Concrete Pavement Preservation Partial Depth Repairs

Similar documents
Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements

550 Surface Treatments

DOWEL BAR RETROFIT DO S AND DON TS

Concrete Pavement Preservation and Optimization

IGGA Guide Specification: Conventional Diamond Grinding for Pavement Preservation Introduction

Special Provision No. 399S43 July This Special Provision deletes and replaces the following specifications:

Alligator Cracking. Light. Medium. High

Concrete Pavement Preservation:

TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS. Financial Project ID , &

Maintenance & Rehabilitation. Treatments. Crack Sealing. Sealant Types. Asphalt Pavement Preservation: Identification of Alternative Treatments

SECTION SITE CONCRETE

General Information for Joints

Maintaining your roads with Asphalt

CONCRETE REPAIR IN ACTION: USING THE MANUAL AS A GUIDE. Christen Longoria, P.E. San Antonio District Project Engineer

Pavement Preservation with Thin Lift Concrete Overlays. Dale Harrington, P.E. Representing the National Concrete Pavement Technology Center

SECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course.

Concrete Pavement Preservation Guide

UNIFIED FACILITIES GUIDE SPECIFICATIONS

FIVE STAR PRODUCTS, INC. (800)

In Service Replacement of Box Girder Bottom Slab

Pavement Management Systems

This specification refers to the following standards, specifications, or publications:

PORTLAND CEMENT CONCRETE OVERLAYS. C. Unbonded Concrete Overlays Over Concrete (with separation layer)

SECTION CAST-IN-PLACE CONCRETE

Optimization of Concrete Maintenance to Extend Pavement Service Life

Chapter 4 Portland Cement Concrete Pavement Guidelines and Policies Publication Edition Change 1 CHAPTER 4

Semstone Construction Details

FIVE STAR PRODUCTS, INC. (800)

Construction Specification for Concrete Bus Pad

Design and Construction of Concrete Overlays. By: James K. Cable, P.E. Cable Concrete Consultation

Con-Spec Industries Ltd.

Mix Design & Construction -1-

SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS

Introduction to Pavement Overlays

DIVISION 3 HEAVY DUTY CONCRETE FLOOR TOPPING SECTION 03340

Asphalt Pavement Maintenance and Rehabilitation Strategies

Concrete Overlays. ACPA Pennsylvania Chapter. ACPA Pennsylvania Chapter. Versatile & Sustainable Solutions. Reasons to Consider a Concrete Overlay

12/11/ th Annual Illinois Bituminous Paving Conference December 11, 2013

BASE CONSTRUCTION MATERIALS A Aggregate

INDEX FOR SPECIFICATIONS FOR CONCRETE PAVEMENT SCOPE Pre-Construction Meeting... 3

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director

Section 504. MICRO-SURFACING

REINFORCED CONCRETE CULVERT STORM DRAIN AND SEWER PIPE FIELD SECTION 1026

SURFACE PREPARATION INSTRUCTIONS: CONCRETE

Tools and Tactics for Roadway Pavement Preservation: An Implementation Guide to Preserving High-Traffic-Volume Roadways

SECTION CAST IN PLACE CONCRETE FOR FLOOR SLABS ON GRADE THAT WILL RECEIVE SEMI-PERMEABLE OR IMPERMEABLE FLOOR FINISHES

OPTIMIZED 3/4" GRADATION LIGHTWEIGHT AGGREGATE REPORT

A. This Section includes resinous flooring systems with epoxy body coat(s).

Session 11: Concrete Overlays

CONSTRUCTION SPECIFICATION FOR CONCRETE CROSSWALK INDEX TS SCOPE...3

WYOMING DEPARTMENT OF TRANSPORTATION SUPPLEMENTARY SPECIFICATION FOR PORTLAND CEMENT CONCRETE PAVEMENT

1. Rapid Set Cement. 2. Methods of preparation. 3. How to stage a job site. 4. Installation Mix, place, finish. 5. Coloring the TRU.

A. Drawings and general provisions of the contract, including General and Supplementary Conditions, apply to this section.

Section 602. CONCRETE PAVEMENT CONSTRUCTION

Section 811. PERMANENT PAVEMENT MARKINGS

PRECAST PRESTRESSED CONCRETE PAVEMENT SECTION 509, AFTER LINE 285, INSERT AS FOLLOWS: SECTION PRECAST PRESTRESSED CONCRETE PAVEMENT

SPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013

Concrete Paving Association of Minnesota CPAM Annual Workshop March 11, Gordy Bruhn- Senior Engineering Specialist

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS

SHRP2 R21 Composite Pavement Systems Project Overview

Overlays. HCC Deck Overlays. Key Decisions for Concrete Deck Overlays

Deterioration of Concrete Roads

FIVE STAR PRODUCTS, INC. (800)

MS-2A LINER SPECIFICATIONS: for STRUCTURAL REPAIR and SEALING of MANHOLES

Section 708. PRESTRESSED CONCRETE BEAMS Description. Manufacture and erect prestressed concrete beams.

