Regional Transmission Organizations. D. William VanderLaan Illinois Commerce Commission January 30, 2014

Similar documents
SPP at a Glance. Located in Little Rock. Approximately 600 employees

The Role of the ISO/RTO in Today s. Robert B. Burke Principal Analyst ISO New England Inc.

Energy Markets - The Basics

Wind Power Transmission Case Studies Project National Wind Coordinating Committee

Draft Whitepaper to Platte River Board of Directors

INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO)

PROPOSALFOR INCLUSION OF A TRANSCO INCLUDING ENTERGY WITHIN THE SPP RTO

Mountain West Transmission Group Frequently Asked Questions Updated through September of 2017

The Virtues of A Virtual RTO

2016 Summer Reliability Assessment

Federal Energy Regulatory Commission Working Paper on Standardized Transmission Service and Wholesale Electric Market Design

Business Practices for. Schedule 21-ES. (Modifications Issued on August 11, 2016)

Regional Cooperation of US States on Electric Transmission Issues

PJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017

Introduction to RRG Drafting Team Proposal

MARKET MONITORS: AN INSTITUTIONAL INNOVATION IN ELECTRICITY REGULATION

Pseudo-Tie Congestion Overlap

Notice of Attachment H Transmission Owners Stakeholder Process for Order No Interregional Cost Allocation Proposals (June 10, 2013)

DRAFT FOR DISCUSSION PURPOSES PROPOSED STRAWMAN PROPOSAL IN RESPONSE TO ORDER 890

The Value of Independent Regional Grid Operators. a report by the ISO/RTO Council

Critical Actions Necessary for Effective Market Monitoring

BEFORE THE PUBLIC SERVICE COMMISSION STATE OF MISSOURI

Independent Transmission Organization. Stakeholder s Meeting December 2006

Energy Imbalance Market Overview

LES Standards of Conduct Implementation and Compliance Procedures

ISO New England Available Transfer Capability. Implementation Document. Version 1.0

2015 ISO/RTO Metrics Report. Summary. November 2015

Capacity Market. Overview RPM Capacity Market. Market Design

Gas Prices and Offer Price Flexibility in Other ISO/RTO Markets

144 FERC 61,056 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Parts 35, 101 and 141

Joint and Common Market ITEM 4 PSEUDO TIES

Generation Capacity Mechanisms and Resource Adequacy Planning

Policy and Regulatory Approaches to Grid Integration of Renewable Energy in the US

The Polar Vortex and Future Power System Trends National Coal Council Annual Spring Meeting May 14, 2014


FERC Policy Goal. Wholesale Customers Benefit through Properly Structured, Competitive, and Reliable Markets

ATTACHMENT C Methodology to Assess Available Transmission Capability

VALUE OF YOUR WIND PPA

Outage Coordination Training MISO Training

Capacity Deliverability. May 27, 2015 MISO-PJM JCM

Solar Integration into the PJM Grid

Interface Pricing Approach Whitepaper May 2015

BILLING CODE P DEPARTMENT OF ENERGY. Federal Energy Regulatory Commission. 18 CFR Part 40. [Docket No. RM ; Order No.

NERC Reliability Functional Model Technical Document Version 5

Updated January 20, 2012 VERMONT ELECTRIC POWER COMPANY, INC AND VERMONT TRANSCO LLC

PJM PROMOD Overview. August 1, PJM

LOAD SERVING ENTITIES PJM REGION

Joint Operating Agreement Between the Midcontinent Independent System Operator, Inc. And PJM Interconnection, L.L.C. (December 11, 2008)

Efficient Electricity Market: Overview of Texas

Risk-Based Registration Technical Justification. August 26, 2014

Technical Assistance between ERERA, WAGPA, NARUC, and OPSI Activity No. 2; Abuja, Nigeria June Overview of OPSI

Summary of 2016 MISO State of the Market Report

Murky Markets: A Review of FERC s Determination of Submarkets in Wholesale Electric Power Mergers

