Alberta Infrastructure. Digital Project Delivery Building Information Modelling Design-Builder Requirements

Similar documents
State of Tennessee Office of the State Architect {TN OSA) Building Information Modeling {BIM) Requirements. Version 1.0

INTEGRATED LIFECYCLE MANAGEMENT BIM/VDC REQUIREMENTS IMPLEMENTATION PLAN

BIM Execution Plan Template. CPG-DGN-PLN-085 Revision 0 08/08/2016

AUGUST 1, 2017 VA BIM STANDARD BIM MANUAL V2.2

1.0 ABOUT THE NU GUIDELINES

- DATA REQUIREMENTS BIM

BUILDING INFORMATION MODELLING BOUYGUES UK THE USE OF BIM TO IMPROVE PROJECT PERFORMANCE

Indiana University. Vice President for Capital Planning and Facilities

BIM Design & Construction Requirements. Follow-up Seminar. September 10,

Building Information Modeling (BIM) Execution Plan

23/01/1438. Management of BIMProject: BIM Management Plan. Mohamed Mohsen Kamel. Prof. Dr. Emad Elbeltagi

IV.E.8 - BIM Standards

BIM V.1 Tables A1

a commentary to the NBIMS-US COBie standard

BIM 2016 and the NEC. Simon Rawlinson, 20 April 2015

BIM Checklist. Introduction

EcoDomus, Inc

BIM EXECUTION PLAN PROJECT INFORMATION PROJECT NUMBER

Facilities Management

The BIM Toolkit. Sarah Delany February 2015 v2.0

BLOCKCHAINS IN CONSTRUCTION & INFRASTRUCTURE HELIUM ALLIANCE

AT THE FOREFRONT OF THE CONSTRUCTION INDUSTRY WITH BUILDING INFORMATION MODELING (BIM): THE CHALLENGES

Exhibit B - A/E Scope of Services (General Contracting Project) State of Ohio Professional Services Agreements for Public Facility Construction

VIRTUAL DESIGN & CONSTRUCTION, THE NEXT LEVEL OF COLLABORATION AND INTEGRATION 2016 Airport Construction Strategy Summit. Special Thanks To:

Autodesk and the UK BIM Level 2 Mandate

Sylvia Kendra Associate Director Facilities Knowledge Management. January 11, 2017

BIM TECHNOLOGY THE IMPACT ON THE PLANNING AND UTILIZATION PHASE HDR TMK, all rights reserved.

National Institute of Building Sciences

Streaming BIM Lifecycle Information. Murray Hestley, Whiting-Turner Construction Eric Nulton, Penn State University

BIDDING FOR BIM. CIF Bidding for BIM. September

Commissioning Guide. Transportation and Works Building Design and Construction Division

Volume II- Project Development Processes

Cookham Wood and BIM: Practical Lessons Learnt Fiona Moore Cirrus Consultant Services 10 July 2014

NC State University OESAD GUIDELINES Contract Year

BIM and Interoperabilty - Critical aspects. Matteo DEL GIUDICE

BIM in Infrastructure

Meeting the Challenge of EPC Project Proposal Schedules. Project Proposal Schedules

Competitive Procurement Evaluation Process Audit

AFRRCS Agency Handbook

Office of Physical Plant Case Study

Employer s information requirements (EIR) An overview of facilities management requirements

BIM and Metadata. Why metadata is relevant to product suppliers

CAD+BIM+GIS+CMMS for Airport Facility Maintenance/Management: Making the best of each tool work - together

Building information modeling and intelligent green buildings

The National BIM Library. Drew Wiggett Head of Product Information

DESIGN & CONSTRUCTION PHASE COMMISSIONING PLAN TEMPLATE

Request For Information (RFI) For a. Spectrum Management & Monitoring System (SMMS)

A197-S4 Maximo Integration Services Asset Inventory and Maintenance Management System. ADDENDA & RESPONSES TO QUESTIONS February 1, 2016

Realizing Complex Design Through BIM The Louisiana State Museum and Sports Hall of Fame

BIM for Contractors: Kickin It Off the Right Way

MIT Design Standards. BIM Execution Plan v6.0

ATTACHMENT D SCOPE OF SERVICES

Intelligent Building Services for Signature Properties

Sustainable Design Services

Building Information Modeling to Facilities Information Management and Beyond

Program Lifecycle Methodology Version 1.7

BIM enhances structural analysis regardless of project size. By Doug Fitzpatrick, P.E., LEED AP and Jeffrey Yoders

Florida Department of Transportation 605 Suwannee Street Tallahassee, FL

Promoting better business outcomes through the use of BIM and digital technologies.

