Meeting the Challenge of EPC Project Proposal Schedules. Project Proposal Schedules

Similar documents
Managing Schedule Change

48R06 SCHEDULECONSTRUCTABI

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

Schedule Guidance Document

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

SECTION NETWORK ANALYSIS SCHEDULES (NCA)

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL

LONG INTERNATIONAL. Andrew Avalon, P.E., PSP and Curtis W. Foster

Procurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202

Owner s Representative SCOPE OF SERVICES

OWN The Owner s Estimate Requirements Document

SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES

Principles of Schedule Contingency Management

6494 Latcha Rd. Walbridge, Ohio v: f: Table of Contents

Facilities Planning and Construction (FP&C)

SECTION CONTRACTOR QUALITY CONTROL

PMBOK Guide Fifth Edition Pre Release Version October 10, 2012

REQUEST FOR PROPOSALS PROFESSIONAL SERVICES FOR THE ROOF AND HVAC REPLACEMENT PROJECT PW1320

Exhibit B - A/E Scope of Services (General Contracting Project) State of Ohio Professional Services Agreements for Public Facility Construction

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

Project Management Concepts, Tools & Techniques

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management

PS-01. Constructability Review Guideline

Jacksonville District Master

ATTACHMENT A INFRASTRUCTURE FOR SPACEPORT DEVELOPMENT DESIGN-BUILD CONTRACTOR SCOPE OF SERVICES. Table of Contents

LNG Experience. Owner & Investor Project Management

Sarasota County Procurement Turnaround Story from Collapse to Recovery Ted Coyman, CPPB Procurement Official Sarasota County

Estimating and Scheduling

White Paper April 23, 2018

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter

Ronald J. Rider, MBA

Pricing to Win and Deliver June 19, 2012

Best Practices for Source Selection Planning

Specifications and Drawings

P6 Instructors Sample Presentation

Transit Return on Investment (ROI) Study Request for Proposals (RFP)

Planning and Scheduling Training Program Course Brochure and Competency Matrix

Scientific Services Program (SSP) Bidder s s Conference

STO Navigator Canada Best-Practices Manual

Procurement Guidelines

Scott M. Francis, P.E., PSP

DATA ITEM DESCRIPTION

P6 Version 8.2 to 8.4 EPPM Web Power Sample Point Slide Show

SECTION CONSTRUCTION OPERATIONS AND SITE UTILIZATION PLAN

Module #4 Time Impact Analysis

Connoisseur Solutions Project Procurement Management

Invitation to Bid for Timber Marking Services

Job Order Contracting (JOC) ITB JE Overview August 2016

VFA SAMPLE RFP (DETAILED FACILITY CONDITION ASSESSMENT)

REVISED NEW HANOVER COUNTY OGDEN SKATEPARK SPECIALTY PRE-QUALIFICATION PACKET

Dulles Corridor Metrorail Project. Project Labor Agreement. Executive Summary. 1.0 Background. 2.0 Project labor agreements (PLAs)

TECHNICAL EVALUATION

Ogden Regional Medical Center Courtyard Remodel. Construction Documents. MountainStar Healthcare PROJECT MANUAL FOR

State Historic Preservation Office. Bidding, Contracting, and Construction Guidelines for the Historic Restoration Fund

600 - Phase C Intermediate Review Checklist for the Architect- Engineer

SECTION QUALITY REQUIREMENTS

AACE Planning and Scheduling Professional (PSP) Certification Preparation Training Course Brochure and Competency Matrix

LONG INTERNATIONAL. Long International, Inc Skytrail Drive Littleton, Colorado USA Telephone: (303) Fax: (303)

1.Which of the items listed below is not one of the software engineering layers?

REQUEST FOR PROPOSAL FOR. CONSTRUCTION MANAGER and DESIGN TEAM FOR. Downtown Preservation Project URBAN RE DEVELOPMENT AUTHORITY OF PITTSBURGH

CONTRACT SERVICES PHASE 1: PRE-CONSTRUCTION

Project Scope Management

Estimating in Disaster Recovery. Prof. Ralph V. Locurcio, PE Director, Construction Management Program Florida Institute of Technology

GROUND RULES AND PRICING INSTRUCTIONS:

Subcontractor Project Management Plan

Copyright 2013 Pearson Education, Inc. Publishing as Prentice Hall 5-1

Department of Public Works Division of Engineering. Nassau County, New York

SCADA System Procurement Alternatives

Construction Formwork Inventory Control Tracking System

STO300-3-Day Primavera P6 Planning & Scheduling for Shutdowns, Turnarounds and Outages

CII Performance Assessment Report Industrial Projects Construction Phase

Metropolitan Washington Airports Authority. Request for Qualifications Information. Architectural / Engineering Task Contract Design Services

DESIGN & CONSTRUCTION PHASE COMMISSIONING PLAN TEMPLATE

Meeting future challenges for pharmaceutical plants today

Forsyth County General Services Department Construction Management Division 201 North Chestnut Street Winston-Salem, NC 27101

Request for Proposals (RFP) Information Technology Independent Verification and Validation RFP No IVV-B ADDENDUM NO.