Appendix 1 PRELIMINARY DELIVERABILITY BASELINE ANALYSIS STUDY REPORT

2750 Monroe Blvd Audubon, PA

Evolution of the Grid in MISO Region. Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017

Future Electricity Markets. Dr. Daniel Matuszak Clean Coal and Carbon Management Office of Fossil Energy U.S. Department of Energy May 24, 2016

DECLARATION OF AUTHORITY. This DECLARATION OF AUTHORITY ( Declaration ) is a declaration and certification made on by and between the following:

Winter Reliability Assessment

EVALUATION OF MIDWEST ISO INJECTION/WITHDRAWAL TRANSMISSION COST ALLOCATION DESIGN. Prepared by Scott Harvey and Susan Pope

Proposed Procedures to Deliver External Capacity between MISO and PJM

Market-Based Policy Concepts for Encouraging Fuel Diversity and Retaining Baseload Zero-Carbon Resources. December 4, 2014

MISO SPP Interregional Stakeholder Advisory Committee. April 8 th, 2014 Carmel, IN

Transmission Planning Strategies to Accommodate Renewables

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

Review Transmission Access Charge Structure. Issue Paper

Issues in the Determination of Tariffs for Ancillary Services

Renewable Electricity Futures Study

Changes To The FERC s Market-Based Rates Requirements

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. Integration of Variable Energy Resources ) Docket No. RM

2014 State of the Market

June 21, Southwest Power Pool, Inc., Docket No. ER Order No. 755 Compliance Filing

2018 Open Access Transmission Tariff (OATT) Rate Case

NBP (ATG) IR 01 March 5, Reference: NBP 18.01

142 FERC 61,070 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

144 FERC 61,053 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ON REHEARING AND COMPLIANCE. (Issued July 18, 2013)

State of the Market Report for PJM

Third Generation California Electricity Market Design

STANDARDS OF CONDUCT IMPLEMENTATION AND COMPLIANCE. Standards of Conduct for Transmission Providers Pursuant to FERC Order No. 717

Wes Yeomans Vice President Operations Management Committee May 31, 2017 COPYRIGHT NYISO ALL RIGHTS RESERVED

OVERVIEW OF REGIONAL ELECTRICITY MARKET INITIATIVES IN THE U.S.

Policy Direction for Alberta s Capacity Market Framework

IMM Quarterly Report: Fall 2017

NYISO Governance Summary of Sector Definitions and Related Terms

2018/2019 RPM Base Residual Auction Planning Period Parameters

Results and Assumptions For Single Economic Dispatch Production Cost Study PROMOD Component

STRATEGIC O V E R V I E W

Coordinated Procurement Transmission in the Northeast

Mexican Electricity Reform

STANDARDS OF CONDUCT IMPLEMENTATION AND COMPLIANCE. Standards of Conduct for Transmission Providers Pursuant to FERC Order No. 717

Getting to 50 GW? The Role of FERC Order 841, RTOs, States, and Utilities in Unlocking Storage s Potential

PLATTE RIVER POWER AUTHORITY OPEN ACCESS TRANSMISSION TARIFF. May 1, 2009

INTERSTATE TRANSMISSION VISION FOR WIND INTEGRATION

Dispatch Signal & Locational Marginal Pricing (LMP)

September 9, The documents submitted with this filing consist of this letter of transmittal and all attachments hereto, and the Agreement.

Transmission Expansion and Interconnection Manual. June 2017

Update on FERC, NERC, DOE & Congress John P. Hughes President & CEO Electricity Consumers Resource Council Washington DC

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) PJM Settlement, Inc. ) Docket No. ES )

NISOURCE INC. TRANSMISSION PROVIDERS WRITTEN PROCEDURES IMPLEMENTING THE FERC STANDARDS OF CONDUCT Pursuant to 18 CFR Section 358.

