Cross River Rail Request for Project Change 27 March 2017

Similar documents
Brisbane Metro: Draft Design Report (DDR) Consultation Comments

Illawarra Business Chamber/Illawarra First. Submission on NSW Draft Freight and Ports Plan

Fishermans Bend Integrated Transport Plan Peer Review John Kiriakidis, GTA Consultants 28/03/2018

Greater Newcastle Transport Plan

Developing a Strategy for Smart and Integrated Ticketing

Executive Summary. Introduction

ARTC INTERMODAL CONNECTIONS & ACCESS

Trade Supply Chain. Developing Rail and Sea Access. Peter Keyte PBPL

Consultation response. February 2014

Strategic Transport Forum

Managing travel to a major health campus: Travel plan for QEII Medical Centre

Integrated transport planning. Report 4:

Intelligent Transport Systems Master Plan

Input from Engineers Ireland Into the Department of Transport s Statement of Strategy

Update Update Christchurch Transport Strategic Plan. Michael Theelen, Chief Planning Officer

SUBMISSION ON THE STRATEGIC INFRASTRUCTURE PLAN FOR SOUTH AUSTRALIA

NEW SOUTH WALES INTERMODAL FORUM. August 2017

Draft Submission to the Inquiry into National Freight and Supply Chain Priorities. August 2017

AUSTRALASIAN RAILWAY ASSOCIATION SUBMISSION

SOUTH EAST EUROPE TRANSNATIONAL CO-OPERATION PROGRAMME

Submission to the Environmental future funding package. February 2017

AUSTRALASIAN RAILWAY ASSOCIATION SUBMISSION

ACTIVE TRANSPORTATION ADVISORY COMMITTEE. Memphis MPO March 30, 2015

Michael Kilgariff Speech to the Queensland Infrastructure Summit Tuesday 8 December 2015

Regional Transport Strategy Integrated Ticketing Action Plan

ESCAP. Ports as gateways to hinterland areas. getting the cogs to work together

EXECUTIVE SUMMARY ORGANIZATION OF REPORT

Inland Rail: Infrastructure Leads Industry

Submission in response to: New South Wales Draft Climate Change Strategic Plan and. Draft Plan to Save Energy and Money

2016/17. Make Raill the Mode of Choice in the National Logistics Chain 0

AT A GLANCE. Cairns Shipping Development Project. Revised Draft Environmental Impact Statement Fact Sheet July 2017.

9.0 Meeting the Challenges

SECTOR ASSESSMENT (SUMMARY): TRANSPORT, AND INFORMATION AND COMMUNICATION TECHNOLOGY. 1. Sector Performance, Problems, and Opportunities

Twin Cities Metro Freight Study Summary of Results

Strategic Rail Investment Priorities November 2017

Speech for Michael Kilgariff To the Australian Regional Development Conference Monday 5 September 2016

Massachusetts Rail Plan. September 16, 2010

3. STATION SPACING AND SITING GUIDELINES

Freight Transport a Modern Day Cinderella

EUROPEAN SEA PORTS ORGANISATION ASBL/VZW ORGANISATION DES PORTS MARITIMES EUROPEENS ASBL/VZW

Statewide Travel Demand Model Update

SOUTH WEST GROUP STRATEGIC PLAN to 2025 FINAL. 5 May South West Group Strategic Plan Final 5 May 2015 Page 1

EU e-maritime Initiative and Maritime ITS

NSW Long Term Transport Master Plan Discussion Paper 2012 Submission by Planning Institute of Australia (NSW Division)

INTEGRATED TRANSPORT PLANNING: A QUEENSLAND EXPERIENCE

COMMUNICATIONS BASED SIGNALLING FOR THE AUSTRALIAN NON-URBAN NETWORK - THE OPERATIONS BENEFITS SUMMARY 1 INTRODUCTION 2 NOTATION

TEXAS FREIGHT MOBILITY PLAN: DRAFT KEY POLICY RECOMMENDATIONS

Swindon Joint Strategic Needs Assessment Bulletin

Drivers of Congestion Growth & Change

Rail, Tram and Bus Union. Submission to the Queensland Government s Draft State Infrastructure Plan (SIP)