RFP CULVER CITYBUS STOP IMPROVEMENT PROGRAM: BUS SHELTER, BENCH, TRASH RECEPTACLE PROCUREMENT, REMOVAL AND INSTALLATION

Meeting future challenges for pharmaceutical plants today

CITY OF MODESTO REQUEST FOR PROPOSAL (RFP) CONSTRUCTION MANAGEMENT SERVICES FOR STATE ROUTE 99 AND PELANDALE AVENUE INTERCHANGE RECONSTRUCTION PROJECT

JOB ORDER CONTRACTING (JOC)

The United States Air Force Design-Build Plus User s Guide

GENERAL SERVICES ADMINISTRATION

Questions and Answers for RFP No. 010 for the provision of prefabricated pharmacy storage units

GSA proposal Steps & Marketing of a GSA Contract Session 5

Design Consultant Cost Estimating Guidelines

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

UNIFIED FACILITIES GUIDE SPECIFICATIONS

FLORIDA DEPARTMENT OF TRANSPORTATION

ECC ENGINEERING MANAGEMENT STRATEGY WORKSHOP

3,740. Demonstrating Competent Performance SIX EXPERIENCE AREAS. INTRODUCTION What is the Architectural Experience Program?

Date: Telephone: Company Name: Address: City: State: Zip Code: Contact Person: Title: Authorized Signature:

REQUEST FOR PROPOSALS FOR AN INTEGRATED PROJECT DELIVERY METHOD UTILIZING DESIGN/BUILD GUARANTEED MAXIMUM PRICE (GMP) SERVICES

SQAR-1. SUPPLIER QUALITY ASSURANCE REQUIREMENTS for DESIGN AND PROCUREMENT SERVICES Revision Date: 2/1/2018

RFP Professional Staff Augmentation for Information Technology Addendum #1 dated 01/29/2016

REQUEST FOR PROPOSAL PROFESSIONAL SERVICES AUTOMATION SOLUTION. Submittal Date: April 22, 11:00 AM (PST)

Operations Management, 11e (Heizer/Render) Chapter 3 Project Management. Section 1 The Importance of Project Management

The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th

Jobsite Layout Considerations

PROJECT DESCRIPTION. The project is the Spartan Complex Seismic Upgrade, San Jose, California.

1.0 BASIS OF ESTIMATE (BOE) HOW TO

Transcription:

Meeting the Challenge of EPC Project Proposal Schedules Ted Douglas, CCC, PSP Construction CPM Conference 2014 Orlando Florida Project Proposal Schedules Outline of Presentation The Challenge of a Proposal Schedule Sources of Schedule Input & the RFP Role of the Scheduler Shortcuts for Schedule Input CPM Proposal Schedule Review Questions & Final Discussion 1

The Challenge Preparing a CPM schedule that meets the request for proposal (RFP) and represents the project team requirements: Understand the Scope of Work of the project Identify key project tasks & deliverables Minimal proposal team interface or guidance Limited time & quick turnaround to complete What is a CPM Proposal Schedule? A realistic time phased project plan that represents how the project will be built that includes: the entire scope of the project Key milestones and phases specific activities with reasonable durations a logic or sequence of work activities how these various activities interrelate 2

Typical RFP Table Of Contents Part I - The Schedule A. Solicitation/Contract Form B. Supplies or Services and Prices/Costs C. Description/Specs./Work Statement D. Packaging and Marking E. Inspection and Acceptance F. Deliveries or Performance G. Contract Administration Data H. Special Contract Requirements Part II - Contract Clauses Part III - List Of Documents, Exhibits, And Other Attachments Part IV - Representations And Instructions a. Representations, Certifications, and Other Statements of Offerors b. Instructions, Conditions, and Notices to Offerors c. Evaluation Factors for Award Accurate Complete Timely Project Management Assistance Project Proposal Stage The Project Management Team reviews the Request for Proposal (RFP) including: Scope of Work for the Project Design drawings, technical specifications and specified construction materials Prepares the proposal cost estimate While the proposal effort is underway the project CPM proposal schedule is prepared. 3

RFP Schedule Assessment Review the RFP to Assess: Scope of Work (inclusions / exclusions) Key Milestones & Phases Start / Completion/ Period of Performance Interface with Agencies and Regulators Procurement of Materials & Equipment Labor requirements / restrictions i.e. prevailing wages / hiring requirements Site Access and Work Restrictions Influence of Weather on the Project RFP Input for CPM Schedule Review the RFP General Conditions: Scope of Work (inclusions / exclusions) Type of Contract (Fixed price/ T&M/ Other) Site Access and Work Restrictions Liquidated Damages / No Damage for Delay Period of Performance: Start Date & Major Milestones Materials and Key Equipment Requirements Regulatory & Agency Permits / Requirements Design Completion Status 4

