Generator Interconnection Affected System Impact Study. Plains & Eastern Clean Line Final Report

Similar documents
System Impact Study E001 Moon Lake 230 kv 200 MW Plant

Standard TPL Transmission System Planning Performance Requirements

Case Metrics 2015 Summer Base Case Quality Assessment Phase I Powerflow and Dynamics Case Quality Metrics FINAL

Standard Development Timeline

S P P 2016 TPL a n d FA C

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: Service Requested

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: IFHS MH MW, firm :00:00 CS

POTOMAC ELECTRIC POWER COMPANY

System Impact Study and Facilities Study Process Manual For Cleco Power LLC

MOD Data for Power System Modeling and Analysis

Standard 600 Determine Facility Ratings, System Operating Limits, and Transfer Capabilities

Overview of Control Area / Balancing Authority Functional Requirements Matt Wolf Manager Operations Support May 5, 2010

Standard PRC-002-NPCC-01 Disturbance Monitoring

Standard Development Roadmap

Artificial Island Proposal III Salem to Red Lion 500 kv Transmission Project

SPP 2017 TPL Planning Assessment Scope. Compliance and Advanced Studies

MISO SPP Interregional Stakeholder Advisory Committee. April 8 th, 2014 Carmel, IN

Methodology PLG-METH-0002-V4

PJM May 2014 Queue Generation Affected System Impact Study

8 th Annual Electric Power Industry Conference

California Independent System Operator Corporation Fifth Replacement Tariff

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014

DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA

2750 Monroe Blvd Audubon, PA

the most promising locations for new renewables in the Imperial CREZ.

Proposed Facility Study Report. Project: A380_A383_A415_A414_A413 MISO # F088. Prepared for Midwest ISO

Investigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection

Methodology PLG-METH-0002-V1

FRCC 2007 SYSTEM OPERATOR TRAINING SEMINARS. Reliability Coordinator Processes and Tools

The Effect of the Volt/Var Control of Photovoltaic Systems on the Time-Series Steady-State Analysis of a Distribution Network

M14B Annual Review. Jonathan Kern Transmission Planning Planning Committee March 8 th, PJM 2018

Virginia Solar Pathways Project

XXXX. Bremner Trio Small Hydro Project. Interconnection System Impact Study

Con Ed/PSEG Wheel Replacement Proposal A joint white paper from the New York Independent System Operator and PJM Interconnection

MISO-SPP Coordinated System Plan Study Report

ENTERGY FACILITY CONNECTION REQUIREMENTS March 2007

Session 9: Photovoltaic System Case Studies And Electric Distribution Planning for DER October 21, 2015 Santiago, Chile

MOD Steady-State and Dynamic System Model Validation

Appendix 1 PRELIMINARY DELIVERABILITY BASELINE ANALYSIS STUDY REPORT

Facility Interconnection Requirements

Research Co-design Activity

International ejournals

SOUTH AUSTRALIA SYSTEM STRENGTH ASSESSMENT

N-1-1 AC Contingency Analysis as a Part of NERC Compliance Studies at Midwest ISO

Technical considerations for integration of distributed renewables on the grid

TSR Modeling in Reliability Planning. Planning Subcommittee October 17, 2017

Methodology for Calculating Operating Limits for Generators

ELECTRIC ARC FURNACE WITH STATIC VAR COMPENSATOR PLANNING AND OPERATIONAL EXPERIENCE

WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY

TRC Solutions. Cost and Feasibility Analysis of a Third Converter Station for the Champlain Hudson Power Express Project

Anchor Data Set (ADS) Definition, Benefits, Implementation and Management Ver. 6-Aug 15 th DRAFT Proposal only

INTERSTATE TRANSMISSION VISION FOR WIND INTEGRATION

Phasor measurement units gain credibility through improved test and calibration standards

ISSN Vol.07,Issue.16, November-2015, Pages:

POWER SYSTEM STABILITY GUIDELINES

Grid Interconnection Issues for Wind Generation

SYSTEM IMPACT STUDY FINAL REPORT

Operating Procedure PURPOSE... 2

Flexible Transmission Decision Support

MAY 1, Variable Generation Integration Costs

Seminar on African Electrical Interconnection. Module 8 - Interconnected Systems Operating Conditions

SCHEDULE 12 Transmission Enhancement Charges. Establishment of Transmission Enhancement Charges.


