Reliability Modelling: Review Process & Methodology

Similar documents
SAM 2.0 Stakeholder Comment Matrix

LOLE Fundamentals Loss of Load Expectation (LOLE) Fundamentals

Calculation of Demand Curve Parameters

SAM 3.0 Stakeholder Comment Matrix

Methodology to Perform Long Term Assessments

SAM 3.0 Stakeholder Comment Matrix

Standard BAL-502-RFC-02

Alberta Capacity Market

GADS and LOLE Considerations in Gas- Electric Coordination. ENGCTF June 13, 2013

APRIL 23, Capacity Value of Wind Assumptions and Planning Reserve Margin

Market Mechanics Review of Net Demand Variability from the E&AS Design Stream Working Group Meeting 6&8

Estimating the Economically Optimal Reserve Margin in ERCOT

RRS Education Session #1

PJM Manual 20: PJM Resource Adequacy Analysis Revision: 08 Effective Date: July 1, Prepared by Resource Adequacy Planning

AUSTRALIAN ENERGY MARKET OPERATOR

Reliability Analysis using PLEXOS

ICA Demand Curve Development:

Demand Curve Analysis

Capacity Performance FAQ Response

Market Settlements - Advanced

Evolution of the Grid in MISO Region. Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017

Net Demand Variability (NDV) Summary

May 4, 2017 PLANNING COMMITTEE. Dear Committee Members:

Bulk Power System Integration of Variable Generation - Program 173

Load Forecast Uncertainty Kick-Off Discussion. February 13, 2013 LOLEWG Item-3

AESO Stakeholder Update on Mothball Outages. July 25, 2016

NPCC 2016 MARITIMES AREA COMPREHENSIVE REVIEW OF RESOURCE ADEQUACY Approved by RCC December 6, 2016

LOLE is expressed as hours per year with the usual target criteria being (0.1 days/year) or 1- day in 10-years MISO Tariff: Module E-1 - The

Evaluating Wind Power Generating Capacity Adequacy Using MCMC Time Series Model

Alberta Capacity Market

Appendix C. Regulatory Compliance Matrix DRAFT 2018 OR IRP

PJM Manual 10: Pre-Scheduling Operations Revision: 36 Effective Date: December 22, Prepared by Operations Planning Division

Appendices. New York Control Area Installed Capacity Requirement. December 2, For the Period May 2017 To April 2018

Policy Direction for Alberta s Capacity Market Framework

TransCanada Power Market Update February 2018

Hydro-Québec TRIENNIAL REVIEW OF RESOURCE ADEQUACY

Capacity Performance Training. June 24, 2015

NPCC 2013 MARITIMES AREA COMPREHENSIVE REVIEW OF RESOURCE ADEQUACY

Modeling Transmission Outages in the CRR Network Model

Defining and Measuring Security of Electricity Supplies

Reliability Assessment of a Power Grid with Customer Operated Chp Systems Using Monte Carlo Simulation

Special Case Resources: Evaluation of the Performance and Contribution to Resource Adequacy

Assessment of Load Shed Service for Import (LSSi) Product

Monte-Carlo Optimization Framework for Assessing Electricity Generation Portfolios

Eastern Wind Integration and Transmission Study

Pre-Scheduling Operations

IRP Advisory Group 2017 IRP Kick Off

Operating Procedure PURPOSE... 1

PJM Manual 18: PJM Capacity Market Revision: 38 Effective Date: July 27, Prepared by Capacity Market Operations

QUÉBEC CONTROL AREA 2004 INTERIM REVIEW RESOURCE ADEQUACY

1.818J/2.65J/3.564J/10.391J/11.371J/22.811J/ESD166J SUSTAINABLE ENERGY

Resource Adequacy Straw Proposal. Seasonality. for addressing. July 31, 2015 MISO Staff

UCAP Calculation Comparison

Generation adequacy and transmission interconnection in regional electricity markets

LIPA Generation Planning Review

Standards Authorization Request Form

2012 Probabilistic Assessment

to Multi-Area Reliability Evaluations

Capacity Performance Training. March 16, 2015

Developing and Delivering Complex Projects using Quantitative Risk Analysis Colin Cropley BE(Chem), PMP, Cert PRINCE2 Practitioner Managing Director,

PowrSym4. A Presentation by. Operation Simulation Associates, Inc. February, 2012

Efficient Evaluation of Nodal Reliability Index based on AC-OPF by Fast Monte Carlo Method

Outage Types and Entering Tickets PJM State & Member Training Dept.

