Attendees: Members in Attendance: Alan Williams, Bert Weaver, Adina Levin, Scott Knies, Deborah Arant, Bruce Friesen, Jim Goddard, Laura Tolkoff

Similar documents
Project Team in Attendance: Leyla Hedayat (VTA), Brent Pearse (VTA), Kevin Kurimoto (VTA), Eileen Goodwin (Apex)

VTA s BART Silicon Valley Phase II Extension

Attendees: Members in Attendance: Alan Williams, Adina Levin, Charlie Faas, Scott Knies, Laura Tolkoff, Deborah Arant, and Bert Weaver

VTA s BART Silicon Valley Phase II Extension

Other Speaking Attendees: Leyla Hedayat (VTA), Brent Pearse (VTA), Jessica Zenk (CSJ), Rosalynn Hughey (CSJ),

Members not in Attendance: Craig Chivatero, Kelly Daugherty, Terry Christensen, Jeffrey Buchanan

Attendees: Members in Attendance: John Urban, Sudhanshu Jain, and Chris Shay

6.2.2 Environmental Consequences and Mitigation Measures

Santa Clara Valley Transportation Authority Board of Directors. General Manager, Nuria I. Fernandez

Chapter ES Executive Summary. Introduction

6.13 Utilities and Service Systems

Westside Subway Extension

VTA s BART Silicon Valley Phase II

BUS RAPID TRANSIT. El Camino Real Bus Rapid Transit Project. Environmental Scoping Meetings February 21 and 28

3.6 Construction Methods

Community Advisory Panel Meeting #

Purple Line Extension. Beverly Hills Community Meeting August 22, 2016

SR 710 North Study. Technical Advisory Committee Meeting No. 16 August 13, 2014 Stakeholder Outreach Advisory Committee Meeting No. 12 August 14, 2014

Los Gatos Creek Bridge Replacement / South Terminal Phase III Project

Eastside Transit Corridor Phase 2

Intent to Prepare a Supplemental Draft Environmental Impact Statement for the Capitol

Risk Evolution from Planning to Construction on the LA Metro Crenshaw/LAX Light Rail Transit Project

Volume I: Draft SEIS/SEIR

VTA s BART Silicon Valley Phase II Extension

High-speed rail will have a profound and transformational impact on the Bay Area. Some of the many benefits include:

4th International Engineering and Construction Conference - July 28, 2006

Phase 2 Update. October 12, 2017

VTA S BART SILICON VALLEY PHASE II EXTENSION PROJECT LOCATION HYDRAULIC STUDY

CONSTRUCTION Introduction to Construction

Regional Connector Transit Project Construction Update. June 9, 2016 Project Wide Community Meeting

Regional Connector Transit Project

Caltrain Business Plan

Metro Purple Line Extension

Caltrain Business Plan

VTA S BART SILICON VALLEY PHASE II EXTENSION PROJECT INITIAL SITE ASSESSMENT

Broadway Grade Separation Study. Palo Alto Rail Committee Meeting November 29, 2017

San Francisco Transportation Task Force 2045

BOARD OF DIRECTORS SPECIAL MEETING Friday, August 15, 2014 MINUTES

Metro Gold Line Eastside Extension Review Advisory Committee May 11, 2006

Transbay Program Phase 2 Downtown Rail Extension (DTX) Tunnel Options Study Briefing

Organization. Project Management Institute, Olympia Chapter Date Nov. 20, 2012

Accept the report on Priority Response to SPUR and Staff Identified Work Items.

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project.

VT 14 East Montpelier Bridge Project Informational Meeting. February 22, 2017

CALIFORNIA HIGH- SPEED RAIL PROGRAM UPDATE. October 9, 2018 SPUR, San Jose, CA

VTA S BART SILICON VALLEY PHASE II EXTENSION PROJECT INITIAL SITE ASSESSMENT

Frequently Asked Questions Connecting Palo Alto

Advanced Construction Techniques

Review of Plans and Specs from a Constructability Perspective

4.0 CONSTRUCTION METHODS AND ACTIVITIES

ISSUED FOR ADDENDUM No. 2 NOVEMBER 23, 2016 ATTACHMENTS. Add the following paragraphs to SC-10 Work Sequence & Constraints.