LOLE is expressed as hours per year with the usual target criteria being (0.1 days/year) or 1- day in 10-years MISO Tariff: Module E-1 - The

Transcription:

Regional Transmission Organizations D. William VanderLaan Illinois Commerce Commission January 30, 2014

History of Regional Transmission Organizations (RTOs) RTOs grew out of FERC Order Nos. 888/889 where the FERC suggested the concept of an Independent System Operator (ISO) as one way for existing electricity power pools to satisfy the requirement of providing nondiscriminatory access to the transmission system. FERC Order No. 2000 encouraged the voluntary formation of RTOs to administer the transmission grid on a regional basis and outlined twelve characteristics and functions that an RTO must satisfy. As of 2012, there are nine ISO/RTOs operating in North America. The Midcontinent ISO ( MISO ) was established in 1998 as an ISO and was approved as the nation's first RTO by FERC in 2001. PJM evolved from a tight power pool and was designated an RTO by the FERC in 2001. 2

FERC Order Nos. 888 & 889 FERC issued Order Nos. 888 & 889 on April 24, 1996. Intended to establish competition in the generation market and enforce fair access of the transmission system by external users. Order Nos. 888 & 889 marked the point where the trading of electricity gained a firm foothold. Order No. 888 was the Standards of Conduct Order, requiring, among other things, the functional separation of power schedulers and marketers within vertically integrated utilities from their company s transmission operations and functions. Order No. 889 was the Oasis Order, detailing exactly how all participants in the electricity market should interact with transmission providers including affiliated power marketers wanting access to their own parent company s transmission system. 3

FERC Order No. 2000 Issued by the FERC on December 29, 1999. Order No. 2000 codified what it means to be an RTO including its minimum characteristics, functions and ratemaking policy. An organization wanting to achieve RTO status must petition the FERC for approval and meet 4 minimum characteristics and 8 minimum functions. RTO participation is voluntary. RTOs only have operational control of a utility s transmission facilities. Characteristics of an RTO 1. Independence from market participants; 2. Appropriate scope and regional configuration; 3. Possession of operational authority for all transmission facilities under the RTO's control; and 4. Exclusive authority to maintain short-term reliability. 4

FERC Order No. 2000, continued. Functions of an RTO 1. Administer its own tariff and employ a transmission pricing system that will promote efficient use and expansion of transmission and generation facilities; 2. Create market mechanisms to manage transmission congestion; 3. Develop and implement procedures to address parallel path flow issues; 4. Serve as a supplier of last resort for all ancillary services required in Order No. 888 and subsequent FERC orders; 5. Operate a single OASIS site for all transmission facilities under its control with responsibility for independently calculating TTC and ATC; 6. Monitor markets to identify design flaws and market power; and 7. Plan and coordinate necessary transmission additions and upgrades. 8. Interregional coordination for reliability and transmission service. 5

U.S. Regional Transmission Organizations 6

MISO MISO was established in 1998 as an ISO and was approved as the nation's first RTO by FERC in 2001. Headquartered in Carmel, Indiana with operation control centers in Carmel and Eagan, Minnesota. Developing an operations center in Little Rock, Arkansas. Generation capacity of 196,824 MW (reliability) and almost 66,000 miles (145,200 km) of transmission. Launched the operation of its day-ahead and real-time energy markets in 2005. Currently wholesale electricity market includes 362 participants that serve over 48 million people, with $18.4 billion annual gross market charges. Launched the operation of its ancillary services markets in 2009, which provide both energy and operating reserves, as well as regulation and response services that support reliable transmission service. MISO operates as reliability coordinator and oversees the regional planning and expansion of the transmission grid within the MISO footprint. 7

PJM PJM was established in 2001 and is headquartered in Valley Forge, Pennsylvania. PJM currently serves over 61 million customers. PJM currently includes more than 830 companies and 1,376 generation sources, which provide 183,604 megawatts of generating capacity. PJM oversees 62,556 miles (146,423 km) of transmission lines and over 6,038 transmission substations. PJM delivers over 832 million megawatt-hours of electricity annually. PJM operates as reliability coordinator and oversees the regional planning and expansion of the transmission grid within the PJM footprint. 8

