Massport Capital Programs Enterprise Schedule Management. Document 11 A. Primavera Schedule Toolkit Vertical Projects. July 2017 Version 1.

Similar documents
COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL

SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

P6 Instructors Sample Presentation

Schedule Guidance Document

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course

Lessons Learned Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International

Procurement Department Bid Office Customer Center 1 st Floor, Room W. Church Street Jacksonville, Florida 32202

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management

P6 Version 8.2 to 8.4 EPPM Web Power Sample Point Slide Show

SECTION NETWORK ANALYSIS SCHEDULES (NCA)

Program Management Procedure. Schedule Management

Primavera P6 R8.3 Professional Fundamentals Training Course Outline

Views and Layouts for Program Management

Plan Your Work, Work Your Plan. Dr. R. Rockland Chair and Professor, Department of Engineering Technology New Jersey Institute of Technology

3-Day Oracle Primavera P6 Professional Fundamentals - Training Outline -

Project Planning and Control Using Oracle Primavera P6 : P8.3, 8.4, 15.2

Application & Management of CPM Schedules

PMP Exam Preparation Course Project Time Management

Estimating Project Schedule-Time and Cost

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 & 8.2 Professional and Optional Client 3 day training course SAMPLE SLIDE SHOW

Project Forecast Survey Results Good Scheduling Practices June 2016

Meeting the Challenge of EPC Project Proposal Schedules. Project Proposal Schedules

by Ron Winter Consulting LLC January 6, 2015

Primavera Training - P6 Basic Course (102)

ATTACHMENT D SCOPE OF SERVICES

PROMASTAR Instructor led Professional Training Services Primavera Accredited/Certified Class Courses

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

Jacksonville District Master

LONG INTERNATIONAL. Andrew Avalon, P.E., PSP and Curtis W. Foster

Forsyth County General Services Department Construction Management Division 201 North Chestnut Street Winston-Salem, NC 27101

Welcome to the Eastwood Harris Pty Ltd PRINCE2 TM Revised 2009 and Microsoft Project 2010 training course

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

Understanding Import & Export with NetPoint 4.2

Exam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4.

Borderlink Resources Limited.

New Features in Primavera Gateway 14.2

Estimating and Scheduling

Angus AnyWhere. Reports User Guide AUGUST 2012

LONG INTERNATIONAL. Richard J. Long, P.E., Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA

Andrew Avalon, P.E., PSP

Exam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4.

Project Management Concepts, Tools & Techniques

Project Time Management

Consulting Newsletter

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by.

Planning & Scheduling CSTM 102

Project Cost Management

PMBOK Guide Fifth Edition Pre Release Version October 10, 2012

Module #4 Time Impact Analysis

Risk Management User Guide

Microsoft Project 2016

[Company] [Company Address] [Project Name] [Sub-Project, phase, etc.]

EJCDC Contract Documents for America s Infrastructure Buy online at

Microsoft Project Tips & Tricks. Project Solutions Group, Inc.

Epicor ERP Project Billing - Fixed Fee Course

2-Day Oracle Primavera P6 Professional Advanced Scheduling - Training Outline -

Document B252TM 2007

Invoice Manager Admin Guide Basware P2P 17.3

Guten Tag. (good day)

P6 Team Member Implementation Stories

THE NATIONAL SHIPBUILDING RESEARCH PROGRAM

Cambridge International AS & A Level Computer Science

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155

Your easy, colorful, SEE-HOW guide! Plain&Simple. Microsoft Project Ben Howard

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk

STO Navigator Canada Best-Practices Manual

Specifications and Drawings

Oracle. SCM Cloud Using Supply Chain Collaboration. Release 13 (update 17D)

Assessing Extensions of Time Tony Farrow Trett Consulting March 2006

14 reasons to use Asta Powerproject for managing construction projects. elecosoft.com. Asta Powerproject: The power behind successful projects

Primavera Curriculum. For the individual

Useful P6 EPPM Terms Security Configuration Process in P6 EPPM Defining Global Security Profiles in P6 EPPM... 19

Workshop: Advanced Cost Management Techniques Using Cobra

EXHIBIT A Scope of Services Program Services Scheduling, GIS and Web Support

P6 Schedule Maintenance Process

BUSINESS ANALYTICS. Version 5.8

Enclosed is Addendum No. 2 to SEPTA's Sealed Bid No ATMM 5 & Market Station Enhancement Project.

