ASSIGNMENT 1 ANALYSIS OF PRESTRESS AND BENDING STRESS BFS 40303

Similar documents
ST7008 PRESTRESSED CONCRETE

7.1 Transmission of Prestress (Part I)

MAHALAKSHMI ENGINEERING COLLEGE

Post-tensioned prestressed concrete bridge - assignment

Fundamentals of Prestressed Concrete Bridge

Design for Shear for Prestressed Concrete Beam

Chapter 5: Introduction To Prestressed Concrete Design

Flexure Design Sequence

CHAPTER 11: PRESTRESSED CONCRETE

SECTION 1 INTRODUCTION TO POST-TENSIONED CONCRETE DEVELOPED BY THE PTI EDC-130 EDUCATION COMMITTEE

Hyperstatic (Secondary) Actions In Prestressing and Their Computation

Concrete and Masonry structures 3

SHEAR BEHAVIOR OF RC DEEP BEAMS WITH SOLID CIRCULAR CROSS SECTION UNDER SIMPLY SUPPORTED CONDITION AND ANTI-SYMMETRIC MOMENT

An Overview on Tendon Layout for Prestressed Concrete Beams

UNIVERSITY OF BOLTON WESTERN INTERNATIONAL CENTRE FZE. BEng (HONS) CIVIL ENGINEERING SEMESTER ONE EXAMINATION 2015/2016

Strength Design of Reinforced Concrete Structures

ADAPT PT7 TUTORIAL FOR ONE-WAY SLAB 1

5.4 Analysis for Torsion

Interaction between ductile RC perimeter frames and floor slabs containing precast units

A Guide for the Interpretation of Structural Design Options for Residential Concrete Structures

Nonlinear Models of Reinforced and Post-tensioned Concrete Beams

Applications of sustainable post-tensioned concrete slabs

Sabah Shawkat Cabinet of Structural Engineering 2017

Prestressed Concrete Girder Continuity Connection

POST-TENSIONING APPLICATION AND TECHNOLOGY. Moe Kyaw Aung

THEORETICAL AND EXPERIMENTAL STUDY OF UNBOUNDED POST-TENSIONED CONTINUOUS SLAB DECKS CONSISTING OF HIGH STRENGTH SCC

Introduction to Structural Analysis TYPES OF STRUCTURES LOADS AND

This final draft of the fib MC2010 has not been published; it is intended only for the purpose of voting by the General Assembly.

Practical Methods for the Analysis of Differential Strain Effects

Seismic Behaviour of RC Shear Walls

INTERNATIONAL JOURNAL OF CIVIL AND STRUCTURAL ENGINEERING Volume 3, No 1, 2012

Lecture Retaining Wall Week 12

STRENGTHENING OF UNBONDED POST-TENSIONED CONCRETE SLABS USING EXTERNAL FRP COMPOSITES

DESIGN OF POST-TENSIONED MEMBERS IN BENDING USING ACI SIMPLIFIED PROCEDURE

CIVIL ENGINEERING YEAR QUESTION BANK

Structural behaviour and failure mechanisms of concrete monoblock railway sleepers

PRESTRESSED CONCRETE DESIGN

BRIDGE GIRDERS TECHNICAL GUIDE

St.MARTIN S ENGINEERING COLLEGE

1. Cast-in-place concrete is specified in Section

ULTIMATE LOAD-CARRYING CAPACITY OF SELF-ANCHORED CONCRETE SUSPENSION BRIDGE

The Hashemite University Department of Civil Engineering. Dr. Hazim Dwairi. Dr. Hazim Dwairi 1

Types of Foundations

UHPC Connection of Precast Bridge Deck

Chapter. Masonry Design

Siddhartha Ray, Molly Mathew, Sanjay Singh3

Strengthening of hollow core precast slabs using FRP composite materials procedure, testing and rating

