,Q Load BLACKLAK N12010 SPRINGER N12077 6.98 2.294 E P,Q Load CLAPHAM N12020 E_12077_12020_1 VN12020 0.0 Shunt -12.5 E C 72.714 km B_12077_12100_1 18.425 km B_12020_10394_1 SVC Cap CLAPHAM SVC 115 69 T_12020_12019_1 Clapham 115/13.8/69 35.81 km B_12020_12100_1 FORSIGHT N10394 CLAPHAM N12019 GLADSTON N12100 18.425 km B_10394_12062_1 115 34.5 T_10394_12105_1 GEWind 115/tertiary/34.5 E_12019_12006_1 E_12019_12021_1 115 230 T_12101_12100_1 Gladstone 230/13.8/115 ROSEBUD N12062 FORFEED N12105 AMISTAD N12006 CLAYTON N12021 GLADSTON N12101 115 13.8 ROSEBUD N12063 T_12062_12063_1 VN12063 Rosebud 115/13.8 <-- 2.07 [km] --> E_12105_12106_1 <-- 2.79 [km] --> E_12105_12108_1 <-- 0.74 [km] --> E_12105_12110_1 <-- 4.95 [km] --> E_12105_12112_1 <-- 2.41 [km] --> E_12105_12114_1 <-- 7.27 [km] --> E_12105_12116_1 6.64 2.182 E P,Q Load E_12021_10358_1 4.05 P,Q 1.331 E Load E_12101_70459_1 FORFEED1 N12106 FORFEED2 N12108 FORFEED3 N12110 FORFEED4 N12112 FORFEED5 N12114 FORFEED6 N12116 VANBUREN N10358 WALSENBG N70459 G_12063_0_s1 Bravo Dome Compressor 2 (6 units) G_12063_0_s2 Bravo Dome Compressor 1 (3 units) 34.5.575 FORWTG1 N12107 T_12106_12107_1 VN12107 Forfeed1 34.5/.575 FORWTG2 34.5.575 N12109 T_12108_12109_1 VN12109 Forfeed2 34.5/.575 FORWTG3 34.5.575 N12111 T_12110_12111_1 VN12111 Forfeed3 34.5/.575 FORWTG4 34.5.575 N12113 T_12112_12113_1 VN12113 Forfeed4 34.5/.575 FORWTG5 34.5.575 N12115 T_12114_12115_1 VN12115 Forfeed5 34.5/.575 FORWTG6 34.5.575 N12117 T_12116_12117_1 VN12117 Forfeed6 34.5/.575 69.0 1 69.0 1 : E : E 12.5 4.16 E_70459_70122_1 230.0 1 : E 115.0 CLAYTON N10068 T4 N10334 COMANCHE N70122 0.726 0.415 2.334-1.037 WALSENBG N70458 7.997 2.629 E E E G_12107_0_1 Forwtg1 (15 x GE 1.5 Wind) G_12109_0_1 Forwtg2 (13 x GE 1.5 Wind) G_12111_0_1 Forwtg3 (12 x GE 1.5 Wind) G_12113_0_1 Forwtg4 (13 x GE 1.5 Wind) G_12115_0_1 Forwtg5 (13 x GE 1.5 Wind) G_12117_0_1 Forwtg6 (15 x GE 1.5 Wind) P,Q Load P,Q Load P,Q Load Net-Equiv SubPage 2 N10292 N10292 N12079 N12079 N70122 N70122 N70458 N70458 N12038 N12038 115 69 T_12077_12076_1 Springer 115/13.8/69 E_12077_12079_1 E_12077_12091_1 SPRINGER N12076 STORRIE N12079 YORKCANY N12091 4.57 1.502 E 115.0 1 : E P,Q Load 69.0 115 69 T_12091_12090_1 YorkCany 115/69 115 13.8 STORRIE N12078 T_12091_12102_1 VN12102 YorkCany 115/13.8 5.38 1.768 YORKCANY N12090 4.83 1.558 YORKCANY N12102-7.4-1.0 E E P,Q Load P,Q Load G_12102_0_s1 York Canyon Compressor 1 E ~ E_12102_0_s2 Figure 5 PSCAD System Single Line Diagram 7.2 Short Circuit Current Calculations The wind farm manufacturer (GE Wind) specified that short circuit studies should be performed with a PSCAD simulation model (as opposed to traditional loadflow short circuit calculations). To verify the system representation in PSCAD, short circuit currents at the Foresight 34.5 kv bus were calculated using PSLF and were compared to those calculated in the PSCAD model. The base case system (without any wind represented) was used for this test case. The comparative results are summarized in Table 4. Table 4 Comparison of Short Circuit Current Calculations from Loadflow Programs Compared to PSCAD Case Description SCC (3Φ Short Notes Circuit Current Level, ka, RMS) 1. Loadflow (PSLF) 3.69 Traditional SCC Calculations. 2. PSCAD (detailed models not used) 3.69 Good verification of system equivalents. ELECTRANIX 15