Comparative Analysis between IG and DFIG for Wind Energy Conversion Systems using STATCOM

Power System Economics and Market Modeling

2012 Grid of the Future Symposium. Modeling and Simulation of Advanced Reactive Compensation Systems in Renewable Energy Applications

October 6, Submitted to: CAISO

Distribution Information Exchange Code

Distribution GIS & Grid Model Data Management

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System

South Plains Transmission Project

Evolution of the Grid in MISO Region. Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017

Hydro-Quebec s experience with HYPERSIM Real-time Power System Simulator

Solar Integration into the PJM Grid

Educating System Operators in the New Millennium! Background. Course Level. Target Audience. NERC Continuing Education Hours

Outage Coordination Training MISO Training

Mitigation of Voltage Fluctuations in Power System Using STATCOM

Western Wind & Solar Integration Studies

(D2-01_28) ROLE OF ICT in Power System


Control Number : Item Number : 58. Addendum StartPage : 0

Regional Transmission Organizations. D. William VanderLaan Illinois Commerce Commission January 30, 2014

WWSIS - 3: Western Frequency Response and Transient Stability Study

Power Plant Model Verification using PMUs

Available Transfer Capability Implementation Document TP-OP-005-r15 Effective Date: AUG Purpose. 2 Scope. 3 Definitions

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. Integration of Variable Energy Resources ) Docket No. RM

Study on the Application of Advanced Power Electronics in Smart Grid

Transmission Expansion Advisory Committee. Reliability Analysis Update

INITIAL ASSESSMENT OF REACTIVE POWER EXCHANGES AT UK GRID SUPPLY POINTS

Effective Management of Distribution Grid Model Data

Available Transfer Capability Implementation Document TP-OP-005-r18 Effective Date: DEC Purpose. 2 Scope. 3 Definitions

SPP at a Glance. Located in Little Rock. Approximately 600 employees

Power Technology Issue 124

ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM

WIND TURBINE PLANT CAPABILITIES REPORT

Manual No. 010 Business Practices Manual Network and Commercial Models

High Voltage Direct Current

LOCAL PLANNING REPORT

BULK ELECTRIC SYSTEM PLANNING CRITERIA

EIPC Roll-Up Powerflow Model

Transcription:

Generator Interconnection Affected System Impact Study Plains & Eastern Clean Line Final Report May 19, 2015 MISO 2985 Ames Crossing Eagan Minnesota - 55121 http://www.misoenergy.org Midcontinent Independent P.O. Box 4202 2985 Ames Crossing www.misoenergy.org Transmission System Operator, Inc Carmel, Indiana 46082-4202 Eagan, Minnesota 55121 317-249-5400

TABLE OF CONTENTS LIST OF TABLES & FIGURES ----------------------------------------------------------------------------------------------- 2 DISCLAIMER ---------------------------------------------------------------------------------------------------------------------- 3 1 EXECUTIVE SUMMARY ----------------------------------------------------------------------------------------------- 4 1.1 TRANSMISSION UPGRADE COST AND ALLOCATION ---------------------------------------------- 4 1.2 STUDY OVERVIEW ------------------------------------------------------------------------------------- 5 2 INTRODUCTION --------------------------------------------------------------------------------------------------------- 6 3 STEADY STATE ANALYSIS------------------------------------------------------------------------------------------ 7 3.1 CRITERIA METHODOLOGY AND ASSUMPTIONS --------------------------------------------------- 7 3.2 COMPUTER PROGRAMS ------------------------------------------------------------------------------ 7 3.3 MODEL DEVELOPMENT ------------------------------------------------------------------------------- 7 3.4 MONITORED ELEMENTS ------------------------------------------------------------------------------ 7 3.5 CONTINGENCY CRITERIA ----------------------------------------------------------------------------- 8 3.6 PERFORMANCE CRITERIA ---------------------------------------------------------------------------- 9 3.7 THERMAL ANALYSIS ----------------------------------------------------------------------------------- 9 3.8 VOLTAGE ANALYSIS ----------------------------------------------------------------------------------- 9 4 STABILITY ANALYSIS ------------------------------------------------------------------------------------------------ 10 5 EFFECTIVE SHORT CIRCUIT RATIO ---------------------------------------------------------------------------- 11 5.1 INTRODUCTION --------------------------------------------------------------------------------------- 11 5.2 METHODOLOGY -------------------------------------------------------------------------------------- 12 5.3 RESULTS ---------------------------------------------------------------------------------------------- 12 6 CONCLUSION ----------------------------------------------------------------------------------------------------------- 13 LIST OF TABLES & FIGURES Table 1.1. Study Project Overview... 4 Table 1.2. Total Estimated Network Upgrade Cost... 5 Table 2.1 Project Overview... 6 Figure 2-1 Approximate Geographic Location... 6 Table 3.1 - Monitored Elements... 8 Table 2.1 Short Circuit Ratios... 12 2