SEMMERING BASE TUNNEL LOGISTIC CHALLENGES

Memorandum. FROM: Jim Ortbal Rosalynn Hughey Barry Ng TO: HONORABLE MAYOR, CITY COUNCIL. DATE: June 16, 2017

Metro Gold Line Eastside Extension Construction Update April 20, Gold Line

Venice Pumping Plant Dual Force Main Project Draft EIR

FINAL ENVIRONMENTAL IMPACT STATEMENT. Final EIS in Focus

TRANSPORTATION RESEARCH FORUM March A State-of-the-Art of Underground Construction In Urban Areas

Transition from Paper Day Passes to Clipper

Eglinton Crosstown LRT Construction Liaison Committee

City of Los Angeles Department of Public Works

DIFFICULT GROUND SOLUTIONS:

COMMUNITY BOARD EIGHT

Introductions Project Updates Summary of Proposed Community Improvements Construction Impacts Management Open House

Presented by: Frank Guyamier

4.5 GEOTECHNICAL, SUBSURFACE, AND SEISMIC HAZARDS

PORT OF MIAMI TUNNEL PROJECT Highlights & Where we are today!

Railyard Alternatives & i-280 Boulevard (rab) Feasibility Study Phase I: Preliminary Options Analysis

Brooklyn Station Construction Open House

Progress update (November to March) 03/23/2009 2

4.0 Coordination and Consultation 4.0 Coordination and Consultation

MOBILITY PARTNERSHIP. Wednesday, August 16, 2017 MINUTES

WELCOME LOCAL SEGMENT PUBLIC MEETING SUMMARY OF PRELIMINARY RESULTS CORRIDOR EVALUATION

Description of Phase 2 Modified Design

COUNTY ENGINEERS ASSOCIATION OF MARYLAND SPRING 2016 CONFERENCE. Conference Center at the Maritime Institute Anne Arundel County, Maryland

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2

Silicon Valley Rapid Transit Corridor Final Supplemental EIR

ADDENDUM #1. PROJECT: Montrose Water Sports Park Construction BID NO: FROM: Scott Murphy DATE: August 15, 2014

Railyard Alternatives & I-280 Boulevard Feasibility Study: Meeting #5 1

Ravenswood Avenue Railroad Crossing Project

Caltrain Planning Update

Environmental Analysis, Chapter 4 Consequences, and Mitigation

MOBILITY PARTNERSHIP. Wednesday, September 14, 2016 MINUTES

Status of Projects to Reduce the Impacts of Transportation on Stormwater using Common Transportation Control Measures

Albany Park Stormwater Diversion Tunnel

Albany Park Stormwater Diversion Tunnel

Constructability Guidelines

SECTION 7. Public Infrastructure, Facilities and Services. 8Chapter 8 INFRASTRUCTURE ELEMENT

Memorandum CAPITAL OF SILICON VALLEY

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION

Lower Penitencia Creek Improvements Project. Community Update & Draft Environmental Impact Report Meeting May 22, 2017

HUDSON TUNNEL PROJECT

Rail-Volution Roundtable Sustainable Planning & Design

February 7, Purpose. Background. the BDCP. needs the project. Discussion. Facilities 1. plants) 1, October 1, 2013,

Jim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project

Application of Accelerated Bridge Construction for Local Agencies

Abo Canyon Second Main Track

Los Angeles Westside Purple Line Extension Project Challenges and Lessons Learned

The Aizhai Suspension Bridge is

SOUND TRANSIT STAFF REPORT MOTION NO. M

Tunnel Works. How we got here - Fort Wayne s Consent Decree. Tunnel Works Program Frequently Asked Questions

Transcription:

Downtown Diridon Community Working Group Meeting Date of Meeting: December 1, 2015 (4:00 p.m. to 6:00 p.m.) Attendees: Members in Attendance: Alan Williams, Bert Weaver, Adina Levin, Scott Knies, Deborah Arant, Bruce Friesen, Jim Goddard, Laura Tolkoff Members not in Attendance: Eyedin Zonobi, Derrik Seaver, Charisse Lebron Other Speaker Attendees: Erica Roecks (VTA), Jim Ortbal (CSJ), Tom Fitzwater (VTA), Michael Lehnen (HMM) Project Team in Attendance: Leyla Hedayat (VTA), Brent Pearse (VTA), Kevin Kurimoto (VTA), Rosalynn Hughey (CSJ), Jessica Zenk (CSJ), Ray Salvano (CSJ), Eileen Goodwin (Apex) Project Team not in Attendance: Michael Brilliot (CSJ) Location: San Jose Chamber of Commerce, 101 W. Santa Clara Street, San Jose CA Summary: The Meeting agenda included: Welcome and Introductions Follow up items Facilitator New Starts Project Development and Schedule Update VTA Staff Construction Methods and Approach Project Team Next Steps VTA staff Review Action Items and Next Meeting Date (February 9, 2016 4 p.m.-6 p.m.) Facilitator Key Issues/Comments/Questions: Comment/Question Follow up items None noted New Starts Project Development and Schedule Update Please explain what you mean by envelope Response BART Phase I environmental document cleared a tighter right-of-way line that the

Construction Methods and Approach Construction of Tunnels How does this presentation compare to the one delivered to the CWG s in 2007? Will there still be flooding concerns? That was an issue highlighted before. How do these construction methods compare to Central Subway project in San Francisco? How much progress can be made in a day with the tunnel boring machine? Can the two tunnels be bored simultaneously? Is there a reason not to work around the clock? Will these machines get stuck like the one in Seattle? What is a conditioning agent? Does the contractor break through between the tunnels for the cross passages? Do the cross passages delay forward progression of the machine? Phase II effort is looking at. The VTA wants to be able to be flexible with the Contractor and transparent with the community on the limits of the potential impacts so we re clearing a larger footprint. This is a lesson learned from Phase I. The team has more information now and the construction methods have evolved. The presentation has been updated to reflect this latest thinking. More information now. We can have Mike address ground water and flooding as part of this PowerPoint. These machines and methods in the presentation are similar to those being used at the Central Subway project. About 50 a day is standard. One 5 ring an hour when things go well for a typical 10 hour work day. They can but at this point it will be up to the contractor to decide how many tunnel boring machines to use at the same time could be one, two, four or even eight. Even when the crews work around the clock they still need to stop the machines for maintenance. The contractor will determine what schedules that will use to run the boring machines. That Seattle machine is much larger than the ones VTA is planning to use for the BART project. The soils are different in Seattle as well. It is not likely that the VTA project will have the same issues. A conditioning agent is a biodegradable soap-like agent making the muck the consistency of toothpaste that allows the boring machine to shape and transport the soil more easily onto the conveyor belt. Yes. They will support and reinforce the break through locations. No. They are often cut in after the tunnels are complete. Page 2

Will the muck come out at only the portals or will they pull much out of the station boxes too? How much extra soil will there be and where will it go? Will there be a constant flow of trucks? Can the CWG get a map of where the proposed cross passages are along the alignment? That will be up to the contractor and how the work is staged. Could be both areas. The soil range quantities will be in the environmental document. Where it gets hauled to will vary. If it is toxic, then it can only go to special sites. Regular soil could go a variety of places and that would be up to the contractor to determine. Some of the soil may even be reused on the project. The Contractor will determine how to stage the hauls. The muck generally needs to dry out prior to hauling away. There may be days with heavy truck traffic other days with fewer trucks depending on site activities. The cities will require the contractor to use only designated City truck routes. The environmental documents have plans showing where the cross passages are expected to go. However, the cross passage locations could be updated in the new environmental document. Here is the link to the most current version from the 2010 Final Environmental Impact Statement: http://www.vta.org/bart/finaleis2010 Is there some ability to adjust cross passage locations? Explain the timing of the grouting relative to the cross passages. Does the disposal of toxic soil cost more and has this been taken into account in the project budget? In the Central Subway project one of the cross passages turned into a sink hole. Construction Methods and Approach Construction of Typical Cut and Cover Appendix C - SVRTP Alternative Plan and Profiles (Phase II alignment begins on Figure C-9 on page 12) There is some ability to adjust but code and safety factors limit a lot of adjustment. Grouting would be done in advance of the excavation however that is up to the contractor. Yes and yes. VTA will be talking to the team behind that project to get lessons learned from them to avoid a similar situation on the BART project. Page 3

