Feasibility study for ISL mine

Similar documents
ISL mine Project and Planning - Feasibility Study -

URANIUM MINING BY IN-SITU LEACHING

HONEYMOON FIELD LEACH TRIAL

Uranium ISL Operation and Water Management under the Arid Climate Conditions at Beverley, Australia

ISL Mining in Kazakhstan and Technology Development Vienna, IAEA, April 2013

Extracting uranium from its ores

This document also includes proposed permit requirements, including response actions, when excursions occur.

The Mineral Industry Environmental Protection Regulations

THE NEW METHOD FOR ISL WELLS PERFORMANCE IMPROVEMENT AT ZARECHNOYE DEPOSIT (KAZAKHSTAN)

Nuclear Energy Fundamentals

Feasibility studies Ulaanbaatar August 2016

SUITABILITY FOR IN-SITU RECOVERY (ISR) CONFIRMED

Water supplied by Marafiq does not meet the process requirements.

We are in the first stage of conducting the laboratory tests to see if copper could be recovered

Fossil Fuels and the environment

Texas Commission on Environmental Quality

Magino Project Environmental Impact Statement. Technical Support Document Water Management Plan

SECTION IRRIGATION WATER WELL

SECTION IRRIGATION WATER WELL

IPS Inclined plate settlers. Maximum process recovery, minimum plant footprint

Geologic Sequestration Science

Site selection: Technical site selection criteria and information needs

CMYK. Pantone. Westbay System. Greyscale. Black on White. White on Black. Multi-level Technology for Subsurface Characterization and Monitoring

ore in Hungary ( )

Overview. Students will...

Westbay System. Multilevel Technology for Subsurface Characterization and Monitoring

Botkin & Keller: Environmental Science: Earth as a Living Planet 8th Edition Guided Reading Assignment: Energy Unit- Chapters

Overview of Chapter 11

Chapter 16 Minerals: A Nonrenewable Resource

Background. AEM Tier 2 Worksheet Farmstead Water Supply Evaluation. AEM Principle: Glossary

East Maui Watershed Partnership Adapted from Utah State University and University of Wisconsin Ground Water Project Ages 7 th -Adult

Remediation of Cretaceous Sediments affected by uranium in-situ leaching (ISL) in the Czech Republic

Design Checklist for EWB-USA Chapters Working on Drilled Well

HEAP LEACHING TECHNOLOGY Moving the frontier for treatment

Mining. What is it? Why do we do it? What does it do to the Earth? How can we be more sustainable?

APPENDIX 22C: CYANIDE MANAGEMENT PLAN

Physical Geology, 15/e

Liberty Star Uranium & Metals Corp. Environmental Mission Statement

Tennessee Underground Injection Control Program Overview

Carbon Capture and Storage

CHALLENGE: Post Operational Clean Out

DRDGOLD Annual Report

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK

In Situ Well Development Techniques for Efficient Production and Groundwater Restoration. John Cash Ur-Energy USA Inc.

The Split Estate Perspective on Uranium. Shannon Anderson Powder River Basin Resource Council

DEVELOPMENT OF URANIUM MINING

EXPERIENCE WITH BACKFILLING UNDERGROUND VOIDS AND SHAFTS DURING MINE CLOSURE

Details of the Proposed Action

Watershed: an area or ridge of land that separates waters flowing to different rivers, basins, or seas. It is the interdependent web of living

D.G.S.W. Pitakumbura Manager (Groundwater Studies) Groundwater Section NWS&DB. Groundwater recharge or deep drainage or

NICO Tailings and Mine Rock Co-disposal Facility (CDF) Design Concept

Locked Cycle Leaching Test and Yellowcake Precipitation

COPPER PRECIPITATION AND CYANIDE RECOVERY PILOT TESTING FOR THE NEWMONT YANACOCHA PROJECT

HEAP LEACHING OF LOW GRADE URANIUM ORES AT SOMAIR

Water Remediation Technology LLC s Process and Licensing A Solution for Radionuclide Water Treatment

INTRODUCTION INTRODUCTION

TRANS-SIBERIAN GOLD PLC

In Situ and Dump Leaching of Phosphate Rock

STANDARD OPERATING PROCEDURES

TITLE 252. DEPARTMENT OF ENVIRONMENTAL QUALITY CHAPTER 652. UNDERGROUND INJECTION CONTROL

#Disrupt Mining: Integrated Extraction and Recovery System for Complex. Ores and Wastes"

