IEEJ : June In the Name of Allah. Prepared by Planning Department 1

Similar documents
Ministry of Water and Power Preface

SECTOR ASSESSMENT (SUMMARY): ENERGY 1

SECTOR ASSESSMENT (SUMMARY): ENERGY Sector Performance, Problems, and Opportunities

The Development of a Gas Fired Thermal Power Facility at Sheberghan: Key Stakeholder Workshop 10 July Introduction and Overview

RECS International Inc. Yachiyo Engineering Co., Ltd. CTI Engineering International Co., Ltd. Sanyu Consultants Inc.

In The Name of Allah. Islamic Republic State of Afghanistan Ministry of Energy and Water

Afghanistan Resource Corridor Development: Power Sector Analysis. Executive Summary

AGRICULTURE PROSPECTS REPORT

Afghanistan Cement Industry

Opportunities and Challenges: Trade & Transit Facilitation Measures in Afghanistan

Afghanistan Food Security Monitoring Bulletin (AFSMB)

The province is divided into 15 districts. The provincial capital is Mazar-e-Sharif which has a population of about 368,100 inhabitants.

Project Concept Note

Launch Ceremony 2 nd Edition of the Provincial Briefs Report. Kabul, June 10 th Ministry of Economy Conference Hall

Electricity. It s essential for modern life. Without it, development is delayed and poverty endures.

Afghanistan Monthly Food Security Bulletin August 2004

Afghanistan Food Security Monitoring Bulletin (AFSMB)

Afghanistan. Renewable Energy Development Issues and Options. Issues and Options 6/26/2018. Public Disclosure Authorized. Public Disclosure Authorized

Preliminary Production Forecasts of the 1384 wheat and paddy

Afghanistan Pre-Harvest Assessment 2015 Preliminary Findings

The Islamic Republic of AFGHANISTAN LAND COVER ATLAS. Photo: FAO / Giulio Napolitano

General Information AREA: Population: 143 thousand. km2 (93% of the territory is covered by mountains) 8,7 mln. people Capital: Dushanbe city Independ

Ministry of Energy and Water

Figure 6.23: Location of Power Distribution Lines and Substations

AFGHANISTAN Special Report December 6, 2017

Sar-i-Pul. NATIONAL RURAL WATER SUPPLY, SANITATION & IRRIGATION PROGRAM (Ru-WatSIP) Provincial Profile

Logar province is located to the south of Kabul and is surrounded by Nangarhar, Pakitya, Kabul, Wardak and Ghazni 2

Enabling PV Afghanistan

Afghanistan Resource Corridor Development: Power Sector Analysis

Panjsher. NATIONAL RURAL WATER SUPPLY, SANITATION & IRRIGATION PROGRAM (Ru-WatSIP) Provincial Profile

SORBON KHOLMUHAMADZODA MINISTRY OF ENERGY AND WATER RESOURCES OF THE REPUBLIC OF TAJIKISTAN

ADB Assistance Program in Afghanistan: Outputs and Outcomes

Energy Sector Progress Report and Work Plan (August 2016 May 2017)

Islamic Republic of Afghanistan: Preparing the Small to Medium-Sized Hydropower Development Project

FOOD SECURITY Chapter Seven

Customs Reforms and Trade Facilitation

Nangarhar Energy Assessment Project ( NEAP) 3-Mar-2009

Islamic Republic of Afghanistan Ministry of Mines

South Asia Energy Security : Challenges And Opportunities

LONG TERM PLANNING, PRINCIPLES & PRACTICAL ANALYSES TURKISH ELECTRICITY TRANSMISSION CORPORATION

Afghanistan Food Security Bulletin November/December, 2004

REQUEST FOR QUOTATIONS

Afghanistan. Issues, Constraints and Objectives

SECTOR ASSESSMENT (SUMMARY): ENERGY. 1. Sector Background, Performance, Problems, and Opportunities

SECTOR ASSESSMENT (SUMMARY): ENERGY

Kandahar. NATIONAL RURAL WATER SUPPLY, SANITATION & IRRIGATION PROGRAM (Ru-WatSIP) Provincial Profile

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT

Use of water and energy resources in Central Asia

2 Strategic goals of Tajikistan NATIONAL DEVELOPMENT STRATEGY ENERGY SECURITY TRANSPORT CORRIDOR FOOD SECURITY

Infrastructure Connectivity in Afghanistan

Report and Recommendation of the President to the Board of Directors

Public Disclosure Copy

SECTOR ASSESSMENT (SUMMARY): ENERGY

PUBLIC SECTOR CASE STORY TEMPLATE

AFGHANISTAN SPECIAL REPORT: Pre-Harvest Assessment May 2013 Wheat harvest volume from May to September likely to be above average