Stations Will this project be utilizing one contract or bid in packages? Is cut and cover only at the stations? When the downtown streets are put back in will there be efficiencies and upgrades to complete streets or be replaced in kind? Is slide 32 a plan or an illustrative? If it is possible to get synergy between the City and VTA on finished condition upgrades that would be desired. What about Diridon pedestrian flow during construction? That is important there are a lot of users. What is the duration of the closure of Santa Clara Street as the station gets built? What is your recommendation Mike for the type of construction method to build the station walls? Is the preferred method Slurry Walls or Deep Soil Mix (DSM)? Why give the contractor the option? What is the superior technique in your opinion? VTA has not determined that yet. VTA will decide the method of delivery by Fall 2017. No the mid-tunnel vent structures will also be constructed using cut and cover methods, although smaller in size and scope. Cut and cover will also be implemented at portal locations to the tunnel. VTA is replacing in kind for the most part but the City of San Jose and VTA are looking at opportunities to make upgrades where there is budget to do so and it makes sense. An illustrative. Comment noted. The contractor will need to provide safe access for pedestrians as part of the project plans and permits. There is no standard time it takes to build a station box. It varies by project. The range of closure will be included in the environmental document in the Construction chapter and more precise information will be developed during final engineering. The Project Team recommended slurry walls at 65% design as the best method because at the time, they could go deeper with this type of construction than DSM. When the contract is released in the future, the technologies could possibly have changed and the recommendation could change as well. Construction methods have improved for both types of construction. Contractor flexibility is desired when possible. There may be a recommendation in the actual bid documents requiring one type of method but the environmental document is clearing both types for added flexibility. Slurry (at the time of the last environmental document), but both could Page 4

Can this topic come back at a future date with more information regarding cost, durations, impacts etc. Does the tunnel boring machine get dragged through the station box? Would the LRT be suspended over the cut and cover for the station box? What is the duration of the phases of construction? If you clear more right-of-way what would stop the contractor from using it? Would the optimizing downtown rail effort you describe be covered in the environmental document? Will Caltrain be able to operate as the Diridon and Santa Clara stations are built? BRT example of business assistance: will VTA be helping the businesses impacted by the BART project? When will art and place making elements be determined? Given the long timeline, why hasn t VTA looked at a mined station? Construction Methods and Approach Underground Stations ~ Utilities & Station Specifics Who is responsible for utility relocation? work, which is why VTA is clearing both. Yes, once more is known additional information could be presented to the CWG on this topic of construction techniques. Yes, it could be but that would be up to the contractor to decide. Yes, that was looked at as an option. VTA has looked at a plan to build a LRT bridge over the cut and cover. It would be able to place the tracks on beams and support them. But details are to be refined should that station location be chosen. It varies, details and ranges will be listed in environmental document. It is a balancing act that VTA and the Project Team are continuously evaluating. Clearing a larger envelope doesn t ensure the space is used or purchased. No that would be covered in a separate environmental document and planning process once a strategy is determined. An update on this project could be presented to the CWG at a later date. Yes, that is the plan. The VTA Board adopted the current business assistance program for the Alum Rock BRT project only. VTA staff is benchmarking outreach programs and will be bringing best practices information to the CWGs and the VTA Board. VTA works with the cities on the art program and the architectural elements. Keep in mind the elements need to be able to be maintained. VTA has looked at mined stations on multiple occasions in the last decade. There is higher risk due to soft ground and water. Costs, schedule and risk were determined to be higher for this type of construction. Both VTA and the utility owners. Page 5