Minerals to Market. September 26 th 2011

Water Well Decommissioning Guidelines

NEPA & Mining Tribal Lands and Environment Forum. August 17, 2015 Minneapolis, Minnesota

Proposed Rule Health and Environmental Protection Standards for Uranium and Thorium Mill Tailings 40 CFR 192

CHAPTER # 4. Fate of Pollutants in the Environment

THE NUCLEAR FUEL CYCLE

Essential elements of use of harmful substances

Engr. Adnan Qamar Lecturer Energy Resources

IN MINING & MINERAL PROCESSING

Application of UNFC-2009 to uranium and thorium projects: Guidelines. Uranium mine at McClean Lake Athabasca Basin, Canada

Earth s Energy and Mineral Resources

Uranium Recovery Regulations and Operations

DE Ferro Natural Water Treatment

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Summary of Issues Strategies Benefits & Costs Key Uncertainties Additional Resources

Module 3 Design and Construction of Water Wells. For more information refer to the Water Wells That Last video (Part I Planning and Construction).

Why Care About Contaminants in Groundwater?

Class III In Situ Uranium Injection Wells and Aquifer Exemptions in Texas: Multiple Levels of Permitting Protection for USDW Protection

Case Study Casing Path Well An Effective Method to Deal with Cascading Water

DALGARANGA GOLD PROJECT CONSTRUCTION UPDATE LESS THAN 5 MONTHS TO FIRST GOLD

POTABLE WATER SUPPLY DEFINITIONS

Enhanced in Situ Leaching (EISLEACH) Mining by Means of Supercritical Carbon Dioxide - TOUGHREACT Modeling

The Mineral Industry Environmental Protection Regulations, 1996

Detail on Concentrate Handling and Disposal Options

WATER TREATMENT PLANTS AND NORM - CZECH EXPERIENCE

Water Treatment Plant Design at the Idaho Cobalt Project

Water Treatment. Water Conditioning Parts - Aquatrol Pressure Tanks

OPTIMISATION STUDY ENHANCES LANCE ECONOMICS

Groundwater. Chapter 10 11/22/2011. I. Importance of groundwater

Management of Uranium Mine Waste Rock and Mill Tailings. Support Document to DIS-10-01

Company Introduction. Management Team & Experience. Company

Natural Resources. Answer Key. Lesson 1. Before You Read 1. Agree 2. Disagree

Figure (12.1) Foundation Grouting

Water exists everywhere on Earth, and covers 70% of its surface. 97% of this water is found in the oceans.

NGWA s Water Well Construction Standard: ANSI/NGWA 01-14

Pump & Treat Remediation

TECHNICAL INFORMATION ABOUT UNDERGROUND STORAGE RESERVOIRS FOR NATURAL GAS

Lecture 12 Fossil Fuels

Environmental characterisation and mine water monitoring

Transcription:

Feasibility study for ISL mine IAEA Technical Meeting Swakopmund, Namibia 1. 5. 10. 2007 Vladimir Benes, DIAMO, s.e., Czech Republic

Introduction (1) It is the first step of designing ISL facilities. The study or report provides an overview of the project and should address all significant issues pertaining to construction, operation and final closure of the project. The Feasibility Study gives a clear view of the scale of production, used technology, required power/heat/water resources, technical-economic parameters and economic effectiveness of the planned facility.

Introduction (2) Usually has several parts: Summary of exploration results, overview of field and laboratory investigation results, Major technological decisions and basic design of mining technology, Environmental protection and restoration planning, Cost analysis.

Overview of investigation results (1) Summarizing the results of: Geological exploration, U-reserves calculation, Hydro geological observation and measurements, Laboratory investigation of ore properties, Pilot plant testing, Mathematical modeling.

Overview of investigation results (2) Presents the main parameters characterizing: Geotechnology of mining, Geological structure of the deposit, Confinement of the deposit to certain stratigrafic horizons, Location of ore bodies within the product horizon, Characteristics of ore bodies in plan and in section

Parameters for ISL Mine 1. Geological ore reserves in categories, including geotechnological types 2. Recoverable reserves in categories, including geotechnological types 3. Leach field area 4. Average operational thickness 5. Workable reserves of ore mass including geotechnological types 6. Porosity, effective porosity of ores 7. Kinetics of leaching 8. Kinetics of reagent consumption 9. Determination of leading process (transport, chemistry) 10. Specific consumption of reagents (per 1 kg of ore, both mineralized and barren) 11. Leaching agent concentration in operational solutions (average) 12. Design time for block acidification 13. Design time for block leaching 14. Well pattern, recovery : injection wells ratio 15. Average design flow rate of operational wells 16. Total period of facility operation 17. Working period (days per year, shifts per day) 18. Below cut off U-reserves

Major decisions Annual U-production area of simultaneously working blocks number of simultaneously working wells volume of processed solution annual reagent consumption Technology of leaching process (acid, alkaline) Technology of solution processing (ion exchange, extraction, etc.), Pumping technique (submersible pumps, air-lifts), Method for under balance of injected solution volume, Technology of restoration.