3. PSCAD (detailed transformers used) 4. PSCAD (detailed line models added) 5. PSCAD (DQ0 machines added, SCC at first cycle) 5. PSCAD (DQ0 machines added, SCC at 4th cycle) 6. PSCAD (detailed SVC replaces SVC modeled as a generator) 3.78 Some detailed transformer 3 winding data had lower impedances compared to loadflow data. 3.80 Fundamental frequency impedance/admittance of detailed line models match the loadflow. 3.79 SCC calculations in the loadflow use sub-transient reactance. 3.5 SCC levels will be lower at the time of opening breakers due to frequency dependent effects in machines (ie XD, XD ) 3.2 In the previous cases, the SVC is represented as a generator, with an impedance that causes the SCC level to be higher. The test cases show that the approach using the PSLF program for short circuit analysis will tend to exaggerate the short circuit levels. In particular: - The short current levels will be lower 3 or 4 cycles into the fault (when the breakers have to interrupt the fault current) compared to the first cycle current levels. The loadflow program often uses subtransient reactance (Xd ) as a machine impedance, which is analogous to taking the first cycle fault current. - The SVC will add short circuit current contribution if represented as a generator with 0 MW output). The real SVC does not contribute to the short circuit current. The PSCAD result is a time domain transient simulation program, so there will also be a decaying dc offset in the fault current waveforms. The fault currents are computed by taking the currents in the first cycle of the fault (maximum current minus the minimum current) /2, and then converted to RMS. A typical short circuit current waveform is shown in Figure 6. ELECTRANIX 16

4.0 Ic Case SC6 showing decaying DC offset 2.0 0.0 y -2.0-4.0-6.0-8.0 0.400 0.450 0.500 0.550 0.600 0.650 0.700 0.750 0.800 Figure 6: Short Circuit Current (SCC) showing decaying dc offset An additional test case was performed to approximate the short circuit impedance of the GE 1.5 MW wind turbines. The PSCAD model of the turbine was run feeding a 1 pu resistance on the.575 kv terminals of the turbine. The unit was then faulted (0 resistance 3 phase fault) and the fault current determined. From the first cycle fault current (averaged over 3 phases), the short circuit impedance is approximately 0.4 pu on a 0.575 kv and 1.5 MVA base. If a fault is prolonged, the Rosebud compressor motors will slow down and the fault currents can exhibit pole-slipping beating characteristics. In reality these motors would trip on under-frequency for prolonged faults. Table 5 shows the short circuit current results from the full PSCAD model with the dc offset ignored: ELECTRANIX 17

Table 5: AC Component of Fault Current (ka, RMS) (120MW Generation at Owaissa Wind Ranch) Case Fault Bus Fault Description SC Current (1st Cycle) SC Current SC Current (3rd Cycle) (6th Cycle) SC1 12062 Rosebud 115kV 2.22 1.70 0.82 SC2 12063 Rosebud 13.8kV 14.90 11.37 4.24 SC3 10394 Foresight 115kV 2.65 1.82 0.92 SC4 12105 **Foresight 34.5kV 8.31 3.34 4.69 SC5 12020 Clapham 115kV 2.96 2.17 1.31 SC6 12019 Clapham 69kV 2.38 2.34 2.05 SC7 12101 Gladstone 230kV 2.05 1.58 1.43 SC8 12100 Gladstone 115kV 4.04 3.25 2.52 SC9 12077 Springer 115kV 3.50 3.11 2.82 SC10 12076 ***Springer 69kV 1.77 1.74 1.74 ** In some cases, beat frequencies due to machine speed changes cause the current to increase from the third cycle to the sixth cycles, or cause the two measurements to be very different. *** Due to conflicting transformer impedance data, the load flow data was used for the Springer transformer for case SC10. This caused the short circuit current on this bus to rise slightly. 7.3 Measurement of Negative (-ve) Sequence Voltage Levels The PSCAD model was run in steady state at 0, 40, 80 and 120 MW wind levels. The instantaneous A, B and C voltages were recorded, processed by Fourier analysis, and then expressed in terms of fundamental frequency sequence components. The ve sequence compensation in the SVC controls was turned off. The ve sequence is predominantly caused by the use of non-transposed transmission lines through 115 kv system. The results are shown in Table 6. Although the wind farm increases the ve sequence unbalance, levels are quite small. The positive (+ve) sequence voltages are controlled (either by the SVC or by the excitation system on the compressor motors) so are constant. ELECTRANIX 18

