16th Annual Surface Water Meeting October 21& 22, 2013

Similar documents
15th Annual Surface Water Meeting October 1& 2, 2012

ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT

Avon Lake Corrosion Control Study and Orthophosphate Implementation. Andrew Skeriotis, Stantec Greg Yuronich, Avon Lake Regional Water

Beginning the Treatment Journey

Ferric Sulfate Success Story - OWASA s Switch to Ferric Sulfate Leads to a Reduction in Disinfection Byproducts

Treatment options for hydrogen sulfide. Testing for hydrogen sulfide

Lake Houston SolarBee Project Report by

THE BOSSIER CITY WATER TREATMENT PLANT (Background and Current Process Layout )

Utility Partner Data Report

DW Module 22 Inorganic Removal Basics Answer Key

ONLINE MONITORING PRACTICES FOR MANGANESE CONTROL IN DRINKING WATER TREATMENT

Rectangular Basin = Volume, gal (Length, ft) x (Width, ft) x (Height, ft) x7.48 gal/cu.ft.

Utility Partner Data Report

Summary of Flint s Implementation of Veolia s Recommendations

Chapter 109 Update. Water Supplier Challenges and Unintended Consequences

City of Topeka Utilities Department

City of Marshall. June 1, Dear City of Marshall Water Customers:

Approved Capacity. March 2010

Water distribution systems throughout

Seasonal Source Water Quality and Treatment Challenges Town of Newburgh s Chadwick Lake Filtration Plant

(b) Water Engineering Basics

The Most Effective Method to Clean a Well uses Well Guard

FROM RAW WATER INTAKE TO DISTRIBUTION NETWORK: THE JOURNEY OF DBP CONTROL

CITY OF LAGRANGE, GEORGIA UTILITY DEPARTMENT WATER CONSERVATION AND DROUGHT CONTINGENCY PLANS

Balancing Microbial Control and Stage 2 DBP Rule Compliance (at Ocean City, Maryland)

Water Treatment Overview. Gabe Sasser December 2016

Submerged Membranes to Replace Media Filters to Increase Capacity 4X for a Small Community. Richard Stratton, PE HDR Engineering, Inc.

OPTIMISATION OF IMAGE FLAT WATER TREATMENT PLANT. Tony Humphries. Tony Humphries, Operator, SEQ Water

WATER SYSTEM PRESENTATION. Presenter: Mike Oemcke Company: OCWA Central New York s Water Authority Department: Water System Engineering

Disinfecting Your Well

DRINKING WATER CONSTRUCTION PERMIT APPLICATON

Ohio Section AWWA NW District Fall Meeting April 20, City of Delaware Water Plant Improvements

OPERATOR DUTIES WEEDKDAY SHIFT

GENERAL SERVICE SCHEDULE GS-TOU OPTIONAL GENERAL SERVICE TIME OF USE METERED RATE

MONTHLY OPERATION REPORT (MOR)--ALL WATER SYSTEMS

Membrane Technology: From Manufacture to. May Production

INDIANA STATE DEPARTMENT OF HEALTH Sanitary Engineering 2 North Meridian Section 5E Indianapolis, Indiana AC 317/

Hydraulic Modeling and System Optimization

Disinfection Byproducts in the Drinking Water What Does it Mean and What is Being Done

THIS POLICY DOES NOT HAVE THE FORCE OF LAW

TITLE 252. DEPARTMENT OF ENVIRONMENTAL QUALITY CHAPTER 631. PUBLIC WATER SUPPLY OPERATION SUBCHAPTER 1. INTRODUCTION

Aquatronics. Course 6: Energy optimization in water supply and wastewater treatment systems Course 7: Fundamentals of closed-loop control technology

HaloSan The Ultimate Solution: Eliminate Iron Bacteria in the Well

Module 1 WATER SUPPLY SYSTEM BASIC OPERATIONS

Water Treatment Plant Startup Issues and Considerations

Hydraulic Modeling Assisting in Water Quality. Jinghua Jing Xiao, Ph.D., P.E. Senior Planning Engineer SE PA-AWWA Fall Conference 2018

A Study of Water Treatment at the Bhandup Water Treatment Plant, Mumbai.