Basic design wellfields (1) The wellfield complex is designated for: Pre-conditioning and leaching the U deposit Leaching solutions injection into the ore bodies The production solution recovery to the surface Solutions transport from/to processing plant This chapter of FS includes: Injection, recovery and monitoring wells Submersible pumps or airlift system for the recovery wells Associated control, piping and power systems Access and service roads

Basic design wellfields (2) Requirements on wells: The arrangement of wells and their performance should provide maximum U recovery from the ore with a minimum loss of leaching solution. The wells should be designed to operate at the maximum possible productivity under the existing conditions at the site. The arrangement of wells should enable the movement of solutions underground to be controlled. The operating life of wells should last as long as required for complete extraction of the wellfield.

Basic design wellfields (3) Requirements on wells: The number and cost of wells required for technical recovery of the ore should also be consistent with the economic parameters which are defined by the feasibility study. The standard quality attained during well installation should be sufficient to meet all expected operational requirements, including the specified equipment and instrumentation. The wells must not be allowed to become a source of environmental contamination.

Basic design wellfields (4) Well construction (injection wells, recovery wells for air-lifts): 1. Casing 110/10 mm of PE with screening (cutted slots), gravel packing, grouting, with about 10-15 m deep sedimentation chamber in the basement rock. 2. Double casing through the drinking water aquifer, the outer column from black iron, double grouting

Basic design wellfields (5) 3. Large diameter wells, casing 218/3 mm stainless steel (or PE), under reaming, gravel packing, screening from stainless steel with molded bridge slots (cutted slots).

Basic design wellfields (5) Airlift wells Hexagonal, r = 15-20 m Tetragonal, line system 28 x 28 m, places with well density increase to 20 x 20 m Line system, 20 x 50 m

Basic design wellfields (6) Submersible pump wells Hexagonal with recovery well in centre, r = 80 m, distance of injection wells = 20 m Line system, distance of lines 100-120 m, distance of recovery wells cca 80 m, double line of injection well with distance 12 m (on axis 6 m).

Basic design wellfields (7)

Basic design wellfields (8) Pipelines: Subdivided into Mains, Branch and Distribution, Geometric consideration, Diameters, Material, Respect to next development of deposit (dimensioning, placement), Access roads, maintenance, Necessity of re-pumping stations.

Basic design wellfields (10) Parameters for the ISL mine design: Well patterns, well density, ratio between recovery and injection wells, Annual total drilling (average for calculated year) including operational and monitoring wells, Total drilling for the development period (startup) including operational and monitoring wells, Quantity of operational wells simultaneously working (both recovery and injection).

Basic design wellfields (11) Parameters for the ISL mine design (cont.): Number of submersible pumps in simultaneous operation, including types Required number of submersible pumps annually replaced or The air-lifts consumption of pressurized air Necessary capacity of pressurized air production, and Specific consumption of electrical power to pump one cubic meter solution from the well.

Basic design processing of solution (1) The processing plant is designated for: U stripping from recovery solutions and production of ISL Mine final product, Preparing the leaching solution, Storage of used chemicals, Production of pressurized air. The chapter presents criteria for: Choosing and evaluating process equipment, setting its arrangement and layout, Setting the construction phases in order to minimize the preparation time for the start-up.

Basic design processing of solution (2) Specifications: 1. Type of ion exchange resin, loading capacity, particle size, volume of resin in operation. 2. Technology of sorption/desorption: fixed bed or continual counter current total volume of resin annual loses of resin 3. Chemistry of resin loading, resin regeneration and chemistry of final product precipitation, 4. Volume and type of equipment (vessels, pumps, piping), 5. Volume of storage tanks, 6. Annual/ daily consumption of chemicals.

