FY Virginia Beach Budget Response to Council Questions

Similar documents
FY STORMWATER UPDATE TO CITY COUNCIL

PROPOSED STORMWATER PROJECT IMPLEMENTATION PLAN. o Execution of New and Expanded Flood Control Projects o Program Options

PRINCESS ANNE DISTRICT STORMWATER PROJECTS


ASHVILLE PARK STORMWATER UPDATE

Office of the City Auditor. Audit of Stormwater Management Utility

Modified FY ,100, ,329,791

Storm Water & Drainage Projects 2011 Program Update

Storm Water and Sanitary Sewer

PROTECTING OUR WATERWAYS: STORMWATER POLLUTION REDUCTION EFFORTS

Audit of Stormwater Management Utility

Stormwater Control and Treatment

City of Fairmont Storm Water Pollution Prevention Plan (SWPPP) January 23, 2017

PLEASE do not reuse without permission from NYCDEP. [Please notify Pinar Balci and Alan Cohn

The newly updated and comprehensive SWMP shall:

PINELLAS COUNTY RESTORE ACT DIRECT COMPONENT PROJECTS IDEAS SUBMITTED TO PINELLAS COUNTY

III. INVENTORY OF EXISTING FACILITIES

FY CAPITAL IMPROVEMENT PROGRAM MID-YEAR STATUS REPORT

CITY OF SAFETY HARBOR ENGINEERING

SURFACE WATER UTILITY FEE

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

Rocky Hill. Challenges

What is a stormwater utility fee?

Municipal Separate Storm Sewer Systems (MS4) Implementation. Craig Carson Montgomery County Department of Environmental Protection

POLICY FOR NATURAL RESOURCE MANAGEMENT AREAS

SW-74 SERENOVA PRESERVE SITES 2, 3, 4, 8 MITIGATION PLAN

East St. Tammany Storm Surge Protection Project Request

BCWMC Capital Improvement Program (approved April 19, 2018; pending minor Plan amendment)

SECTION 7.0 PROJECT FEASIBILITY, ENGINEER S RECOMMENDATION AND DESIGN ISSUES NEEDING RESOLUTION

The Village of Wellington NPDES Guidance/Reference Document

Jacobi, Toombs, and Lanz, Inc.

Appendix D - Evaluation of Interim Solutions

V. DRAINAGE IMPROVEMENTS

FY 2015 Project Rollout

Rainy Season Preparation & Storm Channel Maintenance

AGENDA. 1) Introductions 6:30 (10 min) 2) Review Meeting Goals 6:40 (5 min)

PUBLIC WORKS. Public Works

Newport Bay Watershed Executive Committee

Sea Level Rise Adaptation Strategy for San Diego Bay. Brian Holland, AICP, Climate Program Manager City of San Diego EESTF June 29, 2011

Cokato Lake (86-263) Wright County. Hydrologic Investigation

Appendix C. BMPS, Measurable Goals, and Implementation Schedule

Kane County Natural Hazards Mitigation Committee

Inflow Design Flood Control System Plan for Louisa Generating Station CCR Impoundment. MidAmerican Energy Company

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY

Verbal Interim Progress Report Jim Beever October 25, 2017

Virginia Department of Transportation Pollutant Discharge Elimination System

Public Utilities - Sewer

DALLAS FLOODWAY PROJECT

Stormwater Improvement for St. Armands Key

Lessons [being] learnt 2016 Flood in Cedar Rapids. Sandy Pumphrey Project Engineer II Flood Mitigation

EL PASO WATER - PUBLIC SERVICE BOARD REQUEST FOR SUBMITTALS RFS June 27, 2017

KRISTOPHER J. KRZYSTON, CEI, CEM

ALMY POND TMDL MANAGEMENT PLAN

King County Flood Control District approves grants for flood prevention projects Regional projects to benefit from district funds

Development of a Stormwater Management Plan for Phase II Small MS4s Insight and Innovation

STORMWATER PROGRAM MANAGEMENT PLAN FOR TOWN OF CAPE ELIZABETH, MAINE

SECTION 6: MITIGATION STRATEGIES

Coal Combustion Facility Assessment Report. October 20, 2010

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432

Suffolk Downs Redevelopment. Appendix G: Stormwater Management Supporting Documentation

ENGINEERING REPORT ANALYSIS OF CLOSURES. HOUSATONIC RIVER and NAUGATUCK RIVER FLOOD PROTECTION PROJECTS SECTION 1. ANSONIA and DERBY, CONNECTICUT