Deformation Analysis of Prestressed Continuous Steel-Concrete Composite Beams

PRESTRESSED CONCRETE SEISMIC DESIGN

Scientific Seminar Design of Steel and Timber Structures SPbU, May 21, 2015

Section A A: Slab & Beam Elevation

Special Reinforced Concrete Structural Walls

Principal Bridge Engineer Middle East & India Atkins Abu Dhabi, UAE

Footings GENERAL CONSIDERATIONS 15.2 LOADS AND REACTIONS 15.4 MOMENT IN FOOTINGS

CFRP STRENGTHENING OF CONCRETE BRIDGES WITH CURVED SOFFITS

EXPERIMENTAL RESULTS

THE DESIGN OF LONG CANTILEVER BEAM USING POST-TENSIONED TENDONS IN KUMJUNG STADIUM

Finite Element Simulation of Cantilever Construction Structure

PROFESSIONAL DEVELOPMENT SERIES

Unit 48: Structural Behaviour and Detailing for Construction. Limit State Design

Proposed Modifications to the LRFD Design of U-Beam Bearings

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

Nonlinear Finite Element Analysis of Composite Cantilever Beam with External Prestressing

BRIDGE DESIGN MANUAL UPDATES. Jamie F. Farris, P.E.

Technical Notes 24G - The Contemporary Bearing Wall - Detailing [Dec. 1968] (Reissued Feb. 1987) INTRODUCTION

Bijan Khaleghi, Ph, D. P.E., S.E.

COLUMNS 1- Definition: The Egyptian code defines columns as : 2- Types of concrete columns

POST-TENSIONED SEGMENTAL BRIDGES

FINITE ELEMENT ANALYSIS OF PRESTRESSED CONCRETE BEAMS

COMPERATIVE STUDIES OF REINFORCEMENT CONCRETE BEAM DESIGN USING BS 8110 AND ACI 318 AHMAD ADLI BIN JAMALUDIN AA07192


Chapter Five Torsion. Reinforced Concrete Structures 2 (CEng-3122)

1.7 Prestressing Steel

BEAMS: COMPOSITE BEAMS; STRESS CONCENTRATIONS

INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad

HIGH PERFORMANCE CONCRETE. by John J. Roller CTLGroup

Fundamentals of Post-Tensioned Concrete Design for Buildings

In-plane testing of precast concrete wall panels with grouted sleeve

VIADUCTS BY PUSHING: INCREMENTALLY LAUNCHED BRIDGES

Ultimate strength prediction for reinforced concrete slabs externally strengthened by fiber reinforced polymer (FRP)

Angle Cleat Base Connections

VTU EDUSAT PROGRAMME Lecture Notes on Design of Stair cases

DESIGN OF RETAINING WALLS

Flat Slabs. d 2. A typical flat slab (without drop and column head)

How to Design a Singly Reinforced Concrete Beam

TORSION SIMPLIFIED: A FAILURE PLANE MODEL FOR DESIGN OF SPANDREL BEAMS

Composite Beams of Cold Formed Steel Section and Concrete Slab

Initial Tests of Kevlar Prestressed Timber Beams

BEHAVIOR OF INFILL MASONRY WALLS STRENGTHENED WITH FRP MATERIALS

Civil Engineering-IES-2015 (13 th June 15)

Efficient Mathematical Model for Prestressing Cables and Its Implementation in Computer Analysis

Seismic Detailing of RC Structures (IS: )

Design of Post Tensioned Slab (Review)

ABC: Vigas Pretensadas para Puentes Principios Básicos de Diseño. Pre-Stressed Concrete Structures Basic Concepts

Forensic Testing of Post Tensioned Concrete Girders

Encased Beam with Variable Upper Steel Flange Position

COMPARISON OF PRESTRESSED CONCRETE GIRDERS, WITH DEBONDED STRANDS AND HARPED STRANDS CARMEN DÍAZ-CANEJA NIETO

14.1 PCI Standard Design Practice

Recommendations for additional fire protection of structural elements

DESIGN FOR PROGRESSIVE COLLAPSE 1

Transcription:

