Tunnel Boring Machines

Similar documents
Experts in tunneling with Tunnel Boring Machines

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

Tel: Neil: Tony: Website:

TBM rescue projects using shafts and ground freezing

TBM Selection and Specification

Introduction to Tunnel Construction

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Hardrock Tunnel Boring Machines

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL

Ground Freezing for Tunnel, Shafts, and Adits

Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P.

Diaphragm wall Construction

COMMUNITY BOARD EIGHT

Tunnels. Introduction in Shield tunnelling Pipe jacking & tunnelling Slurry & hydroshield Slurry versus EPB Principles of support pressure

Pipe Jacking. Progress is built on ideas.

Grouting Bilfinger Spezialtiefbau GmbH

Shield TBM risk model based on Bayesian networks applicable in design stage

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

Construction Technology B (CON4313)

EOSC 547: Tunnelling & Underground Design

Pipetron Tunnel Construction Issues

Pipejacking Tunnel Boring Machines TBMs. Michael Frenke, LOVAT Inc.

UNDERPINNING A CRANE FOUNDATION

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

Tunnel. Immersed Tunnels

1 Introduction. Figure 1-1 Japanese scheme for the exploitation of underground space in an inner-city area [155]

SEMINAR. Introduction to Continuous Flight Auger (CFA) piling Thursday 21/8/2013. Facilitator: Martin Larisch

Mechanised Shield Tunnelling

ISM 2007 Toronto, Canada Horst Aschenbroich Dipl. Ing. President & CEO of Con-Tech Systems LTD. Titan Hollow Bar

Pipe Jacking. Japan Sewage Works Association

Design and Construction Issues of the Soft-Eye Headwall for Brisbane AirportlinkM7 s 12.48m Diameter Tunnel Boring Machines

Tunnel Boring Machines used for Irrigation in Andhra Pradesh, India. D.Harding 1 1 The Robbins Company, Solon, Ohio, USA

Qatar Rail Doha Metro

INSIDE. 01 / Doors and windows that are misaligned. 02 / Cracks in the sheetrock. 03 / Doors and windows that are sticking. 04 / Sloping of the floor


DISCUSSION ON UNDERPINNING (28/3/12)

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

Long-Term Relations Between Joint Venture Partners A Supplier s Perspective.

TRANSPORTATION RESEARCH FORUM March A State-of-the-Art of Underground Construction In Urban Areas

TRENCHLESS INSTALLATION OF ROAD DRAINAGE & SERVICE DUCTS

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

Previous Tunnel News

Presented By: Brenden Tippets, Project Executive

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL

2

JACKING LARGE TUNNELS BENEATH ACTIVE RAIL TRACKS. Hatch Mott MacDonald, 177 Milk Street, Boston, MA

USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA. Miranda Roman D. *, LaFaso Edward

TRENCH SAFETY TRAINING

ROTARY DRILLING TECHNIQUES LARGE DIAMETER

4th International Engineering and Construction Conference - July 28, 2006

TRENCHLESS TECHNOLOGY. Department of Civil Engineering.

Australasian Society for Trenchless Technology Standard for Microtunnelling & Pipe Jacking

ITEM 460 REINFORCED CONCRETE PIPE Description. This Item shall govern for the furnishing of reinforced concrete pipe.

Hudson River Tunnels, Mega Projects, and Risk A Designer s Perspective

17/03/2017 CONTENTS. Real Cases Studies in the Region for Pipelines Inspection & Rehabilitation. Introduction CONTENTS. Introduction / Cont.

Behavior of Surrounding Soil during Construction and Its Countermeasures Using Pipe Jacking Method in Deep Strata

From Colonia Jardín to Cuatro Vientos

Energy & Data Transmission Systems for Underground Applications

Performance review of a pipe jacking project in Hong Kong

DESIGN. DEVELOP. DELIVER. CAPABILITY STATEMENT

SECTION GRAVEL PACKED WATER WELL

IMPACTS OF TUNNELS IN THE UK. Non-technical summary

Design Data 4. Jacking Concrete Pipe

Concrete Pipe Jacking

Building pit District adjacent to St.Katharinenkirche Hamburg, Germany

Take Me to the Other Side:

Properties of Concrete. Properties of Concrete. Properties of Concrete. Properties of Concrete. Properties of Concrete. Properties of Concrete

Status Data Acquisition in TBM tunneling. Lars Babendererde

SEATTLE S BRIGHTWATER UNDERGROUND CONVEYANCE SYSTEM TUNNELING & UNDERGROUND CONSTRUCTION

Tunnelling under the Fraser River at 6 bar Design and Construction of the Port Mann Main Water Supply Tunnel

Promoters. Presentation. Tunnel. Tim Smart Head of Engineering & Operations. 20 th October

Wastewater Capital Projects Management Standard Construction Specification

Ground Improvement. Cutter Soil Mixing Multi-Axis Soil Mixing Deep Soil Mixing Jet Grouting Vibro Systems Specialized Geotechnical Grouting

Design Data 4M. Jacking Concrete Pipe

The 114m Preston Tunnel and Rising Main improvement scheme has been completed as part of United Utilities

Principles for Tunnel Design. 20th to 21st April 2017 Kuala Lumpur

Rapid Axial Load Testing of Drilled Shafts

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING

5-20 FOUNDATION REPORT/GEOTECHNICAL DESIGN

Progress update (November to March) 03/23/2009 2

Hydraulic cutting units

ONSITE ASSEMBLY AND HARD ROCK TUNNELING AT THE JINPING-II HYDROPOWER STATION POWER TUNNEL PROJECT

Reaming Tunnel Boring Machine Undercutting Technique

Trenchless Pipeline Crossings

Urban EPB Tunneling in Limited Space: A Case Study of the San Francisco Central Subway Project

Excavation Support Specialists

Desalination Plants. IMIA Conference, Gleneagles, 2008 WG 57 (08) Prepared by:

Hydraulic Rock Storage an efficient system for large grid scale storage

SPECIAL SPECIFICATION 4900 Sacrificial Cathodic Protection Pile Jacket

Walls generally range from 600 to 1500 mm thickness, in wide between 2000 and 3500 mm and can be excavated to depths of 60m or more.