Wakefield Lake TMDL Public Meeting 3/17/2014. Jen Koehler, PE Barr Engineering

Synergy: Addressing Combined Sewer Overflows and Nitrogen

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Conditions of Section 401 Certification for Nationwide Permits and General Conditions. General Condition 12 (Soil Erosion and Sediment Controls)

Watershed master planning, City of Griffin, Georgia, USA

6 Preliminary Assessment of Construction Method and Constructability Issues

Holly Swartz and Jason Shirey

MODEL Stormwater Local Design Manual. City of Centerville

REQUEST FOR CONSTRUCTION BIDS May 23, 2017

Richard V. Busche, P.E., CFM

Princess Anne Plaza and The Lakes Neighborhoods Stormwater Management System Flood Mitigation Plan

Reducing Flood Risk in Toronto. David Kellershohn, M.Eng., P. Eng. Toronto Water, City of Toronto

SBSA. DATE: 31 May 2016 HILL AIR FORCE BASE CEN/CEIE PLAN REVIEW CHECKLIST FOR NEW DEVELOPMENT AND REDEVELOPMENT CONSTRUCTION

Information for File #MVP MVM

ISO-9001:Quality Management System Progress Report

Bijou Area Erosion Control Project

HYDROLOGY STUDY LA MIRADA BOULEVARD La Mirada, California

SFPUC Flooding Workshop Tuesday, February 9, 2016

CHESAPEAKE BAY TMDL ACTION PLAN ( MS4 General Permit)

San Antonio Water System Mitchell Lake Constructed Wetlands Below the Dam Preliminary Hydrologic Analysis

Greenfield Pond B Rehabilitation

PRELIMINARY DRAINAGE REPORT NEWCASTLE FIRE STATION OLD STATE HIGHWAY

Stormwater Local Design Manual For Houston County, Georgia

BOROUGH OF HIGHLANDS STRATEGIC RECOVERY PLANNING REPORT. September 2014

Appendix J. Existing Efforts for Identifying Multi-Benefit Projects

Chapter 4. Drainage Report and Construction Drawing Submittal Requirements

Extended Detention Basin Maintenance Plan for [[== Insert Project Name ==]]

TOWN OF KILL DEVIL HILLS, NORTH CAROLINA ANNUAL PROGRESS REPORT ON ADOPTED HAZARD MUTIGATION PLAN COMMUNITY #

10:00 AM, Wednesday, April 8, 2015

AGRICULTURAL DRAINAGE

MSD Integrated Watershed Management Planning Approach to Achieve Sustainable Communities

City of Virginia Beach Urban Tree Canopy Implementation Plan. Susan French, City Arborist Barbara Duke, Senior Planner

For Public Input Period

New Castle County, DE. Floodplain Regulations

ACTION PLAN FOR RETROFITTING STRUCTURAL BEST MANAGEMENT PRACTICES Storm Water Management Plan

Coastal Restoration and Protection Projects - SLFPA-East and Vicinity

Model Results Operation and Maintenance (O& M) Results Cost-Benefit Analysis Results Conclusions

Transcription:

FY 2018-2019 Virginia Beach Budget Response to Council Questions Question Number: FY19 70 Question: Building on my question number FY19 69 above, under the column heading Budgeted for FY 2019 please provide the planned obligation and expenditures by fiscal year and the material deliverables for those obligations by fiscal year. Date Requested: April 11, 2018 Requested By: Councilman Moss Department: Public Works-Storm Water Response: We have updated the Capital Improvement Program for / FY 2023-24 Summary of s for All Active City Projects worksheet for the Stormwater projects to reflect the current project balances and to show the remaining current year expenditures (attachment). Additionally the notes section has been updated to provide a brief status update regarding current remaining funding for each. Funding and future program expenditures for each are defined in the FY 2018-19 Capital Improvement Program Resources Management Plan.

