PORT OF MIAMI TUNNEL PROJECT Highlights & Where we are today!

Similar documents
Hampton Roads Bridge-Tunnel Expansion Feasibility Study. Design Considerations

3.6 Construction Methods

Getting. Dodge. in and outa

INTERNATIONAL DESIGN & CONSTRUCTION

Ironton Russell Bridge Project

Hampton Roads Bridge-Tunnel

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

HUDSON TUNNEL PROJECT

6 Preliminary Assessment of Construction Method and Constructability Issues

Elizabeth River Tunnels Project. ASHE October Technical Meeting ERT Project Overview October 8, 2015

Hudson River Tunnels, Mega Projects, and Risk A Designer s Perspective

Funding was provided by the City of New York via the Hudson Yards Infrastructure Corporation and Hudson Yards Development Corporation.

Ironton Russell Bridge Project

Mega Projects at WSDOT

introduction Introduction to Bridge and Tunnel Engineering Characteristics of ideal bridge Ideal location Factors affecting bridge type Classification

Large Diameter Highway Tunnels

THE KOSCIUSZKO BRIDGE PROJECT. The New York State Department of Transportation. Page 1

Ironton Russell Bridge Project

FTBA 2018 Construction Conference Major Projects Update

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Exposition Light Rail Transit Project

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)

Pattullo Bridge Replacement Project. Cost Report

Lesner Bridge Replacement

Rt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016

6.2.2 Environmental Consequences and Mitigation Measures

I-74 Corridor in the Quad Cities A State of the Art Design

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)

STATE UNIVERSITY CONSTRUCTION FUND

Final Recommendations Identification of Improvements, Strategies, and Solutions

Section 13. Guidelines for the Design of Ground Mounted Sign Supports

Santa Clara Valley Transportation Authority Board of Directors. General Manager, Nuria I. Fernandez

Overall project. The $288 million Phase 2 DesignBuild project starts construction. this spring, with completion by December 31, 2016

McGraw Hill Yearbook of Science & Technology Traffic Operations and Structures: : Tampa's Reversible Express Lanes

4th International Engineering and Construction Conference - July 28, 2006

I-10 Master Plan Escambia and Santa Rosa Counties TPO Meetings. Tier II June 11 th & 13 th, 2012

Transbay Program Phase 2 Downtown Rail Extension (DTX) Tunnel Options Study Briefing

Transportation Modeling Tools. Rainer Dronzek November 3, 2006

PortMiami Rail Intermodal and Bascule Bridge Rehabilitation Project TIGER II Grant

I-35W Retaining Wall Design Exhibit A - Draft Scope of Work

Metro Purple Line Extension

Tunnel. Immersed Tunnels

Ironton Russell Bridge Project

REHABILITATION PACKAGE 4-a

Project Team. D6 South Miami-Dade Resident Engineer Erik Padron, P.E. D6 Construction Project Manager Dari Vorce

Glenmore Causeway Upgrades Project. Calvin T. McClary, P. Eng., Manager, Transportation Engineering, ISL Engineering and Land Services Ltd.

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

Crossrail and our international tunnelling expertise

The Gateway Expressway FTBA Conference. February 2-3, 2017

Evergreen Line Rapid Transit Project

Promoters. Presentation. Tunnel. Tim Smart Head of Engineering & Operations. 20 th October

Implementing Asset Management: WSDOT s Experience

Tunnel Works. How we got here - Fort Wayne s Consent Decree. Tunnel Works Program Frequently Asked Questions

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

CROSSRAIL INFORMATION PAPER D8 TUNNEL CONSTRUCTON METHODOLOGY

Constructability Guidelines

Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

HIGH MAST CAMERA POLE ASSEMBLY GENERAL

HANDHOLES, PULLING VAULTS AND JUNCTION BOXES

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

INTERSTATE CORRIDOR PLANNING

SPACE TYPE: OUTSIDE PARKING (STRUCTURE)

MATERIAL ALLOWANCES AND UNIT PRICES

SELECTION OF TUNNEL METHODS. By: Dr. Gary S. Brierley

Forsyth County Procurement

Bonner Bridge Replacement Update:

Jim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project

Brooklyn Station Construction Open House

Manufacturing Facilities Proposal

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

Florida s Turnpike Enterprise Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20 Summary of Projects in FDOT District Four

SECTION 1101 TRAFFIC SIGNALS AND APPURTENANCES END OF SECTION

Get In, Get Out, Stay Out!