REGIONAL RAIL REVIVAL

FOCUS40 MassDOT Board Presentation March 13, 2017

VALUE OF RAIL The Contribution of Rail in Australia

Vanasse Hangen Brustlin, Inc. DRAFT. Appendices. MIS Appendices

Avalon Airport Rail Link. Community and Stakeholder Issues and Ideas Report Understanding what s important. December 2011

Intelligent Transport Systems Action Plan - Key questions and answers

Stakeholder Consultation Outcomes

B-triple Road Network. NFF Submission

14.0 TRANSPORTATION PLANNING RULE COMPLIANCE

TBARTA 2015 Regional Transportation Master Plan 2040 Regional Long Range Transportation Plan AUGUST 2015

Passenger service for the Dudding Hill line: brief for feasibility study

Project Appraisal Using PRISM Simon Hubbard 28 th September 2004

How can we encourage public transport use and alleviate Sydney s congestion problem?

Qube Holdings Limited. Presented to. Challenges & Efficiencies Presentation to AmCham May 2015 Maurice James Managing Director

City of Greater Geelong. Response to Infrastructure Victoria s Second Container Port Advice evidence base discussion paper

Pre- submission Core Strategy and associated documents consultation. Submitted on behalf of Extra Motorway Services Area Group

Queensland Building Plan. Response from Engineers Australia

Baltimore & Potomac Tunnel Project.

Report of the Executive. The purpose of this report is to brief Members on progress with regard to the Coach trial within Liverpool ONE Bus Station.

Submission of Dún Laoghaire-Rathdown County Council to BusConnects Dublin Area Bus Network Redesign

2017 TRANSPORTATION POLICY STATEMENT

FREIGHT ON RAIL. Rail is part of the road congestion solution to the A14 2 nd March Philippa Edmunds

N4 Collooney to Castlebaldwin Road Scheme

Transport choices for everyone

ARTC Statement of Corporate Intent 2017/18

Murray-Darling Basin Authority Basin-wide environmental watering strategy

AUSTRALASIAN RAILWAY ASSOCIATION SUBMISSION

DEVELOPING AN INTEGRATED TRANSPORT STRATEGY FOR JORDAN: THE FOUNDATION FOR INTEGRATING JORDAN IN THE IMPLEMENTATION OF A REGIONAL RAIL SYSTEM

Technical Support for Bus Service Planning

Association Stakeholders Call for National Freight Program and Stronger Federal Role

ALC Brief Inquiry into National Freight and Supply Chain Priorities 18 May 2018

David King, Railway Procurement Agency 14 th November 2012

SWDP 4: Moving Around South Worcestershire. SWDP 4: Moving Around South Worcestershire. Managing Travel Demand

Urban transport research in the European Union

Long-term Plan Transport Proposal. 29 October 2014

Multi-Modal Integration: Case Study KMRL. 4 th November 2017 Presented By: Praveen Goyal Director (Systems)

Fishermans Bend. Integrated Transport Plan Victorian Planning Panels. Cccc Eco City World Summit July Neal Giles, Fishermans Bend Taskforce

AYRSHIRE ROADS ALLIANCE WRITTEN SUBMISSION

Integrated Ticketing Action Plan Summary. A Catalyst for Change The Regional Transport Strategy for the west of Scotland

Speech for Michael Kilgariff Queensland Transport Infrastructure Conference Tuesday 5 May 2015

Government response to the Auckland Plan. Introduction. Alignment of Auckland Plan with Government priorities

UNDERSTANDING KEY DRIVERS OF PUBLIC TRANSPORT PATRONAGE GROWTH - RECENT SOUTH EAST QUEENSLAND EXPERIENCE

WELLINGTON NORTHERN CORRIDOR. Project Summary Statement 21 December 2009

2015 CEF Transport Calls

European Mobility Network EU TEN-T Policy & CEF Pawel Stelmaszczyk European Commission DG MOVE

COMPLETING NORTH-SOUTH CORRIDOR

We congratulate the Department of Planning (DoP) on preparing the sub regional strategy in a timely manner.