The benefits of reinventing the wheel BIM AND IPD BRING FUNDAMENTAL CHANGES TO ROLES IN A STRUCTURAL ENGINEERING FIRM

REQUEST FOR PROPOSALS (RFP) Design Services for District Heat Distribution System

BIM ADOPTION AND IMPLEMENTATION FOR ENGINEERING & CONSTRUCTION INDUSTRY PRACTICES

600 - Phase C Intermediate Review Checklist for the Architect- Engineer

Enabling Siemens PLM Software for the AEC Industry. Lake Constance 5D-Conference 2013 Constance, 28th-29th of October

The Issue of Conversation & Communication

Strategic Revit MEP Object Organization From BIM to Asset Management

The Accenture/ Siemens PLM Software Alliance

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

Shutdown Requests. Gian Catano Contract Administrator December 17, 2014

Student Government Office Renovations Design/Construction Administration Services Code Item 305

CWG-002 BIM Management Plans

Data Requirements for the Construction and Management of Buildings

Maximo v Feature Pack release. October 21, 2016

Request for Consulting Services For the Preparation of an Economic Development Strategy EXECUTIVE SUMMARY

O10 BIM for specialist sub-contractors and trades BIM IN PRACTICE

Benjamin D. Hall Interdisciplinary Research Building

Addendum #02 New County Office Building Responses to RFP Questions

Implementation of the German Road Map for Digital Design and Construction Prof. Dr.-Ing. Markus König. Milano, 9 marzo 2017

Passit4Sure.OG Questions. TOGAF 9 Combined Part 1 and Part 2

CITY OF ROHNERT PARK CITY COUNCIL AGENDA REPORT

WHOLE LIFECYCLE INFORMATION FLOW UNDERPINNED BY BIM: TECHNOLOGY, PROCESS, POLICY AND PEOPLE

REQUEST FOR PROPOSAL TOWN OF MIDDLESEX, NEW YORK WATER SYSTEM IMPROVEMENTS PROJECT

Jay Miller Director of Operations Baker Electric Solar

POSSE System Review. January 30, Office of the City Auditor 1200, Scotia Place, Tower Jasper Avenue Edmonton, Alberta T5J 3R8

COBie and the Demanding Client

REQUEST FOR PROPOSALS ( RFP ) NUMBER PROVINCIAL ORGAN AND TISSUE DONATION INFORMATION MANAGEMENT SYSTEM DEPARTMENT OF HEALTH

ARCHITECTURAL / ENGINEERING SERVICES RFQ. North Sound Behavioral Health Organization

STATE OF FLORIDA, DEPARTMENT OF MILITARY AFFAIRS CONSTRUCTION & FACILITY MANAGEMENT OFFICE PUBLIC ANNOUNCEMENT

BIM objects: what manufacturers and specialist contactors need to know. Ben Councell

BIM M Masonry Wall Project and Revit Guide BIM FOR MASONRY MISSION STATEMENT

Association of Consulting Engineering Companies British Columbia User Guide to Implementing Qualifications Based Selection

Amendment Record Purpose Scope Acronyms & Definitions Applicable Documents Requirements 7

Design + Construction Strategies 30 April 2014 IDIQ Contract #F10CC10036 Task Order #: Page 0 of 54

Life Cycle Costing as part of decision making - use of building information models

US AIR FORCE BIM PROJECT EXECUTION PLAN (USAF PxP) VERSION 1.0 FOR [PROJECT TITLE] DEVELOPED BY [AUTHOR COMPANY]

Session 7 Part A Revit for Urban Design

Building Information Modelling UK Experience & International View. BIM Task Group Briefing Presentation. Adam Matthews, UK BIM Task Group

Cleveland Clinic. BIM Implementation Plan TABLE OF CONTENTS

APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES

Titel: The importance of a Project WBS for a BIM Usage Plan. Date: Autor: M.Sc: Probal Tagore Brahma

