Sample Slide Show THIS SLIDE REQUIRES NEW PICTURE. Administration. Course Objectives. Course Agenda. Course Agenda

Similar documents
P6 Version 8.2 to 8.4 EPPM Web Power Sample Point Slide Show

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management

P6 Instructors Sample Presentation

P6 Instructors Sample Presentation

P6 Instructors Sample Presentation

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 & 8.2 Professional and Optional Client 3 day training course SAMPLE SLIDE SHOW

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course

Welcome to the Eastwood Harris Pty Ltd PRINCE2 TM Revised 2009 and Microsoft Project 2010 training course

IPECC C ONSULTANTS Course Title: Primavera Enterprise 6.0. Primavera Enterprise. Project Management, Training & Contract Workforce

Primavera P6 R8.3 Professional Fundamentals Training Course Outline

Sample book with two chapters

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by.

3-Day Oracle Primavera P6 Professional Fundamentals - Training Outline -

VERSIONS 8 AND 15 EPPM WEB Sample Book with two chapters only ADMINISTRATORS GUIDE PAUL EASTWOOD HARRIS

Principles of Planning for Building and. by Eastwood Harris Pty Ltd. Introduction Emergency Evacuation. Course Outline.

1Z

PROMASTAR Instructor led Professional Training Services Primavera Accredited/Certified Class Courses

How to Develop, Manage and Communicate Effective Schedules Using Primavera P6 Professional

Sample book with one chapter

Exam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4.

Network Diagram 11/10/2016 WORK BREAKDOWN STRUCTURE (WBS)

P3 to P6 Professional Migration Guide

Primavera Training - P6 Basic Course (102)

Project Planning and Control Using Oracle Primavera P6 : P8.3, 8.4, 15.2

Useful P6 EPPM Terms Security Configuration Process in P6 EPPM Defining Global Security Profiles in P6 EPPM... 19

Analytics Cloud Service Administration Guide

Plan Your Work, Work Your Plan. Dr. R. Rockland Chair and Professor, Department of Engineering Technology New Jersey Institute of Technology

Microsoft Office Project 2010 Basic Course 01: Getting Started

P6 Analytics Reference Manual

Lessons Learned Schedule Updating and Maintenance using Primavera P6

Risk Management User Guide

Borderlink Resources Limited.

Contents Getting Started... 9 Sample Dashboards... 17

2-Day Oracle Primavera P6 Professional Advanced Scheduling - Training Outline -

Embarking new Project

Welcome to the Project Manager guide

The Basics 7. Introduction 8 Project Management 9 What s New? 10 Version Comparison 12 The Gantt Chart 14 Getting Help 15 Summary 16

What's New New Features in Primavera P6 EPPM 18

Contents at a Glance COPYRIGHTED MATERIAL

Team Member Application

Managing Projects (Course Code: 5927A) Course length: 3 days

Contents Getting Started... 7 Sample Dashboards... 12

What's New New Features in Primavera P6 EPPM 18

Microsoft Office Project 2007, Managing Projects

Lessons Learned Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International

(Really) Understanding Microsoft Project

Notice: Falsification of timesheets, whether submitting or approving, can be grounds for immediate termination.

Mastering Microsoft Project 2010

Schedule Management User Guide

PAYGLOBAL EXPLORER USER GUIDE

1Z Oracle 1Z0-567 Primavera P6 Enterprise Project Portfolio Management 8 Essentials Version: 4.9

Views and Layouts for Program Management

Building Flexible Project Plans with Microsoft Project 2010

A Xymphonic Systems White Paper Anyplan Product Overview

Scheduler Book Mode User Guide Version 4.81

KeyedIn Projects Project Manager User Guide

User Guidance Manual. Last updated in December 2011 for use with ADePT Design Manager version Adept Management Ltd. All rights reserved

P6 Team Member Implementation Stories

Release Notes Assistance PSA Suite 2016 Spring Release

MSP How to guide session 3 (Updating)

Project Management Courses

Software Application Lab 2018 PROJECT PLANNING & SCHEDULING USING PRIMAVERA. CIT, Gubbi, Dept. Of Civil Engg. Page 1

Introduction to Cognos Analytics and Report Navigation Training. IBM Cognos Analytics 11

CCC Wallboard Manager User Manual

MS Project 2007 Overview Table of Contents

Microsoft Project Tips & Tricks. Project Solutions Group, Inc.

