Environmental and Social Impact Assessment [ESIA] for Proposed Liquefied Natural Gas (LNG) Project at Tema in the Greater Accra Region of Ghana

Similar documents
TEMA LIQUEFIED NATURAL GAS PROJECT ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT

CHAPTER 7 STAKEHOLDER ENGAGEMENT

Ministry of Energy and Water Government of Lebanon

Background Information Document

1 PROJECT OVERVIEW. Quantum Power Ghana Gas Limited 1 Knight Piésold Consulting GMF

LNG Import Facility Infrastructure Options

ASX/MEDIA RELEASE 23 APRIL 2015 MAGNOLIA LNG PROJECT TOLLING AGREEMENT UPDATE WITH MERIDIAN LNG

On Board Regasification for LNG Ships. 22 nd World Gas Conference WS 3-2 Tokyo 2003 Wayne Perry

Background Information Document

ECO-FRIENDLY LNG SRV: COMPLETION OF THE REGAS TRIAL

OLT Offshore LNG Toscana Alessandro Fino CEO

SHAPING THE NATURAL GAS MARKET OF CYPRUS

GUIDE FOR APPLICANTS

9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE Introduction

Conversion of Kurnell refinery to a fuel import terminal

REPUBLIC OF KENYA MINISTRY OF ENERGY AND PETROLEUM KENYA PETROLEUM TECHNICAL ASSISTANCE PROJECT (KEPTAP) PROJECT MANAGEMENT UNIT (PMU)

Nearshore Regasification Terminals and FSRUs

African Gas Infrastructure: Project Development and Financing

PIPED-GAS REGULATION FEBRUARY 2017

GLOSSARY. Quantum Power Ghana Gas Limited ix Knight Piésold Consulting Environmental and Social Impact Assessment

This is a working draft report provided for information purposes only, and may be modified prior to finalisation. It has been prepared on the basis

FUGRO GROUP LNG FIELD DEVELOPMENT AND FACILITIES. TACKLING your complex challenges. UNDERSTANDING your operational objectives

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS AND WASTE MANAGEMENT LICENSE APPLICATION PROPOSED EXTENSION OF ASH DAMS AT HENDRINA POWER STATION, MPUMALANGA

The Republic of South Africa. Department of Energy REQUEST FOR INFORMATION IN RESPECT OF THE DESIGN OF A GAS TO POWER PROGRAMME

Petronet LNG Ltd., India. LNG Terminal Design- Major Design Considerations

LNG Houston, February 6-7 th, The case for developing a Floating LNG Receiving Terminal on the US East Coast

Challenges for Marine LNG Import to Unlock Gas to Power+ across Africa

URS- EIA- REP Date of Issue 19th November 2012

We deliver gas infrastructure

Who is WesPac Midstream?

V International Seminar on Port Engineering, Concepción, Chile. Site Selection & Design of Marine Terminals

COMPLETING THE LNG VALUE CHAIN

CHAPTER 3: GENERAL DESCRIPTION OF THE PROPOSED COEGA INTEGRATED POWER PROJECT

Classification of the Largest Ever Floating Storage Regasification Unit

6th Annual LNG Transport Handling & Storage 2016 Forum. FSRU as The Pivotal Point for Effective LNG Distribution

New York State Offshore Wind Master Plan. October 20, 2017

Capability Statement Gas and liquid bulk terminals Delta Marine Consultants

INFORMATION BOOKLET. June Harbour Master - Burtonport

Discover a proven way! Arturas Drungilas. Marketing and Corporate Affairs Director

Appendix A: Project Characteristics

LNG Supply Chain Infrastructure Configuration

Need For The Project

KOGAS s Technical Capability and Plan on Off-shore Plant Business

GHANA PROJECT PIPELINE PRESENTATION

Floating storage and regasification barges

The changing landscape of gas pipelines in SE Europe & the

17 th INTERNATIONAL CONFERENCE & EXHIBITION ON LIQUEFIED NATURAL GAS (LNG 17)

The general design of a LNG-terminal. Background

PERSPECTIVE OF NATURAL GAS SUPPLY FOR POWER GENERATION IN THE SUB- REGION

FRAMEWORK FOR AQUACULTURE DEVELOPMENT ON THE VOLTA LAKE. Implementation Guidelines Document

Project Overview. Northwest Innovation Works LLC and the Port of Kalama propose to develop and operate

The Adoption of FSRU For Cost-effective LNG Import Solution

Chemplast Sanmar Limited Marine Terminal Facility, Chitrapettai Village Cuddalore District, Tamil Nadu

THE TRANSFER OF LNG IN OFFSHORE CONDITIONS. SAME SONG NEW SOUND

GNL Mejillones, GenCo oriented

Avoiding the Disconnect

Floating LNG What are the key business development risks and mitigation strategies in a FLNG project?