Northern Virginia Region Draft Needs Summary

PIA NSW SUBMISSION SYDNEY METRO NETWORK STAGE 1 (CBD METRO) ENVIRONMENTAL ASSESSMENT

Transportation and Utilities

Transcription:

Cross River Rail Request for Project Change 27 March 2017

About Engineers Australia The Institution of Engineers Australia (Engineers Australia) is the not-for-profit professional association for engineers. Established in 1919, Engineers Australia is constituted by Royal Charter to advance the science and practice of engineering for the benefit of the community. Engineers Australia is the trusted voice of the profession. We are the global home for engineering professionals renowned as leaders in shaping a sustainable world. Introduction Engineers Australia would like to thank the Queensland Government for the opportunity to make comment on the Request for Project Change (February 2017) to the previously proposed reference design for the Cross River Rail project. Engineers Australia congratulates the Queensland Government for continuing to progress the design refinement for this vital project. Engineers Australia supports the valuable additional work represented within this Request for Project Change, particularly in relation to the construction planning aspects that greatly assist with definition of revised project scope and community impacts. It is clear from this Request for Project Change that additional design effort has been focussed on the integration of this project into its pre-existing environment. However, Engineers Australia would like to take this opportunity to raise some further considerations and observations that we trust will strengthen the overall project outcomes and may assist in the important task of gaining community ownership for the implementation of this vital project. At this stage of the development process, these further considerations and observations by Engineers Australia primarily relate to Volume 1 of the Request for Project Change documentation, since Volume 1 addresses the proposed changes, the reasons for these changes, and the effects of these changes. Planning Integration In the current absence of an effective Strategic Integrated Transport Plan for South East Queensland, Engineers Australia appreciates that it is difficult now to provide the appropriate strategic context for such a major project. This is particularly relevant for this project, since it not only has strategic transport outcomes, but also has significant land use planning outcomes and indeed impacts on the community s ability to achieve the overall desired outcomes outlined in the Draft South East Queensland Regional Plan currently in the process of being finalised for public release in mid-2017. However, Engineers Australia considers that this essential integration should be further emphasised within this Request for Project Change.

Tangible ways of achieving this additional planning emphasis within the current project change documentation are suggested as: 1. Section 1.3 (Relationships with Other Projects) and Section 5.2 (Transport Network) should also refer to the strategic network projects identified within the Draft South East Queensland Regional Plan (October 2016), over both that plan s 50-year strategic horizon and more specifically within the 25-year focus horizon for that draft plan, particularly with relation to the role of Cross River Rail as a strategic network expansion enabler. 2. The discussions and plans of each of the proposed station locations (Fig 5.4 -Boggo Road; Fig 5.6 Woolloongabba; Fig 5.7 Albert Street; Fig 5.8 Roma Street; Fig 6.13 Exhibition) should also specifically identify neighbouring bus interchanges to emphasise the existence of those nodes together with the ability for seamless mode transfers between bus and rail services. Currently they are not shown as key local characteristics of relevance to the Cross River Rail project. 3. Where key land use planning has been identified that is relevant to the functionality of Cross River Rail, it should be shown and highlighted as important to community outcomes. For example, the planned land use redevelopment near the Exhibition Station; the proposed land use development near Boggo Road and Woolloongabba stations; and the redevelopment master plans for the Roma Street precinct should all be highlighted (the inclusion of a dedicated walkway between Boggo Road and PA Hospital is noted). This integration and connectivity is an important outcome for this project. 4. It is noted that the scope proposed for this project has been reduced from the reference project scope, particularly identified by the shifted tunnel portal locations thereby reducing overall tunnel length from 10km to 5.9km. The project change report identifies an anticipated 5 year construction period (2018-2023) with a target demand rail plan for 2026 (ie +3 years post-commissioning) in Fig 5.2. There is little discussion about the implications for the 2036 target demand (ie +13 years postcommissioning) identified in Section 4.2 and Table 4.1, or the implications beyond that date that will arise from outcomes of the South East Queensland Regional Planning (both within its 25 year and 50 year horizons). It is suggested that the currently proposed project scope should be presented as a first stage of a larger scheme that is proposed to be incrementally implemented over time. Only in this way can the community and industry have confidence that the proposed current investment is sound in the longer term; appropriate future-proofing has been incorporated; strategic network expansion is being planned to meet future planning needs; and that appropriate integration (both land use and transport) requirements have been considered. 5. Whilst the content of the Request for Project Change report deals primarily with passenger rail requirements, these requirements cannot be addressed in isolation. As noted in Section 4.4 of the Project Change report passenger and freight rail services share a significant proportion of the South East Queensland rail network.

