DECOMMISSIONING STRATEGIES AND PLANS. By: Elna Fourie Necsa South Africa Manager: Decommissioning Services

Similar documents
Decommissioning of Nuclear Facilities. The Decommissioning Process. Lesson Objectives. Decommissioning. Decontamination. Decommissioning Objective

IAEA SAFETY STANDARDS for protecting people and the environment. Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle Facilities

IAEA SAFETY STANDARDS for protecting people and the environment. Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle Facilities

Decommissioning Worldwide and NEA Activities

Decommissioning Planning

Joint ICTP-IAEA School on Nuclear Energy Management. 15 July - 3 August, Lecture Notes. I. Mele IAEA, Vienna, Austria

ADVANCED DECOMMISSIONING COSTING CALCULATION TOOLS FOR PILOT VIENNA TRIGA MARK-II RESEARCH REACTOR

New Swedish Regulations for Clearance of Materials, Rooms, Buildings and Land Efraimsson, Henrik Swedish Radiation Safety Authority, SWEDEN

ROMANIA National Commission for Nuclear Activities Control (CNCAN) Report. on in Decommissioning Activities. Dr. Lucian BIRO Director General

Decommissioning three main strategies: Immediate dismantling, Safe enclosure (Deferred dismantling), Entombment

REGULATION ON RADIOACTIVE WASTE MANAGEMENT

International Structure for Decommissioning Costing (ISDC) ISDC Costing Methodology, Principles. CERREX Costing Software for Research Reactors

Pham Hoai Phuong and Pham Van Lam NUCLEAR RESEARCH INSTITUTE, VAEC

A Radiation Protection Perspective- Decommissioning of the Moata Reactor. Biological Shield Dismantling

DECOMMISSIONING IS INEVITABLE: PLANNING SOONER RATHER THAN LATER CAN HAVE BIG PAYOFFS FOR NUCLEAR POWER PLANTS AND UTILITIES

2007 ANS Topical Meeting on Decommissioning, Decontamination and Reutilization September 2007, Chattanooga, TN, United States of America

C. Kennes - C. Mommaert - M. Van haesendonck (Bel V) H. Libon - A. De Backer (Belgonucleaire) Decommissioning of Belgonucleaire MOX plant

IAEA-TECDOC-1478 Selection of decommissioning strategies: Issues and factors

Radiation Protection Challenges associated with the dismantling of Nuclear Power Plant

Applicability of EPRI Decommissioning Pre-Planning Manual to International Decommissioning Projects

The EnBW Strategyfor Decommissioningand DismantlingofNuclearPower Plants»

WM 2010 Conference, March 7-11, 2010 Phoenix, AZ

Safety principles of radioactive waste management activities and supportive IAEA documents

Spanish Management Issues in Radioactive and Nuclear Waste Materials Dr. Amparo González Espartero

DECOMMISSIONING PROGRAMS AND TECHNOLOGY DEVELOPMENT IN JAPAN ATOMIC ENERGY RESEARCH INSTITUTE

NUCLEAR SAFETY REQUIREMENTS BSR

Adapting Dismantling and Decommissioning Strategies to a Variety of Nuclear Fuel Cycle Facilities 12237

BAE SYSTEMS Marine Ltd s strategy for the decommissioning of the Barrow nuclear licensed site

Linde FUSRAP Site Tonawanda, New York

RADIOACTIVE GRAPHITE MANAGEMENT AT UK MAGNOX NUCLEAR POWER STATIONS. G. HOLT British Nuclear Fuels plc, Berkeley, United Kingdom 1.

DECOMMISSIONING OF NUCLEAR FACILITIES IN UKRAINE

San Onofre Unit 1 Decommissioning

TOPICAL SESSION MANAGEMENT OF DECOMMISSIONING WASTES

Hugo E. Rivera Project Officer May 2012

Decommissioning and Site Release Problems for Georgian Nuclear Research Reactor IRT-M

Alec Kimber Australian Nuclear Science & Technology Organisation

Decommissioning of Nuclear Facilities: The Work Ahead and How to Succeed

Decommissioning and Radioactive Waste Management in Lithuania

Gerhart Grinanger, NOELL GmbH, Postfach 6260, D-8700 Wizrzburg, Germany

STRUCTURAL RADIATION SAFETY AT A NUCLEAR FACILITY

Regulatory Approach on Decommissioning of Nuclear Installations in Argentina. Siraky, G.

