HYBRID CONCRETE MASONRY CONSTRUCTION DETAILS. TEK 3-3B Construction (2009) Related TEK: 14-9A

Similar documents
NCMA TEK RESIDENTIAL DETAILS FOR HIGH WIND AREAS. TEK 5-11 Details (2003)

ALLOWABLE STRESS DESIGN OF CONCRETE MASONRY LINTELS. TEK 17-1C Structural (2009) Related TEK: Uniform load. Triangular load. Concentrated loads

NCMA TEK TEK 19-5A FLASHING DETAILS FOR CONCRETE MASONRY WALLS

Contents. 1.1 Introduction 1

SEISMIC DESIGN AND ANALYSIS OF HYBRID MASONRY WITH FUSE CONNECTORS ROBERT ASSELIN THESIS

Masonry movement joints

NCMA TEK. TEK 14-5A Structural (2006) LOADBEARING CONCRETE MASONRY WALL DESIGN

Stone and Masonry Veneer

4.6 Procedures for Connections

ASD OF CONCRETE MASONRY LINTELS BASED ON THE 2012 IBC/2011 MSJC. TEK 17-1D Structural (2011) Related TEK: 14-7C, 14-13B, 17-1C, 17-2A

Structural System. Design Criteria Fire Resistance Concrete designed for 2 HR rating (worst case) Geotechnical Report Allowable Bearing Capacity

CONCRETE MASONRY VENEERS TEK 3-6C

Statement of Special Inspection Requirements

ISSUE A Code Change # 2 Class 3 and Class 4 Buildings

Masonry and Cold-Formed Steel Requirements

MOUNTAIN STATE BLUE CROSS BLUE SHIELD HEADQUARTERS

East Lyme Middle School EAST LYME MIDDLE SCHOOL

TECHNICAL REPORT 1. Structural Concepts / Structural Existing Conditions. Penn State Hershey Medical Center Children s Hospital. Hershey, Pennsylvania

NCMA TEK DESIGN AND CONSTRUCTION OF DRY-STACK MASONRY WALLS TEK Provided by: Cinder & Concrete Block Corporation

Details for Exterior Brick Masonry Veneer Supported by Metal Plate Connected Wood Trusses

Types Of Roofs - Vault

Lateral System Analysis and Confirmation Design November 15, 2004

Question 8 of 55. y 24' 45 kips. 30 kips. 39 kips. 15 kips x 14' 26 kips 14' 13 kips 14' 20' Practice Exam II 77

Table 3. Detailed Comparison of Structural Provisions of IRC 2000 and 1997 NEHRP (Continued)

On Cold-Formed Steel Construction. Light Gauge Steel Engineers Association Washington, D.C Toll Free (866)

Structural Engineering, Mechanics, and Materials. Preliminary Exam - Structural Design

CONNECTOR B L O C K S H E A R. Design for Composite Structural Action BLOCK SHEAR CONNECTOR APPLICATION. Airspace

Fairfield Inn and Suites Pittsburgh, PA

LATERAL LOAD BEHAVIOR OF UNBONDED POST-TENSIONED HYBRID COUPLED WALLS. Qiang SHEN Graduate Research Assistant. Yahya C. KURAMA Assistant Professor

VOLUNTARY - EARTHQUAKE HAZARD REDUCTION IN EXISTING HILLSIDE BUILDINGS (Division 94 Added by Ord. No. 171,258, Eff. 8/30/96.)

STRUCTURAL MASONRY SPECIAL INSPECTOR. Study Guide

Contents. Tables. Notation xii Latin upper case letters Latin lower case letters Greek upper case letters Greek lower case letters. Foreword.