Recommended Specifications For Portland Cement Pervious Pavement

SPECIAL SPECIFICATION 4900 Sacrificial Cathodic Protection Pile Jacket

Stanford University Facilities Design Guidelines SECTION SEAL COATS. C. Section : Traffic Striping and Pavement Markings

BIO-AQUIFER STORM SYSTEM

LS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION

SECTION INTERLOCKING PRECAST CONCRETE UNIT PAVERS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

UFC March 2001 CANCELLED UNIFIED FACILITIES CRITERIA (UFC) CONCRETE REPAIR APPROVED FOR PUBLIC RELEASE; DISTRIBUTION UNLIMITED

Surface Repair Using Form-and- Pour Techniques

Evaluation of Premature PCC Pavement Longitudinal Cracking in Colorado

SPALL REPAIR TEST AND EVALUATION (BRIEFING SLIDES)

MNDOT PAVEMENT DESIGN MANUAL

Rapid Overlays for Deck Preservation Virginia Concrete Conference Richmond, Virginia March 8-9, 2012

INDOT Thin Concrete Overlay Initiatives. Tommy E. Nantung INDOT Division of Research and Development

Rapid Repair Materials and Construction Rapid Bridge Repair Workshop Holiday Inn Tanglewood-Roanoke, Virginia May 21 and 22, 2009

Surface Repair Using Form-and-Pour Techniques

SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS

A. Submittal Procedures: See Article 13 of the General Conditions.

2001 SCOPE. This section covers all cast-in-place concrete, including reinforcing steel, forms, finishing, curing, and other appurtenant work.

Application Guides for BASF Floor Products

ULTRA-HIGH STRENGTH SHEAR KEY GROUT

1301 SCOPE. This section covers asphaltic concrete (AC) pavement for roadways and parking areas.

CONSTRUCTION SUMMARY REPORT

Section 505. CHIP SEALS

SECTION GROUT. A. American Society for Testing and Materials (ASTM):

HDX TECHNICAL SPECIFICATION

Polymer Concrete Patching Materials. Todd Donmyer P.E. Area Engineer District 61

SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT

SECTION CONTROLLED LOW STRENGTH MATERIAL

CONSTRUCTION BULLETIN

Electronic Machinery Grouting Manual

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL

What s New in Concrete Paving? G o rdon K. R ay

SECTION CONCRETE LINED CANALS AND RESERVOIRS

PROJECT CONTRIBUTORS

Transcription:

Concrete Pavement Preservation Partial Depth Repairs National Concrete Pavement Technology Center North Dakota Ready Mix and Concrete Products Association Dan Frentress P.E. IGGA 1

Partial-Depth Repair Purpose: Repair surface distresses Reestablish joint reservoir Used for: Midslab surface spalling Joint spalling Severe scaling Remove and Replace Deteriorated Surface Concrete 1 3 2 2

Benefits Restores structural integrity Improves ride quality Extends the service life Restores a well-defined uniform joint sealant reservoir 3

Good Candidate Projects Spalls caused by: Incompressibles in joints Localized areas of weak material Joint inserts Surface deterioration caused by: Reinforcing steel too close to surface Poor curing or finishing practices Recommended evaluation procedures: Distress surveys Sounding and cores from pavement 4

Poor Candidate Projects Spalls due to dowel bar misalignment Spalls at working cracks due to shrinkage, fatigue, or foundation movement Spalls due to D-cracking or reactive aggregate 5

Good Candidate? PDR Placed in 1992 Picture taken in 2005 6

Bad Candidate! 7

Good Candidate? 8

Material Selection Factors Allowable lane closure time Ambient temperature Cost Size of repair Estimated performance Normal opening strength for partial depth repairs to 1,800 to 3,000 psi Most agencies maintain a Qualified Products List that provides approved materials for use by the agency. 9

Construction Steps 1. Repair dimension selection 2. Concrete removal 3. Repair area preparation 4. Joint preparation 5. Bonding agent application 6. Patch material placement 7. Curing 8. Diamond grinding (optional) 9. Joint sealing 10