IAEA-TECDOC-1133 The decommissioning of WWER type nuclear power plants

RADIOACTIVE CONTAMINATED SCRAP IN METAL RECYCLING FACILITIES

STURGIS Barge Decommissioning Project

- 1 - Ingenieurgesellschaft für wissenschaftlich technischen Umweltschutz

Draft Summary of Plant Life Management in Transition from Operation to Decommissioning for Nuclear Power Plants. Prepared by core team

Decommissioning of NPPs with spent nuclear fuel present - efforts to amend the German regulatory framework to cope with this situation

Prospective Radiological Environmental Impact Assessment for Facilities and Activities

ANSTO s POLICY for MOATA & HIFAR. Prepared by John Rowling November 2007

Decommissioning of Nuclear Facilities. Waste Management

Decommissioning in Germany: Greifswald NPPs. Bernd Rehs Federal Office for Radiation Protection (BfS)

Safety Assessment for Decommissioning of a Nuclear Laboratory

Decommissioning the North Korean Nuclear Facilities: Approaches and Costs 1

Radiation and Nuclear Safety Authority Regulation on the Safety of Disposal of Nuclear Waste Adopted in Helsinki on 22 December 2015

Lessons Learned from Shut-Down to Decommissioning Plan at the Army Pulse Radiation Facility

TECHNICAL MEETING ON TECHNICAL SUPPORT ORGANIZATION (TSO) ROLE AND RESPONSIBILITIES May 2013

DEPARTMENT OF MINERALS AND ENERGY RADIOACTIVE WASTE MANAGEMENT POLICY AND STRATEGY FOR THE REPUBLIC OF SOUTH AFRICA

Preparation for Future Defuelling and Decommissioning Works on EDF Energy s UK Fleet of Advanced Gas Cooled Reactors

Waste Management for Decommissioning of Nuclear Power Plants An EPRI Decommissioning Project Report

PRESENT STATUS OF LEGAL & REGULATORY FRAMEWORK AND DECOMMISSIONING PLANNING FOR DNRR. Prepared by NUCLEAR RESEARCH INSTITUTE, VAEC.

The Strategies of Research and Education on Decommissioning of Nuclear Facilities in the University of Fukui

The decommissioning of nuclear plants and facilities is

Zion Project Overview S. Chris Baker VP EH&S

RESEARCH REACTOR FRJ-1 (MERLIN) THE CORE STRUCTURES OF THE REACTOR BLOCK ARE DISMANTLED

Benefits from R&D for D&D Projects Preparation

INPRO TM Towards Nuclear Energy System Sustainability Waste Management and Environmental Stressors

ENVIRONET Network on Environmental Management and Remediation. Terms of Reference

LAW OF THE PEOPLE'S REPUBLIC OF CHINA ON PREVENTION AND CONTROL OF RADIOACTIVE POLLUTION

0 SUMMARY 4. 1 INTRODUCTION AND METHOD Purpose Method Scope and Assumptions Scope Assumptions 12

Experiences on a Regulatory Clearance of the Radioactive Wastes at KAERI

Copyright BKW Energie AG

Dismantling of nuclear facilities in France: what is at stake?

Greenhouse Gas Emission of European Pressurized Reactor (EPR) Nuclear Power Plant Technology: A Life Cycle Approach

Operational Decommissioning Experience in France Radioactive Waste Management and Radiation Protection Issues

Decommissioning Activities at IPEN/CNEN-SP Brazil

ENVIRONMENTAL IMPACT ASSESSMENT (EIA) AND THE ENVIRONMENTAL IMPACT STATEMENT (EIS) 2.0 Developments requiring preparation of an EIS

PLAN FOR MOATA REACTOR DECOMMISSIONING, ANSTO

RADIATION PROCEDURES MANUAL Procedure Cover Sheet

IAEA-TECDOC-1572 Disposal Aspects of Low and Intermediate Level Decommissioning Waste