SEISMIC RESPONSE OF LINEAR, FLANGED, AND CONFINED MASONRY SHEAR WALLS

An information series from the national authority on concrete masonry technology. Drainage swale. (optional) Cap unit. (optional)

A/E REVIEW CHECKLIST STRUCTURAL

REINFORCED ENGINEERING HANDBOOK CLAY AND CONCRETE MASONRY SEVENTH EDITION. John M. Hochwalt, PE, SE KPFF Consulting Engineers

Precast concrete is significantly being used in earthquake

Displacement Based Assessment and Improvement of a Typical New Zealand Building by an Average Engineer

Council on Tall Buildings. and Urban Habitat BACKGROUND SECTION STEEL REINFORCED CONCRETE SHEAR WALL STEEL PLATE COMPOSITE SHEAR WALL

SCHOOL DISTRICT PALM BEACH COUNTY BUILDING DEPARTMENT PLAN REVIEW CHECK LIST -- STRUCTURAL

A seismic engineer s note book

MASONRY. masonry wall construction. chapter 10 SUBJECT

WALL SYSTEMS ( Ref: The Building Illustrated, Ching, Francis DK )

[TECHNICAL REPORT 3] Lateral System Analysis

Principles of STRUCTURAL DESIGN. Wood, Steel, and Concrete SECOND EDITION RAM S. GUPTA. CRC Press. Taylor& Francis Group

Plan Check No. Checked by: An Appointment Is Required for Verification

CORPORATE HEADQUARTERS

Accommodating Expansion of Brickwork

FOUNDATIONS. Foundations Copyright G G Schierle, 2006 Press Esc to end, for next, for previous slide 1

BS EN :2004 EN :2004 (E)

Seismic Design of Precast Concrete Structures

CADS A3D MAX. How to model shear walls

Connection Design Assistance Manual

Technical Report 1. Seneca Allegany Casino Hotel Addition. Salamanca, NY

Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact

CBC SECTION/TABLE NUMBER NEW -CHANGE COMMENTARY. X Flexible and Rigid definitions removed and found in ASCE 7-10

A Guide for the Interpretation of Structural Design Options for Residential Concrete Structures

Structural Redesign Gravity System

The designer shall also submit additional information required by the University as described and underlined below.

Simplified Building Schematic for Typical Floor (Levels 9 through 22):

OCTAGONAL SHAPE REDUCES AIRPLANE HANGAR COSTS

Design of Column Base Plates

Volume 1. HOW TO MAKE A DREAM HOUSE EARTHQUAKE RESISTANT Contents

Sonnet Textile Industries Ltd.

Chapter 2 Notation and Terminology

Composite Steel/Concrete

ADDENDA #9- RFP Sylvania CC building Re-Roof Progressive Design Build for Sylvania Campus CC Building Re-Roof Services

SEISMIC REHAB OF RC STRUCTURES

Structural Technical Report I October 5, 2006 Structural Concepts / Structural Existing Conditions Report

CVEN 483. Structural System Overview

HYBRID DESIGN REDUCES COSTS WHEN DESIGN FIRST BEGAN. Switching from a concrete frame to steel beams and concrete columns proved advantageous

WOOD I-JOIST AWARENESS GUIDE

2012 IBC/2011 MSJC MASONRY CODE COMPILATION

(800) (562) A Subsidiary of the International Code Council

SEISMIC BEHAVIOR AND DESIGN OF STEEL SHEAR CONNECTIONS WITH FLOOR SLABS

Structural Training - Part 1:

Jackson Crossing Located in Alexandria, VA. Technical Report 1 Michael Bologna

There are countless ways to improve constructability on your next project. Here are 50 of them. the need for it or specify it on the design drawings.

Project. San Jose City College Physical Education Building. Prepared For. Prepared By PLACE IMAGE HERE. Ken Bauer, AIA Principal

PRECAST CONCRETE CONNECTIONS - US PRACTICE

DESIGN OF GRAVITY-LOAD RESISTING FRAMES FOR SEISMIC DISPLACEMENT DEMANDS

SPECIAL INSPECTION AND OBSERVATION PROGRAM City of Walnut Creek Building Division. Project Address:

fourteen Structural Planning 1 APPLIED ACHITECTURAL STRUCTURES: DR. ANNE NICHOLS SPRING 2019 lecture STRUCTURAL ANALYSIS AND SYSTEMS ARCH 631

REINFORCED CONCRETE WALL BOUNDARY ELEMENT LONGITUDINAL REINFORCING TERMINATION

Chapter 2 QUALITY ASSURANCE

DESIGN STANDARDS WASHINGTON UNIVERSITY SCHOOL OF MEDICINE

Statement of Special Inspections Michigan Building Code 2012 (MBC 2012)

Executive Summary...2 Introduction...3 Structural System Overview Buffalo,...4 Foundation...4 Floor System...4 Gravity System...4 Lateral System...