Design and development of a decline shaft through poorly consolidated Kalahari deposits at Ghaghoo Diamond Mine.

REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID

METHOD STATEMENT for INSTALLATION OF MICROPILE

Installation Guidelines for Flygt Pumps Pump Anchoring Recommendations

Transcription:

Tunnel Boring Machines IMIA WGP 60 Michael Spencer, Zurich London (Chairman) Alessandro Stolfa Generali Heiko Wannick Munich Re Ronan Gallagher Allianz John Forder Willis Beat Guggisberg Allianz Eric Bentz SCOR Steve Cross Zurich Chris Blueckert Zurich Presented by Michael Spencer IMIA Conference, Istanbul 29 th Sep. 2009

History 1825 Sir Marc Isambard Brunel Tunnelling Shield Rotherhithe Tunnel 5 floods in all 2

Early Soft Soil Tunnels Early Soft Soil Tunnels London Underground late 19 th Century 3

Hard Rock Machines Henri-Joseph Maus Mountain Slicer 1845 failed Wilson Patented Stone Cutting Machine 1853 failed James Robbins 1950 first successful machine used in Shale and worked 10 times faster than conventional methods 4

Soft Rock Machine 5

Hard Rock Machine 6

Hard Rock Machine 7

Largest Machines To Date 8

Trailing Equipment 9

Start of the Art Maximum diameters Slurry Machine 15.43 M EPB 15.2 M Maximum Water Head above 4.5 bars (45m head of water) Marmaray 8 bars Hallandsas 8 bars Maximum Speeds Closed Mode 0-8cm/min 10

Operational Parameters Speed of the Shield Torque of the cutter head Thrust of the jacks Pumping flows in a slurry machine Viscosity of excavated soil in an EPB Quantity of soil excavated Changes in the chracteristics of the soil granularity/ viscosity colour 11

Loss Exposures TBM Fabrication and delivery to site TBM Assembly at site Excavation of the tunnel Disassembly and reshipment 12

Manufacture / Fabrication Manufacturing and delivery time up to 12 months new less for refurbished machines Main perils fire flood cat nat Transport marine, air, land is it covered in the Car policy? Land routes to some site especially hydro projects are often difficult Suppliers extensions 13

Assembly and Testing At site Up to 3 months, storage much longer in case of delays Lifting and lowering into position Flooding fire and theft Landslide and collapse of ground around the machines Faulty workmanship skilled technicians (preferably from the suppliers especially during testing) OFTA Onsite first Time Assembly Supplier Gurarantee for 50 or 100m 14

TBM Before excavation 15

Excavation Works Flood Fire and Explosion Tunnel Collapse Unexpected ground conditions Wrong Machine Inexperience of the operator Machinery Breakdown Breakthrough 16

Loss Prevention Mechanical and electrical Breakdown Hydraulic Oils Materials non toxic and flammable Contact surfaces sharp edges and hot surfaces Rupturing of pipes and hoses Safe access to the cutter head Handling of heavy loads Pumping equipment Control systems 17

TBM Launch and Arrival Launch normally into a diaphragm wall or secant bored pile wall Sealing Ring gasket system (lip seals) and soil/rock sealing block (jet grouting or lean concrete secant bored piles) Arrival the most critical as the whole tunnel can be flooded Flying launch steel structure and a hydraulic unit with hollow piston jacks faster and safety advantages 18

Launch and Arrival 19

TBM Affect of Third Party exposures Damage Category Severity Typical Damage 0 Negligible Hairline Cracks 1 Very Slight Fine Cracks 1mm 2 Slight Cracks to 5mm 3 Moderate Cracks 5-15mm 4 Severe Cracks 15-25mm 5 Very severe Major repairs 20

TBM Prediction of Settlement For TBMs zone of influence is centred along the centreline of the tunnel = depth of the invert below ground level on either side of the centreline Damage caused by rotation, angular strain, relative deflection, tilt, horizontal strain extent depends on the condition of the existing buildings and structures 21

Insurance recommendations Period Of Cover Check whether cover is required only on site or for storage transport and fabrication Excavation cover Check equipment is adequately protected against fire. Are there adequate safety measures in place taking into account the ground conditions? Ancillary covers: Is cover for abandonment and recovery expenses included? What is the cover for consumables? Is cover required for machinery breakdown? What is the basis of indemnity? 22

Losses 1987 Tooting Bec Open face boring machines compressed air Inundation requiring ground freezing to repair 1990 Great belt Link Flood to closed face machine left open for maintenance to the face 2 machines underwater Fire to one machine at the end of the drive Socatop fire aboard a service train for the TBM 23

Socatop 24

Great Belt Link 25

Machinery Breakdown Main losses are to Main bearing Motor Breaker Gripper and Pad 26

Conclusion The TBM has revolutionised the construction industry Developments in new machines may present challenges TBMs are varied and must match the conditions in which they need to work Commercial considerations may affect the risk levels an underwriter may face There is a lack of information about losses Closer cooperation between tunnelling machine suppliers contractors and the insurance industry The very nature of these machines and the conditions in which they work means these should only be underwritten by specialist underwriters 27