SD:SPUR Scoping Document Waste Management Framework Guidance Note No.1. Waste Characterisation and Management of Residual Wastes. Final, August 2009

Uranium mining legal and regulatory framework

Standardised Reporting of Radioactive Discharges from Nuclear Sites

Radioactive Waste Management Agency. and. Nuclear Safety Authority. in Belgium

EDF DECOMMISSIONING PROGRAMME - A PREREQUISITE FOR THE ERECTION OF NEW NUCLEAR POWER PLANTS IN FRANCE

MFC CH-TRU Waste Certification Plan

RECYCLING OF URANIUM- AND PLUTONIUM-CONTAMINATED METALS FROM DECOMMISSIONING OF THE HANAU FUEL FABRICATION PLANT

RESEARCH REACTOR DECOMMISSIONING PLAN

Interim Guidance on the Regulation of In-situ Disposals of Radioactive Waste and Residual Radioactive Contamination on Nuclear Authorised Premises

Development of technologies for the processing and disposal of radioactive waste

Decommissioning Group Ketut Kamajaya

Joint Convention on the safety of spent fuel management and on the safety of radioactive waste management

P. Brennecke, S. Steyer Bundesamt für Strahlenschutz Willy-Brandt-Strasse 5, D Salzgitter, Germany

The ICRP Proposed Maximum Public Dose Constraint of 0.3 msv/y: a Major Issue for the Nuclear Industry

Overview of Hanford Site Risk Assessment to Support Cleanup Decision Making

French National Plan. for the management of Radioactive Materials and Waste SUMMARY

Greifswald Project Introduction/Experience summary Axel Bäcker

Radiological hazards from uranium mining.

LEGAL AND REGULATORY FRAMEWORK FOR RADIOACTIVE WASTE MANAGEMENT AND DECOMMISSIONING IN SLOVAK REPUBLIC

during Normal Operations

SHIPMENT/RECEIPT OF RADIOACTIVE MATERIAL RCT STUDY GUIDE

Transcription:

DECOMMISSIONING STRATEGIES AND PLANS By: Elna Fourie Necsa South Africa Manager: Decommissioning Services 2011

SELECTION OF A DECOMMISSIONING STRATEGY The two most common decommissioning strategies are immediate dismantling and deferred dismantling. A combination of these options, known as phased decommissioning, which consists of periods of active dismantling interspersed with safe enclosure phases, is also common. In the case of front end NFC facilities uranium is the most significant nuclide present. Uranium is a long lived isotope and there is no radiological justification for a deferred decommissioning strategy. In the case of uranium mining and milling facilities the adverse effect on the environment (e.g. possible contamination of groundwater) is a major driver for immediate decommissioning. There is a possibility that the engineering safety barriers implemented at the liquid waste/tailings and other storage areas could fail and that the proper monitoring carried out during the operation of the facility is not continued as accurately after shut-down of the facility. 2

DEFINITIONS Phase 1 decommissioning covers the facility Termination of Operation and the minimum decommissioning activities such as the removal of inventory to obtain a state of passive safety. This phase is associated with a facility-specific care and maintenance programme which is developed to be commensurate with acceptable risk. Phase 1: Preparation for decommissioning. This phase includes: The development of a decommissioning strategy. Initial decommissioning planning. Radiological and chemical characterisation of the facility. Preliminary decontamination and initial cleanup that could include the fixing of contamination until the next phase is implemented. Normally after the first phase of preparation and initial cleanup the facility is placed under surveillance or safekeeping as a passively safe facility. 3

DEFINITIONS Phase 2 decommissioning covers the dismantling and removal of the components, systems and equipment including decontamination as appropriate with the aim of restricted re-utilisation of facilities or reducing care and maintenance requirements. Phase 2: Implementation of Decommissioning The preparatory work for Phase 2 requires more in-depth evaluation. An adequate number of radiation and contamination surveys should be conducted to identify all the remaining radionuclides present in inner and outer surfaces throughout the facility, maximum and average dose rates and surface contamination levels. All the inventory that was not removed during Phase 1 decommissioning should be listed. Contamination inside pipes and equipment should also be characterised and quantified as far as possible. The selection of the correct dismantling and decontamination techniques is critical. 4