Note to Section and Project Managers: show the project balances for all your active projects in InSITE (i.e. projects that are not yet closed out). The best report to use for this exercise is the "FSG- BUILDINGS (or other section) PROJECTS", which shows for each section one line of InSITE. See Budget and Management Services Beachnet page for how to run this report). Summary of s for All Active City Projects (Excludes Schools) in the City's Financial System Storm Water 7400 Aragona Drainage Improvements 3,760,000 3,218,902 0 This project delayed construction improvements to coordinate with the cleaning and CCTV inspections of the existing neighborhood storm drain system. Anticipate using total funds on two project phases. First phase to be advertised in Summer 3,218,902 2018. 7047 Ashville Park Drainage Improvements 2,000,000 1,271,940 0 This is a new project in FY 2018. The Project will receive $9.0 Million over the next 3 years to construct the initial phases. The project will be divided into two construction phases. The less complex storm drainage improvement will be constructed in the first phases and the complex improvement, including those that will require property acquisition and / or environmental 1,271,940 permitting, will be constructed in the latter phase. 7036 Baker Road Culvert & Ditch Improvements 450,000 467 0 This project is being managed by the SGA Department in coordination with the Burton Station Rd. improvements and the Burton 467 Station SGA improvements. Anticipate construction beginning in Summer 2018. Project will use all funding. 7037 Bellamy Manor Outfall Ditch 750,000 19,305 10,000 9,305 The project is currently under construction. Anticipated construction completion in July 2018. 7041 Central Resort District Drainage Improvements 300,000 270,800 0 This funding provides seed funding for further evaluating the alternative concepts previously developed. The project is anticipated to exceed $100 M. The first phase of this multiple phase projct is to improve the existing drainage culverts located along the drainage channel from MOCA to Beach Garden Park. Future considerations are to direct approximately 15 to 25 acres from 21st Street to Baltic Ave. instersecton to the existing 16th Street Pump Station as a way to address roadway and property 270,800 flooding within this locatlized area. The comprehensive Citywide sea level rise / recurrent flooding analysis has completed the majority of the risk analysis city-wide. Work is well underway on the second phase of the project to develop strategies and engineering responses to mitigate that risk. 7030 Citywide Sea Level Rise/Recurrent Flooding Analysis 3,844,447 $ 1,458,300 500,000 958,300 The remaining funding will be used to complete watershed level response plans, including budgetary planning. 7402 College Park/Level Green Drainage Improvements 498,687 $ 286,186 0 The initial evaluation is complete and the project is coordinating cleaning and CCTVing existing storm drain pipe sections to 286,186 better define areas for improvements. Design will begin in FY 19 and construction is anticipated to begin in FY 20. 7151 Eastern Shore Drive Drainage 14,139,356 $ 9,737,871 3,800,000 The project is in the design phase. It will include the installation of multiple sluice gates, pump stations and storm drain pipe systems which will be installed in multiple phases to coordinate with the impacts to the neighborhoods and transportation roadway system. An initial phase was completed in late summer 2017, which included installing tide gates at specific locations to provide protection from minor storm events until the major improvements can be installed. This project is anticipated to be a $80 M plus potential project. Design is underway for Phase I Section 1 (Lynnhaven Colony and Vista Circle area) and Section 2 5,937,871 (Cape Story by the Sea). 7053 Bradford Lake / Chubb Lake 1,084,100 $ 899,284 300,000 This is a new project in FY 2018. Project is in the initial study phase which will develop the program scope and better define the estimated project cost. The project will include box culverts under major arterial roadways; drainage improvements for Bradford Lake / Chubb Lake; and drainage ditch improvements to the existing outfall ditch system that drains through Expeditionary Base - 599,284 Little Creek. Current project estimate is $32 M. 4/27/2018 V:\Departments\Management Services\FY19\Council & MLT\Council Questions\FY19 70a- Storm Water Management Section.xlsx Page 1 of 6