Table 6: Measurement of Voltage Sequence Components (pu) Clapham (SVC 115 kv Bus) Rosebud (Compressor 13.8 kv Bus) Case +ve Seq -ve Seq 0 Seq +ve Seq -ve Seq 0 Seq 1 (0 MW Wind) 1.02 0.0023 0.00019 1.02 0.0036 0 2 (40 MW Wind) 1.02 0.0038 0.00046 1.02 0.0026 0 3 (80 MW Wind) 1.02 0.0058 0.00058 1.02 0.004 0 4 (120 MW Wind) 1.02 0.0074 0.0006 1.02 0.006 0 Note that the loads in the PSCAD model are symmetrical on all 3 phases, whereas the loads in the real system can be unbalanced and will add to the levels shown in Table 6. 7.4 Interactions between the Clapham SVC and the Wind Turbines The PSCAD models were run over a 10 second period to look for interactions between the SVC and the Wind Turbines units. In all cases (0, 40, 80 and 120 MW of wind) there were no apparent oscillations or control interactions. The SVC controls use Proportional-Integral controllers, but fortunately they are considered with a droop characteristic that prevents multiple operating points and minimizes hunting problems with other nearby fast-acting control devices such as the Owaissa WTGs. 7.5 Impact of Pulsating Bravo Dome Compressor Motors on the Wind Turbines The compressor motors at Bravo Dome (Rosebud) and York Canyon are piston driven, which generate pulsations and flicker into the electrical network. The concern is that these frequencies can coincide with mechanical modes of resonances on the wind turbine blades and shaft system. The GE wind model in PSCAD does not include details on the mechanical modes of oscillation. To address this concern, the model was run in steady state and the instantaneous electrical power into a wind turbine unit was calculated. The frequencies that can appear on the shaft (due to the electrical system) were then computed by Fourier analysis. The Fourier results are summarized in Table 7. The only significant interactions between the electrical grid and the wind turbine occurred near 5 Hz and at the 2 nd harmonic (120 Hz). The 2 nd harmonic component of electrical power is due to the presence of ve sequence unbalanced voltages and currents (the ve sequence transforms into the 2 nd harmonic on the electrical torque of the machine). The 5 Hz component was much smaller (.16%) whereas the 2 nd harmonic component was larger (up to.96%). From system measurements and calculations, it is known that the mechanical modes of resonances on the compressor motors at Bravo Dome are 5.025 Hz and 5.4054 ELECTRANIX 19

Hz. The Fourier analysis (reported in Table 7) was performed over a 1 second steady state period (which results in a frequency resolution of 1 Hz), so these two frequencies combine into the 5 Hz value. To provide more details, Case 4 was run for 100 seconds in steady state (which results in 0.01 Hz resolution in the frequency domain), and the Fourier analysis repeated. This time the electrical power showed clear 5 Hz and 5.45 Hz components (5 Hz: 0.001258 pu, 5.45 Hz: 0.0002174 pu, 120 Hz, 0.009649 pu). It was observed that the 5 Hz component was larger then the 5.45 Hz component. Table 7: Effect of Pulsating Motor Load on Wind Turbines (WTG #1) Harmonic Frequencies Present on Wind Turbine Electrical Power (pu on Total WTG Rated Power (N*1.5MW)) Case (FFT Scan of Instantaneous Electrical Power 1 Hz to 10 khz) 2 (40 MW Wind) 5 Hz: 0.00163 120 Hz: 0.0035 3 (80 MW Wind) 5 Hz: 0.00154 120 Hz: 0.0066 4 (120 MW Wind) 5 Hz: 0.00149 120 Hz: 0.0096 Note: FFT (Fourier analysis) performed over 1 second period, so frequency resolution is 1 Hz. The electrical power that appears at the WTG terminals will result in an electrical torque with similar frequency components. The frequencies on the electrical power match those of the Rosebud motors (5.025 Hz and 5.4054 Hz). 