Oakland County Department of Information Technology

City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services

GROUND RULES AND PRICING INSTRUCTIONS:

Errata 1 st Printing. Errata 2 nd Printing

Managing Schedule Change

Project Engineers and Supervisors Conference. CPM Scheduling

13 Project Graphics Introduction

Project Management Basics

Scott M. Francis, P.E., PSP

Program Evaluation and Review Technique (PERT)

Construction Formwork Inventory Control Tracking System

AACE Planning and Scheduling Professional (PSP) Certification Preparation Training Course Brochure and Competency Matrix

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter

Schedule Margin. Contingency for Schedulers. John Owen, Product Manager Schedule and Risk, Deltek

Task Control for bpm'online. User Manual

Application for Focus on Energy s Biogas Feasibility Study Grants for Anaerobic Pretreatment and Anaerobic Digester Facilities

Time Reporting User Guide

Document No: SB002-P3 Revision No: Last Updated: April

Strategic Management Guide

THE HOME DEPOT. Vendor SSR Training Guide

14 reasons to use Asta Powerproject for managing construction projects

Transcription:

Massport Capital Programs Enterprise Schedule Management Document 11 A Primavera Schedule Toolkit Vertical Projects July 2017 Version 1.5

Contents 1.0 INTRODUCTION 2 1.1 DISCLAIMER 2 2.0 TOOLKIT SCHEDULE COMPONENTS 3 2.1 SCHEDULE FILE 3 2.2 PRIMAVERA SCHEDULE SETTINGS 3 2.3 CALENDARS 4 2.4 MILESTONES 5 2.5 ACTIVITY SETTINGS 6 2.6 COST LOADING 8 2.7 SCHEDULE LAYOUTS 9 2.8 BASELINE SCHEDULES (TARGETS) 10 2.9 NARRATIVE 11 Publication Version Control: Document Title Version Date Author Reviewed By MPA Schedule Toolkit 1.4 6/13/2016 Massport Project Controls/ MPA Project Controls 4/13/2016 PMA Consultants MPA Schedule Toolkit 1.5 8/07/2017 PMA Consultants MPA Project Controls 1

1.0 INTRODUCTION The Authority s Schedule Toolkit is an extension of the Project Schedule Specification and is intended to provide Contractors with support and guidance in meeting the requirements of the schedule specification. The toolkit is comprised of this document, a Primavera schedule XER file and Primavera schedule layout PLF files. The toolkit provides the following benefits: provided vendors with a schedule backbone that support the software requirements, minimizes the administrative burden of adjusting the vendor schedule platform to meet these requirements, provide standard reports, calendars, activity IDs and layouts that meet the Authority s requirements. 1.1 Disclaimer It remains the Contractor s responsibility to ensure that the schedule submittal meets the Authority s Contract and specification requirements. The Contractor remains responsible for the project scope of work, the means and methods, and the planned sequence of work. The Contract and specification control for instances where there are discrepancies between these documents and the toolkit. The Authority does not guarantee that the toolkit is free from errors or inconsistencies, and the presence of such errors or inconsistencies does not relieve the Contractor from preparing schedule submittals in accordance with the Contract requirements and the specific requirements of the Engineer. The Authority makes no representations or warranties of any kind, express or implied, about the accuracy, reliability, or completeness with respect to the toolkit or any of the information, services, or related content contained therein for any purpose. The Authority assumes no liability or responsibility for any damages (whether incurred directly or indirectly) or loss of any kind that might arise from the use of, misuse of, or the inability to use the information contained in the toolkit. The Authority assumes no liability for improper or incorrect use of the toolkit. The Authority reserves the right to update, remove, or amend any of the information contained in the toolkit as needed without prior notice. Refer to the Authority s website for updates to this toolkit. 2

