Supplier Pre-qualification. AEP Southern Operations Melbourne June 2012

Similar documents
WorleyParsons Procurement How Can We Balance Quality With Value? Tim Armstrong Village Urban Resort, Bury 20 October 2015

Australian Resources, Energy & Utilities Conference

Contractor Selection & Management Guideline Rev01. Revision 00. April 2011

Your industrial operations, maintenance and services solutions

QUALITY INTEGRATED ENGINEERING SERVICES to the energy sector

Oman LNG LLC Pre-Qualification Questionnaire GA Call-Off Contract for Supply of Furniture

Oman LNG L.L.C. Pre-Qualification of Tenderers NGH : PROVISION OF MANPOWER RECRUITMENT SERVICES

SHARING YOUR VISION. BUILDING SUCCESS.

CAPABILITY STATEMENT PRIZM Engineering Pty Ltd ABN

Deep Panuke. 01U 02 May 2013 Issued for Use John Nowlan Hugh Farrell R. MacQueen

QEN Construction of New Shaded Car Parking. Oman LNG L.L.C. Pre-Qualification of Tenderers QEN Construction of Artificial Grass

engineering. procurement. construction. management

AECON POWERS THE INDUSTRY

Polaris Engineering. Excellence in service. Every time

Trends and Issues in Container Transport. Larry Shughart, Global Lead for Transportation TRF Annual Meeting, March 2012 Tampa, FL

January 2014 COMPANY PRESENTATION

WELL ENGINEERING SERVICES

Techlift International Limited Capability Statement

Pre-qualification Reform Project. Briefing Document Common Assessment Standard

OIL & GAS DOWNSTREAM ASSET OPTIMISATION AND COMPLIANCE FOR PROCESS INDUSTRIES, STORAGE AND DISTRIBUTION

Procurement Standard. For further information contact

Project Management Consultancy Services. Ensuring safe and successful execution of your projects

PROCUREMENT DEFINITION

Deep Panuke. 01U 9 Oct. 08 Issued for Use C. Hewitt J Gillis R. MacQueen Rev Date Reason for Issue Prepared Checked Approved Title

This document describes how Austin implements projects using The Austin Method. Step 1 Preliminary Design and Engineering

HSES-SP Management in Contracts. HSE Prequal Questionnaire for Bidders.

Project Management Consultancy Services. Ensuring safe and successful execution of your projects

Contents. 1. Certification of Materials 2. Supply of Materials

USAID Iraq Infrastructure Reconstruction Program Basrah Contractor-Supplier Conference

Step 1 Preliminary Design and Engineering

Bidders Pre-Qualification Questionnaire For ONSHORE/OFFSHORE EPCI HOKCHI PROJECT

ASSET MANAGEMENT SERVICES

J&P OMAN COMPANY ORGANISATION P.110 PROCEDURE. Page: 1 of 16. Document Title: Issue Date: 13/04/2014. Revision Date: 06/06/2016 Revision No.

The Kvaerner management system. An introduction to how we manage our business

Asset Integrity Solutions. All-of-facility care for complete field life

Just around the corner. at 490 locations worldwide.

Deep Panuke. J. Nowlan / D. Green. D. Riffe R. MacQueen M. Weatherston Rev Date Reason for Issue Prepared Checked Approved Approved Title

NABI/KCL Oilfield Construction Services Guyana (JV)

At Procurement Australia, We get it.

Integrated Risk Management Solutions

Head Office and Workshops Auckland Office Taupo Office Brisbane Office

Developing an Internal Quality Auditing Program

ASARA ENGINEERING COMPANY PROFILE

COMPANY CIVIL CONSTRUCTION PROFILE

Oman LNG L.L.C. Pre-Qualification of Tenderers QEN Supply and Installation of Ambient Air Quality Monitoring Station

DOCUMENT CONTROL INFORMATION

Deep Panuke. 01U 12 Mar 08 Issued for Use C. Hewitt N. Coonan D. Riffe R. MacQueen Rev Date Reason for Issue Prepared Checked Checked Approved Title

Deep Panuke. J. Nowlan / D. Green. D. Riffe R. MacQueen M. Weatherston Rev Date Reason for Issue Prepared Checked Approved Approved Title

Pegasus Manufacturing SUPPLIER QUALITY REQUIREMENTS MANUAL

QEN Construction of New Kitchen and Modification to Contractor s Yard Canteen. Oman LNG L.L.C. Pre-Qualification of Tenderers QEN

Oman LNG LLC. Pre-Qualification Questionnaire. QEN EPC to Construct Car Parking Sheds with Solar Photovoltaic Panels

INTRODUCTION... 3 HOW DO I GET STARTED?... 6 WHAT IS THE STOW-TT PROCESS? Phase 2: Assignment of Assessor / Audit Planning...

