Buying Electricity from Quebec: The Case Against New Intertie Capacity

Similar documents
Rethinking Ontario s Long-Term Energy Plan

Electricity Supply. Monthly Energy Grid Output by Fuel Type (MWh)

21,363 MW 22,774 MW ONTARIO ENERGY REPORT Q JULY SEPT 2014 ELECTRICITY. Electricity Highlights Third Quarter Ontario s Power Grid

ELECTRICITY TRADE AGREEMENT. An Assessment of the Ontario-Quebec Electricity Trade Agreement

Ontario/Quebec Electricity Trade Agreement

Ontario s Changing Energy Landscape

Coal Closure In Ontario

Emission Reduction and Long Term Energy Planning

LONG-TERM SOLUTIONS FOR NEW YORK S CLEAN ENERGY FUTURE

Summary of Presentation

PLANNING FOR TODAY, TOMORROW, AND THE FUTURE. P. 1

Decarbonizing the North American Northeast Power Sector: BAU or Integration?

Energy Use in Ontario

18-Month Outlook. An Assessment of the Reliability and Operability of the Ontario Electricity System FROM APRIL 2018 TO SEPTEMBER 2019

Overview of IPSP for Web Teleconference Amir Shalaby, VP, Power System Planning

The Optimal Approach to Firming Windpower

MODULE 5: Market and System Operations & Transmission and Distribution Outlook. August 2016

This analysis was prepared by Matt Gurnham under the direction of Peter Harrison and Jeffrey Novak.

WATER AND WIND QUÉBEC S CLEAN, RENEWABLE ENERGY RESOURCES

HYDRO-QUÉBEC ELECTRICITY: CLEAN, RENEWABLE AND RELIABLE. November 2015

The Governance of Regulatory Agencies: A Case Study of the Ontario Energy Board

Décarboniser l électricité du Nord-Est américain :

Oral Presentation. Exposé oral. Submission from Strategic Policy Economics. Mémoire de Strategic Policy Economics CMD 18-H4.77

Peter Smith P.Eng and Guy Van Uytven, M. Eng., MBA, P.Eng., FCSSE

Pan-Canadian Wind Integration Study (PCWIS) A presentation by the Canadian Wind Energy Association (CanWEA) and GE Energy Consulting October 2016

New England Power Sector Overview

the power is in our hands

Overview of OPA and IPSP for PEO Mississauga Chapter Bing Young, Director, Transmission Integration

There is also some shared jurisdiction on environment issues where there is no clear demarcation.

NALCOR ENERGY. Comments on Draft Request for Proposals for Clean Energy and Transmission

NPCC 2016 Ontario Interim Review Of Resource Adequacy

Hydro One Experience with Renewable Distributed Generation & Advanced Distribution System Initiative

1.818J/2.65J/3.564J/10.391J/11.371J/22.811J/ESD166J SUSTAINABLE ENERGY

Danielle Powers. June 3, 2010

OPG REPORTS 2017 FINANCIAL RESULTS. OPG records increase in net income for third consecutive year

Putting Ontario s Long-Term Energy Plan Into Action

Renewables-Based Distributed Energy Resources in Ontario

Ontario Cap and Trade: Overview and Scope of the Challenge. Ontario Energy Association February 18, 2016

3.05. Electricity Power System Planning. Chapter 3 Section. 1.0 Background. 1.2 Key Players Involved. 1.1 What Is Electricity Power System Planning?

An Introduction to PJM: Focus on its Markets and Opportunities for Demand Resources OHA Annual Energy & Sustainability Conference

MEETING ENERGY NEEDS WITH CLEAN AND RENEWABLE POWER

NYISO s Integrating Public Policy Project

NPCC 2015 Ontario Comprehensive Review Of Resource Adequacy FOR THE PERIOD FROM 2016 TO 2020 DECEMBER 2015

Economics and Politics of Carbon Pricing

Lower Churchill Project

The Year to Date in PJM: Operations and Markets

New England Electricity Outlook

Canadian Wind Energy Association Operations and Maintenance Summit

NPCC 2018 Ontario Comprehensive Review Of Resource Adequacy FOR THE PERIOD FROM 2019 TO 2023 APPROVED BY THE RCC ON DECEMBER 4, 2018

ISO New England Regional Electricity Outlook

Overview of the IESO- Administered Markets. IESO Training

18-Month Outlook. An Assessment of the Reliability and Operability of the Ontario Electricity System FROM OCTOBER 2017 TO MARCH 2019

MODULE 1: State of the Electricity System: 10-Year Review. August 2016

ISO New England s 2011 Natural Gas Study

NPCC 2018 MARITIMES AREA INTERIM REVIEW OF RESOURCE ADEQUACY. Approved by RCC December 4, 2018