Integrated Life Cycle Management for Nuclear Power Plant Long Term Operation

Appendix 1 PRELIMINARY DELIVERABILITY BASELINE ANALYSIS STUDY REPORT

Interface Pricing Approach Whitepaper May 2015

Phase 2 of 2015 General Rate Case Marginal Cost and Sales Forecast Proposals


Methodology PLG-METH-0002-V1

Assessing capacity value of wind power

Calculation of system index - Basic idea. Load model Alternative 2. Thermal power station model. Equivalent load. Example 6.8:

Phase 2 of 2009 General Rate Case Marginal Cost And Sales Forecast Proposals

RPM 301 Performance in Reliability Pricing Model

Anchor Data Set (ADS) Definition, Benefits, Implementation and Management Ver. 6-Aug 15 th DRAFT Proposal only

Electric Reliability Organization Enterprise Performance Metrics

Duration-Limited Storage De-Rating. Factor Assessment Final Report

Mid-term Adequacy a glance

1.818J/2.65J/3.564J/10.391J/11.371J/22.811J/ESD166J SUSTAINABLE ENERGY. Prof. Michael W. Golay Nuclear Engineering Dept.

AESO Practices for System Access Service. May 31, 2013

Capacity Accreditation and External Resource Zones 06/30/2016

Environmental Compliance (Slides 7-15) Angila Retherford, Vice President Environmental Affairs and Corporate Sustainability

Evaluating the Impact of Wind Power Uncertainty on Power System Adequacy

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

LOAD SERVING ENTITIES PJM REGION

Standard Development Timeline

2012 PJM Reserve Requirement Study

Simulation as Support for PBL Contract Design

Generating Capacity Reliability Assessment of the Itaipu Hydroelectric Plant via Sequential Monte Carlo Simulation

The Integration of Price Responsive Demand into PJM. Wholesale Power Markets and System Operations. Paul Centolella and Andrew Ott 1.

Ph.D. Defense: Resource Allocation Optimization in the Smart Grid and High-performance Computing Tim Hansen

Capacity Resource Performance in NYISO Markets

Life Cycle Assessment A product-oriented method for sustainability analysis. UNEP LCA Training Kit Module f Interpretation 1

INTEGRATED TRANSMISSION PLANNING MANUAL

No Longer at a Loss for Words

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

Methods for Forecasting Energy Supply and Demand

2017/2018 RPM Base Residual Auction Planning Period Parameters

Flexible Ramping Product Cost Allocation Straw Proposal

Managing Volatility. Risk in mining investment decisions. Managing Volatility

Mid-term Adequacy Forecast of the Czech Republic ČEPS 08/2016

Transcription:

Reliability Modelling: Review Process & Methodology Adequacy and Demand Curve Workgroup Sept 20 th, 2017 Public

Reliability Modelling Background Per SAM 2.0: AESO is the responsible party for modelling reliability requirements, subject to appropriate governance The resource adequacy criterion and the reliability measure is expected to be a government policy decision Target procurement volume to be based on probabilistic resource adequacy requirement modelling considering supply adequacy impacts of all resources regardless of their capacity market eligibility A methodology is required to determine and evaluate the required reserve margin and the amount of capacity to procure 1

SAM 3.0 Objective: AESO Reliability Model Seeking Workgroup recommendation (acceptance) of the methodology and key inputs of the AESO reliability modeling that will determine the amount of capacity required to meet the defined reliability target. Through the review process feedback and acceptance will be sought from the workgroup to validate that the AESO is using: Reasonable assumptions and methodologies Clear transparent process Industry standard practices 2

SAM 3.0 Objective: AESO Reliability Model Con t Meeting Action: Seek agreement on the objective and intent of achieving WG recommendation (acceptance) on the methodology and key inputs of the AESO reliability modeling, and the process to reach such recommendations. 3

Suggested Reliability Modeling Review Process Sept 20 th, 2017 Seek input and agree to review process Agree to which aspects of methodology and input to review Feedback to date is to review all inputs Oct 11 th, 2017 AESO provide WG material on intended methodology & inputs Oct 18 th, 2017 (Full day) Review material for clarity, identify issues and other options WG members can bring one technical support staff if desired Identify follow up actions Nov 15 th, 2017 Revisit follow up action regarding methodology and inputs Nov 29 th, 2017 Recommendation: Reliability methodology and inputs 4