Simply. manage. SureTrak Project Manager 3.0. all your projects. the best way to

SUPPLY MANAGEMENT GUIDE INDEPENDENCE MEDICAL

Project Management Concepts, Tools & Techniques

Cogito Time & Attendance. Version 3.0. User Manual

CHAPTER 21: SCHEDULING SERVICES FOR YOUR CUSTOMERS

MICROSOFT PROJECT 2007 Level 1

itaskx 3 Project Management User Manual

Microsoft Project 2013 Core Essentials

Workshop: Advanced Cost Management Techniques Using Cobra

DIRECT SUPPLIER ROSTER TOOL HOW TO GUIDE

Microsoft Office Project 2007, Managing Projects

Time and Leave Reporting User Guide for Full Time Employees. July, P age

Time and Leave Reporting User Guide for Full Time Employees. July, P age

Task Control for bpm'online. User Manual

MICROSOFT PROJECT 2007 Level 1

Enterprise by HansaWorld Resource Planner

Principles of Planning for IT Projects

Your easy, colorful, SEE-HOW guide! Plain&Simple. Microsoft Project Ben Howard

REPORTS. Version 5.5 5/15/2014. Page 0 of SmartLinx Solutions, LLC.

Table of Contents SMART STAFF EZ HR, SCHEDULING, TIME & PAYROLL INTEGRATION. - USER S MANUAL -

Index. Sarah Critchley 2018 S. Critchley, Dynamics 365 CE Essentials,

Welcome to. Enterprise Manager. Sodexo: GM/Manager Manual

MICROSOFT PROJECT 2010 Level 1

Payroll Basics for ADP Workforce Now. Automatic Data Processing, LLC ES Canada

Angus AnyWhere. Reports User Guide AUGUST 2012

RELEASE NOTES MEX V (Build ) MEX Ipswich Road Annerley QLD PO BOX 6118 Buranda QLD 4102

New Client Training. Paychex Time and Labor Online Paychex, Inc. All rights reserved. TLO

Massport Capital Programs Enterprise Schedule Management. Document 11 A. Primavera Schedule Toolkit Vertical Projects. July 2017 Version 1.

Introduction to Project Management

CAT Enterprise. Glossary. A (Back to Top) A B C D E F G H I J K L M N O P Q R S T U V W X Y Z. Activity See Development Activity.

Ultimate Study Guide: Foundations Microsoft Project Dale A. Howard Gary L. Chefetz

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

1 - Introduction to Microsoft Project Describe how Project relates to the discipline of Project management.

Transcription:

THIS SLIDE REQUIRES NEW PICTURE Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 to 15.1 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Page 2 Administration Evacuation Facilities, timings and meals Mobile phones & Emails Introductions: Your name, The types of projects you are involved in, Your experience in scheduling software and What you seek from this course, Course attendance sheet, Course conduct. Course Objectives This course objectives are to teach participants: Introduction to the user interface, How to create and plan projects without resources including creating the WBS, adding activities, relationships and constraints, Formatting, filters, layouts and printing, Assigning Baselines and updating an un-resourced project, Adding and assigning Roles and Resources, Updating a Resourced project, Successful completion of the workshops is required to complete the course. Page 4 Page 5 Course Agenda DAY 1 1 - Introduction 2 - Creating a Project Plan 3 - Starting Up and Navigation 4 - Creating a New Project 5 - Defining Calendars 6 - Creating a Primavera Project WBS 7 - Adding Activities and Organizing Under the Wbs 8 - Formatting the Activity Window and Views 9 - Adding Relationships 10 - Activity Network View 11 Constraints continued Course Agenda DAY 2 12 - Printing and Reports 13 - Scheduling Options and Setting a Baseline 14 - Updating an Unresourced Schedule 15 - Administer Menu 16 - Creating Roles and Resources 17 - Assigning Roles, Resources and Expenses 18 - Resource Optimization 19 - Updating a Resourced Schedule 20 - Other Methods of Organizing Project Data 21 Index. Page 6 Page 7