ALTERNATE DESIGN METHODOLOGY FOR UNREINFORCED MASONRY BUILDINGS

Student Services & Classroom Addition SECTION VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

SECTION PLATE CONNECTED WOOD TRUSSES

SECTION VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

CORPORATE HEADQUARTERS

CONNECTOR S T U D S H E A R. Design for Composite Structural Action STUD SHEAR CONNECTOR APPLICATION

David A. Walenga Technical Assignment #1

Eurocode 8 Timber and Masonry structures

Mandatory Wood Frame Soft-story Retrofit Program STRUCTURAL DESIGN GUIDELINES

Lateral System Analysis and Confirmation Design

Supplemental Plan Check List for Unreinforced Masonry (URM) Retrofit

Supplemental Plan Check List for Concrete Special Moment Resisting Frame

Transcription:

An information series from the national authority on concrete masonry technology HYBRID CONCRETE MASONRY CONSTRUCTION DETAILS TEK 3-3B Construction (2009) INTRODUCTION Hybrid masonry is a structural system that utilizes reinforced masonry walls with a framed structure. While the frame can be constructed of reinforced concrete or structural steel, the discussion here includes steel frames with reinforced concrete masonry walls. The reinforced masonry infill participates structurally with the frame and provides strength and stiffness to the system. It can be used in single wythe or cavity wall construction provided the connections and joints are protected against water penetration and corrosion. The hybrid walls are constructed within the plane of the framing. Depending on the type of hybrid wall used, the framing supports some or all of the masonry wall weight. Hybrid masonry/frame structures were first proposed in 2006 (ref. 1). There are several reasons for its development but one primary reason is to simplify the construction of framed buildings with masonry infill. While many designers prefer masonry infill walls as the backup for veneers in framed buildings, there is often a conflict created when structural engineers design steel bracing for the frame which interferes with the masonry infill. This leads to detailing and construction interferences trying to fit masonry around braces. One solution is to eliminate the steel bracing and use reinforced masonry infill as the shear wall bracing to create a hybrid structural system. The concept of using masonry infill to resist lateral forces is not new; having been used successfully throughout the world in different forms. While common worldwide, U.S. based codes and standards have lagged behind in the establishment of standardized means of designing masonry infill. The hybrid masonry system outlined in this TEK is a unique method of utilizing masonry infill to resist lateral forces. The novelty of the hybrid masonry design approach relative to other more established infill design procedures is in the connection detailing between the masonry and steel frame, which offers multiple alternative means of transferring loads into the masonry or isolating the masonry infill from the frame. Prior to implementing the design procedures outlined in this TEK, users are strongly urged to become familiar with the hybrid masonry concept, its modeling assumptions, and its limitations particularly in the way in which inelastic loads are distributed during earthquakes throughout the masonry and frame system. This system, or design methods, should not be used in Seismic Design Category D and above until further studies and tests have been performed; and additional design guidance is outlined in adopted codes and standards. CLASSIFICATION OF WALLS There are three hybrid wall types, Type I, Type II and Type III. The masonry walls are constructed within the plane of the framing. The classification is dependent upon the degree of confinement of the masonry within the frame. Type I walls have soft joints (gaps that allow lateral drift at the columns or vertical deflection at the top) at the columns and the top of the wall. The framing supports the full weight of the masonry walls and other gravity loads. Type II walls have soft joints at the columns and are built tight at the top of the wall. Type III walls are built tight at the columns and the top of the wall. For Type II and III walls, the masonry walls share the support of the vertical loads, including the wall weight, with the framing. CONSTRUCTION Type I Hybrid Walls Practically speaking, the concept of Type I walls is that the masonry wall is a nonloadbearing shear wall built within Related TEK: 14-9A Keywords: frame structures, infill, hybrid, shear walls, tie-down, reinforced masonry NCMA TEK 3-3B 1