7.6 Harmonic Studies The GE wind model for PSCAD is not a detailed switching based model (it is possible to represent the Voltage Sourced Converter used in the double wound generator and thereby model the switching of the electronic devices) so it cannot inherently reproduce the level of harmonics in the system. However, GE provided a table of measurements of voltage and current harmonic magnitudes. This information can be used to estimate how the addition of the wind turbine units will affect the Total Harmonic Distortion (THD) levels in the nearby system. To study this, it was assumed that the harmonics that appear on the 115 kv system at Foresight can be represented as a current injection onto the 115 kv bus (this is reasonable because these harmonic currents must pass through the inductance of the 115/34.5 kv transformers and 34.5 kv unit transformers, thus approximating a current source). The harmonic currents (measured from the 575 volt terminals of a single GE wind turbine) were output to a text file, and then read in by a customdeveloped component in PSCAD. The harmonic currents on each phase were then re-constructed (essentially an inverse Fourier transform) and injected onto the 115 kv system (scaling factors were applied for the number of wind turbines in service and the different voltage level). A validation test of the new model was made by performing a Fourier analysis from the time domain current injections and comparing them to the original measured harmonics in the frequency domain (with excellent results). ELECTRANIX 20

The resulting THD levels are shown in Table 8 and graphically in Figure 7 for varying levels of wind output. Table 8: THD Level of Foresight 115 kv Bus (%) Wind Farm Harmonics AddedWind Farm Harmonics Removed Wind MW Phase A Phase B Phase C Phase A Phase B Phase C 0 1.476 1.404 1.435 1.476 1.404 1.435 40 1.327 1.26 1.291 1.321 1.258 1.288 80 1.278 1.212 1.239 1.247 1.196 1.223 120 1.316 1.257 1.254 1.229 1.19 1.218 Maximum Individual Harmonic: 1.064 (phase B of 0 MW case, 65 Hz) (all other cases had all individual harmonics below 1%) THD (%) 1.6 1.5 1.4 1.3 THD Levels at Foresight 115 kv Phase A (without wind harmonics) Phase B (without wind harmonics) Phase C (without wind harmonics) Phase A (with wind harmonics) Phase B (with wind harmonics) Phase C (with wind harmonics) 1.2 1.1 1 0 40 80 120 Wind MW Figure 7: THD Level of Foresight 115 kv Bus (%) It is interesting to note that the largest single component of frequency in these cases was a 65 Hz component (+/- 1 Hz), which was 1.064%. This occurs because of the pulsation effect of the compressor motors (the 5 and 5.4 Hz mechanical mode of oscillation appears on the electrical grid as 65 and 65.4 Hz as seen on the instantaneous voltage waveshape, and which reflects through in the RMS measurement as an approximate 5 Hz component). This 65/5 Hz component of 115 kv voltage can possibly be minimized with flicker reduction controls on the SVC (this was not represented in the SVC model). ELECTRANIX 21