THE COMPANY THE COMPANY

SENIOR PROJECT MANAGER

United Nations Development Programme (UNDP) FOR THE

EXPRESSION OF INTEREST

Deep Panuke. 01U 27 Feb 08 Issued for Use C. Hewitt N. Coonan D. Riffe R. MacQueen Rev Date Reason for Issue Prepared Checked Checked Approved Title

GAIL (India) Limited CENTRAL INTEGRITY MANAGEMENT GROUP, NOIDA NOIDA 06 th January, 2018

Kurnell Refinery Conversion Project

ECMWF Copernicus procurement process

Energy Efficiency in Sustainable Port Development and Operations

FOR THE PROVISION OF A TEAMBUILDING FACILITATOR TO CARRY OUT TEAM BUILDING PROGRAMME FOR EXECUTIVES, SENIOR MANAGEMENT AND RETAIL LEADERSHIP.

ICN Gateway Tips for improving my company profile

Oman LNG L.L.C. Pre-Qualification Questionnaire QEN KV & 6.6KV SWITCHBOARD INSPECTION, SERVICE & TESTING OF HV CIRCUIT BREAKERS

QUALITY ASSURANCE / QUALITY CONTROL POLICY

Liquefied Natural Gas to Power IPP Procurement Programme

Enwon (Australia) Pty Ltd

SUPPLY CHAIN BRIEFING EIC CONNECT OIL, GAS & POWER 2013 ST. REGIS HOTEL, SAADIYAT ISLAND, ABU DHABI

THINKING DIFFERENTLY ABOUT LATE LIFE ASSET MANAGEMENT AND DECOMMISSIONING

ENGINEERING CONSULTANCY SERVICES

The Devil is in the Details!

INTEGRATED RISK MANAGEMENT SOLUTIONS

Liquefied Natural Gas to Power IPP Procurement Programme

SQAR-1. SUPPLIER QUALITY ASSURANCE REQUIREMENTS for DESIGN AND PROCUREMENT SERVICES Revision Date: 2/1/2018

AS/NZS ISO FUTURE Of Australia s Welding Industry. How To Use It. Weld Australia. Helping Secure The

UK Nuclear New Build. Challenges and Solutions for Chinese Supply Chain Companies. Courtesy of EDF Energy

There are currently national certifying organizations that cover certification for businesses owned by: Aboriginal Peoples

Driving value for your business

POSITION DESCRIPTION

RFP Operations Services Ref. #: UNDP/BMS/OIMT/RFP/2016/001. Questions and Answers Round 1 19 September 2016

MAALIM AL-TAALUQ FOR GENERAL TRADE AND CONTRACTING COMPANY

The Principles of the Lean Business System: #6 Partnering. Lean in the 21 st Century Series Professor Peter Hines

Rail Safety Management Procedure General Engineering and Operational Systems - Asset Management of Rolling Stock

COMPANY PROFILE. Version: 1.0 ORIGINAL. Page 1 of 17

INTRODUCTION TO ISO 9001:2015. A One-Day Awareness On ISO 9001:2015 Quality Management Systems And The Impact On The Work Place

Atlantic Canada Offshore Petroleum Industry - Supply Chain Management

Engineered Excellence

Mining & Metals - EPCM

CORPORATE QUALITY MANUAL ISO 9001:2008 INTRODUCTION

Tony Hey Bechtel Oil, Gas and Chemicals, Inc. June 22, 2010

Saudi Aramco s Prequalification Process Passport to Opportunity. October 25, 2016

SUPPLIERS AND SUBCONTRACTORS

Transforming Ideas for the Energy We Use. gaiconsultants.com/energy. Energy

Facilitating relationships that build businesses.