Instruction : Answer all question ASSIGNMENT 1 ANALYSIS OF PRESTRESS AND BENDING STRESS BFS 40303 1. A rectangular concrete beam, 100 mm wide by 250 mm deep, spanning over 8 m is prestressed by a straight cable carrying an effective prestressing force of 250 kn located at an eccentricity of 40 mm. The beam supports a live load of 1.2 kn/m. (a) Calculate the resultant stress distribution for the central cross section of the beam. The density of concrete is 25 kn/m 3. (b) Find the magnitude of the prestressing force with an eccentricity of 40 mm which can balance the stresses due to dead and live loads at the bottom fiber of the central section of the beam. [Ans: (a) Stress at top = 14.2 N/mm 2 (compression), stress at the bottom = 5.8 N/mm 2 (compression); (b) Prestressing force = 170 knj.] 2. A prestressed concrete beam supports a live load of 4 kn/m over a simply supported span of 8 m. The beam has an I-section with an overall depth of 400 mm. width of the flange is 200mm. The beam is to be prestressed by an effective presstressing force of 235 kn at a suitable eccentricity such that the resultant stress at the soffit of the beam at the central of the span is zero. (a) Find the eccentricity required for the force. (b) If the tendon is concentric, what should be the magnitude of the prestressing force for the resultant stress to be zero at the bottom fiber of the central span section. [Ans: (a) e = 84 m; (b) 450 knj] 3. A prestressed concrete beam, 200 mm wide and 300 mm deep, is used over an effective span of 6 m to support an imposed load of 4 kn/m. The density of concrete is 24 kn/m 3. At the quarter-span section of the beam, find the magnitude of: (a) The concentric prestressing force necessary for zero fiber-stress at the soffit when the beam is fully loaded; and (b) The eccentric prestressing force located 100 mm from the bottom of the beam which would nullify the bottom fiber stress due to loading. [Ans: (a) 367.2 kn: (b) 183.6 kn] 4. A concrete beam of symmetrical I-section spanning 8 m has flange width and thickness of 200 and 60 mm respectively. The overall depth of the beam is 400 mm. The thickness of the web is 80 mm. The beam is prestressed by a parabolic cable

with an eccentricity of 15 mm at the centre and zero at the supports with an effective force of 100 kn. The live load on the beam is 2kN/m. Draw the stress distribution diagram at the central section for: (a) Prestress + self-weight (density of concrete = 24 kn/m 3 ); and (b) Prestress + self-weight + live load. [Ans: (a) 0.7 N/mm 2 at top and 3.6 N/mm 2 at bottom (compression); (b) 7.4 N/mm 2 (compression) at top and -0.2 N/mm 2 (tension at bottom)] 5. A concrete beam with a double overhang has the middle-span equal to 10 m and the equal overhang on either side is 2.5 m. Determine the profile of the prestressing cable with an effective force of 250 kn which can balance a uniformly distributed load of 8 kn/m on the beam, which includes the self-weight of the beam. Sketch the cable profile marking the eccentricity of cable at the support and mid span. [Ans: e (support) = 100 mm; e (centre of span) = 300 mmj]

Instruction : Answer all question ASSIGNMENT 2 LOSSES OF PRESTRESS BFS 40303 1. A pre-tensioned beam of rectangular cross-section, 150 mm wide and 300 mm deep, is prestressed by 8, 7 mm wires located 100 mm from the soffit of the beam. If the wire are initially tensioned to a stress of 1100 N/mm 2, calculate their stress at transfer and the effective stress after all losses, given the following data: Up to time of transfer Total Relaxation of steel 35 N/mm 2 70 N/mm 2 Shrinkage of concrete 100 x 10-6 300 x 10-6 Creep coefficient - 1.6 E s = 210 kn/mm 2 E c = 31.5 kn/mm 2 [Ans: 977.5 N/mm 2, 793.6 N/mm 2 ] 2. A prestressed concrete pile of cross-section, 250 mm by 250 mm, contains 60 pretensioned wires, each of 2 mm diameter, distributed uniformly over the section. The wires are initially tensioned on the prestressing bed with a total force of 300 kn. If E s = 210 kn/mm 2 and E c = 32 kn/mm 2, calculate the respective stresses in steel and concrete immediately after the transfer of prestress, assuming that up to this point the only loss of stress is that due to elastic shortening. If the concrete undergoes a further shortening due to shrinkage of 200 x 10-6 per unit length, while there is a relaxation of 5 per cent of steel stress due to creep of steel, find the greatest tensile stress which can occur in a pile 20 m long when lifted at two points 4 m from each end. Assume creep coefficient as 1.6. [Ans: 1389.3 N/mm 2, 4.7 N/mm 2, -0.42 N/mm 2 ] 3. A post-tensioned cable of a beam 10 m long is initially tensioned to a stress of 1000 N/mm 2 at one end. If the tendons are curved so that the slope is 1 in 15 at each end with an area of 600 mm 2, calculate the loss of prestress due to friction, given the following data: Coefficient of friction between duct and cable = 0.55 Friction coefficient for wave effect = 0.0015/m During anchoring, if there is a slip of 3 mm at the jacking end, calculate the final force in the cable and the percentage loss of prestress due to friction and slip. [Ans: 526.6 kn; 12.3 percent] 4. A post-tensioned concrete beam with a cable of 24 parallel wires (total area = 800 mm 2 ) is tensioned with 2 wires at a time. The cable with zero eccentricity at the ends