1 - INTRODUCTION 1.1 - Purpose 1.2 - Required Background Knowledge 1.3 - Purpose of Planning 1.4 - Project Planning Metrics 1.5 - Planning Cycle 1.6 - Levels of Planning 1.7 - Monitoring and Controlling a Project. 1.1 Purpose of the course Provide a method for planning, scheduling and controlling projects using Primavera, Within an established Enterprise Project database or a blank database, Up to an intermediate level. Page 8 Page 9 1.2 - Required Background Knowledge The ability to use a personal computer and understand the fundamentals of the operating system, Experience using application software such as Microsoft Office and An understanding of how projects are planned, scheduled and controlled, including understanding the project management processes applicable to your projects. 1.3 - Purpose of Planning The ultimate purpose of planning is to build a model that allows you to predict which activities and resources are critical to the timely completion of the project, Strategies may then be implemented to ensure that these activities and resources are managed properly, thus ensuring that the project will be delivered both On Time and Within Budget. Page 10 Page 11 Planning aims to: Identify the total scope and stakeholders Plan to deliver the scope and understand the risks Increased project costs or reduction in scope and/or quality, Evaluate different project delivery methods Additional change over and/or operation costs, Identify the deliverables under a logical breakdown of the project, often called WBS or PBS Extensions of time claims, Loss of your client s revenue, Identifying activities required to produce the deliverables Contractual disputes and associated resolution costs, Identify and optimize the use of resources The loss of reputation of those involved in a project, Evaluate if target dates may be met and Identify risks and plan to minimize them Loss of a facility or asset in the event of a total project Provide a baseline plan failure. Assist in stakeholders communication Assist management to think ahead and make informed decisions. Page 13 Page 12 Planning helps to avoid or assist in evaluating:

2 - CREATING A PROJECT PLAN - SUMMARY 2.1 - Understanding Planning and Scheduling Software 2.2 - Enterprise Project Management 2.3 - Understanding Your Project 2.4 - Level 1 Planning Without Resources 2.5 - Level 2 Monitoring Progress Without Resources 2.6 - Level 3 Scheduling With Resources, Roles and Budgets 2.7 - Level 4 Monitoring and Controlling a Resourced Schedule. Now lets get our hands dirty! Page 51 Page 52 3 - STARTING UP AND NAVIGATION - SUMMARY 3.1 - Special Note Regarding Web Based Project Management Tools 3.2 - Logging In 3.3 - Primavera P6 Architecture 3.4 - P6 Web Functionality Areas and Interface 3.5 - Viewing Project Data 3.6 - Understanding the Projects Window 3.7 - Right-clicking with the Mouse 3.8 - Full Screen Mode Icon 3.10 Search Function Continued Page 53 3 - STARTING UP AND NAVIGATION SUMMARY (cont) 3.11 Accessing Help 3.12 Find and Replace 3.15 Closing Down 3.16 - Workshop 1- Navigating Around the Windows. Page 54 3.1 - Special Note Regarding Web Based Project Management Tools Web based technologies often require specialist knowledge to implement to ensure the software functions as designed. During the course of writing this book the author found that dependent on the configuration settings of the browser it was occasionally needed to allow pop ups to activate, The system configuration of both the hardware and software can also impact the speed of the system when implemented and due to the multitudinous number of different system combinations. 3.2 - Logging In The Administrator will provide you with: A web Address to access the Primavera Web Access software Login screen, which may be different to the one below, A Username and a Password, Open the Advanced tab to select another database or to change the Language, A database to log into that may be different to the one below, Click onto the Login button: Page 55 Page 56

5.8.2 - Remove a Base Calendar from a Calendar To remove a Base Calendar from an existing you will have to delete the text from the box. 5.10 - Adjusting Calendar Working Hours It is strongly recommended that the working hours per day are all the same and have the same start and finish time; otherwise, one-day activities may span two days and two-day activities may span three days, etc, The instructor will demonstrate how to adjust the calendar working hours. Page 117 Page 118 5.11 - Calendars for Calculating Summary Durations The summary duration of bands are calculated by: When all the activities in a band share the same calendar then the summary duration is calculated on the calendar of the activities in the band, and When activity calendars for the are different the summary duration is calculated on the Project Default calendar: 5.12 - Tips for Mixed Calendar Schedules When a project has mixed calendars with different start and finish times then one day activities may span 2 days: Techniques that may be considered to prevent this: Apply an appropriate lag to the relationship, or Assign all the calendars the same Start and Finish time but adjust the duration of the lunch break so the days have the desired number of hours. Page 119 Page 120 5 - DEFINING CALENDARS - SUMMARY 5.1 - Database Default Calendar 5.2 - Accessing Global, Resource and Project Calendars 5.3 - The Project Default Project Calendar 5.4 - Creating a New Global Calendar 5.5 - Creating a New Project Calendar 5.6 - Shared Resource Calendar 5.7 - Administer, My Calendar 5.8 - Promote, Copy, Rename and Delete a Calendar 5.9 - Base Calendars 5.10 - Adjusting Calendar Working Hours 5.11 - Calendars for Calculating Project, WBS and Other Summary Durations 5.12 - Tips for Mixed Calendar Schedules. 5.13 - Workshop 3 - Maintaining the Calendars The normal working week at OzBuild Pty Ltd is Monday through Friday, 8 hours per day excluding public holidays, The installation staff works Monday through Saturday, 8 hours per day and the some holidays, You will create two calendars, a 5 and a 6 day per week with some holidays. Page 121 Page 122