CPM Schedule Specification Review the RFP Scheduling Specification: CPM Software Specified Standard Codes / WBS / Activity IDs Frequency Updates & Progress Reporting Schedule Baseline & Change Management Schedule Level of Detail Resources - Crews / Budget Loading On site Scheduler Support Scheduler Qualifications / Prior Experience Maximum RFP Schedule Durations Frequently Scheduling Specifications state that the maximum activity duration cannot exceed 21 calendar days duration except for: Concrete curing Submittal reviews Equipment fabrication & deliveries 5

What Phases are in the Project Scope? Feasibility & Planning Design Procurement Construction Execution *Start-up & Operations CPM Schedule Detail Good work, but I think we need a little more detail right here. 6

EPC Project Procurement Phase Normally at 90% design completion, the owner/ CM / project management team: prepares the project for procurement prepare the subcontracts, bid packages pre-qualify vendors, suppliers, and trade contractors recommends modular, pre-assembly, stick build or a combination of construction methods RFP Construction Execution Planning How will the project be executed? Direct hire or CM (subcontractors) Construction phasing Responsibility matrix contractor interfaces Site assessment Testing and Start-up planning High level schedule (timeline) at this phase 7

Project Site Location The Project Site will have an influence on the CPM Schedule: Remote Site Location = Logistics Vendor & Design Support Sources Temporary Facilities / Utilities Site Access: Badging / Craft Parking Work Restrictions: Hours of Work Weather / Temperature / Environmental Equipment, Materials & Supplies Storage Project Site Planning site access and egress site drainage temporary facilities: buildings; plumbing; power staging areas for rigging, pre-assembly & field erection work lay-down areas / fabrication shops: avoid double handling Environmental, safety and security 8

Role of the Scheduler To prepare a CPM schedule that meets the request for proposal (RFP) and represents the project team proposed plan: Entire scope of work for the project Identify key project milestones Phases / key tasks & deliverables Start Date / Completion Date Contract Period of Performance Important Interfaces: Design & Procurement Role of the Project Scheduler o The Project Scheduler is designated to develop & maintain the construction progress schedule. o The Project Scheduler shall be present at the Preconstruction Schedule Meeting, and shall attend all meetings, which may affect the CPM schedule. o The Project Scheduler shall be prepared to discuss, in detail, the proposed sequence of work and methods of operation. o The Project Scheduler shall be knowledgeable of the status of all aspects of the work throughout the length of the Contract, including but not limited to: original contract work, additional work, new work, and changed conditions of work. 9

CPM Schedule Prep Shortcuts Create a CPM proposal schedule faster? Stick Build the proposal schedule (activity by activity & link by link) Generic Schedule Templates Similar Historic Projects Modular CPM Series Generic Schedule Templates Accurate Complete Timely Project Management Assistance 10

Similar Historic Projects Historical Data: Construction phases compared for similarities: Example: TVA Steam Plants for AFB Project: Site & Coal Handling Facilities; Powerhouse; Water Treatment Plant; Transformer & Switch Yards Other Projects TVA Nuclear Power Plants Construction Chemical Weapons Demilarization Projects DOE Management & Operations Program Modular CPM Series Modular CPM predefined strings of activities Used for a Specific Business Line Created detailed CPM at the proposal stage: Site Prep & Common Facilities; Critical Equipment: GTG; HRSG; & STG Balance of Plant Equipment; i.e. Switch Yard Vendor Designed (Pre-engineered) Buildings Other Modular Series include: Support Strings: Engineering/ Procurement General Design: By Discipline / By System Procurement Durations / Dates for Fab & Delivery ~ Stephen Goodman Modular CPM, AACE 1992 11

Why a CPM Schedule Review? The primary objective of a proposal schedule review is to determine if the project CPM schedule is accurate, logical and achievable and meets all the requirements of the RFP. Proposal CPM Schedule Review Compare the RFP & CPM Schedule to Assess: Complete Scope of Work (inclusions / exclusions) Reasonable Work Sequence & Activity Durations Adequate Procurement lead time for Materials & Equipment Interface of craft trades & engineering disciplines Site Access and Work Restrictions Impacts of Weather on the Project 12

Review - Means, Methods, Materials Construction Means Availability of skilled labor force Labor intensity of installation (congestion) Accessibility to project site Construction Methods Contracting strategy Biddable & Buildable Start-up and Commissioning Construction Materials Fabrication requirements & Time Availability & Delivery when required Proposal CPM Schedule Review Meets RFP scheduling specification Complete scope of project Key Milestones Sequence of work phases Reasonable activity/ phase durations Inter-discipline coordination Delivery of key equipment & materials Impact of weather on project 13

CPM Proposal Schedule Submittal The CPM proposal schedule submittal must be in accordance with the RFP scheduling specifications: Schedule Format: CPM / Bar Chart / etc. Level of detail and specified activity durations Graphics / Layouts / Listings / Resource Curves Narrative /Basis of the Schedule Electronic (CD) Format Project Proposal Schedules Summary of Presentation The Challenge of a Proposal Schedule Sources of Schedule Input & the RFP Role of the Scheduler Shortcuts for Schedule Input Proposal Schedule Review Questions & Final Discussion 14