Note to Section and Project Managers: show the project balances for all your active projects in InSITE (i.e. projects that are not yet closed out). The best report to use for this exercise is the "FSG- BUILDINGS (or other section) PROJECTS", which shows for each section one line of InSITE. See Budget and Management Services Beachnet page for how to run this report). Summary of s for All Active City Projects (Excludes Schools) in the City's Financial System 7413 Neighborhood Storm Water Infrastructure Improvements - II 4,049,995 371,679 300,000 This project is funding multiple minor drainage improvements that went to construction in winter and summer 2017. Remaining funding will be used to fund future neighborhood SD improvements located throughout the City. This project also funded the preliminary evaluation / engineering report of Ashville Park and Sherwood Lakes. Current projects include Country Club Rd. 71,679 Drainage Improvements, 50th/ 51st Street Drainage Improvements and Goodspeed Road pump station improvement evaluation. 7005 North Lake Holly Watershed 18,671,135 $ 1,485,767 50,000 Four phase of construction have been completed with the fourth phase being complete in Jan. 2018. Three more phases are scheduled for construction between January 2018 and Winter 2022. An additional $4.8 M will be allocated to this project to 1,435,767 assist with these construction cost. 7050 Princess Anne Plaza Drainage Area 2,000,000 577,501 500,000 This is a new project in FY 2018. The Project was broken out of the Windsor Woods Drainage Improvement Project. The project is in the initial study phase which will develop the program scope and better define the estimated project cost. Current project 77,501 estimate is $66 Million. 7048 Sherwood Lakes Drainage Improvements 1,000,000 $ 562,944 0 This is a new project in FY 2018. The project will receive $2.0 Million in FY 19 which will be used to construct the pump station for the North Lake and an interconnecting storm drain pipe between the South Lake and North Lake. The improvements will help maintain the normal water surface elevation in both lakes between elevation 3.0 and 4.0 feet which will provide storm drainage storage capacity for major rainfall events. Anticipate advertising the pump station and interconnecting SD pipe in May 2018 and 562,944 construction NTP in Aug. 2018. 7016 South Lake Holly Watershed 16,609,587 $ 1,526,629 50,000 Three phases of construction are complete. The last phase began construction in October 2017 and is anticipated to be 1,476,629 complete by December 2019. 7024 Southern Canal/Lead Ditch and Culvert Improvements 2,350,000 685,644 200,000 The project completed three major culvert improvements in 2016. The next phase addresses undersized pipes and ditches in the 485,644 Charity Neck Rd and Pleasant Ridge Road area. 7027 SWM Master Planning, Analysis, and Inventory 8,070,906 $ 3,487,423 1,200,000 This project funds activities associated with the new Virginia Stormwater Management Act for water quantity control. It is updating the comprehensive storm water master plans to link with the City's GIS system to meet the maintenance and water quality needs dictated by the City's VPDES permit. Currently 5 watersheds are complete; 14 watersheds are in the modeling 2,287,423 phase; and 12 watersheds remain to be modeled. 7051 The Lakes Drainage Improvements 2,000,000 $ 1,048,662 500,000 This is a new project in FY 2018. The Project was broken out of the Windsor Woods Drainage Improvement Project. The project is in the initial study phase which will develop the program scope and better define the estimated project cost. Current project 548,662 estimate is $28 Million. 7028 Windsor Woods Drainage $ 11,177,237 $ 5,714,787 $ 1,400,000 Maintenance drainage improvements for Windsor Woods /Presidential Canal and North Gate channel are anticipated to be completed by July 2018. The Project is in the initial study phase which will develop the program scope and better define the estimated project cost. Current project estimate is $35 Million. An additional $5.3 M was allocated to the project in March 2018 (from FEMA reimbursement funding) to fund 3 initial drainage projects. Additionally an early implementation drainage phase 4,314,787 (Club House Road Drainage Improvement) is under design and anticipates beginning construction in January 2019. 7406 Elizabeth River TMDL Implementation Plan 7,500,000 2,752,310 204,000 The Kemps Lake BMP Retrofit Project is anticipated to begin construction in July 2018 pending completion of acquisition. The Chatham Hall Pond Retrofit is in the initial design phase and will be funded from this project. Both of these project will expend 2,548,310 the available balances by June 2018. The balance will be used to complete design and construction of projects identified to address TMDLs in the watershed. Two projects have begun design in FY18 for the Bayville Park Pond Retrofit and the Lynnhaven Park Retrofit projects. The remaining 7153 Lynnhaven Watershed Restoration 6,176,582 $ 1,486,014 $ 766,000 720,014 project balance will be used for the construction of both of these projects which are anticipated to be completed in FY19. 4/27/2018 V:\Departments\Management Services\FY19\Council & MLT\Council Questions\FY19 70a- Storm Water Management Section.xlsx Page 2 of 6