6 - CREATING A PRIMAVERA PROJECT WBS 6.1 Opening and Navigating the WBS 6.2 - Creating and Deleting a WBS Node 6.3 - WBS Node Separator 6.4 - Activity Window Work Breakdown Structure Lower Pane Details 6.5 - WBS Categories 6.6 - Why a Primavera WBS is Important 6.7 - Workshop 4 Creating the Work Breakdown Structure. 6 - CREATING A PRIMAVERA PROJECT WBS The Project WBS function is designed to record a hierarchical WBS that has been developed on a traditional basis as outlined in many project management documents, A well-structured WBS should: Include all the project deliverables and Be set at the appropriate level for summarizing project activities and reporting project progress, The project should be granulated (broken down) into manageable areas by using a project breakdown structure based on attributes of the project such as the Phases or Stages, Systems and Subsystems, Processes, Disciplines or Trades, and Areas or Locations of work. Page 123 Page 124 Project Breakdown Structures There are two types of Project Breakdown Structures that may be utilised to programme a project: Hierarchical and Matrix Either or both may be used in the one programme, The predominant method in P3 and SureTrak is the matrix format using Activity Codes, The predominate method in Primavera Project Manager is the WBS function and this is a Hierarchical structure. Simple Examples of WBS Structures The WBS for three buildings on one site may look like the pictures below: In which situations would each example be applicable? Page 125 Page 126 6.1 - Opening and Navigating the WBS The project must be open and the Activities window must be displayed, Ensure you have a view with a WBS icon beside it: 6.2 - Creating and Deleting a WBS Node To create a new WBS Node select a WBS Code or Name and either: Right-click to display the menu and use the menu commands Add Child WBS or Add Sibling WBS, or Use the menu toolbar Add Child WBS icon, Then use the icons on the Move toolbar to put the WBS Nodes at the right level or to reorder them, The commands Add, Delete, Copy, Cut and Paste all work to create, delete, move, and copy WBS Nodes. Page 127 Page 128

10 - ACTIVITY NETWORK VIEW 10.1 Introduction to the Activity Network View 10.2 - Early Date, Late Date and Float Calculations 10.3 - Workshop 8 Scheduling Calculations and Activity Network View. 10.1 - Introduction to the Activity Network View The Activity Network, also known as the PERT View, displays activities as boxes connected by the relationship lines: Page 195 Page 196 10.1 - Introduction to the Activity Network View This chapter will not cover this subject in detail but will introduce the main features, Many features available in the Gantt Chart View are also available in the Activity Network View, Some of the functions of the Activity Network View are shown in the book. 10.2 - Early Date, Late Date and Float Calculations To help understand the calculation of late and early dates, float and critical path, we will now manually work through an example, The boxes below represent activities. Page 197 Page 198 Forward Pass The forward pass calculates the early dates: EF = ES + DUR 1 Start the calculation from the first activity and work forward in time. Backward Pass The backward pass calculates the late dates: LS = LF DUR + 1 Start the calculation at the last activity and work backwards in time. Page 199 Page 200