Utilizing Soybeans for Nutrition And Income In Afghanistan By Nutrition and Education International (NEI)

DISASTER RISK MANAGEMENT OVERVIEW

SECTOR ASSESSMENT (SUMMARY): ENERGY

Electricity Sector Development Trends in an After-war Country: Afghanistan Aspiration for an Independent Energy Country

1) Sheberghan Gas Field Investigation and Power Plant Conceptual Design Project

THEME Country profile Current state of energy sector Outlook of energy demand and supply The energy policy Documents and its implementation. Short ter

AFGHANISTAN. Speaking Points. Eng. Aman Ghalib Dy. Mini Energy Minister of Energy and Water Islamic Republic of Afghanistan

FLOATING SOLAR POTENTIAL IN CENTRAL AND WEST ASIA

Country Presentation Bangladesh

Content Sri Lanka At a Glance Energy reserves Current Energy Policy and Measures Past Energy Demand and Supply Outlook of energy Demand and Supply Ene

THE REPORT ON THE COUNTRY

SECTOR ASSESSMENT (SUMMARY): ENERGY (ELECTRICITY TRANSMISSION AND DISTRIBUTION)

The Contribution of Regional Markets to Afghan Wheat Supplies May 2007

COUNTRY PRESENTATION. Regarding PAKISTAN. TARIQ QAZI Chief Executive Officer NATIONAL TRANSMISSION & DESPATCH COMPANY PAKISTAN

Regional Infrastructure Impact for Central Asia

TAJIKISTAN S ENERGY PROFILE - POTENTIAL & PERSPECTIVES. KHUSRAV ABDULLOEV Ministry of energy and water resources of the Republic of Tajikistan

First Meeting of Task Force 2 on Advance Transmission System Interconnections

Dear ladies and gentlemen!

PROJECT TECHNICAL DESCRIPTION

DEVELOPMENT OF ELECTRICITY TRADE IN CENTRAL ASIA SOUTH ASIA REGION 1

Electricity Sector Transitions in an after War Country: A Review of Afghanistan s Electricity

Developing a Regional Roadmap on Energy Connectivity. China Electric Power Planning & Engineering Institute Bangkok

Power sector Policy,Legal and regulatory Frame work Sri Lanka. Sulakshana Jayawardena Actg.Director(Pl.and Dev.) Ministry of Power & Energy

Plant Load Factor: 50%

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No.

Cooperation in the Energy Sector

Country Report of The Islamic Republic of Pakistan

Hydro One Experience with Renewable Distributed Generation & Advanced Distribution System Initiative

Report on Grievance Redressed Mechanism (GRM) & Safeguard Training

SECTOR ASSESSMENT (SUMMARY): ENERGY. 1. Sector Performance, Problems and Opportunities

NOOR AGRO GROUP. Established in 1993 PROFILE. 2 nd Point of Contact. Deputy Director Integrated Development Unit

Afghanistan: Railway Development Study Financed by the Asian Development Bank (ADB)

Contents. Partnerships Logistics & Pipeline Security WFP AFGHANISTAN MONTHLY REPORT NOVEMBER World Food Programme. Programa Mundial de Alimentos

REGIONAL SUPPLY AND MARKET OUTLOOK Central Asia. October 7, 2016 KEY MESSAGES

SAARC:- Energy Security

Draft Strategy and Work Plan ( ) for Regional Cooperation in the Energy Sector of CAREC Countries

Grid Resilience in Developing Countries

Sustainable Energy for All Afghanistan

INTERNATIONAL TRANSIT TRANSPORT CORRIDORS AND PORTS OF ENTRY/EXIT. Article 1: Content of the Annex

SECTOR ASSESSMENT (SUMMARY): ENERGY 1

Seasonal Food Security Assessment Afghanistan

Cambodia s First Solar Park

SUMMARY SECTOR ASSESSMENT: ENERGY 1

Quarterly Report. Afghanistan Reconstruction Trust Fund MAY 2017 JULY SUPERVISORY AGENT: Management Systems International. Date: 15 March 2018

Nuclear energy development in the Republic of Armenia. IAEA, Amsterdam June

Transcription:

IEEJ : June 2011 In the Name of Allah Prepared by Planning Department 1

Islamic Republic of Afghanistan Ministry of Energy & Water Status of the Power Sector in Afghanistan Past, Present, and Future 2

Ministry of Energy and Water Electricity Sector Policy Provide overall direction for electricity sector development and formulate broad policies and regulations for the benefit of all of Afghanistan that is consistent with other national development plans and laws; Initiate the establishment of an independent electric regulatory entity; Promote private sector participation and investment in the electricity sector; Encourage the expansion of access to underserved and rural communities; Stimulate the rational use of new and renewable sources of energy; and Represent the government of Afghanistan in electricity matters pertaining to regional interconnections and international organizations. 3