Repair Dimension Selection Sounding 11

Repair Dimension Selection (TOP VIEW) Boundary saw cuts min. 2 in. (50 mm) deep, 3 in. (76 mm) outside distressed area. Overlap cuts at corners and approx. 1 in. (25 mm) across joint. Saw cut approx. 2 in. (51 mm) away from joint for protecting opposite face. Saw cut skimming opposite joint to provide clean vertical face. 12

Concrete Removal Saw-and-Remove Diamond-bladed saws are used. Sawing provides vertical faces and square corners. The initial sawcut may be either at those marked boundaries at 2: deep or at the boundaries and in a criss-cross pattern. Material is removed with lightweight jackhammers. PROS: Very little spalling of remaining pavement occurs. Crews are typically familiar with this method. CONS: Water from sawing leaves area saturated, possibly delaying the repair process. Polished vertical edges may lead to poor bonding. 13

Concrete Removal Jackhammering Removal begins at center and extends outward Remove top 1/3 but no more Care not to fracture sound concrete Removal near joints should be done w/10-15 lb. hammer to avoid damage Operate hammer no greater than 35% 14

Concrete Removal Cold Milling Transverse Milling (small head, moves along joint) Longitudinal Milling (wide head, pick up & move over) Some states (at least MO, MI, WI, and MN) have had good success using cold milling. PROS: Rough, irregular surface that promotes bonding. Efficient and economical when repairing large areas. CONS: May cause spalling on adjacent pavement edges. Equipment may be difficult or expensive to obtain for some projects. Small patches (<3 ft2) cannot be fixed using this method. Creates a standard size, which may not conform to site needs. 15

Minnesota Standard This standard developed and used by the Minnesota DOT allows the contractor to choose milling or jack hammers for removal of deteriorated concrete. Milling Option Requires a taper of two inches difference between the bottom of the patch and the top of the patch. 10 bottom vs. 12 top. Allows the use of a rounded edge left be the mill and the use of light jack hammers to remove any delaminated concrete exposed by the milling operation. Sand is allowed under exposed dowel bars on a limited basis. Sawing and Chipping Option Saw around the removal area to a depth of 2 inches. Use a light jack hammer of 35 lbs or less to remove the deteriorated concrete. A taper of between 30 60 degrees is required between the bottom of the repair to the top. 10 bottom vs. 12 top. Sand is allowed under exposed dowel bars on a limited basis. Exposed dowels must be coated with duct tape to prevent bonding to patch mix. 16

Minnesota Standard Plate for PDR 17

Milling Machine-V Head for Partial Depth Patch Weight 9 Tons Little dust Removal rate 8 ft. / minute 18

Skid Steer for Milling Partial Depths Best suited for corner spalls and random cracks, it can maneuver better than the larger mills. Skid Steers weigh about 8000 pounds and can have removal rates of 2 3 feet per minute. Light weight skid steers can cause spalling at edges, but most minor spalls will be patched with concrete mix. It is easy to lift the front end off the ground during milling, but can be done with minor spalling. 19

Concrete Removal Cold Milling Milling Across the Joint Milling Along the Joint 20

Checking for Sound Concrete Done after the Mill Use lightweight jack hammer (15 30 lbs) for any debris removal 21

Joint Preparation joint 75 3 mm Remove bond breaker after patch finished & seal joint scoring 75 3 mm Plan View bond breaker Polystyrene Polyethylene patch pavement 25 1 mm 1 in = 25.4mm Profile View Fig. 5.3 on p. 5.10 22

Partial-Depth Repair Need for Compressible Insert Point Bearing Popout & Breakage Joint Closure Debonding Expansion Expansion 23

Example of Compression Relief Failure of Partial Depth Joint Repair BELIEVE IT when it calls for Compression Relief 24

Repair Area Preparation Sandblasting 26

Repair Area Preparation Air Blowing Air blow to remove dust and debris Minimum 90 psi Free of oil and moisture Direct away from patches 27

Final Blowing of Debris with Leaf Blower 28

Milled Crack and Joint 29

Ankeny Partial Depth 30

Fill Void Below Joint Use Sand to provide compression relief in milled crack (no lockup) Must use caution when needing to do a lot of this before patching Repair will not last as long as one placed in sound concrete 31

Precautionary Note in Specs Sand can prevent locking of the joints together due to concrete infiltration when placing repairs. This will probably result in a reduced repair life. The following is an example of over using the sand principle. Duct tape is an excellent way to prevent bond on exposed old dowel bars. 32