Is there an opportunity for retail? BART is moving toward activating the stations with more retail? Will VTA do this too? Does VTA need to use BART criteria? Explain slide 44 detail. Could there be a different crossover track area? Is VTA only looking at clearing one area? The location identified is impactful and disruptive. What if BART has a Phase III and the Phase II stops at Diridon, is this still the location for the crossover. VTA should do a better job of explaining the reasons behind the crossover track location and the tie to the Operations and Maintenance. The project seems to be impacting the proposed Tramwell Crow development at Diridon. Can you explain? Is Tramwell Crow going to have to wait until after BART is built? Construction Methods and Approach Construction Staging Areas (CSAs), Vent Structures and Newhall Yard Maintenance Facility Will the excavation for cut and cover at Diridon be covered for all of the area or only the streets? Will the construction of the vent structure at Santa Clara/13 th impact both sides of the street? It would be good to have retail in front of the vent structure. VTA wants the station areas to be active. VTA and BART coordinate regarding all aspects of the project including lessons learned at other BART stations. VTA is looking at generating revenues at the stations as you know from the financial presentations, so it is likely that VTA will have retail in the stations. Done. VTA has analyzed the cross over location and no other location options will be in the environmental document. The cross over location identified is the optimum location for ongoing operations of the system. Operations and Maintenance costs are very important factors as well as construction impacts. The VTA Board direction and the New Starts application supports a Phase II project with four stations and a maintenance facility. Comment noted. The project team will work on this information and bring it back to the CWG. The VTA, City and developer have been meeting to coordinate the proposal and the BART project. The development project has been informed of the BART project s requirements to not impact tunnel design. VTA will continue to coordinate with the developer. No they are planning construction in 2017. The temporary decking will be on Cahill, Montgomery, and Autumn Streets only. Yes, but the construction area will be about 50 so the impacts should not be too great. Comment noted. Page 6

Do stations get constructed first before the tunnel boring machine (TBM) arrives? For utilities do you have information regard short term and ultimate utility relocations? Will there be transfers and detours of transverse utilities? Will the utilities be managed when they re put back together? Merging utilities in a master plan would be desired. If the clearance envelope is building to building, how do you deal with historic buildings with basements? Look in the EIR scoping comments at the many suggestions to bring BART under the Caltrain tracks for better interface and more room at the Diridon station. LRT should be improved downtown. VTA should be improving access at Diridon. Is there anything in writing about the Diridon Intermodal Study? The BART footprint seems to go all the way the Los Gatos Creek. Can the creek and the Diridon station be tied together better? Can the systems facilities go elsewhere? Seems like next to the creek is a less than ideal location. Not necessarily, the contractor will determined construction order. At a minimum, the Support of Excavation (SOE) end walls need to be installed before the tunnel boring machine can travel through. Yes. There will be temporary relocations and/or bypasses. There is a BART standard for minimum separation from top of structure to the utilities. VTA is researching utility relocation from other projects VTA has taken into account the historic buildings, the foundation types, the soil conditions etc. Projects like the BART project can and have been built near existing historic structures successfully. The contractor and the project team will need to take care and monitor the buildings and the techniques involved. Comment noted. The Diridon Intermodal Study previously mentioned with this group will prioritize which connections need to be made seamless. Not all connections will be high priorities. Yes, the scope is being drafted and we can share with the CWG when it is available. The footprint goes over in that direction because that is where systems facilities will be located. VTA will be doing an access planning study next summer and those kinds of trails and connections will be looked at and shared with the City so they can incorporate them into their plans and budgets. VTA looked a variety of locations and this was determined to be the best location. Page 7

Could the muck be used to help restore the wetlands? Will the research currently being gathered on construction techniques be included in the environmental document? Is VTA surveying utilities before the contractor comes on board? When will the next E&Y financial information be available? Comment noted. Interesting concept. VTA is not planning to VTA is clearing the most conservative and is hoping to optimize everything. Yes, VTA is looking at best practices. We will send a link to E&Y materials when they are available. Follow-Up Items: Put PowerPoint animation on line Provide link to current placement of cross passages see link provided above Add to CWG work plan more discussion about cut and cover construction technique options, more information regarding cost, durations, and impacts when they are better known Provide more information that determined the optimal location of the cross over track Provide the scope for VTA s Diridon Intermodal Study to the CWG when available Send link to E&Y materials when available Prepared by: Eileen Goodwin, Apex Strategies Distribution: CWG Project Team City Staff Distribution list Page 8