What are the Benefits of an RTO? Non-Discriminatory Access to the Transmission System. Facilitated through the use of an Open Access Transmission Tariff (OATT) that is governed by FERC and administered by the RTO. Efficient market operations. This means operating energy, capacity, and ancillary service markets using low-cost unit commitment, dispatch and congestion management techniques. Larger, Competitive and More Liquid Energy Markets. RTO rules encourage greater market participation, greater liquidity and increased market options for energy buyers and sellers. Coordinated Regional Planning. RTO-administered integrated transmission system planning with regional expansion needs and plans is intended to produce greater transmission benefits at a lower cost than a utility-by-utility process. 9

RTO Benefits, continued Improved Reliability. This is typically achieved through efficient resource sharing and formalized rules for handling seams issues with neighboring RTO and non-rto entities. Competitive Markets. RTOs employ an independent market monitor that is charged with assessing market competitiveness and preventing the exercise of market power by RTO members. Alternative Resource Options. RTOs have recently pushed hard to integrate alternative resources, such as demand response and renewable energy, in the RTO s resource mix. Risk Management Tools. RTOs provide market participants with various hedging/financial products, including financial transmission rights, intended to allow market participants to mitigate transmission congestion risks. 10

Quantitative Benefits of RTOs? PJM claims that its services provide regional savings benefits of more than $2 billion annually including savings from energy production cost of $340-$445 million annually. MISO claims total annual economic benefits in the range of $1.8- $2.4 billion, including an estimated $180-$200 million annually for its centralized dispatch of energy operations. There is some dispute concerning the valuation of these RTO benefits and cost savings. However, it is clear that most RTO stakeholders see positive benefits from participation in an RTO. There are still areas where market design and operational considerations could provide even greater benefits to RTO stakeholders. 11

Seams Issues between PJM & MISO MISO and PJM both operate very large electricity markets and share a common border. The border of PJM and MISO is jagged and runs through the middle of Illinois. This seam raises efficiency questions and operational concerns. The FERC conditioned the initial configuration of PJM and MISO on the seams issues between PJM and MISO being addressed by a Joint and Common Market (JCM) that would allow both markets to operate as if one large market. The JCM was intended to address issues such as joint-regional transmission planning, economic dispatch, data exchange, outage and market coordination, and price transparency/convergence between the two RTOs. 12

Seams Issues between PJM & MISO RTOs, some Stakeholders and the FERC lost their enthusiasm for a JCM and removed the JCM obligation from MISO and PJM. Recent complaints filed by utilities in both PJM and MISO regarding an alleged lack of interregional planning and capacity portability between PJM and MISO have resurrected both concerns and efforts regarding the development of a PJM-MISO JCM. The FERC issued an order finding that the issues raised in the interregional planning complaint were premature and overlapped with issues in another FERC docket (Order No. 1000) and has effectively held the complaints in abeyance until those issues are resolved. The FERC has also directed the two RTOs to hold discussions and develop proposals to address JCM issues. FERC Staff was also ordered to participate in the discussions and monitor their progress in resolving the JCM issues. 13

Tres Amigas SuperStation Located in Clovis, New Mexico. Will connect the Eastern Interconnection, the Western Interconnection and the Texas Interconnection via three 5 GW superconductive high-voltage DC transmission lines. ERCOT currently has 5 DC ties to the two interconnections, totaling 1,100 MW. The Tres Amigas design is scalable to 30 GW. Primary purpose is to serve as a power market hub and to facilitate the transfer of renewable electricity among the three interconnections. Will also increase reliability of the U.S. grid. Cost estimates vary between $1-$2 billion. Project was initiated in 2009. Current expected commercial start-up date is 2016. 14