Hole to Bottom 33

Minnesota Standard Plate 34

Bonding Agent Application Surface should be clean and in a saturated, surface-dry condition. Apply cementitious bonding agents with a wire brush; apply epoxy bonding agents with a soft brush. Coat all horizontal and vertical surfaces. Excess grout or epoxy should not be permitted to collect in pockets. Cement Grout The grout should be placed immediately before the repair material so that the grout does not set. Any bonding material that is allowed to set must be removed. Epoxy 35

2 Parts Type I Cement 1 Part Water 1 Part Sand Grout Recipe Mixed to the consistency of thick cream or kool whip Placement immediately before concrete. Has a shelf life of 60 minutes. 36

Grout used to Seal Edges of Partial Depth Repairs 37

Patch Material Placement Batch small quantities PCC materials should be placed when the temperature is above 4 C (40 F) and rising Some epoxy materials placed in lifts Overfill patch area by ~3 mm (1/8 in) Consolidate material with small spud vibrator Screed and hand trowel, working from the center of the patch to the edges 38

Mobile Concrete Batch Plant It has 5 bins that hold sand, aggregate and cement products to batch small quantities of material. It uses a belt scale to control the mix proportions for the patch mix being produced. 39

Hand Batching Methods Mixed by proportions on the back of a truck Buy prepackaged bags of material One such product is the Minnesota 3U18 mix 40

Sample Minnesota Partial Depth Mix 3U18 Partial Depth Mix Small Aggregate 100% passing 3/8 sieve Per Cubic Yard 850 lbs Type I Cement Uses 295 pounds of water Uses 1328 pounds of Coarse Aggregate Uses 1328 pounds of Sand A target W/C of 0.35 Type E Water Reducing and Accelerator 6.5% Air Maximum 1 inch slump Cure time of 12 hours Coarse Aggregate gradation will be the following 100% passing the 3/8 inch sieve 55% - 95% passing the #4 sieve Not more than 5% shall pass the #50 sieve 41

Patch Material Placement 42

Finishing Tip 43

Sealing Edges and Runouts The edges of the repair should be sealed with grout to help prevent moisture infiltration, as shown in the photo. 44

Curing P.D.P. Have large surface areas in relation to their volumes (which can lead to rapid moisture loss) Prevent moisture loss White-pigmented curing compound commonly used (some require 1.5 to 2 times normal rate) Opening to traffic Mix / temperature dependent Common values: 1,800 to 3,000 psi 45

Completed Partial Depth Repairs Transverse Joint done in 1987 Random Crack done in 1999 Picture taken in 1999 City Street in South St Paul, MN. 46

Rochester, Mn 2007 Patch Picture 2011 47

CASH 22 East side of Rochester, Mn PDR in 2007 48

Partial Depth Longitudinal Crack Repair 49

I-35 South of Duluth, Mn Project done in 1991 Picture taken in 2000 Centerline 8 miles long 50

Deteriorated Areas were not Repaired in Original Work (Joint and Crack had received a Partial Depth Repair on either side of Deteriorated Areas) 51

Key Factors For Success Proper selection of candidate projects Proper material selection Identification of repair boundaries Use of joint/crack reformers Achieving good bond Patch area clean and dry Sandblasting sidewalls Application of bonding agent Proper placement and curing 52

PDR and DBR Hwy 71 North of Windom, MN Built in 1962 with Quartzite Rock Partial Depth and Dowel Bar Retrofit, Diamond Grinding in 2007 53

Mn/Road DBR in Existing Basket 54

Mn/Road Test Facility 55

Mn/Road Old WB I-94 First time the old concrete pavement is being used for research. Built in 1973 9 concrete thickness 24 wide 27 Reinforced panels with Skewed Joints 56

Faulted Slabs 57

Locate Old Dowels with MIT Scan 58

Old Dowels Marked in Red 59

Slot Removal Max 30 lb. Chipping Jack Hammers 60

Slot Removal Some existing dowel basket shipping wires found in rubble. Old dowels were 1 X 18 No epoxy coating 61

View of hole at side of Slot 62

Sheet Rock Compound House construction Sheet Rock compound used to fill hole next to slots. With Excessive compound use Performance is questionable!!! 63

Broken Dowel 64

Some Holes at bottom of Slot 65

Dowel Placement 66

Concrete Placement 67

Inside Wheel Paths 100 IWP - All Points (Before and After Joint) & Load Levels 90 80 70 60 50 Fall IWP Spring IWP 40 30 20 10 0 0 10 20 30 40 50 60 68

Mn/Road DBR in Existing Basket 69

Questions? International Grooving and Grinding Association Website www.igga.net Daniel P. Frentress P.E. Email dfren@wcta.net Office Phone 218-564-4982 Cell 612-619-8399 70