Disclaimer The accuracy of the conclusion contained in this study is sensitive to the assumptions made with respect to the generation addition (size, location, modeling data), prior queued generation projects, and other network changes being contemplated outside this study. Any change in these assumptions will affect this study s conclusion. 3

1 Executive Summary This report documents the affected system impact due to the interconnection of the Plains & Eastern HVDC project on the MISO Transmission system. Clean Line Energy Partners LLC is currently developing the Plains & Eastern Clean Line Project (P&E Project) which will use HVDC technology to deliver wind and solar generated electricity from southwestern Kansas, the Texas Panhandle and northwestern Oklahoma to serve load centers in the Tennessee Valley Authority (TVA) and other areas of the southeastern United States. It includes an approximately 700 mile +/- 600kV HVDC transmission link, capable of delivering 3500 MW to the inverter in the TVA system. Please note that this report only documents the system impacts on the MISO system from an Affected System perspective, it does not grant any interconnection or transmission rights on the MISO system. Two power flow scenarios were studied - Near term (2017) and Out-Year (2024). Steady State AC analysis was performed to identify any reliability criteria violations caused by the interconnection of the study project. The analysis did not identify any constraints in both the near term (2017) and the out year (2024) scenarios. Based on steady state results and consensus from the Ad-hoc group, no transient analyses were performed as part of this Affected System Study (AFS). Table 1.1. Study Project Overview Project Type Control Area County Point of Interconnection (POI) Summer Injection(MW) HVDC Injection TVA Shelby Shelby 500kV 3500 1.1 Transmission Upgrade Cost and Allocation The cost allocation of Network Upgrades for the study project reflects responsibilities for mitigating system impacts affected by the study project. The steady state thermal and voltage analyses have not identified any injection constraints. No network upgrades are being proposed at this point as outlined in Table 1.2 4

Table 1.2. Total Estimated Network Upgrade Cost ERIS Network Upgrades ($) Steady- State & Voltage Stability Transient Stability Shortcircuit NRIS Network Upgrades ($) Deliverability $0 N/A Future N/A Interconnection Facilities ($) N/A Non MISO POI Shared Network Upgrade Total Cost ($) N/A $0 1.2 Study Overview The study was performed by MISO. An ad hoc group was formed to participate in the study. The ad hoc group reviewed the study models and provided feedback on issues including but not limited to the equipment rating verification, suggestions for Network Upgrades, physical limitations at the existing substations, etc. The following companies were invited to participate in the study: AMRN, EES, EMI, LAGN, SMEPA, CLECO, LAFA, AECI & TVA The Affected system study included the following evaluations: A steady state thermal and voltage analysis to identify the limiting conditions at increasing levels of generation for NERC category A, B, and selected C events. An Effective Short Circuit Ratio(SCR) Calculation 1.2.1 Steady State Analyses The steady state thermal and voltage analyses have not identified any injection constraints. No network upgrades are being proposed at this point. 1.2.2 Stability Analysis This has been redacted from the scope of this study. 1.2.3 Effective Short Circuit Ratio The effective short circuit capabilities were found to be acceptable to accommodate the injection from the HVDC facility. No additional transient voltage control devices are currently being recommended. 5

2 Introduction The proposed project is a 700 mile +/- 600kV Line Commutated HVDC transmission link, capable of delivering 3500 MW to the inverter in the TVA system. This report presents the results of an Affected System Study (AFS) performed to evaluate the impact of interconnection on the Midcontinent ISO(MISO) facilities. Table 2.1 Project Overview Project Type Control Area County Point of Interconnection (POI) Study Sink Summer Injection(MW) HVDC Injection TVA Shelby Shelby 500kV TVA 3500 As shown in Figure 2-1, the study project is located in Shelby County in Tennessee. Figure 2-1 Approximate Geographic Location 6