This is a working draft report provided for information purposes only, and may be modified prior to finalisation. It has been prepared on the basis

Gorgon Gas Development and Jansz Feed Gas Pipeline

The Eastern Mediterranean and European Energy Landscape: Trends and Opportunities

Saudi Aramco General Bid Slates (GBS)

CoTE Presentation LNG to Power Stornoway s Renard Mine Canada LNG Export 2015 May 19, 2015

DUTY PORT MANAGER Competitive salary + benefits

UPDATE OF THE AUTHORISATION OF A LNG CARRIER TO UNLOAD AT THE LNG TERMINAL IN PANIGAGLIA PANIGAGLIA LNG TERMINAL

Wharf structures and Quay Deck landing areas, will be built in stages to accommodate the following transport fleet:

Development of LNG solutions in the Baltic States

Innovations for the Global LNG Industry Bringing Continents of Energy Together Marine Technology Society March 22, 2007

Asia s First FSRU And its Role in Pushing LNG Development in Indonesia

Presentation on Initiatives to Improve Cargo Handling at the Port of Mombasa. Muhamad A. Jezan Resident Representative

February 2012 Tweneboa, Enyenra, Ntomme T.E.N. Development Project Environmental Impact Assessment Scoping Report and Terms of Reference (ToR)

MINISTRY OF ENERGY UNLOCKING ECOWAS GAS MARKET: FROM LNG TO GAS-TO-POWER. Ghana s Downstream Sector and Investment Opportunities in Gas Sector

Capabilities in LNG

Transportation and regasification infrastructures

small to mid-scale LNG solutions LNG-TO-POWER

CHAPTER 13 ASSESSMENT OF SOCIO-ECONOMIC IMPACTS AND MITIGATION

Small Scale LNG From Concept to Reality. Chris Johnson, General Manager, LNG New Markets, Shell

Opportunities for Pan GCC Natural Gas Grid

GLADSTONE LNG leads the way with its first LNG shipment in 2012

Investment Opportunity LNG Terminal

Environmental Governance in Myanmar. U Than Aye Director Environmental Conservation Department

FSRUs: Accommodating Emerging Markets Gas and Power Needs

GRAIN LNG Challenges & benefits for the deployment of LNG in ports. October 2017 BPA Conference, Poole, UK

Conversion table working groups Name working group Old number New number Conception des barrages mobiles et de barriers anti-tempêtes PIANC WG 101

Floating Regasification The Aegean LNG terminal

Petronas Gas Berhad KINDLY REFER TO THE LAST PAGE OF THIS PUBLICATION FOR IMPORTANT DISCLOSURES INVESTMENT HIGHLIGHTS KDN: PP 10744/06/2012

KARENSLYST ALLÉ 4, 0278 OSLO, NORWAY P.O. BOX 157, 0212 OSLO, NORWAY

TABLE OF CONTENTS Clearances Minimum Distance Between the berth and the Center of the Channel Turning Basin...

LNG PUMPS FOR FLOATING STORAGE AND REGAS UNIT

Developing and Implementing Floating <Title of Presentation>

Loading Master for Oil, LNG/Gas and Petrochemical Terminals

Proposed G3 Terminal Vancouver Project Update. Presented to North Shore Waterfront Liaison Committee January 14, 2016

LNG Importation Initiative. Saldanha Cape Town Corridor. Fossil Fuel Foundation 21 May 2014

MARINE POLLUTION DEGRADATION MITIGATION MANAGEMENT IS ESSENTIAL FOR IMPROVING MARINE ENVIRONMENT

Clean LNG fuel for Black Sea-Danube-Rhine corridor

B.C. TOWBOAT INDUSTRY CONFERENCE

Preamble. Mindful of: Noting

INTRODUCTION. List of Figures. List of Tables

Gas Australia Asia Pacific Conference October, Perth

Till date, Rotary has built more than 60% of independent storage tanks in Singapore.