122 Norwegian Oil and Gas Recommended Guidelines for the Management of Life Extension

BOWEN BASIN MINING CLUB

TENDERING #4 Tendering (CONS6811) Lara Tookey

Your leading supplier of integrated products and services

Reducing risk, improving performance

Transcription:

Supplier Pre-qualification ICN Presentation Jeff Ward Location Quality and Inspection Services Manager Jeff Ward, Location Quality and Inspection Services Manager AEP Southern Operations Melbourne June 2012

WorleyParsons is a leading professional services provider to the energy, resource, and complex process industries. Our services cover the full asset spectrum both in size and Our services cover the full asset spectrum both in size and lifecycle from the creation of new assets to services that sustain and enhance operating assets.

With 37 800 people in148 offices throughout 44 countries With 37,800 people in148 offices throughout 44 countries, we provide our customers with a unique combination of extensive global resources, world-recognized technical expertise and deep local knowledge.

We have seven differentiators which form the strategic We have seven differentiators which form the strategic focus that drives success in our business and that differentiate us in our markets.

WorleyParsons was ranked No. 1 in ENR s Top 200 Engineering Design Firms in 2011

WorleyParsons services four Customer Sector Groups

Infrastructure & Environment Resource Infrastructure Urban Infrastructure Ports & Marine Terminals Water & Wastewater Transport Environment

Minerals & Metals Base Metals Coal Chemicals Ferrous Metals Alumina Aluminium Iron Ore Gas Cleaning

Power Advanced Coal Coal Gas Turbine Based Plants Nuclear Renewable Energy Transmission Networks

Hydrocarbons Arctic Gas Processing Heavy Oil & Oil Sands INTECSEA LNG Onshore Production & Enhanced Oil Recovery Pipeline Systems Offshore Topsides Petrochemicals Refining Sulphur Technology Unconventional Oil &Gas

Phase Diagram

Improve Delivers value, year on year, for our long term customers. Successful Improve contracts are based on strong long- term relationships utilizing trust and teamwork. This enables everybody to focus on the critical issues that drive long term contract performance improvement.

AEP Southern Operations Australia East and Pacific is one of nine geographic regions. Southern Operations comprises six locations; Adelaide Footscray Geelong (incorporating Tasmania) Hunter Melbourne Sydney Although all engineers in some way support client procurement efforts, WP only has Procurement staff in Hunter, Sydney y and Melbourne.

Recent EPCM projects Victoria CSBP Ammonium Nitrate Orica Project Trident Ammonium Nitrate Origin Yolla Mid-Life Enhancement Origin Thylacine platform modifications Longford Gas Conditioning Project Ma aden Phosphate project EMAL Emirates Aluminium Patricia Balleen Upgrade Alcoa Portland projects Alcoa Point Henry projects Mobil Altona Refinery various projects Qenos various projects

Yolla MLE project photos

Yolla MLE modules arrive Feb 2012

Zero Harm is WorleyParsons corporate vision i for Health, Safety and the Environment

OneWay WorleyParsons actively works to align our expectations and behaviors to achieve Zero Harm in our dedication to continuous improvement. These expectations are reflected in our integrity it management framework, OneWay, and linked to our global systems and procedures.

12 OneWay elements 1. Leadership and 7. Working with Vendors Governance and Contractors 2. Risk Management 8. Field Execution 3. Caring for Our People 9. Management of Change and the Environment 10. Crisis and Emergency 4. Selection and Management Competency 11. Incident and Behavior 5. Working with Customers Analysis 6. Engineering g 12. Assessment and Improvement

Element 7 Working with Vendors and Contractors Element Intent Goods and services provided to us or our customers meet appropriate p health, safety and environmental standards. Health, safety and environmental aspects are addressed as part of the prequalification, bid evaluation and order performance processes. Note Element 6.1 (Engineering) also states; New plant, equipment and processes are designed or selected with consideration of known and projected health, safety and environmental requirements, including provision for decommissioning and disposal.