the frame which also supports out-of-plane loads (see Figure 1). The details closely match those for current cavity wall construction where the infill masonry is within the plane of the frame, except that the vertical reinforcement must be welded to the perimeter framing at supported floors. Since the walls are generally designed to span vertically, the walls may not have to be anchored to the columns. The engineer s design should reflect whether anchors are required but only for out-of-plane loads. The masonry does have to be isolated from the columns so the columns do not transmit loads to the walls when the frame drifts. In multi-story buildings, each wall is built independently. Walls can be constructed on multiple floors simultaneously. Because the steel framing is supporting the entire wall weight, Type 1 walls are more economical for lower rise buildings. It is possible with Type 1 walls to position the walls outside the framing so they are foundation supported as in caged construction (ref. 1), providing a more economical design for the framing. Type II Hybrid Walls With Type ll walls, the masonry wall is essentially a loadbearing shear wall built within the frame: it supports both gravity and out-of-plane loads (see Fig. 1). There are two options: Type IIa and Type IIb. The engineer must indicate which will be used. For Type IIa walls, the vertical reinforcement (dowels) must be welded to the perimeter framing to transfer tension tie-down forces into the frame. The vertical dowels also transfer shear. For Type IIb walls, vertical reinforcement only needs to be doweled to the concrete slab to transfer shear forces because tie-down is not required. This simplifies the construction of multi-story buildings. The top of the masonry wall must bear tight to the framing. Options include grouting the top course, using solid units, or casting the top of the wall. The top connectors must extend down from the framing to overlap with the vertical wall reinforcement. Since the walls generally span vertically, the engineer must decide whether column anchors are needed similar to Type I walls. These anchors only need to transmit out-of-plane loads. The design must take into account the construction phasing. In multi-story buildings, each wall may be structurally dependent on a wall from the floor below which is very similar to a loadbearing masonry building. Type III Hybrid Walls This wall type is fully confined within the framing at beams and columns. Currently, there are no standards in the United States that govern Type III design. Standards are under development and research is underway to help determine structural and construction requirements. Therefore, no details are provided at this time. DETAILS Sample construction details were developed in conjunction with the National Concrete Masonry Association, International Masonry Institute (IMI), and David Biggs. They are hosted on the NCMA web site at www.ncma.org and the IMI web site at www.imiweb.org. Alternate details for hybrid construction are continually under development and will be posted on the web sites. There are several key details that must be considered, including: the wall base, the top of the wall, at columns, and parapets. Base of Wall As previously noted for Type I and Type IIa walls, vertical reinforcement must be anchored to either foundation or frame to provide tension-tie downs for the structure. Figure 2 shows the reinforcement anchored to the foundation with a tension lap splice, and also shows the reinforcement anchored at a floor level and tension lap spliced. BEAM OR GIRDER COLUMN GAP 1 GAP 3 TYPE I SHEAR WALL GAPS 1, 2: NO IN-PLANE LOAD TRANSFER GAP 3: TRANSFERS IN-PLANE SHEAR LOAD; NO AXIAL LOAD BEAM OR GIRDER COLUMN GAP 1 SHEAR (IN-PLANE) Type I Hybrid Wall NO GAP SHEAR (IN-PLANE) TYPE II SHEAR WALL Type II Hybrid Wall Figure 1 Hybrid Wall Types I and II GAP 2 COLUMN AXIAL LOAD GAP 2 COLUMN GAPS 1, 2: NO IN-PLANE LOAD TRANSFER (SOFT JOINTS) BEAM/GIRDER TRANSFERS IN-PLANE SHEAR LOAD 2 NCMA TEK 3-3B