PAST 4

Electricity Status Pre-2002 Total operating generation capacity was 291 MW Hydro: 257 MW Diesel Gen-set: 34 MW Total consumers supplied: 117,000 5

PRESENT 6

Power Sector Status After 2002 Power generation and import has been increased from 264 MW to 700 MW. Installed capacity to import power from neighboring countries has been raised from 50 MW to 335 MW. Total 110 KV, 220 KV transmission lines length have been raised from 745 Km to 1,665 Km. Kabul and provinces distribution networks have been undergoing rehabilitation and extension. Total number of consumers has been increased from 117,000 to 633029. 7

Available Power Generation capacities in overall Afghanistan Hydro 252 MW Thermal (Kabul & Mazar-e-Sharif) 90 MW Diesel 74 MW Import capacity 212 MW Renewable Energy 13.1 MW Small Diesel Gen-Set 65.5 MW Total 706.6MW Total number of electricity customers is about 633029 representing 36% of the country population. About 60% of customers are in Kabul. 8

Existing Power Plants

Present Capacity of Absorption for Importing Power From Turkmenistan: 84 MW from 110 KV line to Andkhoy, Jawzjan, Saripul, and Maymana 76 MW from 220 KV line (used at 110 KV) to Herat and Rubat Sangi From Uzbekistan 300 MW from 220 KV line for Kabul City and provinces situated in traverse to the line. From Tajikistan 25 MW from 110 KV line to Kunduz From Islamic Republic of Iran: 72 MW through 132 KV double circuit TL to Herat and Ghorian substations 3 MW through 20 KV double circuit to Herat 4 MW through 20 KV line to Nimroz 10

Existing Transmission Import Lines.

Cost of Imported Energy Average purchase rate of imported energy 3.125 US cent/kwh Average overall cost of imported energy 6.5 US cent/kwh Average selling rate of imported energy 6.026 US cent/kwh 12

Cost of bill for Imported Energy Cost for bill of Hydro Power - Residents (Kabul,Pul-e-Khumri,Jalal Abad, Kandhar, Helmand) 1-300 KW/h 1.5 Afg - Industrial Centers (MMI registered) 301-700 KW/h 4 Afg - Commercial/Governmental/Embassies 701< KW/h 10 Afg - Residents (Herat, Fariab, Jouzjan, Sar-e-pul, Kundoz) 10 KW/h 13

Installed Capacity in Kabul The total installed capacity of power generation in Kabul Zone is 258 MW including: 188 MW Hydro 95 MW Thermal 133 MW Diesel 128 MW import 14

Present Status of Electricity in Kabul City Available capacity in Kabul Zone is 231 MW Substations absorption ability is about 437 MVA Network absorption ability is around 200 MVA Number of Kabul City consumers is 237248 Kabul City energy requirements is about 300MW in summer peak and 400 MW in Winter peak 15

Energy Sector Development THE FUTURE 16

Energy Resources Potential Hydro power potential: 23,000 MW (large, medium, small dams and micro hydro power plant ) Natural gas: 60 billion cm approx. Petroleum : 12 million tons Coal reserves : 100 million tons (in different locations throughout the country (establishing the precise quantities and qualities require further studies) Solar and wind potential: (Mapping to be completed and least cost options to be pursued ) Most of these foresaid reserves have not been exploited yet. 17

Power Plant Projects Under Construction Salma Hydro Power Plant of 42 MW capacity Parandy of Panjsher Hydro Power Plant of 4.05 MW capacity Construction of Chamkany,Bamyan, Charday Ghorband,Asad Abad of Kunar; and Machlghu of Paktya provinces micro-hydro-power Plants 18

Improvement of the Present Status of Power Short Term Actions (1385-1388) Purchasing of Diesel Gen-set Rehabilitation of the existing Hydro and Thermal Power Plants Upgrading of Distributing Networks in order to reduce technical and commercial losses Importing power from neighboring countries Developing Renewable Energy resources 19

Improvement of the Present Status of power Short Term Actions (1385-1388) Completion of NEPS high voltage transmission lines. Development of domestic sources of energy Installation of a gas-fired thermal power plant of 105 MW in Sheberghan. 20

Improvement of the Present Status of Power Cont. Medium Term Actions (1385 1390) HPP Feasibility Studies Initiated and ongoing: Baghdara Hydro Power Plant Kukcha & Kunar Kilaghai Kama River (starting) Fara Roud Gul Bahar HPP Feasibility Studies to be initiated: Surobi 2 Kajakai 2 Olambagh Amu & Panj River Kala Gosh 21