Element 7 Expectations Establish Contract Strategy Pre Qualification Tender & Award Mobilisation & Set-up 7.1 Vendors and Contractors are evaluated during selection to verify they have the necessary competence, experience and capability to undertake the required activities Execute De-Mob and Close out 7.2 Selection and evaluation criteria include an assessment of company health, safety and environment values, commitment and performance, as well as processes used for incident reporting, risk management, change management and assessment and improvement. 7.3 Our commitment to developing a culture that reflects the OneWay vision is communicated during the selection and evaluation process 7.6 Clear performance standards, including expected behaviours are developed, agreed and stewarded. Deficiencies are identified, communicated and corrected. EVALUATE DEFINE EXECUTE

Element 7 Expectations Establish Contract Strategy Pre Qualification Tender & Award Mobilisation & Set-up Execute De-Mob and Close out 7.4 Bridging documentation is in place via a gap analysis to demonstrate alignment of standards, processes and procedures between us and our contractors and, where the need is identified, our vendors. 7.5 Processes and procedures are in place to ensure all work (including short term and one-off) off) activities are effectively managed. 7.77 Contractors and vendors participate in our programs and activities specific to their scope of work. 7.8 Performance is assessed and documented following completion of work. EVALUATE DEFINE EXECUTE

ISO requirements ISO9001 section 7.4.1 The organisation shall evaluate and select suppliers based on their ability to supply product in accordance with the organisations requirements. Criteria for selection, evaluation, and re-evaluation shall be established. Records of the results of evaluations and any necessary actions arising from the evaluation shall be maintained. AS4801 section 4.4.6.2 Hazard identification; the identification process shall also include consideration of the purchasing of goods and services, and the contracting and subcontracting of plant equipment services and labour including contract specification and responsibilities to and by contractors. Records shall be maintained i to demonstrate t conformance to the requirements of the standard. ISO14001 section 4.4.6 The organisation shall identify and plan by establishing implementing and maintaining procedures related to the identified significant environmental aspects of goods and services and communicating applicable procedures and requirements to suppliers including contractors.

Registering g with WorleyParsons

Web portal

Welcome page

Sharing our Vision

Entry form

Entry form (cont)

Entry last one!

Useful information to include / attach Anything that helps us identify whether you can do the job in the time we need it, in a safe way! Assurance! People Structure of company Experience / how long have your people worked for you? CV s of key people; safety, quality, construction, etc. Premises Crane capacity What thickness plate can you cut, press, roll, etc. Size of workshop. Is the floor concrete, clean and level? Painting inside a shop or in open air? Are you adjacent to a wharf? Are you surrounded by low bridges?! Do you have segregated facilities for stainless steels?

Useful information (continued) Schedule What is your shop availability when we ll need it? Production scheduling capabilities Do you use other suppliers for key components? Are there any IR issues that could affect schedule? Subcontractors Which other companies do you regularly use? How do you assess their work before you use them? Does your ITP include their work? Will you inspect? Where are they based? What will they be used for? Remember YOU ARE YOUR SUPPLIER IN OUR EYES

Useful information (continued) Procedures and systems Do you have third party certification to ISO9001? AS4801? ISO14001? Product certification standards? Do you hold ASME stamping privileges or similar? Are you familiar with safety systems that will be used on client sites? Stepback, Take Two, JSA s s, work permits? Evidence of client or government approval and familiarity. Evidence of Management Review of your systems. Lean Manufacturing or Six Sigma approaches? Company Quality Manual / Project Quality Plan Company HSE Manual / Project HSE Plan Company policies Quality, HSE, Drug and Alcohol, etc. Example of your Manufacturer s Data Record (MDR) Example Inspection and Test Plan (ITP)

Useful information (continued) Financial Capabilities Assure us that we are not going to have equipment trapped in your shop by receivers! Provide company performance data Evidence of approval by third parties, e.g. Dunn and Bradstreet etc. Details of similar projects. Name of customer, location and your scope pick ones in our industries When did your involvement start and end? Hint - we re not that t interested t in old projects (e.g. greater than three years).

What next? EPCM organisations go through the following process; Draw up bidders list from prequalified organisations, both from our list and the client list. QA and/or HSE might need to come and audit you! WP send out Invitation to Tender / Request For Quotation which includes Engineering g Requisition, Specifications, Datasheets, Drawings, etc. Commercial short-listing between Procurement and Customer occurs Technical Bid Evaluation by Engineering, clarifications Commercial Bid Evaluation of technically accepted bidders Issue Purchase Order

Summary Prequalifying with WorleyParsons or other EPCM requires a bit of time and effort the first time. There are sound reasons why yyou should be putting these documents together and stepping back and looking at your business anyway! Being registered does not guarantee that you ll get the work, however not being registered will virtually guarantee you won t get the work! Registering interest with WorleyParsons is easy through our Web Portal.

Any yquestions? Thank-you