Transcription:

Alberta Infrastructure Digital Project Delivery Building Information Modelling Design-Builder Requirements

Table of Contents Building Information Modelling Objective 2 1. BIM Manager 3 2. BIM Execution Plan (BEP) 3 3. Model Requirements 3 3.1 General 3 3.2 BIM Software 4 3.3 Level of Development 4 3.4 Geo-referencing 4 3.5 Rooms and Spaces 4 3.6 Model Structure 5 3.7 Mechanical, Electrical, Plumbing (MEP) Systems 5 3.8 Element Properties 5 3.9 Coordination 5 3.10 Record Modelling 6 4. Model Availability 6 5. Delivery Requirements 6 5.1 Model Delivery 6 5.2 Drawing Delivery 7 1 BIM Design-Builder Requirements v1.0

Building Information Modelling Objective The Province s objective for the use of Building Information Modelling (BIM) is to deliver higher value in quality, timeliness, cost, and a useable product for Facility Management (FM) at the end of the project construction lifecycle. While the objective of BIM is to have information contained in a model, the asset information associated to elements in a Record Model a contained in the COBie file. BIM Design-Builder Requirements v1.0 2

1. BIM Manager.1 The Design-Builder shall designate one individual, the BIM Manager, who is accountable to the Province for:.1 Ensuring compliance with the Province s BIM Design-Builder Requirements..2 Coordinating and attending the BIM kick-off meeting with the Province within two (2) weeks of project award..3 Developing, maintaining, updating, distributing, and providing clarifications to the BIM Execution Plan (BEP)..4 Facilitating the implementation of BIM procedures as detailed in the BEP and ensuring the reliability of information in the Design-Builder s deliverables..5 Creating the Record Model by coordinating updates to the Design Models..6 Leading and facilitating all BIM project meetings with project team members, including the Province..7 Executing quality control (QC) processes for proper modeling, standards adherence and classification of all required elements. 2. BIM Execution Plan (BEP).1 The BEP is a process management document created by the Design-Builder in consultation with the Province. The BEP shall define how the Design-Builder teams use BIM to meet the Province s Requirements. The Design-Builder shall:.1 Use the BEP template (GOA-AI-TSB-SPE_BEP_Template) provided by the Province as the basis for the BEP, with additional modifications according to the needs of the Design-Builder..2 Submit the BEP to the Province within 30 days following project award for review and confirmation of acceptance..3 Resubmit the BEP to the Province for review and confirmation of acceptance whenever it is revised. 3. Model Requirements 3.1 General.1 All elements within the scope of work shall be modelled at a Level of Development (LOD) defined by the Design-Builder in the BEP..2 All schedules, detailing, and annotations shall be created natively in the model authoring software. Dimensions shall not be overridden..3 All existing conditions for renovation or retrofit projects shall be modeled and include all disciplines affected by the proposed work. 3 BIM Design-Builder Requirements v1.0

3.2 BIM Software.1 The Province is vendor neutral regarding the use of specific model authoring software. Model authoring software shall:.1 Support the most current ISO 16739 standard (Industry Foundation Classes (IFC) for data sharing in the construction and FM industries)..2 Have parametric modelling capabilities..3 Be used as intended. All elements shall be modeled or created using the tool within the software that is designated for that specific element or purpose. 3.3 Level of Development.1 The Design-Builder shall develop a project specific LOD matrix that includes:.1 Element geometry at all project phases..2 Element data at all project phases..3 Element tolerances for the Record Model..4 Assignment of responsibility for elements..2 The LOD defined for each project design phase shall effectively communicate design intent. 3.4 Geo-referencing.1 All models shall be referenced to one of the following coordinate systems:.1 NAD83 3TM 114 for projects in Edmonton and Calgary..2 NAD83 10TM 115 for projects in the remainder of Alberta..2 All buildings shall have a project base point (defined origin 0,0,0) and be related to a survey point (such as a geodetic survey marker)..3 All elements shall be modeled at true scale and at true elevation above sea level..4 All elements shall be oriented in accordance with the geographical north orientation (true north). 3.5 Rooms and Spaces.1 All rooms and spaces shall be generated with the appropriate tool and associated with bounding elements..2 There shall be no space gaps in the model..3 Bounding boxes shall be used to represent rooms and spaces..4 Project rooms and spaces shall be named and numbered consistently across all models..5 All rooms and spaces shall be classified according to the Province s Asset Classification Standard..6 Any exceptions to the above shall be outlined and justified in the BEP. BIM Design-Builder Requirements v1.0 4