Reliability Modelling: Methodology Public

Reliability Modelling Principles and Objectives Principles Reliability is a top priority of the AESO Additional priorities for the modeling process include: Reasonable assumptions Clear transparent process Industry standard practices Appropriate oversight and governance Objectives Assess physical reliability metrics (frequency, duration and magnitude) to determine the reserve margin and target procurement volume Use Monte Carlo simulations of hourly load and generation to determine tradeoff between capacity and reliability Multiple iterations of output required for convergence AESO External 6

Monte Carlo Simulation Monte Carlo simulation performs risk analysis by building models of possible results by substituting a range of values (a probability distribution) for any factor/input that has inherent uncertainty Results are calculated repeatedly, each time using a different set of random values from the probability functions Monte Carlo simulation produces distributions of possible outcome values Monte Carlo simulation may involve thousands or tens of thousands of iterations before it is completed 7

Why use a Monte Carlo Simulation? Supply shortfalls can have many drivers, uncertainty in load, uncertainty in generator availability, energy limited variable resources and intertie/transmission outages A deterministic selection of extreme events will not give an accurate representation of the operation of any system during such an event, nor would it be possible to estimate a distribution of when such events could occur Since most reliability events are high impact, low probability events, a large number of possible scenarios must be considered to capture uncertainties 8

Consistency with Industry Guidelines and standards for reliability NERC BAL-502-RFC-02 (not currently adopted in Alberta) To establish common criteria, based on one day in ten year loss of Load expectation principles, for the analysis, assessment and documentation of Resource Adequacy for Load http://www.nerc.com/files/bal-502-rfc-02.pdf North East Power Coordinating Council Directory 1 Each Planning Coordinator or Resource Planner shall probabilistically evaluate resource adequacy of its Planning Coordinator Area portion of the bulk power system to demonstrate that the loss of load expectation (LOLE) of disconnecting firm load due to resource deficiencies is, on average, no more than 0.1 days per year. https://www.npcc.org/standards/directories/directory_1_tfcp_rev_2 0151001_GJD.pdf 9

Anticipated Inputs Load Hourly Probabilistic (economic- and weather-driven) Generation Fleet Installed capacity based on existing and anticipated future units Outages (Maintenance, Planned, De-rate and Forced Outage) Consideration of output profiles from variable/intermittent resources Intertie (imports) Expected intertie capacity, availability, and behavior Inputs and methodology to be discussed in greater detail at the October 18 Working Group meeting; detailed list of inputs shared with WG 10

Anticipated Output Hourly supply cushion data Reliability metrics Frequency Loss of Load Expectation (LOLE) Duration Loss of Load Hours (LOLH) Magnitude Expected Unserved Energy (EUE) Determine the reserve margin and target procurement volume Multiple iterations / seeds for convergence Will evaluate output: Over a spectrum of reserve margins / capacity volumes By season (as required) AESO External 11

Anticipated Modelling Assumptions Transmission System Unconstrained transmission system per SAM 2.0 Physical reliability metric, not economic AESO will use off-the-shelf software tool Industry standard Validation project currently underway to determine appropriate tool 12

Key Interdependencies Can begin modelling before these are determined but they are required for final reliability model outputs and demand curve calculation Self-supply The amount of capacity to be procured by the AESO to meet load needs and ensure reliability is dependent on self-supply treatment Eligibility The unforced capacity (UCAP) methodology and treatment of resources in the reliability model should be consistent to the extent possible Seasonality Reliability model provides insights into the seasonal reliability issues and seasonal capacity needs Others? AESO External 13

SAM 3.0 Objective: AESO Reliability Model Meeting Action: Seek agreement on the aspects of methodology and key inputs of the AESO reliability modeling that the workgroup wishes to review. 14

Next Steps Timelines of the Adequacy and Demand Curve work group on Reliability Modelling Oct 11 th, 2017 AESO provide WG material on intended methodology & inputs Oct 18 th, 2017 Review Reliability Model methodology and inputs Nov 15 th, 2017 Revisit AESO Reliability Model methodology and inputs Nov 29 th, 2017 Recommendation: Reliability methodology and inputs 15