Note to Section and Project Managers: show the project balances for all your active projects in InSITE (i.e. projects that are not yet closed out). The best report to use for this exercise is the "FSG- BUILDINGS (or other section) PROJECTS", which shows for each section one line of InSITE. See Budget and Management Services Beachnet page for how to run this report). Summary of s for All Active City Projects (Excludes Schools) in the City's Financial System 7410 Southern River TMDL Implementation Plan 900,000 $ 451,171 $ 100,000 The remaining balance will be used to perform project identification and evaluation to address TMDLs in the watershed. It will 351,171 also be used to construct the identified projects in FY19. 7414 Storm Water Quality Enhancements - II 9,365,254 $ 2,574,327 $ 191,000 Funding will be used for the implementation of the projects and programs identified during FY18 for the local TMDL action plan development. The funding will be used for construction of the projects identified in the action plan, which will be scheduled in 2,383,327 FY19. 7042 Surface Water Regulatory Compliance 5,031,942 $ 1,557,292 $ 450,000 The remaining funding will be used to continue regulatory compliance activities for the dry weather screening program, industrial inspections program, illicit discharge program, stormwater awareness training program, and public outreach strategy 1,107,292 implementation. The funding is allocated to meet the City's Cost Participation agreement with the Army Corps of Engineers for the construction of the Lynnhaven River Ecosystem Restoration Project. Funding for the cost share by the Army Corps of Engineers has been delayed. 7043 Water Quality and Restoration Participation Projects II 1,516,773 $ 1,516,773 $ - 1,516,773 This project is anticipated to begin construction in FY19. 7200 Severe Repetitive Loss Grant Program 1,847,009 199,205 0 199,205 Work continues on resolving final construction claim issues for this Grant. Construction bids received exceeded funding. Currently working with FEMA and induvial home owners to through dept of emrgcy mngmnt 7411 Oceanfront Storm Water Facilities Maintenance 3,858,000 $ 843,132 $ 818,000 This work to protect and maintain the Federal/City Hurricane Protection Project at the Oceanfront includes replacing the stormwater outfall piping flap gates at $200K in Winter 2017/18 to Spring 2018, Seawall Construction Joint Sealings at $25K during non tourist times, Seawall Structure Sealing at $35K during non tourist times, Stair Nosing repairs for the steps down to the beach from the Boardwalk to protect pedestrian feet at $300K during non tourist times, Oceanfront Stormwater Pump Station Maintenance repairs at $50K during non tourist times, Full Depth Boardwalk Repairs at $75K during non tourist times, and various smaller projects to support this vital infrastructure as well as a small remainder to carry over into the next FY for other 25,132 programming needs. Note that all of this work is also heavily weather dependent. 7032 Flood Mitigation Assistance Grant Program 1,227,144 1,014,214 0 1,014,214 This Federal Emergency Management Agency Grant program is under review and revision. Funds are to be carried over to the next FY until review is completed. (Construction bids received exceeded funding and the Department of Emergency Management is working with FEMA and the induvial home owners to see if an agreement can be reached to help move the project forward.) This Federal Emergency Management Agency Grant program is under review and revision. Funds are to be carried over to the next FY until review is completed. (Construction bids received exceeded funding and the Department of Emergency Management 7044 Flood Mitigation Grant Program II 874,061 $ 726,232 $ - 726,232 is working with FEMA and the induvial home owners to see if an agreement can be reached to help move the project forward.) 4/27/2018 V:\Departments\Management Services\FY19\Council & MLT\Council Questions\FY19 70a- Storm Water Management Section.xlsx Page 3 of 6