3 Steady State Analysis 3.1 Criteria Methodology and Assumptions The objective of this AFS is to identify all adverse system impacts on the MISO transmission system as a result of the Plains & Eastern HVDC injection in TVA. 3.2 Computer Programs Steady-state analyses were performed using PSS E version 32.2.1 and PSS MUST version 11.0.1. 3.3 Model Development The starting models used for the thermal analysis were developed from the MTEP14 models with additional modification for access planning studies and used for the DPP- 2014-August study. Models were created using the Model on Demand (MOD) base cases, then load and generation changes were made to represent a summer peak scenario. All approved MTEP A projects submitted to MOD with effective dates through June 1, 2017 for the near term and June1, 2024 for the Out year scenarios were applied to the models. The injection into TVA was modeled as a generating facility at unity power factor and dispatched to the entire TVA footprint The power flow cases were solved with transformer tap adjustment enabled, area interchange disabled, phase shifter adjustment enabled and switched shunt adjustment enabled. 3.4 Monitored Elements The study area is defined in Table 3.1. Facilities in the study area were monitored for system intact and contingency conditions. Under NERC category A conditions (system intact) branches were monitored for loading above the normal (PSS E rate A) rating. Under NERC category B and C conditions, branches were monitored for loading as shown in the column labeled "Post-Disturbance Thermal Limits". In addition to the criteria below, all buses with defined voltage criteria have been monitored as per their planning voltage schedules. 7

Table 3.1 - Monitored Elements Thermal Limits Voltage Limits Owner / Area Monitored Facilities Pre-Disturbance Post- Disturbance Pre- Disturbance Post- Disturbance 327 / EES & 69 kv and above 100% of Rate A 100% of Rate B 1.05/0.95 1.05/0.92 EES-EAI 351 / EES & 69 kv and above 100% of Rate A 100% of Rate B 1.05/0.95 1.05/0.92 EES-EMI 332 /LAGN 69 kv and above 100% of Rate A 100% of Rate B 1.05/0.95 1.05/0.92 349 /SMEPA 69 kv and above 100% of Rate A 100% of Rate B 1.05/0.95 1.05/0.92 502 /CLECO 69 kv and above 100% of Rate A 100% of Rate B 1.05/0.95 1.05/0.92 356 /AMMO 100 kv and above 100% of Rate A 100% of Rate B 1.05/0.95 1.05/0.90 357 /AMIL 100 kv and above 100% of Rate A 100% of Rate B 1.05/0.95 1.05/0.90 503 /LAFA 69 kv and above 100% of Rate A 100% of Rate B 1.05/0.95 1.05/0.92 330 /AECI 69 kv and above 100% of Rate A 100% of Rate B 1.05/0.95 1.05/0.92 3.5 Contingency Criteria Contingency information as supplied by member of the Ad Hoc Study Group and included the following contingency files: A variety of contingencies were considered for steady-state analysis: NERC Category A with system intact (no contingencies) NERC Category B contingencies o Single element outages, at buses with a nominal voltage of 69 kv and above, in areas: EES, EMI, LAGN, SMEPA, CLECO, LAFA, AECI & TVA o Multiple-element outages initiated by a fault with normal clearing such as multi-terminal lines. NERC Category C o Selected NERC Category C events in the study region In addition to theabove, blanket statements were included for all single contingencies 60 kv and above for areas shown in Table 3.1. For all contingency analyses, cases were solved with transformer tap adjustment enabled, area interchange adjustment disabled, phase shifter adjustment disabled (fixed) and switched shunt adjustment enabled 8

3.6 Performance Criteria A branch is considered a thermal injection constraint if both of the following conditions are met: 1) The branch is loaded above its applicable normal or emergency rating for the post-change case, and 2) the generator has a larger than 20% DF on the overloaded facility under post contingent condition or 5% DF under system intact condition, or 3) the megawatt impact due to the generator is greater than or equal to 20% of the applicable rating (normal or emergency) of the overloaded facility, or 4) the overloaded facility or the overload-causing contingency is at generator s outlet. A bus is considered a voltage constraint if both of the following conditions are met. All voltage constraints must be resolved before a project can receive interconnection service. 1) the bus voltage is outside of applicable normal or emergency limits for the postchange case, and 2) the change in bus voltage is greater than 0.01 per unit. 3.7 Thermal Analysis The analysis did not identify any thermal injection constraints both in the near term (2017) and out year (2024) scenarios as per the above planning criteria. 3.8 Voltage Analysis The analysis did not identify any steady state voltage constraints both in the near term (2017) and out year (2024) scenarios as per the above planning criteria. 9