The THD levels increase as wind power levels increase, however this is compared to a theoretical wind generator that does not produce harmonics (ie the table shows the results with the wind turbine harmonic currents on and off). The results also show that the base case (without any wind production) has higher THD levels. The representation of the wind turbine harmonics as a current source (as seen from the 115 kv side) is an approximation. If THD levels are at high levels, a more detailed GE wind model for PSCAD is required which represents the VSC as switching devices. Another test was done using linear harmonic impedance scanning A graph showing the harmonic impedance as a function of frequency (as seen from the Foresight 115 kv bus) is shown in Figure 8. In this case, 120 MW of GE wind turbines are in service and are approximated with a 0.4 pu inductive source impedance. 1000 +ve and 0 Seq Harmonic Impedance 800 600 Ohms 400 200 0 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Harmonic # 0 Sequence +ve Sequence Figure 8: Harmonic Impedance at Foresight 115 kv Bus (120 MW Wind Case 4) 7.7 Impact of Closing the Gladstone to Walsenburg 230 kv line When the new 230 kv line from Gladstone to Walsenburg is out of service, a large phase shift will exist between the systems on either side of the breaker (from PSLF loadflow studies, the phase shift was more then 35 degrees in the base case). The concern was that closing the line breaker could cause a large transient effect on the compressor motors at Rosebud or on the Wind Farm units. ELECTRANIX 22

To investigate this, loadflow cases were run with this line open at Gladstone but energized at Walsenburg. The case was then translated to PSCAD (using E-TRAN) and multiple runs were performed which closed the breaker sequentially every 20 degrees of one cycle (all three phases closed at the same time). The over-frequency and under-frequency protection systems of the compressor motors were modeled (the GE Wind model already had protection systems included in the model). The state of each compressor motor (Rosebud 1, Rosebud 2 and York Canyon) as well as each wind turbine unit was monitored to look for trips due to the breaker closing. The breaker closing times were chosen to occur at the maximum frequency of the smallest Rosebud compressor motor (the steady state motor frequency will change with a 5 Hz and 5.4 Hz component due to the piston pulsating effect) and then varied every 20 degrees over a full cycle (19 runs). This was repeated for the minimum frequency swing, and was repeated for all 4 wind turbine output levels (0, 40, 80 and 120 MW). In all cases the compressor motors and the wind turbine units did not trip. However, it is conceivable that a larger phase angle across the contacts of the open circuit breaker at Gladstone could occur for a particular power flow condition, and a greater deviation of frequency of the compressor motors will result when the circuit breaker is closed. The open circuit phase angles observed in the models for the respective power flow conditions for this study were as shown in Table 9: Table 9: Phase angles across open circuit breaker at Gladstone for different generation levels at the Owaissa Wind Ranch. Power Generated at the Owaissa Wind Ranch 0 MW 40 MW 80 MW 120 MW Phase angle across the open Gladstone 230 kv breaker 55 O 40 O 28 O 17 O The increase in generated power from the Owaissa Wind Ranch reduces the phase angle across the open Gladstone 230 kv circuit breaker, and lessens the impact on the frequency swing of the Bravo Dome compressor motors when the circuit breaker is closed. It is noteworthy that site measurements (and PSCAD models) indicate the compressor motor frequencies change significantly due to the pulsating piston effect. Fault analysis is typically conducted in transient stability algorithms, but the pulsation effect of the compressor motors is not included in the WECC models. If future motor-trip protection studies are to be undertaken, the steady state pulsating effects of the motors should be included (either in transient stability models or in PSCAD). ELECTRANIX 23