and 150 mm at the centre is on a circular curve. The span of the beam is 10 m. The cross-section is 200 mm wide and 450 mm deep. The wires are to be stressed from one end to a value of f 1 to overcome froctional loss and then released to a value of f 2 so that immediately after anchoring, an initial prestress of 840 N/mm 2 would be obtained. Compute f 1 amd f 2 and the final design stress in steel after all losses given the following data: Coefficient of friction for curvature effect = 0.6 Friction coefficient for wave effect = 0.003/m Deformation and slip of anchorage = 1.25 mm E s = 210 kn/mm 2 E c = 28 kn/mm 2 Shrinkage of concrete = 0.0002 Relaxation of steel stress = 3 per cent of the initial stress [Ans: f 1 = 954 N/mm 2 ; f 2 =866.2 N/mm 2 ; 668.4 N/mm 2 ] 5. A pretensioned beam 250 mm wide and 300 mm deep is prestressed by 12 wires each of 7 mm diameter initially stressed to 1200 N/mm 2 with their centroids located 100 mm form the soffit. Estimate the final percentage loss of stress due to elastic deformation, creep, shrinkage and relaxation using IS: 1343-80 code and the following data: Relaxation of steel stress = 90 N/mm 2 E s = 210 kn/mm 2 E c = 35 kn/mm 2 Creep coefficient ( ) = 1.6 Residual shrinkage strain = 3 x 10-4 [Ans: 22%]

ASSIGNMENT 3 ULTIMATE LIMIT STATE DESIGN /ANCHORAGE ZONE STRESS BFS 40303 Instruction : Answer all question 1. The end block of prestressed concrete beam, rectangular in section, is 120 mm wide and 300 mm deep. The prestressing force 250 kn is transmitted to concrete by a distribution plate, 120 mm wide and 75 mm deep, concentrically located at the ends. Calculate the position and magnitude of the maximum tensile stress on horizontal section through the centre of the end block using the methods of (a) Magnel (b) Guyon and (c) Rowe. Design the reinforcement for the end block for the maximum transverse tension. Yield stress in steel = 260 N/mm 2. [ANS: (a) 3.3N/mm 2 (150 mm); (b) 2.415N/mm 2 (99 mm); 8N/mm 2 (30 mm);a s = 252mm 2 ] 2. A prestressing force of 250 kn is transmitted through a distribution plate 120 mm wide and 120 mm deep, the centre of which is located at 100 mm from the bottom of an end block having a section 120 mm wide and 300 mm deep. Evaluate the position and magnitude of the maximum tensile stress on a horizontal section through the centre of the distribution plate using the methods of (a) Magnel (b) Guyon and (c) Rowe. Find the area of steel necessary to resist the largest tensile force resulting from any of their methods. Yield stress in steel = 250 N/mm 2. [ANS: (a) 1.72N/mm 2 (150 mm); (b) 1.975N/mm 2 (88 mm); 5.04N/mm 2 (50 mm); A s = 265mm 2 ] 3. The end block of a prestressed concrete beam, 200 mm wide and 400 mm deep, has two anchor plates, 200 x 50 mm deep, at 80 mm from the top and 200 x 80 mm deep located 100 mm from the bottom of the beam, transmitting forces of 250 and 300 kn respectively. a. Find the position and magnitude of the maximum tensile stress on a horizontal section passing through the centre of the beam using Guyon s method, b. Evaluate the maximum tensile stress on section passing through the larger and smaller prestressing forces using Guyon s and Rowe s method. [ANS: (a) 5.515 N/mm 2 ; (b) 2.09N/mm 2 section through larger force 4.9 N/mm 2 ]