3.6 Model Structure.1 Models shall be separated by discipline. Each discipline model shall contain the elements that relate to their discipline s design..2 Model divisions shall be documented in the BEP..3 Elements shall not be duplicated across discipline models. 3.7 Mechanical, Electrical, Plumbing (MEP) Systems.1 The model shall be structured such that any individual MEP System and all its elements are connected and can be traced and isolated throughout the facility..2 The systems list shall be agreed upon by the Design-Builder and the Province and documented in the BEP. 3.8 Element Properties.1 All elements shall be assigned the correct categorization. Exceptions to element categories based on software limitations shall be outlined in the BEP..2 All elements shall be classified in accordance with the Province s Asset Classification Standard. There shall be no exceptions to element classifications..3 Schedules shall be derived from the properties of the model and remain unaltered. Schedules shall not be augmented with unconnected data..4 Element properties shall be populated with accurate information of the specified or designed assets..5 Additional element properties shall include the following properties as listed in Table 1: Table 1: Additional Element Property Classifications Property Definition Applies to AI_Type_Class Defines the Province s classification of asset types COBie assets AI_System_Class Defines the Province s classification of Systems All elements AI_Space_Class Defines the Province s classification of spaces and rooms Spaces and rooms 3.9 Coordination.1 The Design-Builder shall use the models to perform spatial coordination and interference checks at all design and construction phases..2 Define the coordination and interference review process in the BEP. 5 BIM Design-Builder Requirements v1.0

3.10 Record Modelling.1 The Design-Builder is not required to migrate asset data contained in the Construction Operations Building information exchange (COBie) file to the Record Model..2 The Design-Builder shall update the model geometry throughout the construction phase of the project to reflect approved project changes, including:.1 Project change orders..2 Site instructions..3 RFI responses and clarifications..4 Shop drawings..5 As-Built Drawings..3 The Design-Builder shall provide evidence of updates to the design model to the Province upon request..4 The Record Model shall contain the accurate representation of all assets included in the COBie File, including:.1 The as-built quantity and size.2 The actual orientation, location, elevation, and routing of major services.3 The connection to the appropriate system in the model as per the As-Built drawings.5 The LOD for the Record Model shall, at a minimum, be equivalent to the LOD specified at final design phase..6 The Record Model shall not include the original manufacturer s data parameters..7 All views and sheets produced to create contract drawings for the project shall remain in the model..8 The Record Model shall be submitted within 30 days of project Substantial Performance..9 The Record Model shall be submitted within one version year of the current model authoring software release..10 The Design-Builder shall update the COBie file, provided by the Province, with a unique element identifier from the model as per the Province s COBie Requirements..11 The Design-Builder shall submit the updated Record COBie file at Substantial Performance. 4. Model Availability.1 The Design-Builder shall submit all project models, including Construction Models (if available) to the Province at a frequency defined in the BEP. 5. Delivery Requirements 5.1 Model Delivery.1 All model files shall be delivered in the native model authoring format at the designated project phases documented in the BEP. BIM Design-Builder Requirements v1.0 6

.2 The Design-Builder shall deliver an IFC (2x3 coordination view V2.0) file to the Province upon request..3 The model delivery package shall include:.1 A Model Submittal Report (the Province shall provide Model Submittal Report Template)..2 All model files..3 All linked/referenced files..4 Any additional setting file that is necessary to extract or print any information from the model..4 All models delivered at designated project phases shall be cleaned of extraneous working material before being delivered. This extraneous material may include:.1 Abandoned design..2 Unused elements..3 Empty layers..4 Inaccurate content which may be produced in BIM production. 5.2 Drawing Delivery.1 All drawing submissions shall be produced directly from the model authoring software..2 All drawings shall be contained in the model and display all views, model elements, schedules, and annotations used to produce the drawings. 7 BIM Design-Builder Requirements v1.0