2.0 Toolkit Schedule Components 2.1 Schedule File This attached schedule template was created in Primavera P6 release 15.1 and was designed in an effort to aid the Contractor in developing a schedule that will meet the Contract specifications. The template includes standard resources ids, cost accounts, project and activity codes, work breakdown structure organization, work calendars, and standard layouts. In order to use the template, the Contractor will need to save the XER file to the scheduler s local drive, open Primavera and import the file. 2.2 Primavera Schedule Settings The template has been developed using the following schedule settings, which can be found under tools/schedule/options. The Contractor shall adhere to these settings. 3

2.3 Calendars Primavera uses activity calendar assignments to model the allowable work periods. The Authority has developed several standard calendars to represent the work periods normally encountered on Authority projects. These calendars were developed in accordance with the standard specifications and many of the common work restrictions. The Contractor is suggested to use these calendars whenever possible; however, it is the Contractor s responsibility to ensure that the calendars are in compliance with all project restrictions. The Contractor should ensure that each activity in the schedule is assigned to a calendar that is appropriate for the work type. The Contractor must ensure that Calendars are maintained at the Project Level. Global calendars will not be accepted. The following standard Calendars have been created: The Contractor must request the use of any additional calendars prior to their use. The template schedule has been updated to include Massachusetts holidays through 2029. Holiday references: http://www.sec.state.ma.us/cis/cishol/holidx.htm 4

2.4 Milestones The Contract requires the following milestones to be included with all schedule submissions. The required project milestones vary by project type, either horizontal, vertical, or other projects, as shown below. All Contract milestones should be assigned to a 7 day calendar with no holidays provided. As noted in the schedule specification, the activity ID and activity name must match what has been provided in the specification (as listed below). In addition, the activity ID and activity name must not change through the life of the project. Vertical Projects Design Activities Activity ID Activity Name MPA2000 Design NTP MPA2100 Completion of Programming / Feasibility (0% 20%) MPA2200 Completion of Concept Design (0% 20%) MPA2300 Completion of Schematic Design (20% 30%) MPA2400 Completion of Design Development (30% 50%) MPA2500 Completion of Construction Documents (50% 100%) Construction Activities Activity ID Activity Name MPA5000 Construction NTP MPA5100 Enabling Work Complete MPA5200 Environmental Remediation Complete MPA5300 Weathertight MPA5400 Commissioning/Testing Complete MPA5500 Construction Substantial Completion (TCO) MPA5600 Construction Cert of Occupancy (COO) MPA5700 Final Completion 5

2.5 Activity Settings Work Breakdown Structure Each schedule submission must adhere to the WBS provided below. This WBS is included in the schedule toolkit XER file. The WBS structure shown below is the primary means for schedule organization and grouping. Additional WBS detail may be added and utilized at the Contractor s discretion. WBS Structure: Vertical Design Contracts WBS Structure: Vertical Construction Contracts 6

*Note: Procurement WBS Node shown as example for clarity. Contractor is responsible for development the Procurement node to accurately reflect the Divisions/Bid Packages included in the Contract Documents. Activity Codes The WBS will serve as the primary method for schedule organization and grouping. However, activity codes may be added and utilized at the vendor s discretion. The Contractor must ensure that Activity Codes are maintained at the Project Level. Global activity codes will not be accepted. 7

2.6 Cost Loading The Authority requires that each schedule submission include cost loading. The following process is required for all schedule submissions: Each schedule submission will reflect the total project price. The entire bid price (plus approved changes) must be loaded into the schedule. o For Vertical Projects, cost loading must be provided at the buy/bid package level. o For Horizontal projects, cost loading must be provided at the CSI summary level. Level of effort (LOE) activities must be created for each buy/bid package or CSI summary level. LOE activities must be tied appropriately into the CPM network to reflect the appropriate buy/bid package or CSI scope. An example for construction cost loading is provided below. The WBS includes sections for Design Cost Summary activities and Construction Cost Summary activities, depending on the project type. Each LOE activity must be assigned a non labor resource entitled resource ID: MPA LS (MPA Lump Sum). This resource has been created by MPA and is included within the schedule toolkit XER file. An example is shown below. Each LOE activity must be assigned a cost distribution curve. The use of a cost account codes are not required The use of expenses for cost loading will not be accepted. Cost should be maintained at the Global Level. All schedule submissions must adhere to the following Primavera cost settings: The duration type for each activity should be set to Fixed Duration and Units before associating any cost or resources to the activity. 8