D7: TUNNEL CONSTRUCTION AND METHODOLOGY

Stabilization of Running Granular Soils in TBM Alignment with Sodium Silicate Grout

CONSTRUCTION CHALLENGES WITH CUTTER SOIL MIXING IN POROUS

Chapter 4 Bridge Program Drawings

A new elevated pathway provides safe passage for pedestrians and cyclists near one of the Windy City s premier tourist destinations.

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

In Service Replacement of Box Girder Bottom Slab

Aviation Capital Construction Program Update

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors

Clearview Parkway LA 3152 Stage 0 Feasibility Study and Environmental Inventory

DURISOL PRECAST NOISE BARRIERS PRODUCT GUIDE

US 14 EIS (New Ulm to N. Mankato) Interchange and Intersection Type Comparison

Commercial Remodel Permit

Interstate 66 Widening from. RFQ Information Meeting. January 4, 2012 Christiana Briganti-Dunn, P.E. District Project Manager

SECTION CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

SCHEDULE G REGULATIONS, STANDARDS AND SPECIFICATIONS FOR THE INSTALLATION OF STREET LIGHTING

Highway Construction Program

FOR INTERSTATE 81 AND ROUTE 37 INTERCHANGE FREDERICK COUNTY, VIRGINIA MILEPOST 310

RESIDENTIAL CONSTRUCTION New Dwellings and Additions

Woodbine Station Upgrades

SELLWOOD BRIDGE REPLACEMENT PROJECT

Construction of Bridges

The Aizhai Suspension Bridge is

ASSESSING THE IMPACT OF SECURITY MEASURES AT GATES OF SEAPORTS ON TRAFFIC OPERATION

FINAL ENVIRONMENTAL IMPACT REPORT. CHAPTER ONE: EXECUTIVE SUMMARY with RESPONSES TO COMMENTS

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

Transcription:

PORT OF MIAMI TUNNEL PROJECT Highlights & Where we are today! FEBRUARY 12, 2014 FTBA CONSTRUCTION CONFERENCE

PROJECT PARTNERS Public Sponsors 90% Equity Partner Contractor 10% Equity Partner Operator Federal Support

OVERVIEW OF PROJECT COST Overall Project Cost $1.2B Design & Construction Cost $663.5M $100M during Construction consisting of 4 defined milestone payments: 1 st Milestone - $20m Tunnel Design Complete (Paid) 2 nd Milestone - $40m TBM at work in 1 st Bore (Paid) 3 rd Milestone - $25m TBM at work in 2 nd Bore (Paid) 4 th Milestone - $15m Substantial Completion of MacArthur Causeway $350M at Final Acceptance of Construction Total Milestone Payments = $450M Concessionaire compensated through Milestone payments during construction period Availability payments during operating period ($32.5M adjusted for inflation)

PUBLIC-PRIVATE PARTNERSHIP OVERVIEW Concessionaire will design, build, finance, operate and maintain (DBFOM) tunnel for 35 years Design and construction - first 55 months Operation and maintenance - remaining 30 years and 5 months through facility hand-back No tolls

PROJECT BENEFITS American Airlines Arena Bayside Marketplace Provide a direct connection between the Seaport, Airport and the Interstate Highway System Maintain PortMiami as the county s second leading economic generator Relieve congested downtown Miami streets of Port passenger and cargo traffic, improving safety as trucks also traverse areas of pedestrian activity Facilitate ongoing and future development plans in and around downtown Miami

SCOPE OF WORK MacArthur Cswy Bridge Widening Shifting of EB MacArthur Cswy Twin tunnels under Government Cut Modification of Dodge Island Roadway System