For Type IIb walls, the vertical reinforcement does not have to be anchored for tension forces because it only transfers shear forces. Figure 3 shows the reinforcement anchored to the foundation. Figure 4 shows the reinforcement anchored at a floor level. The designer must determine if the dowel can be effectively anchored to the slab for shear or if it must be welded to the framing as shown for Type I and Type IIa walls. Top of Wall For all wall types, the top of the wall must be anchored to transfer in-plane shear loads from the framing to the wall. It also accommodates out-of-plane forces. This is accomplished by a connector. Figures 5 and 5A show an example with bent plates and slotted holes. For Type I walls, the gap at the top of the wall must allow for the framing to deflect without bearing on the wall or loading the bolts. For Type II walls, the gap is filled tight so the framing bears on the wall. The vertical reinforcement must overlap with the connectors at the top of the wall. Since the top course could be a solid unit, the connector should extend down to a solid grouted bond beam. Top of wall construction raises the most concern by designers. Constructability testing by masons has been successfully performed. The design concept for the connectors is: 1. Determine the out-of-plane loads to the wall top. 2. Design the top bond beam to span horizontally between connectors. Connector spacing is a designer's choice but is generally between 2 and 4 ft (6.09 and 1.22 m) o. c. 3. Using the in-plane loading, analyze the connector and design the bolts. 4. If the design does not work, repeat using a smaller connector spacing. The steel framing is affected by out-of-plane load transfer to the beam's bottom flange. Beam analysis and flange bracing concerns for the steel are identical to those for any infill wall. Column For Type I and IIa walls, the wall must be kept separated from the columns so that when the frame drifts it does not bear on the wall. Lightweight anchors can be used to support outof-plane loads if desired. Figure 6 shows a possible anchor. Figure 3 Type IIb Foundation Detail Figure 2 Type I and IIa Foundation and Floor Detail Figure 4 Type IIb Floor Detail NCMA TEK 3-3B 3

Note: For Type I walls, provide soft joint (gap to allow for movement. For Type II walls, fill gap tight. Figure 5 Top of Wall Details 4 NCMA TEK 3-3B

Figure 5 Top of Wall Details (continued) Figure 5A Connector Plate Detail NCMA TEK 3-3B 5

Figure 6 Column Details Option 1 Figure 7 Parapet Details 6 NCMA TEK 3-3B

Option 2 Option 3 Figure 7 Parapet Details (continued) NCMA TEK 3-3B 7

Parapet Parapets can be constructed by cantilevering off the roof framing. Details vary depending on the framing used but are similar to Figure 2. Figure 7 shows three variations for: concrete slab, wide flange framing, and bar joist framing. There is a plate on the beam's top flange for the bar joist and wide flange framing options. QUALITY ASSURANCE Special inspections should be an essential aspect of the quality assurance plan. Besides verifying the vertical reinforcement is properly installed as required by Building Code Requirements for Masonry Structures (ref. 2), the connector must be checked as well. If Type I walls are used, the bolts from the connector to the wall must allow for vertical deflection of the framing without loading the wall. CONCLUSIONS Hybrid masonry offers many benefits and complements framed construction. By using the masonry as a structural shear wall, the constructability of the masonry with the frames is improved, lateral stiffness is increased, redundancy is improved, and opportunities for improved construction cost are created. For now, Type I and Type II hybrid systems can be designed and constructed in the United States using existing codes and standards. Criteria for Type III hybrid systems are under development. Design issues for hybrid walls are discussed in TEK 14-9A and IMI Tech Brief 02.13.01 (refs. 3, 4). REFERENCES 1. Biggs, D.T., Hybrid Masonry Structures, Proceedings of the Tenth North American Masonry Conference. The Masonry Society, June 2007. 2. Building Code Requirements for Masonry Structures, ACI 530-08/ASCE 5-08/TMS 402-08. The Masonry Society, 2008. 3. Hybrid Concrete Masonry Design, TEK 14-9A. National Concrete Masonry Association, 2009. 4. Hybrid Masonry Design, IMI Technology Brief 02.13.01. International Masonry Institute, 2009. NCMA and the companies disseminating this technical information disclaim any and all responsibility and liability for the accuracy and the application of the information contained in this publication. NATIONAL CONCRETE MASONRY ASSOCIATION 13750 Sunrise Valley Drive, Herndon, Virginia 20171 www.ncma.org To order a complete TEK Manual or TEK Index, contact NCMA Publications (703) 713-1900 8 NCMA TEK 3-3B