In the activity view, select Enterprise/Resource, then select the Resource item that is tracking Cost (in the Toolkit, the resource field for cost is MPA LS ). Then select the Details tab, then ensure the boxes for Auto Compute Actuals and Calculate Costs from Units are unchecked. 2.7 Schedule Layouts The Authority requires that each schedule submission be accompanied by the following standardized schedule reports. Each report should be created (PDF format) and submitted as required in the schedule specification. The Authority has created several Primavera Layouts file (PLF) for use of the Contractor to meet the requirements of the specifications. The Contractor should download the Primavera Layout file (.PLF). The following layouts have been created: 1. All Activities (General Schedule Layout) 2. Critical Path/Longest Path Layout 3. Monthly Cash flow Layout 4. Look ahead Layout 5. Recent Progress Layout To import layout files, follow the steps listed below: 1. Import each Layout separately (Navigate to View/Layouts/Open/Import) 2. Once imported, select the layout you wish to use (Navigate to View/Layouts/Open) The Authority requires the following information to be included within all schedule reports, unless otherwise noted. Schedule Information Columns View: o Current Schedule: Activity ID, Name, Start*, Finish*, Total Float, o Baseline Schedule: Baseline Start, Baseline Finish, Baseline Total Float, Variance of Baseline Finish o *Start and Finish dates should be the Primavera fields labeled Start and Finish. Schedule Information Bars View: o Bars presented, colors, target information, calendar formatting, etc. Appropriate grouping and sorting Appropriate color formatting Appropriate data filtering Administrative Report Information: o Header and footer information, Report titles, Page break locations, page numbers, etc. 9

2.8 Baseline Schedules (Targets) In order to track schedule variance over time (against previous schedule submissions), all schedule reports must include variance tracking to the previous month and current accepted baseline schedule. The previous month s schedule file should be set as the Primary Baseline, the current accepted baseline file should be set to the User Baseline Primary. This setting can be found in Primavera at project/assign baseline 10

2.9 Narrative As stated in the schedule specification, Division IIB, Article 53, all schedule submissions shall include a detailed written narrative. The Contractor s narrative should address the following: Provide a milestone chart. Include the original and modified Contractual (or approved baseline) dates as well as the current and previous forecasted dates for all interim and Contractual milestones. Provide variance columns for the following a) current vs Contractual, b) current vs modified Contractual, c) current vs previous. Provide executive summary. Longest Path. o Describe the scope of work and major sequences for all activities on the Longest Path. Provide explanation for any changes since the previous schedule update. o Provide a comparison of early and late dates for longest path activities. Provide explanation for changes on the top three longest paths; o Describe the Contractor's plan, approach, methodologies, and resources to be employed for completing the work for top three longest paths. Progress: o Provide a summary of work progress during the update period. o Provide a summary of the look ahead for the forthcoming update period. o Provide a summary of all changes to the schedule during the update period; including additions, deletions or changes to the following: milestones, activities, logic relationships, codes, WBS, etc. Provide references to any Notice of Delay that has been issued. Provide a detailed discussion of added activities within the schedule that reflect the delay and how delay affects the project critical path. Provide explanation for all areas where any specification requirements are not being addressed or followed. Provide a list of response required for key decisions. Indicate which items are critical or near critical (based on project total float), as well as the need date for the response. Provide explanation of possible considerations to achieve early completion or schedule recovery. Provide a list of all activity calendar being used. Provide explanation for use of shift work. Provide explanation for any changes to activity calendar usage since previous schedule submissions. Provide explanation for all out of sequence schedule logic. Provide explanation for each instance of out ofsequence activity logic. Provide a project monthly cash flow, by the buy/bid package or CSI level. In addition, address variance from the previous forecasts. Planned Percent Complete Update. 11