The somewhat brief discussion in Section 4.4, based on a reduction in forecast freight demand, seems at odds with other marketplace data (such as that being used to justify the national inland rail project investment) and concludes that the existing track demand conflicts between Dutton Park and Salisbury should remain for the foreseeable future. This results in continuing the existing constraints on Port of Brisbane operations in peak commuter periods; reliance on possible solutions by ARTC (potentially rendering the Dutton Park flyover as redundant infrastructure); and strategic constraints on passenger train conflicts between all station and express service patterns over this section. These conflicts will be exacerbated should the future passenger rail corridor to Greenbank, Flagstone and Beaudesert be realised as foreshadowed within the draft South East Queensland Regional Plan. It would appear that this significant strategic issue is insufficiently addressed within the Request for Project Change report. 6. The discussion in Section 5.2.2 regarding Roma Street station changes, is based on the premise that the Long-Distance Coach terminal will be relocated to a location to be determined by the proponent (Queensland Government). This facility is a key part of the regional and state-wide transport network and is historically located at Roma Street to facilitate relatively seamless inter-modal transfers with all other public transport modes servicing South East Queensland. It is suggested that the determination of where this facility will be relocated to is an important aspect of the community consultation process and should have been addressed as an integral part of the overall project planning process. Demand Forecasting The discussion on demand forecasting in Section 4.2 of the Request for Project Change report appropriately identifies that the demand forecasts are a key driver of the project justification and are influenced by a complex array of variables associated with the overall development of our broader community, not the least of which is land use trends and changes. The average daily user demands stated in Section 4.2 of the Request for Project Change report equate to a level by 2026 of 208% of the 2015 levels (equating to an average annual growth rate of 6.9%pa over that 11-year period), and a level by 2036 of 289% of the 2015 levels (equating to an average annual growth rate between 2026 and 2036 of 3.3%pa). Whilst the report focuses on the 2026 demand levels (despite this being only +3years postcommissioning as discussed above), there is little discussion regarding the requirements to address the forecast 2036 demand levels, even if it is through a staged implementation process. Table 5.9 provides forecast demand levels in the form of passenger movements at the respective station locations forecast for the year of opening (approximately 2023, based on a 5year construction period). Whilst the primary purpose of this data is to identify the impacts of the proposed project changes, ie demand forecasts use the reference project forecasts as a datum, there is little discussion regarding the impacts of changed land use near the proposed stations. As an example, passenger throughput numbers are now

forecast to decrease significantly at Roma Street station, presumably since the long distance coach terminal is now to be located elsewhere and the western tower of the existing air space development is to be demolished. However, with new air space development (potentially over the changed station location and possibly over the existing surface platforms at Roma Street Station) the passenger throughput demand at this location could vary significantly from those within the Request for Project Change report. Whilst it is appreciated that any such developments would introduce a range of additional planning parameters that cannot be accurately defined at this time, such outcomes should be discussed and planned for so that the broader outcomes from this project can be more widely understood and appreciated within our community. Conclusion Engineers Australia supports long term strategies that include land use management, infrastructure pipelines and sustainable communities. Engineers Australia believes that governments should prepare, fund and publish long term plans for cities and regions; integrated infrastructure, land use and transport network plans that support those regional plans; and that communities should be comprehensively engaged to ensure the of high level of ownership to those strategic plans. Engineers Australia welcomes the release of the Request for Project Change report for Cross River Rail, a project that we regard as vital to the development of Greater Brisbane and the South East Queensland region generally. Engineers Australia looks forward to any opportunity to discuss these comments and observations on the Request for Project Change report in more detail with you. Contact: Stacey Rawlings Division Manager Qld Ph: 07 3226 3041 E: srawlings@engineersaustralia.org.au