DEFINITIONS Phase 3 decommissioning covers the activities required for the clearance of facilities. Activities may range from final decontamination of facilities to clearance levels, or complete demolition of buildings and removal of all contaminated materials. Phase 3 (in particular for nuclear facilities) is the ultimate endpoint of decommissioning after which a facility is released or removed from further regulatory control. 5

DEFINITIONS Care and maintenance: Actions such as surveillance, inspection, testing and maintenance to ensure that facilities are maintained in a safe state between decommissioning phases. Clearance: Removal of radioactive materials and/or chemicals or radioactive/chemical objects within authorised practices from any further control by the relevant regulatory authority. Decommissioning plan: A Decommissioning plan must be submitted to the Regulator as a basis for authorisation of specific actions or phases of decommissioning. Decommissioning: Actions, including Termination of Operation, dismantling and decontamination taken at the end of the useful life of a nuclear or chemical facility (building and process equipment) in retiring it from service with adequate regard for the health and safety of workers and members of the public and protection of the environment. The ultimate goal of decommissioning is clearance for reuse of buildings or total removal of buildings and site restoration (green fields). The time period to achieve this goal is dependent on the circumstances of each case. 6

DEFINITIONS Decommissioning option: One of various decommissioning strategies, such as immediate dismantling and safe enclosure or deferred dismantling, which may be considered when decommissioning is being planned. A variety of factors, such as further use of the facility, the availability of technologies and waste management facilities, will influence which decommissioning option is ultimately chosen. Decommissioning strategy: Decommissioning strategy must be submitted as part of the prior safety assessment and must be updated throughout the operation of the authorised action as a basis for detailed decommissioning planning. Decontamination: The removal or reduction of radioactive or chemical contamination by a physical, chemical or metallurgical process. Dismantling: The disassembly and/or removal of any structure, system or component during decommissioning. Dismantling may be performed immediately after the Termination of Operation of a facility or may be deferred. Termination of Operation: The activities involved during the period from the time when normal operation ceases until the facility permanently stops processing. 7

DEFINITIONS Nuclear Fuel Cycle Facilities: The following facilities are regarded as NFC Facilities : Uranium mining and milling facilities. Uranium conversion facilities. Uranium enrichment facilities. Fuel fabrication facilities. Fuel reprocessing facilities. 8

SELECTION OF A DECOMMISSIONING STRATEGY There are a large number of nuclear and radiological facilities including legacy sites worldwide that have been decommissioned successfully, are either currently in an active decommissioning phase or will require decommissioning in the near future. The IAEA has developed safety standards and recorded technical information for use by regulators, operators, owners and decommissioning specialists for more than 30 years. Decommissioning activities must be performed with an integrated approach to achieve a progressive and systematic reduction in radiological hazards and ensuring the safety of workers and the public and the protection of the environment, throughout as well as after the project. 9

NUCLEAR FUEL CYCLE FACILITIES The specific decommissioning problems encountered by the NFC facilities as compared to reactors are due to their extreme diversity, which are reflected in the wide range of functions carried out in the areas required to be dismantled. There are different types of equipment requiring decommissioning ranging from hot cells, glove boxes, shielding and other containment systems, to large storage vessels and non-process mechanical equipment such as overhead cranes. The types of contamination encountered (alpha, beta and gamma) and chemical contamination are also diverse. It must be ensured that the correct radiological and chemical characterisations are done from the planning phase throughout the project to ensure that the chances of discovering unforeseen high levels of contamination are limited. 10

CONSEQUENCES OF SHUT-DOWN Termination of NFC operations results in a significant impact on the local economy because most of these facilities supplied various job opportunities. The NFC facilities occupied large areas with large components and complex equipment and facility arrangements that required labour skills ranging from highly skilled to non-skilled labour. After the termination of operations these areas or facilities require some form of control until fully decommissioned. In the case of uranium mining and milling the shutdown is due to a sudden downward fluctuation in selling price or depletion of ore that resulted in a forced shut down. These unplanned shut downs usually go hand-in-hand with a lack of resources and retrenchment of personnel. 11