MACARTHUR CAUSEWAY BRIDGE WIDENING Interior Widening for additional traffic lanes to tunnel continue Work on Piers 16, 17, 18 & 19 as well as demo of site establishment Pier Construction (10 segments cut into existing walls to splice reinforcement with #11 rebar for erection of the piers

TUNNEL BORING MACHINE EB & WB BREAK-IN, BREAKOUT & TUNNEL Mining of the Eastbound Tunnel began on November 11, 2011 and was completed on July 31, 2012 (751 Rings & 4,186 LF) Mining of the Westbound Mining began October 29, 2012 and was completed on May 6, 2013 (745 Rings & 4,152 LF)

BORED TUNNEL TYPICAL SECTIONS Two 12 Travel Lanes 2-6 Shoulders on both sides 2-2 Maintenance Walkway in each Tunnel Internal Diameter of Tunnel is 37 Spacing between Tunnels varies from 21 & 60

CUT & COVER TYPICAL SECTIONS

Tunneling Profile Section & Cross Passages Tunnels are approximately 4200 ft. long +40 ft. under the bottom of Government Cut & approximately 120 ft. below the surface at deepest point 5% Grade 5 cross passages

CROSS PASSAGES CONSTRUCTION CROSS PASSAGE LENGTHS CP1 15 ft. CP2 36 ft. CP3 37.5 ft. CP4 43 ft. CP5 10.5 ft. Five cross passages, or emergency exits, are being built between the two tunnels. Cross passages are approximately 700 feet Cross passages 1, 4 and 5 are not underneath the channel and were pretreated from ground surface using cutter-soil mixing panels that form a grouted block of soil and were excavated. Cross passages 2 and 3, which go underneath Biscayne Bay, were treated with a brine to freeze the ground and excavated.

CROSS PASSAGES GROUND FREEZING PROCESS 44 freezing pipes were installed Estimated freeze time once brine installed at -22 F was 40 days. A small cooling unit was installed in the second tunnel to cool the lining segments and ensure efficient closing of ice ring. Steel support frame was installed to prevent movements of the first tunnel due to ice pressures. Steel door was installed as fail safe to be closed in case of an emergency during excavation.

CROSS PASSAGES MECHANICAL AND ELECTRICAL INSTALLATION

CURRENT INTERIOR VIEW OF TUNNEL

CONCEPTUAL INTERIOR VIEW OF TUNNEL Aluminum Architectural Panels will be installed as final finish Installation of internal structures and Mechanical- Electrical-Plumbing-Fire (MEPF) continue to be installed in both tunnels including fire main piping, electrical conduits and cabling, junction boxes and ITS equipment.

WATSON ISLAND PORTAL CONSTRUCTION

DODGE ISLAND PORTAL CONSTRUCTION

WATSON & DODGE ISLANDS PORTAL DESIGN Tunnel Portal construction continues and will house the Flood Gates which come down in the event of a storm to prevent flooding of tunnels

WATSON & DODGE ISLAND SUPPORT BUILDINGS CONSTRUCTION Both buildings structural elements are complete Mechanical, Electrical & Plumbing (MEP) as well as finishes for buildings continue to be installed Installation of building ventilation, sprinkler system and electrical (switchboards & cabling), as well as fire alarms are under works

SUPPORT BUILDINGS CONSTRUCTION

Dodge Island Roadway Improvements EB & WB Port Boulevard was shifted to Final Condition South Cruise Boulevard was completed New Truck Bridge was partially open to one lane Construction continues on internal roadways

PROJECT SCHEDULE July 31, 2012 Completion of eastbound tunnel May 6, 2013 Completion of westbound tunnel Spring 2014 Completion of Dodge Island roadway improvements May 19, 2014 Substantial Completion - Port of Miami Tunnel opens to traffic, O&M Period begins August 18, 2014 Final Completion As of 2/12/14 - Construction Days to Date: 1552 of 1765 (55 months) = 87.9% of Design-Build

Questions?