Note to Section and Project Managers: show the project balances for all your active projects in InSITE (i.e. projects that are not yet closed out). The best report to use for this exercise is the "FSG- BUILDINGS (or other section) PROJECTS", which shows for each section one line of InSITE. See Budget and Management Services Beachnet page for how to run this report). Summary of s for All Active City Projects (Excludes Schools) in the City's Financial System 7415 Lake Management II 27,260,128 $ 5,700,655 $ 3,415,000 Projects include Whitehurst Dredged Materials Management Area Haul Road Extension Construction $150K anticipated Spring 2018, New Dredged Materials Management Area Site Permits and Engineering for New Dredged Materials Management Area Site $75K Spring 2018, Green Run 2 Dredging Construction at $1.3M in Fall 2017, Green Run 3 Dredging Design $200K Spring 2018, Green Run 4 Dredging $500K Summer 2018, Green Run 5 Dredging $500K Summer 2018,, Windsor Oaks West Dredging Canals 1 and 2 at $1.3M started in Winter 2016/17, Windsor Okas West 3 dredging summer 2018 $700K. State Mandated BMP/Lake Inspections at $300K started in Winter 17, Minority Mowing Contractor BMP Maintenance $200K continues Spring 2018, Remainder is contingency and carried over for following FYs for multiple large expenditures scheduled for out years including remainder of FY 18 Construction at $1.6M per Top 50 Lake Dredging schedule as well as multiple other lake dredging 2,285,655 projects at $3.1+M. 7416 SW Infrastructure Rehabilitation & Improvements II 33,106,982 $ 3,045,757 $ 1,700,000 Projects include Fleet Terrace Anticipated Construction $100K Fall 2018, Magic Hollow Storm Drain CCTV and Design $400K Spring 2017, Malibu CCTv Designa nd Construction 350K spring 2018, Landstown lakes CCTV Design and Construction 250K Spring 2018, Bellamy manor CCTV Design and Construction 400K Summer 2018. Various Corrugated Steel Pipe Repairs (partial-ferrell Parkway Ph 1) at $500K in Summer 2018, Lakeview Drive Construction $1.4M Fall 2018, 22nd at Cypress Emergency Repair $550K Winter 17(under construction), Dam Neck Road Phase IIA Construction (complete), Century Drive Storm Pipe Extension at $350K (complete), Green Run Bike Path Drainage Improvements at $110K in Winter 2018, Green Run / Princess Anne Road Berm Drainage Improvements at $55K in Winter 2018, Various Sites CCTV for stormwater pipe inspection and cleaning throughout the City at $750K continuously, Various Stormwater Pipe Cave-In repairs throughout the City at $1M continuously, with remaining 1,345,757 small projects throughout the FY and is contingency and to be carried over to next FY. 7034 Stormwater Operations Modular Building 890,000 225,050 0 225,050 This project was substantially completed in Spring 2017. Remaining funds will be transferred to 7411 7412 Storm Water Pump Station Modifications 5,025,229 $ 447,072 $ 412,000 Projects include pump station electrical work $150K throughout FY 18, 16th street stormwater pump station improvements (complete) 42nd Street stormwater pump station repair/rehab $40K(complete), Cape Story stormwater pump station (interim work) $25K, 61st stormwater pump station modifications $75K Summer 2018, stormwater pump station controls (SCADA) $125K for 79th street(complete), stormwater wet well cleaning and inspections $20K throughout FY 18, and various or miscellaneous unplanned repairs necessary to keep stormwater pump stations in operation. SCADA system completion 350K(complete). 35,072 Remainder of funds will be rolled over to next FY. Projects include Independence Blvd at Shoreline Court Pipe and Ditch construction $600K (complete), Off Road Ditch clearing - contract 1 $500K throughout FY 18, Hungarian Road Off Road Ditch and Culvert drainage improvements $125K (complete) FY 18 Off Road Ditch design and environmental permitting $150K Spring 2018, Off Road Ditch cleaning - Contract 2 $500K throughout FY 18, and small remainder to carry over to next FY. Note the off road ditch work is heavily weather and crop schedule 7023 Primary System Infrastructure Improvements II 8,350,000 $ 777,800 $ 750,000 27,800 dependent. 4/27/2018 V:\Departments\Management Services\FY19\Council & MLT\Council Questions\FY19 70a- Storm Water Management Section.xlsx Page 4 of 6

Note to Section and Project Managers: show the project balances for all your active projects in InSITE (i.e. projects that are not yet closed out). The best report to use for this exercise is the "FSG- BUILDINGS (or other section) PROJECTS", which shows for each section one line of InSITE. See Budget and Management Services Beachnet page for how to run this report). Summary of s for All Active City Projects (Excludes Schools) in the City's Financial System 7026 Residential Drainage Cost Participation Program II 250,000 $ 37,057 $ 19,000 The spending plan for this program is based on requests from citizens for participation in the program. In FY 2015/16, City Council authorized expanding this program to include Citizen cost-participation for treatment of aquatic plant and nuisance and algae control. s expected to draw down this account to zero dollars or near-zero dollars each FY as Citizen knowledge of 18,057 this program becomes widely disseminated. Fy17-Fy 18 expenditures 25K for the treatment of several lakes within the city. 7067 Primary System Infrastructure Improvements 437,556 9,478 9,478 0 This funding will be expended down to zero dollars with other related program projects and then closed out the end of FY 2018. 7152 Dam & Spillway Structural Improvements 585,637 127,251 127,251 This funding will be for Hydro surveys to support the pending regulated dams and spillways per the new regulations established by the DCR in 2014. Project remaining funds will also support Kingston Lake Dam Design and Construction spillway elevation change from +7.4 to +7.8. (Summer 2018)with remainder expended down to zero dollars with other related program projects and 0 then closed out the end of FY 18. 4/27/2018 V:\Departments\Management Services\FY19\Council & MLT\Council Questions\FY19 70a- Storm Water Management Section.xlsx Page 5 of 6