13.3.8 - Displaying the Baseline Data The Baseline Dates may be displayed by: Displaying the Baseline columns: 13.4 - Additional Baseline Fields P6 R8.3 has added extra baseline fields in the Customize Columns form; BL is the Project Baseline BL1 is the Primary User Baseline Showing a baseline bar on the Bar Chart by selecting the appropriate bars in the Customize Gantt Chart Options form, Bars tab. Page 269 Page 270 13 - SCHEDULING OPTIONS AND SETTING A BASELINE - SUMMARY 13.1 - Understanding Date Fields 13.2 - Scheduling Options General Tab 13.3 - Setting the Baseline 13.4 Additional Baseline Fields 13.5 - Workshop 11 WBS, LOEs and Setting the Baseline. 13.5 - Workshop 13 WBS, LOEs and Setting the Baseline We will first look at how WBS and LOE activities work and Then set a Baseline. Page 271 Page 272 14 - UPDATING AN UNRESOURCED SCHEDULE 14.1 - Practical Methods of Recording Progress 14.2 - Understanding the Concepts 14.3 - Updating the Schedule 14.4 - Progress Spotlight and Update Progress 14.5 - Suspend and Resume 14.6 - Scheduling the Project 14.7 - Comparing Progress with Baseline 14.8 - Progress Line Display on the Gantt Chart 14.9 - Corrective Action 14.10 - Check List for Updating a Schedule 14.11 - Workshop 12 Progressing and Baseline Comparison Page 273 14.1 - Practical Methods of Recording Progress The following information is typically recorded for each activity when updating a project: Page 274 The activity start date and time if required, The number of days or hours required to complete the activity or the date and time the activity is expected to finish, The percentage complete, and If complete, the activity finish date and time. A printout of the schedule may be used for recording the progress of the current schedule:

17.10 - Resource, Planning Window The Resource, Planning window is out of the scope of this book but it allows high level resource planning by allowing resources or roles to be assigned at WBS Node level: 17.11 - Expenses Expenses are intended to be used for one off nonresource type costs, Expenses may be created using the Expenses tab of an activity, They may have both a costs and quantities: Page 341 Page 342 17.12 - Suggested Setup for Creating a Resourced Schedule This section of the book contains a check list you should consider when setting up a new project. Page 343 17 - ASSIGNING ROLES, RESOURCES AND EXPENSES - SUMMARY 17.1 - Understanding Resources 17.2 - Understanding Resource Calculations and Terminology 17.3 - Project Preferences Form, Resource Defaults 17.4 - My Preferences Applicable to Assigning Resources 17.5 - Activities Window Resource Information 17.6 - Assigning and Removing Roles 17.7 - Assigning and Removing Resources 17.8 - Demand Resources 17.9 - Resource and Activity Duration Calculation and Resource Lags continued Page 344 17 - ASSIGNING ROLES, RESOURCES AND EXPENSES - SUMMARY 17.10 - Resource, Planning Window 17.11 - Expenses 17.12 - Suggested Setup for Creating a Resourced Schedule. 17.13 - Workshop 14 Assigning Resources and Expenses to Activities The Resources must now be assigned to their specific activities. Page 345 Page 346

20.2 - Activity Codes Activity Codes may be used to Group, Sort, and Filter activities from one or more open projects, Activity Codes, such as Phases, Trades, or Disciplines, are often defined in the Activity Codes Definition form, Activity Code Values are defined in the in the Administer, Enterprise Data, Activities, Activity Codes tabs, such as: Page 377 Phases of Design, Procure, Install and Test, Trades of Brickwork, Plumbing and Electrical, and Disciplines of Concrete, Mechanical, Pipework, Activity Codes are assigned from the Activities Window using the Codes tab in the lower pane or displaying the appropriate Activity Code column, The instructor will demonstrate. 20.3 - User Defined Fields User Defined Fields are similar to Custom Data Items in P3 or Custom Fields in Microsoft Project and provide the ability to assign additional information to database records, They may be used for recording information about the data field as an alternative to Activity Codes and other predefined Primavera fields, The type of data that may be assigned to User Defined Fields would be equipment number, order number, variation or scope number; road, railway or pipeline changes; address and additional costs data, continued Page 378 User Defined Fields Activity data may be filtered, grouped, and sorted using these User Defined Fields in a similar way to Activity Codes, Data may be imported into the fields and, unlike Activity Codes, the data item does not have to exist in the database before importing, There are a number of predefined fields that may be renamed and new ones may be created., The instructor will demonstrate UDFs. 20 - OTHER METHODS OF ORGANIZING PROJECT DATA - SUMMARY 20.1 - Understanding Project Breakdown Structures 20.2 - Activity Codes 20.3 - User Defined Fields Page 379 Page 380 20.4 - Workshop 17 Activity Codes and User Defined Fields (UDF) This workshop will look at creating an Activity Code and some UDFs, We will create an activity code to represent the departments responsibilities for the Project. Review Expectations Any questions, Complete Feedback Sheet, Have we met your expectations? Page 381 Page 382 TCC0205-TRG-TM-SP10\A2

Database Cleanup at end of course, if required: Please could you delete all: User Filters User Layouts The resources created but NOT your Resource node Your projects. Thank you for attending Page 383 Page 384