WILDERNESS MOUNTAIN WATER SERVICE 2014 ANNUAL REPORT OCTOBER 5, 2015

DW Module 23: Organic Removal Answer Key

RECORD DRAWINGS NOTE: alt32 ARCHITECTURE DESIGN 310 OLD VINE STREET, SUITE 300 LEXINGTON, KY 40507

Renovation of the Filters at the Soldier Canyon Filter Plant in Fort Collins, Colorado

City of Redding Water Utility 2006 Consumer Confidence Report

UCMR4 Cyanotoxins. What Will You Do If You Find Them? Keith W. Cartnick AWWA PA Annual Conference 2019

Lowering The Total Cost Of Operation

WEFTEC.06. Lake Okeechobee, Actiflo, peroxone, surface water, Cyanobacteria

Town of Christiansburg 2017 DRINKING WATER QUALITY REPORT

ATTACHMENT A TO THE AGREEMENT FOR ENGINEERING SERVICES. Project: Chloramine Replacement Alternative Evaluation

Removal of Manganese by Microfiltration in a Water Treatment Plant*

Pressure Distribution Design

2017 Annual Drinking Water Quality Report Sampson County District I - Clinton Water System Number:

Start and Finish Dates: You will have 90 days from this date in order to complete this course

Pueblo Water 2017 Water Quality Report

Disinfection Overview. Module 3

CHAPTER SEVEN: UTILITIES

COWRA S WATER TREATMENT PLANT - A CHANGE IN PROCESS CONTROL PHILOSOPHY. Ken Keliher. Cowra Council

Side by Side Piloting of Process Alternatives Yields Direct Performance Comparison

WATER QUALITY NEW ORLEANS AND FLINT CEDRIC S. GRANT EXECUTIVE DIRECTOR, SEWERAGE & WATER BOARD OF NEW ORLEANS MARCH 16, 2016

Costs and Benefits of Implementing the Disinfection Requirements Rule for Philadelphia Water

2015 Annual Report. Magic Lake Estates Water and Sewer Services Annual General Meeting August 13, 2016

Table of Contents. 0.0 Executive Summary Potable Water Demand Projection Introduction... 35

1 American Water College

TITLE 252. DEPARTMENT OF ENVIRONMENTAL QUALITY CHAPTER 631. PUBLIC WATER SUPPLY OPERATION SUBCHAPTER 1. INTRODUCTION

MUNICIPALITY OF ROBLIN

CLARENCE COLLIERY WATER TREATMENT

BWA Drinking Water Quality Report

TITLE 252. DEPARTMENT OF ENVIRONMENTAL QUALITY CHAPTER 631. PUBLIC WATER SUPPLY OPERATION SUBCHAPTER 1. INTRODUCTION

Evaluating Water Quality from Source to Tap: Using Hydraulic Modeling, Statistical Analysis and Other Tools to Improve Water Quality

Integrating Ozone and Ion Exchange into a 40 Year Old Lime Softening Plant

Written submission from Scottish Water

TITLE 252. DEPARTMENT OF ENVIRONMENTAL QUALITY CHAPTER 631. PUBLIC WATER SUPPLY OPERATION SUBCHAPTER 1. INTRODUCTION

The next step in ozone purification

Water Audit and Water Loss Abatement Program

Copies: Mark Hildebrand (NCA) ARCADIS Project No.: April 10, Task A 3100

Ohio EPA s Manganese Compliance Strategy September, 2017

Does ultrasound work for bluegreen algae control at lower cell counts (1000 cells/ml)? This would be for MIB/G control.

Water Supply FAQ August 11, 2015

Strategic Plan. A public, non-profit agency providing water, sewer and reclaimed water services to the Carrboro-Chapel Hill community.

Developing a Municipal Source Water Protection Plan: A Guide for Water Utilities and Municipalities

Field experience by water treatment facilities of Chlorine Dioxide & Chlorine Compound Disinfectant, replacing the traditional chlorine treatment

PERFORMANCE AND RESIDUAL MANAGEMENT ASSESSMENT OF 5 MGD MEMBRANE WATER PLANT. Presented by: Stephen P. Dorman, P.E.

Guidance on Controlling Corrosion in Drinking Water Distribution Systems

TTHM Reduction Corrective Action Update 1 st Progress Meeting October 18, Robert Horvat, P.E x1501

Pilot Testing and Evaluation of Three Filtration Technologies for the Eugene / Springfield Wastewater Treatment Plant

Quality REPORT. annual. Presented By. Water Testing Performed in 2017 PWS ID#: IL

GOSFORD S EXPERIENCE IN MANAGING IRON AND MANGANESE. Michelle Pankhurst & Michael Redrup. Gosford City Council

Seattle Public Utilities Water Supply FAQ

Dipti Shah, Town of Gilbert Tuesday, January 25, 2011

A Flight Plan for Success: Practical Aspects of Pilot Testing in Planning, Design and Optimization

SYSTEM ID: KY 3 NARRATIVE DESCRIPTION

Transcription:

ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT August 30, 2013 Volume 5, Issue 2 Alabama s Optimization Program Inside this issue: Water Based Batteries 3 Representative Distribution Sampling Storage Tanks Degraders of Water Optimization Poster 16th Annual Surface Water Meeting Agenda 16th Annual Surface Water Meeting Registration Form DWB Reminders All distribution samples should be using the physical address not names. Stage 2 started January 1, 2012 for all water systems Parent System OELs Have Started UCMR3 to started in 2013 LT2 Plans Due October 1, 2014 (Schedule 1) Next issue of Drawing The Graph tentatively for April 2014 4 4 5 6 7 16th Annual Surface Water Meeting October 21& 22, 2013 The ADEM Drinking Water Branch is proud to announce that its 16th Annual Surface Water Meeting is now open for registration. The meeting will be held on October 21st and 22nd, 2013. Registration will start at 11:00 a.m. on the 21st with presentations starting at 1:00 p.m. and registration will start at 7:00 a.m. on the 22nd with presentations starting at 8:00 a.m. This year s meeting will cover a wide variety of topics similar to previous years. The topics covered this year vary from a traditional Drinking Water Update and will focus on new regulatory requirements that will affect your water system and the possibility of cutting your energy costs. Please plan on attending this year s meeting to make sure that you are up-to-date on all the latest requirements. The agenda and registration form are attached to this newsletter and can be downloaded from the ADEM website at http://www. adem.state.al.us/waterdivision/drinking/dwmaininfo.htm. 15th Annual Surface Water Meeting October 2012 Manganese Treatment using Simulated Data Chad Smith (Cullman Utilities Board) The City of Cullman operates and maintains a 24 MGD water treatment plant that uses Lake Catoma as its source. Lake Catoma is an approximately 540 acre 90 feet deep reservoir. The City of Cullman Water Treatment Plant provides water to all the citizens of Cullman as well as most of the citizens of Cullman County. The size and the depth of Lake Catoma create an ideal environment for soluble manganese. The depth of the reservoir promotes stratification and anaerobic conditions in the lower layers along with dissolution of manganese from sedimentation on the lake bed. The removal of soluble manganese from drinking water can be difficult but is necessary in order to remain compliant with regulations and to protect the health and property of customers. In the case of manganese treatment, manganese found in surface water can exist in multiple oxidative states which make treatment difficult. The Cullman Treatment Plant has used several methods over the years to treat manganese in its drinking water; one of the early more successful methods being oxidation through elevated ph and addition of high doses of chlorine. Unfortunately, the treatment of raw surface water using (See Manganese on Page 3) ADEM s mission is to Assure for all citizens of the State a safe, healthful and productive environment.

Page 2 Manganese (Continued From Page 1) free chlorine has been proven to be a major contributing factor to the formation of disinfection byproducts. This is due to high concentrations of organic carbon available to react with free chlorine prior to coagulation and sedimentation. The Cullman Treatment Plant has remained in compliance over the years but, with the additional testing required by Stage 2 monitoring for consecutive systems, wholesale customers would find it difficult for the combined distribution system to remain in compliance with the new rule. The Cullman Treatment Plant turned to potassium permanganate as a way to oxidize soluble manganese. Potassium permanganate oxidizes soluble manganese into a precipitous form that will readily settle out in the settling basins or be filtered out. The treatment plant has had moderate to significant success using this method as potassium permanganate has a fast reaction time and the plant has minimal contact time from the raw water intake to the plant. Potassium permanganate fastest reaction time occurs when the ph is above 7 Through experience and experimentation, the treatment plant has found that a manganese residual up to 0.1 mg/l in the filtered sample is sufficient in keeping finished water residuals below 0.04 mg/l. This method has decreased the potassium permanganate dose by 20 50%. The disadvantages the treatment plant discovered about using potassium permanganate is that the dose must be precise and an overdose will create a pink coloration in the water. If the dose is too low, soluble manganese will pass through the filters and cause staining as well as taste and odor problems. The treatment plant for years used a standardized formula that did not consider other raw water characteristics that could place additional demand on the potassium permanganate. This method required operators to calculate potassium permanganate dosages based on results from raw water testing (primarily the amount of iron and manganese present in the raw water). Operators then had to wait until the water had traveled through the treatment plant in order to evaluate how well the new dosage had worked. Unfortunately, raw water characteristics change constantly and a standardized formula can only work when conditions are always known. With the help of vendors and research, the Cullman Treatment Plant has developed a testing and monitoring program that is more efficient in the removal of manganese as well as chemical conservation. The operator collects a grab sample immediately after the flash mix, filters the sample using a 0.45 micron syringe filter, and tests the resulting sample for total manganese. It is important to note that this sample must be collected, filtered, and tested in a timely manner as the manganese in the sample will continue to be oxidized while in the presence of potassium permanganate. The results are then recorded for future reference. Through experience and experimentation, the treatment plant has found that a manganese residual up to 0.1 mg/l in the filtered sample is sufficient in keeping finished water residuals below 0.04 mg/l. Results greater than 0.1 mg/l require dosage adjustments and additional testing. This method has decreased the potassium permanganate dose by 20 50%. The plant has also benefited from reduced color and turbidity in the settling basins caused by residual potassium permanganate. This is a direct result of using simulated results to determine how the potassium permanganate dose will perform in the plant. This method allows a more precise dose to be administered, gives operators more control over raw water manganese treatment, and allows chemicals such as chlorine to be moved further back in the treatment process and used for protection in the distribution system as opposed to an oxidizer for manganese. Operators no longer need to guess if potassium permanganate doses will work; they simply draw the samples, simulate what will happen in the plant, and adjust the dose accordingly. Operators must be aware that the simulated method relies heavily on historical data for maximum effectiveness. This is because an over dosage of potassium permanganate will result in an elevated manganese reading just as will an under dosage. Historical data gives operators reference material to determine what dosages have worked most effectively in the past with similar raw water characteristics.