4 Stability Analysis Based on the steady state results and ad-hoc group agreement this set of analysis has been redacted from the study. Should the interconnection choose to submit a firm transmission service request with MISO, a stability study may need to be performed. 10

5 Effective Short Circuit Ratio 5.1 Introduction The strength of the A.C. network at the bus of the HVDC substation can be expressed by the short circuit ratio (SCR), defined as the relation between the short circuit level in MVA at the HVDC substation bus at 1.0 per-unit A.C. voltage and the D.C. power in MW. ( ) ( ) The capacitors and A.C. filters connected to the A.C. bus reduce the short circuit level. The expression effective short circuit ratio (ESCR) is used for the ratio between the short circuit level reduced by the reactive power of the shunt capacitor banks and A.C. filters connected to the A.C. bus at 1.0 per-unit voltage and the rated D.C. power. ( ) ( ) ( ) Lower ESCR or SCR means more pronounced interaction between the HVDC substation and the A.C. network. A.C. networks can be classified in the following categories according to strength Strong systems with high ESCR: ESCR > 3.0 Systems with low ESCR: 3.0 > ESCR > 2.0 Weak systems with very low ESCR: ESCR < 2.0 In the case of high ESCR systems, changes in the active/reactive power from the HVDC substation lead to small or moderate A.C. voltage changes. Therefore the additional transient voltage control at the inverter bus is not normally required. The reactive power balance between the A.C. network and the HVDC substation can be achieved by switched reactive power elements. In the case of low and very low ESCR systems, the changes in the A.C. network or in the HVDC transmission power could lead to voltage oscillations and a need for special control strategies. Dynamic reactive power control at the A.C. bus at or near the HVDC substation by some form of power electronic reactive power controller such as a Static Var Compensator (SVC) or Static Synchronous Compensator (STATCOM) may be necessary. 11

5.2 Methodology TVA provided the sequence data for the study. The short circuit fault MVA was calculated using the Automatic Sequencing Fault Calculation (ASCC) activity in PSS/E. The following Flat conditions were used - BUS VOLTAGES SET TO 1 PU AT 0 PHASE ANGLE - GENERATOR P=0, Q=0 - TRANSFOMRER TAP RATIOS=1.0 PU and PHASE ANGLES=0.0 - LINE CHARGING=0.0 IN +/-/0 SEQUENCE - LOAD=0.0 IN +/- SEQUENCE, CONSIDERED IN ZERO SEQUENCE - LINE/FIXED/SWITCHED SHUNTS=0.0 - DC LINES AND FACTS DEVICES BLOCKED - TRANSFORMER ZERO SEQUENCE IMPEDANCE CORRECTIONS IGNORED As per the Interconnection Customer, the reactive compensation at the inverter station will be provided by 4 x 252 MVAR AC filters, this amount of compensation will be reduced from the short circuit levels to yield effective short circuit numbers. 5.3 Results A 3 phase fault was applied at the Shelby 500kV bus in TVA to determine existing short circuit capacity. An additional sensitivity was performed by taking the strongest short circuit source out of service to account for prior outage conditions. The Shelby Sans Souci 500kV line was found to be the strongest short circuit source and was taken out of service to simulate a prior outage condition. The table below summarizes the findings System Condition Prior Outage Table 2.1 Short Circuit Ratios Short Circuit Capacity (MVA) Short Circuit Ratio Effective Short Circuit Ratio N-0 None 25190 7.2 6.91 Shelby Sans Souci N-1 500kV line 18758 5.36 5.07 System Strength Strong system with high ESCR Strong system with high ESCR The effective short circuit capabilities under system intact and N-1 conditions were found to be acceptable to accommodate the injection from the HVDC facility. No additional transient voltage control devices are currently being recommended. 12

6 Conclusion This report documents the affected system impact due to the interconnection of the Plains & Eastern HVDC project on the MISO Transmission system. Steady State AC analysis was performed to identify any reliability criteria violations caused by the interconnection of the study project. The analysis did not identify any constraints in both the near term (2017) and the out year (2024) scenarios. An effective short circuit ratio calculation was performed to identify the need for transient reactive support devices and mitigate any risk of commutation failure. The effective short circuit capabilities were found to be acceptable to accommodate the injection from the HVDC facility. No network upgrades are currently being proposed for this interconnection from an affected system perspective. 13