CONSEQUENCES OF SHUT-DOWN Phase 1 should immediately proceed as part of the shut-down activities, while the technical resources, specialist and supporting facilities that were available during operation are still on the site. Necsa had to contract in 3 old guys (Richard 75 years old) to assist in the decommissioning project due lack of other specialists on site/countrly 12

PREPARATION WORK A survey of radiological and non-radiological hazards should be made as an important input to the compilation of a decommissioning plan and a safety assessment for decommissioning that will be used for the implementation of safety aspects during the execution of the decommissioning activities. The proper recording of information while the staff are still on the site is an essential part of the survey. The survey should be conducted to identify the inventory and location of radioactive materials as well as other hazardous materials. Hazardous Chemical Substances (HCS) such as asbestos, mercury and polychlorinated biphenyls (PCBs) require special consideration to prevent harm to human health and to the environment. Failure to identify these HCS could have a major impact on the decommissioning project cost. 13

DECOMMISSIONING PLANNING The decommissioning plan must at least contain the following: PURPOSE: What is the reason for compiling a decommissioning plan. There could be more than one reason but the main purpose is to obtain approval for a project. The purpose of the plan is to request authorisation and approval from the National Nuclear Regulator and other regulatory and financial bodies (internal or external from the organisation). The plan should thus explain to all interested parties how you intend to decommissioning the facility in a safe and effective manner, how long it will take you to complete the project, how much will it cost you do execute the project and what are the benefits of performing the project. 14

DECOMMISSIONING PLANNING SCOPE AND OBJECTIVE: The scope and objective of each decommissioning project could be different and are influenced by the end-state required for the facility. Will you remove the facility after the completion of the decommissioning project from regulatory control. The Scope of the decommissioning plan must at least include the various approvals and resources required prior to commencing with the project. The objective must state the final state of the facility. 15

DECOMMISSIONING PLANNING RESPONSIBILITIES: As part of the planning for decommissioning it is important to clarify each role player and their responsibilities. The responsible personnel should be appointed in their capacity and their various authorisation and accountability should be well defined. 16

DECOMMISSIONING PLANNING FACILITY HISTORY: This information is very critical and as much of the history should be recorded and evaluated to determine what the risks are (element of surprise). The incident or nuclear occurrence history should be analysed to assist in determining the total scope of the project. Do the radiological characterisation results compare with the history records of the facility. Maybe a Cliché but still valid : ALWAYS EXPECT THE UNEXPECTED 17

DECOMMISSIONING PLANNING OTHER ELEMENTS OF PLANNING ARE: Sequence of Work Waste Management Radiological Hazards Environmental Control General Working conditions (working on heights, confine spaces, temperatures etc.) Chemical Hazards Record Control Public Participation Etc. 18

SELECTION OF TECHNOLOGIES There are various state of the art decommissioning technologies that can be used for characterisation, decontamination, dismantling, waste processing, remote handling, etc. Such technologies are readily available in developed countries but are often costly and hard to apply in the absence of adequate resources and fully developed infrastructures. This leaves developing countries with challenges often leading to serious delays in performing decommissioning activities. Some decommissioning projects have been deferred since the mid 1970s. The lack of resources and available technologies, however, is not the only reason for this. The lack of waste management and waste disposal in many instances is contributing to selecting the deferred decommissioning option. There should also be a balance between developing project specific technologies and purchasing technologies in the open market based on cost, stakeholder satisfaction and safety 19

OPERATIONAL LIVES VS DECOMMISSIONING PERIOD The operational lives for the NFC facilities and the associated decommissioning times required, are different for various facility. The time required for decommissioning, however, is influenced by the end state specified for the decommissioning project. A decision that the facility is to be reused for radiological purposes and the aim is not unrestricted release will have a significant influence on the time required for decommissioning. Uranium mining and milling facilities: 25 years of operation and approximately 1 year required for decommission. Uranium conversion facilities: 3 0 years of operation and approximately 3-5 years required for decommission. Uranium enrichment facilities: 30 years of operation and approximately 10 years required for full decommissioning. Fuel fabrication facilities: 25 years of operation and approximately 2 years required for decommissioning. Fuel reprocessing facilities: 25 years of operation and more than 15 years for decommissioning. 21

Thank You!!!