Basic design processing of solution (3) Specifications (cont.): 7. Determination of storage volume type for injection and recovery stream: basins tanks 8. The design should foresee a potential expansion of any process circuit without halting the plant operation, 9. The design should support necessary mechanization and automation of operations and maintenance at the site, 10. Decision if satellite sorption stations will be erected, their capacity,

Basic design processing of solution (4) Parameters for the ISL mine design: The volume of solution to be treated is the major process parameter of each processing plant (10 6 m 3 per year, m 3 per hour), Annual consumption of reagents and materials, Initial load of expensive agents and materials (adsorbents, extractants, etc.), Annual consumption of expensive agents and materials, Process water consumption, Steam consumption, Electric power consumption.

Environmental protection (1) Atmosphere This section gives characteristics of geographical and climatic conditions of the construction site, as well as the present background baseline concentrations of harmful impurities in the near surface layer of the atmosphere prior to the facility construction. Pollution sources are to be determined including estimates of harmful materials which may pose health hazards.

Environmental protection (2) Water resources: The natural pre-mine conditions of water resources are presented. The total water use is to be calculated considering both surface and underground sources. Land List of measures to be provided for protecting and utilizing the Earth s surface ( removing and storing the fertile top layer of soil, followed with later utilization; prevention of acid spills, recultivation of disturbed land, and planting vegetation in the areas of production sites, etc.)

Restoration technology (1) The chapter presents criteria for: Decommissioning wells, pipelines, equipment, buildings Surface reclamation full/particular, Ground water restoration after mining or starting parallel with operation, Waste materials management/technology.

Restoration technology (2) The main parameters for the ISL mine design: Technology of contaminated water treatment, Consumption of necessary reagents, Power consumption, Waste materials management.

Cost analysis (1) Supported by detailed schedules for: Initial capital equipment and costs, Annual drilling programmes and costs, Annual energy requirements and costs, Wellfield installation material and labor, Annual manpower requirements and costs, Reagents consumption and costs, Sustaining capital requirements and costs, Decommissioning plans and costs, Surface reclamation plans and costs, Ground water restoration plans and costs, etc.

Cost analysis (2) Capital Investment Requirements: Drilling, Roads, Well fields construction, Chemical plant construction, Ion exchange resin 1 st filling, Environmental Monitoring Costs.

Cost analysis (3) Operating Costs: Chemicals + resin loses replacement, Transportation cost supply of reagents, Electrical power, Other energy, Manpower labor cost, Maintenance of equipment, Sustaining capital requirements and cost.

Cost analysis (4) Closure Costs: Decommissioning Surface reclamation Ground water restoration Costs.xls

Type 1 Type 2 Capital costs $/kg U % $/kg U % Drilling, well completion 20.13 18.88 12.24 19.55 Wellfields construction 11.74 11.01 6.51 10.40 Processing plant construction 5.44 5.11 3.31 5.29 Storage services 0.60 0.57 0.37 0.59 Solutions under balance 3.43 3.21 2.08 3.33 General repair/maintanance 3.63 3.40 2.21 3.52 Total 45.0 42.18 26.71 42.68 Operational costs (annually) $/kg U % $/kg U % Power 6.87 6.45 4.30 6.87 Reagents 16.91 15.85 8.88 14.19 Man power 17.50 16.41 10.94 17.48 Repair and mainatance 1.50 1.41 0.94 1.50 Well maintanance 1.20 1.13 0.75 1.20 Control and monitoring 1.55 1.45 0.97 1.55 Transportation 0.60 0.56 0.38 0.60 Services 1.20 1.13 0.75 1.20 Delivery overhead costs 1.92 1.80 1.03 1.64 Overhead administrative costs 4.40 4.13 1.95 3.12 Solutions underbalance 8.00 7.50 5.00 7.99 Total 61.65 57.82 35.87 57.32 Unit cost 106.63 100.00 62.58 100.0 Restoration funding 26.66 25.00 15.64 25.0 SUMMARY UNIT COST 133.29 78.22

Summary Based on a comparison of experience between conventional and ISL uranium mining (both acid and alkaline), ISL was found to have the following advantages: low capital and operational project costs, high cash flow within one year, rapid payback of investment, reduced length of project development, low power consumption and less equipment required,

Summary (cont.) reduced labour per unit produced, reduced radiation exposure and lower environmental impacts (contamination, etc.), greatly reduced solid waste (no tails), economic recovery of low grade ores, thus increasing resource utilization, possibility of recovering uranium from deposit inaccessible by other extraction methods.

Thank you for your attention