Improvement of the Present Status of Power Transmission Grid National Grid System Development Plan > 500 kv Turkmenistan to Mazar-i-Sharif > 220 Kv Hayratan-Kabul Tajikistan Pul-i-Khumri Kunduz-Taluqan Kabul - Lugar Gardez Khost Ghazni Paktika Kajakai Kandahar Farah-Herat > 110 Kv Sher Khan Bandar-Amam Saheb Naghlu Jalalabad Mehtarlam Badghees Turkmenistan Sher Khan Bandar- Quala-e-Zal 22

Improvement of the Present Status of Power Transmission Grid The first phase of the National Grid System is the North East Power System: NEPS 23

Objectives of the North-East Power System (NEPS) Establishing of the first branch of National Grid Supplying of power to Northern, North-Eastern and Southern Provinces Possibility of importing power from Uzbekistan, Tajikistan and Turkmenistan Transmitting of Energy from domestic energy sources Transmission of Electricity to neighbor countries through Afghanistan. 24

The North East Power System

Substation (S/S) Expansion- Construction Program Expansion of North West and Kabul North S/S Construction of 220/20 KV Grid S/S in Kunduz, Mazar-e-Sharif Taluqan, Puli-Khumri, Khulm, Aybak, Doshi, Charikar, Chimtala Gardez, Pul-e- Alam, Khost, Ghazni and Paktika Construction of 110/20KV S/S in Laghman- Jalalabad, Sar-e-Pul, Amam Saheb and Qualae-Zal 26

Donor Organizations NEPS 220 KV Hairatan-Kabul Transmission Line Asian Development Bank $113.1 million World Bank $94.383 million Islamic Development Bank $16.5 million Gov t. of India (GoI) $126 million Gov t. of Germany (KFW) Euro22.5 million or $31.5 million Gov t. of Afghanistan $118.243 million Gov t of Iran $ 7.1 million US Gov t. (USAID) $340 million Total $846.826 million 27

Progress of Hairatan-Kabul 220KV Transmission Line (442 Km) Uzbekistan Border to Puli-Khumri Section (240Km) competed: Hairatan Naibabad-Mazar-e-Sharif-Puli-Khumri completed. Hairatan-Naibabad Mazar-e-Sharif (ADB) completed. Naibabad to Puli-Khumri (ADB) completed Naibabad switching station (ADB) completed Erection of Mazar-e-Sharif (50 MVA) and Puli-Khumri (32 MVA) 220/110 KV (S/S), (Germany-KFW) completed. Transmission line capacity is 300 MW Provinces impacted : Balkh, Semangan and Baghlan 28

Progress of Hairatan-Kabul 220KV Transmission Line (442 Km in length) Puli-Khumri to Kabul Section (202 Km): Puli-Khumri to Chimtala to Kabul North West S/S to Kabul North S/S Puli-Khumri to Chimtala (GoI) completed. Chimtala S/S (GoI) In construction 95% completed. Aybak S/S,Doshi and Charikar S/S (in procurement stage) Provinces impacted: Baghlan,Parwan, Kapisa and Kabul 29

NEPS in Development NEPS POWER IMPORT STATUS 30

Tajikistan- Puli Khumri 220 KV Transmission Line Capacity : 300 MW (D/C dual conductor) Donor: ADB Developing regional energy trade competition Provinces impacted by grid extension: Northern, North-East and South-East Provinces Present status : Under Implementation stage 31

Turkmenistan - Naibabad 500KV Transmission Line Line Capacity : Nominal 300 MW (TBD) Donor : Unfunded Provinces impacted by grid expansion :Northern, North-Eastern, Southern and South-Eastern provinces Present States: Technical discussions for locating of border point for crossing of the transmission line, between both sides is under way. 32

Preference to the Importing of Power in Medium Term Access to cheaper energy in the range of (currently 2 to 6 US cent Per KWh ) Availability of surplus power in neighboring country to be accessed Purchasing power from neighboring countries is cheaper than the domestic energy sources > Hydro Power 4.6 US cent per KWh > Thermal Power 32 US cent per KWh > Diesel Gen-sets 20 US cent per KWh 33

Long Term Planning HPP Construction: Baghdara (nominally 220 MW) Surobi 2 (nominally 180 MW) Kajakai 2 (nominally 100 MW) Specification of Kukcha River potential Specification of Kunar River potential Thermal Plant - Construction of coal fired thermal Power Plants 34

Sources of Electrical Power in Afghanistan Afghanistan main sources of Power are as follows : Hydro Natural gas Petroleum Coal Renewable Energy 35

Thanks for Your Kind Attention Contact : report@tky.ieej.or.jp 36