4. The end block pf a prestressed beam, 250 mm wide 500 mmm deep in section, is prestressed by two cables carrying forces of 450 kn each. One pf the cable is parabolic, located 125 mm below the centre line at the centre of span (10 m) and anchored at a point 125 mm above the centre line at the ends. The second cable is straight and located 100 mm from the bottom of the beam. The distribution plates for the cables are 100 mm deep nd 250 mm wide. Calculate the maximum tensile stress along the axis of the beam using Guyon s method. Also evaluate the maximum tensile stress on horizontal sections passing through the centre an anchor plates using Guyon s method and Rowe s method. 5. A Freyssinet anchorage (125mm diameter), carrying 12 wires of 7 mm diameter stressed to 950 N/mm 2, is embedded concentrically in web of an I-section beat at the ends. The thickness of the web is 225 mm. Evaluate the maximum tensile stress and the bursting tensile force in the end block using Rowe s method. Design the reinforcement for the end block. [ANS: 5 N/mm 2 ; 125 kn ;550 mm 2 ]

ASSIGNMENT 4 PRESTRESS DESIGN CONCRETE SECTION BFS 40303 Instruction : Answer all question 1. A prestressed concrete beam of rectangular section, 90 mm wide and 180 mm deep, is to be designed to support two imposed loads of 3.5kN, each located at one-third points over a span of 3 m. If there is to be no tensile stress in the concrete at transfer and service loads, calculate the minimum prestessing force and the corresponding eccentricity. D c =24 kn/m 3. Loss ratio= 0.8. [Answer: P= 74.5 kn: e=35.6 mm] 2. A prestressed concrete T-beam is to be designed to support an imposed load of 4.4kN/m over an effective span of 5 m. The T-beam is made up of a flange 400 mm wide and 40 mm thick. The rib is 100 mm wide and 200 mm deep. The stress in the concrete must not exceed 15 N/mm 2 in compression and zero in tension at any stage. Check for the adequacy of the section provided, and calculate the minimum prestressing force necessary and the corresponding eccentricity. Assume 20% loss of prestress. [Answer: P= 181 kn: e=78 mm] 3. A post-tensioned beam of span 15 m and overall depth 900 mm has uniform symmetrical cross-section of area 2 x 10 5 mm 2 and the second moment of area of 212 x 10 8 mm 4 units. The prestress is provided by a cable tensioned to a force of 1450 kn at transfer. If the beam is to support a uniformly distributed live load of 21kN/m and the minimum load is that due to the self-weight of the beam, calculate the vertical limits within which the cable must lie along the beam length. The permissible compressive stresses at transfer and working load are 14 and 16.8 N/mm 2 respectively. The tensile stresses at transfer working load ate zero and 1.75 N/mm 2 respectively. D c =24 kn//m 3. Loss of prestress = 20%. [Answer: at midspan: e a = 312 mm; e b =249 mm; At support: e a =219 mm; e b =376 mm]

4. A prestressed I-section of minimum overall depth 300 mm is required to have an ultimate flexural strength of 86kN m. Find: (a) Suitable minimum dimensions of the top flange (b) The total number of 5 mm wires required in the bottom flange. The cube strength of concrete is 60 N/mm 2 and the tensile strength of steel is 1600 N/mm 2. [Answer: (a) 160 mm; (b) 13 numbers] 5. Design the prestressing force required for the tie member of reinforced concrete truss. The service-load tension in the tie member is 360kN and the thickness of the member is fixed as 150 mm. The permissible compressive stress in concrete at transfer is 15 N/mm 2 and tension is not permitted under service loads. The loss ratio is 0.8. High-tensile wire of 7 mm diameter, tensioned to a stress of 1000 N/mm 2 and having an f pu = 1500 N/mm 2 are available for use. The tensile strength if concrete is 2.5 N/mm 2. A load factor of 1.7 at the limit state of collapse and 1.2 against cracking is to be provided in the design. [Answer: Section150 mm by 200 mm; Prestressing force = 450 kn, Number of 7 mm wires= 12]