The Future of the Ocean Economy - Offshore Wind

Transcription:

BACKGROUND INFORMATION DOCUMENT QUANTUM POWER OPERATIONS LIMITED Environmental and Social Impact Assessment [ESIA] for Proposed Liquefied Natural Gas (LNG) Project at Tema in the Greater Accra Region of Ghana SCOPING PROCESS Introduction Quantum Power Operations Limited (herein referred to as Quantum Power) is a developer, owner and operator of electricity generation assets and power-related infrastructure throughout Africa. Quantum Power intends to construct and develop a Liquefied Natural Gas (LNG) project. The proposed project is located at Tema in the Greater Accra Region and it s characterized by other such heavy industrial operations. The project will install, commission and operate the infrastructure required to import, store, re-gasify Liquefied Natural Gas ( LNG ) and deliver re-gasified LNG to off-takers in the Tema area for an initial period of ten (10) years. Prior to commencing with construction of the LNG facility, approvals are required in terms of the Environmental Permitting as by under Regulation 3 of Environmental Assessment Regulations 1999 (LI 1652). The competent authority for the Environmental and Social Impact Assessment (ESIA) process is the Environmental Protection Agency (EPA). Knight Piesold Ghana Limited has been appointed as the independent environmental assessment practitioner (EAP), to undertake the ESIA and associated public participation processes for this project DUE DATE FOR COMMENT: 25 TH JUNE, 2014

Purpose of this Document This document serves to provide you with a brief introduction to the proposed project and the manner in which Interested and Affected Parties (I&APs) can become involved in the ESIA process. Additional documents will be available at various stages during the environmental assessment process to provide I&APs with information and further opportunities to raise issues of concern and suggestions for enhanced benefits Project Background The proposed project if approved will be the first Liquefied Natural Gas (LNG) facility development in Ghana. The development will affect three main administrative districts (Tema, Kpone and Ningo Prampram) who may wonder what LNG is, so a brief introduction is provided here. LNG is produced at an LNG plant by cooling natural gas to a very low (cryogenic) temperature until the gas becomes a liquid. The process reduces the volume of the natural gas to 1/600th of its unliquefied volume. This much smaller volume allows large amounts of natural gas to be transported economically over long distances by special ships called LNG carriers. When the LNG is unloaded at an international port, it is usually transported via pipeline to a nearby re-gasification terminal, where the LNG is heated and returned to its gaseous state. The resultant natural gas is then distributed to customers via natural gas pipelines and reticulation systems.

PROJECT DESCRIPTION The project will install, commission and operate the infrastructure required to import, store, regasify Liquefied Natural Gas ( LNG ) and deliver regasified LNG to off-takers in the Tema area for an initial period of ten (10) years. Objectives To deliver natural gas to the Independent Power Producers ( IPPs ) and industrial consumers with initial focus on Tema and its environs. The project will provide a single contract point for end-users covering storage, regasification and transmission of Natural Gas. The Project will operate primarily on a tolling basis. The price of LNG will be a pass through. Project Components The proposed project shall have the following components and infrastructure; Floating Storage and Regasification Unit ( FSRU ) Offshore Mooring and Support for Floating Units ( FSRU as well as LNG Supply Vessels) Subsea Gas Pipeline Landing Facilities and Distribution AFFECTED ENVIRONMENT The proposed project will be located in the Heavy Industrial Area of the Tema Metropolis. The projects distributed and landing facilities will travel across Kpone Katamanso and Ningo Prampram Districts within the metropolitan area. Residential and agricultural (farming) activities are dotted along the project location sites. Other characteristic features of the landing area are; biodiversity spots, wetlands and scattered mangroves I. Floating Storage and Regasification Unit ( FSRU ) The FSRU will berth at the offshore mooring jetty. It will have a storage capacity of 170, 000 m 3. The FSRU initial send-out rate capability will be of 250MMscf/d (able to supply approx. 1250MW of combined cycle capacity) with ability to deliver up to 750MMscf/d II. Offshore Mooring and Support for Floating Units ( FSRU as well as LNG Supply Vessels) The Floating Units will be connected to a five (5) kilometers subsea pipeline attached to the offshore mooring jetty. The mooring system will rest on permanent piles in the seabed and support a permanently moored storage and regasification vessel, an LNG trading vessel and a riser from the subsea pipeline. III. Subsea Gas Pipeline Twelve (12) kilometers of 18-inch seabed pipe will be laid to transport re-gasified LNG from the offshore facility to the shore near Tema. The pressure and temperature of the pipeline will meet the requirements of the onshore pipeline distribution network to which it will be connected (see below for subsea gas pipeline design). IV. Distribution and Landing Facilities Construction of an 18-inch gas pipeline distribution network to supply off-takers at their plant gates via onshore landing facilities and a metering station. (see below for distribution and landing sites).