Water-based batteries: With the right rate structure, can water utilities back up the electricity grid? By Mary Tiger, Environmental Finance Center at the University of North Carolina, Chapel Hill Page 3 The Electric Power Research Institute and the U.S. Environmental Protection Agency estimate that 3-4% of U.S. national energy consumption is used for drinking water and wastewater services. That equates to between 2.9 and 3.9 quads annually (a quad is a quadrillion British Thermal Units), based on 2011 data from the U.S. Department of Energy. Pumping - raw water, treated water, and wastewater - demands the bulk of that energy. While the industry has little control over its wastewater pumping load, it has more control over when and how it pumps raw and treated water into and within its system. Through modification to pumping schedules, water utilities have an enormous potential to reduce peak load on the country s electricity grid and subsequently save substantial money. In other words, water utilities can use most of their energy at night, when energy is relatively abundant and less expensive, to fill reservoirs and elevated storage tanks. Operating this way, the country can use its water infrastructure as a sort of battery for its electric infrastructure. But in order for this to take place, energy utilities need to make available a rate structure that financially incentivizes this type of energy management, and water utilities need to understand and manage their electricity consumption and demand to take advantage of them. The Environmental Finance Center has been working with groups of small water systems in Utah, Alabama, and North Carolina to do just this. As part of this effort, one utility has captured the financial benefit of understanding and managing energy use according to a time-of-use (TOU) rate structure. The electricity utility that sells energy to the water utility in question has a General Service tariff that charges non-residential customers a seasonally-adjusted charge for power (a demand charge, measured in kilowatts, i.e. kw) and a seasonally-adjusted charge for energy (measured in kilowatt-hours, i.e. kwh) on top of a base customer service charge. As an alternative to this tariff, the energy utility also offers two energy time-of-day options. Under TOU Rate A, the utility bills the non-residential customer considerably less for energy consumed (kwh) off-peak ($0.114/on-peak kwh versus $0.034/off-peak kwh in the summer). The non-residential customer also has a demand charge that is less than that under the General Service tariff. Non-residential customers must purposely opt into TOU Tariff A (or B). The Public Works Director for the water utility assessed option A and realized that, with operational adjustments and no disruption to his service levels, he could take advantage of this energy time-of-day option and reap great savings (over $7,000/month) for his utility. The graph displays the difference in monthly electricity costs between the three available rate tariffs for the water utility. The water utility s excellent energy management measures include: Filling reservoirs at night. Carefully monitoring when electricity meters are read. Running one pump instead of two at booster stations that have two pumps. This insures that the peak kw will be half of what it might have been when two pumps run. Permanently taking unnecessary pumps off-line. After determining monthly pumping needs, turn off unnecessary pumps for a given month. The water utility estimates that, in principle, it could save an additional $2,600/month (beyond TOU Rate A) by transitioning to a demand time-of-day option (TOU Rate B) that eliminates demand charges altogether for off-peak demand and charges a relatively low on-peak demand charge. However, the electric utility has a stipulation in their TOU Tariff B, generally referred to as a ratchet charge, that would charge for any on-peak demand for twelve-months out; in other words, the highest monthly amount you paid in the last 12 months will be what you pay each month for a year forward. With public health, fire protection, and quality-of-service at the top of the utility s priority list, the financial risk associated with this tariff may or may not outweigh the benefit. Has your organization evaluated your electricity rate structure, and looked at alternative options? If not, as you can see, the potential for great savings, depending on what your electricity provider offers, may be there. But a careful analysis of the potential risks and rewards will be important to undertake.

ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT Drinking Water Branch P.O. Box 301463 Montgomery, AL 36130-1463 Phone: 334-271-7773 Fax: 334-270-5631 Thinking Outside The Box For More Information Contact Tom Garrett, AWOP Coordinator thg@adem.state.al.us (334) 271-7931 William McClimans, Assist. Coord wdm@adem.state.al.us (334) 271-7985 Representative Distribution Sampling William McClimans (ADEM Drinking Water Branch) When most operators collect samples from the distribution system they flush the sample tap before collecting the sample for analysis. This flush time varies from water system to water system and even from operator to operator within the same water system. When operators are asked how long they flush the sample tap, answers have ranged from five minutes, two cigarettes, or until I obtain the results that I expect. Using these flush times operators generally are not accurately capturing the water quality in the distribution system at the sample location. Representative sampling captures the water quality at the sample location, not several blocks away that might occur with long flush times. Most operators do not realize that there is only about three gallons of water in 100 feet of a 3/4-inch service line. Using pipe volume and a flow rate, EPA s Technical Support Center developed the following table to help operators determine an appropriate flush time for each sample location. So next time you are sampling you might want to think about Am I getting a truly representative sample. Tap Flush Time Approaches (assumes tap sampler is used @ flow rate of 2 gpm; OR that flow rate can be measured) Objective: assess water quality in the proximity of the sample location; under flushing may result in sampling from the service line; over flushing may pull water from another part of the system! Rule of Thumb approach is easiest (ok for one-time sampling): 2 minute total flush time before sampling (assumes pipe diameter is ¾ inch or less; pipe length is less than 100 feet, flow rate is 2 gpm) CFT approach should be determined if time allows: Flush for two times the CFT at 2 gpm (from matrix, below) before sampling 1. Estimate the (total) length and diameter of service line; utilize operator s knowledge of system, a system/site map, and/or design standards as needed Outside the building: Assume service line diameter is ¾ inches (unless indicated differently) Measure the distance between meter/curb stop and where the line enters the building Drawing the Graph Editor William McClimans wdm@adem.state.al.us (334) 271-7985 Inside the building: Assume same diameter (¾ inch) unless indicated differently Try to select a tap very near where the service line enters the building, because it can be EXTREMELY difficult to measure the length of indoor plumbing 3. Determine the necessary flush time (from matrix) based on the outdoor and indoor lengths/diameters; assume 2 gpm flow rate 4. Attach tap sampler and turn on tap (cold water, if applicable) and start the timer. If tap sampler is not used, verify the flow rate is 2 gpm; adjust flow rate and/or flush time if needed. 5. After twice the CFT stop flushing and collect the water sample(s). Considerations Do not sample from a home/business with a point-of-entry or point-ofuse treatment system! Try to select a tap that has a garden hose fitting to allow for use of the tap sampler (to regulate the flow to 2 gpm); outdoor garden spigot is ideal (remove hose!) Avoid sampling from industries or large buildings where the service line has a large diameter. CFT can be very long Storage Tanks Degraders of Water Quality William McClimans (ADEM Drinking Water Branch) The State s AWOP Team has been using continuous chlorine analyzers off and on for several years. During the past year, chlorine analyzers have been attached to several water storage tanks to analyze the chlorine residual entering and exiting the storage tank. Some of the results have been as expected and others continue to astound us on the water quality coming out of the storage tank. The limited data gathered so far this past year shows that if a tank is well mixed and turns over in a reasonable time then the chlorine loss in the storage tank is minimized. One tank that is well mixed and turns over within 5 days shows the chlorine decay to only be 0.5 mg/l from when the tank is filling to the end of its drain cycle. Another tank that is not well mixed but turns over in about 2 days shows the chlorine demand to be at least 1 mg/l as the tank routinely has no chlorine residual for several hours or even days. Using this information it becomes evident that managing your water storage tanks is of vital importance to maintaining water quality in your distribution system. If you are experiencing problems with the water quality in your distribution system (i.e. low or no chlorine residual) you may want to evaluate your water storage tanks to determine what effect they have on your distribution system s water quality. The easiest way to start would be to conduct a tank turnover and mixing analysis. The department has a spreadsheet to assist with the calculations and if you don t have a SCADA system, the Department has digital pressure loggers that can be used to collect the necessary data. If you would like assistance to get started analyzing your water storage tanks, please contact your ADEM inspector.

Page 6

Page 7