1.0 Proposed Subsea Gas Pipeline Design Network

2.0 Proposed LNG Distribution and Landing Facilities

PROJECT DELIVERY, STATUS AND TIMELINES By the initial market studies it is expected that the project will commission and deliver first gas by first quarter in 2016. Other completed aspects of the projected development are summarised below; A significant proportion of the preliminary front-end engineering and design (pre- FEED) has already taken place and the equity required for the project is available. Government of Ghana has MoU with the project and is willing to take up to 10% of the Project s equity through nominated public institutions. Award of MetOcean Study of the Proposed Project Site to IntecSea Appointment of Owner s Engineer in 4th quarter 2013 MoU and Term sheets with prospective off takers Selection Process of FSRU Provider underway

ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT [ESIA] The objectives of the ESIA process are to provide: Interested and Affected Parties (I&APs) with adequate information to understand the potential environmental and socio economic impacts associated with the proposed project and opportunities for them to comment on the ESIA process; The engineering team with information that will assist them to incorporate effective measures into the design and execution of the project to minimise negative impacts and enhance benefits of the project; and The regulatory authorities with sufficient information to serve as a basis for sound decision making and grant of Environmental Permit. Legislative Requirements The proposed ESIA will be undertaken in terms of the Environmental Assessment Regulations 1999 (LI 1652) and the Environmental Protection Agency Act 1994 (Act 490). In addition, the following legislation will also be applicable to the propose project and the related legislative requirements will need to be fulfilled as part of the ESIA process: Energy Commission Act 1997 (Act 541 Ghana Maritime Authority Act 2002 (Act 630) Ghana Shipping (Protection of Offshore Operations and Assets) Regulations 2011 Oil in Navigable Waters Act, 1964, Act 235 Beaches Obstruction Ordinance of 1987 Cap 240 Lands (Statutory Wayleaves) Act 1963 (Act 186) Detailed legislative requirements of the proposed project will be presented during the Scoping phase. An integrated legislative approach will be adopted by Knight Piesold to identify all relevant legislation in relation to the project development. Key Environmental Considerations Identified Initial site visit to the project and project affected sites have considered the following estimated predicted impacts: Effects of noise on marine fauna and flora (especially marine mammals) Interference with fishing activities Effects on terrestrial ecology and biodiversity Interference with marine traffic Social economic, land ownership resource use Health and Safety

PUBLIC CONSULTATION AND PARTICIPATION Public participation and stakeholder consultation are a key component of environmental decision making process and will constitute a major part throughout the ESIA process. The consultation exercise and program will involve both institutional and public engagement. It will be directed and focused at promoting capacity building of stakeholders to the project development. A summary description of the public participation ESIA process and associated activities: 2 nd Quarter 2014 (May, 2014) PROJECT ANNOUNCEMENT Formal announcement of project to all stakeholders: Announcement letter and BID distribution; Placement of site notices; Placement of adverts Registration of I&APs. Key stakeholder / focus group meetings. 2 nd Quarter 2014 (June, 2014) SCOPING Announce availability of Draft Scoping Report for public review Lodge Draft Scoping Report available in the mass media Hold meetings with I&APs. Update Draft Scoping Report, Comment and Response Report. Submit Final Scoping Report to EPA and make available for public review period 3 rd Quarter 2014 (July-Aug, 2014) IMPACT ASSESSMENT Announce availability of Draft ESIA and PEMP Reports for review. Lodge Draft ESIA and EMP Reports available at public places Hold public meetings with I&APs. Update of Draft ESIA and PEMP Reports, Comment and Report Submit Final ESIA and PEMP Reports to EPA for public review 4 th Quarter 2014 (Sep, 2014) DECISION MAKING Announce decision from competent authorities to I&APs. Provide the needed information for appeals process in announcement Your registration as an I&AP and comments are important to this process. You are invited to raise issues of concern, identify opportunities and provide suggestions associated with the proposed project, pertaining to potential positive or negative environmental and social impacts which should be investigated during the ESIA process. You are invited to register as an IAP for PPP for this project. If you wish to be registered, please complete attached registration form and return to Knight Piésold (details below). WE THANK YOU FOR YOUR PARTICIPATION For additional information please contact: Knight Piésold Ghana Limited No. 20, 2 nd Close Airport Residential Area P.O. Box CT 4122, Cantonments, Accra p. +233 30 7021155 e. accra@knightpiésold.com