Electricity Power System Planning

OTHER REVENUES REGULATED HYDROELECTRIC

Electricity Generation Optimization in a Period of Surplus Baseload Generation

Canada s Energy Future: Energy Supply and Demand Projections to Emerging Fuels and Energy Efficiency Highlights

Distributed Energy Resources (DERs) and electricity sector evolution: an Ontario perspective on challenges and opportunities

Analysis of Potential Impacts of CO 2 Emissions Limits on Electric Power Costs in the ERCOT Region

CAISO s Plan for Integration of Renewable Resources

Meeting Natural Gas/Electricity Challenges in New England

Wind Energy in Canada

An Assessment of the Reliability of the Ontario Electricity System from January 2003 to June 2004

Wide-Area Trans-Regional Northeast Reliability Assessment

Analysis of Benefits of Clean Electricity Imports to Massachusetts Customers. Massachusetts Clean Electricity Partnership

Paul Acchione, P. Eng., B.A.Sc., M. Eng. Chair OSPE Energy Task Force Management Consultant MIDAC Corp. January 19, 2012

Analysis and Scenario Modelling of the Ontario Power System

Submission to the Standing Committee on General Government Re: Bill 150 The Green Energy and Green Economy Act

HYDRO-QUÉBEC A N AT U R A L A L LY F O R MA S S AC H U S E T T S E N E R G Y T R A N S I T I O N

National Energy Board. Reasons for Decision. Hydro-Québec EH November For Exports to Citizens Utilities Company

Catalogue no X. Electric Power Generation, Transmission and Distribution

18-MONTH OUTLOOK: An Assessment of the Reliability of the Ontario Electricity System. From October 2008 to March 2010

REFORMING CONSERVATION BUILDING A NEW FRAMEWORK DECEMBER 3, 2018

The New England Clean Power Link A powerful wind and hydro partnership for Massachusetts

Boardman to Hemingway Transmission Line Project

Ontario s Electricity System: Program and Pricing Update

QUÉBEC CONTROL AREA 2004 INTERIM REVIEW RESOURCE ADEQUACY

Eastern Interconnection Planning Collaborative

Increasing Renewable Energy Generation in Kansas

Strategies to Reduce Ontario s Electricity Grid s GHG Emissions Using CHP Systems

Pacific Northwest Power Supply Adequacy Assessment for 2019 Final Report

BC HYDRO S LONG-TERM PLAN PRESENTATION TO THE COLUMBIA BASIN REGIONAL ADVISORY COMMITTEE

18 Month Outlook. An Assessment of the Reliability and Operability of the Ontario Electricity System FROM OCTOBER 2016 TO MARCH 2018

Moving Ahead: Smart Meters and TOU Pricing in Ontario, Canada

POLICY BRIEF #25 BUILDING GLOBAL ENERGY INTERCONNECTION (GEI) TO PROMOTE 2030 AGENDA FOR SUSTAINABLE ENERGY DEVELOPMENT.

Independent Supply Decision Review

Managing the Reliability of the Electric Grid While the Power Industry Undergoes Rapid Transformation

Well-Planned Transmission to Integrate Customer Needs and Resources

Market Impact Assessment: Preliminary DAM Results Overview

CONTINUING ACHIEVEMENT CLIMATE STRATEGY SUBMISSION

NPCC 2017 Ontario Interim Review of Resource Adequacy

ERCOT in 2018: Challenges & Opportunities

PJM s Experience with the RPM Capacity Market

The Impacts of the Green Communities Act on the Massachusetts Economy:

2030 Power System Study Report to the New England Governors 2009 Economic Study: Scenario Analysis of Renewable Resource Development

Leading the Charge: Submission for Ontario s 2017 Long-Term Energy Plan

The Hydro Province. *Manitoba Hydro is the licensee of the Trademark and Official Mark.

Analysis of New Nuclear: Darlington Environmental Impact Statement

Transcription:

APRIL 2017 IN THIS ISSUE: Buying Electricity from Quebec: The Case Against New Intertie Capacity by Marc Brouillette www.thinkingpower.ca

THE AUTHOR Marc Brouillette As principal consultant at Strategic Policy Economics (Strapolec), Marc Brouillette has been advising provincial and federal government ministries, agencies and Crown corporations for more than 20 years on issues in the aerospace, energy and gaming sectors. He specializes in matters that involve technology-based, public-private initiatives in policy-driven regulated environments. Marc acted as both a nuclear and financial advisor to Natural Resources Canada on the restructuring of Atomic Energy of Canada Limited s nuclear science and technology laboratory. Recently, he has been a regular commentator on policy matters related to Ontario s energy sector. His in-depth and detailed assessments include: Ontario Emissions and the LTEP, a submission during the 2016 Long-Term Energy Plan consultation process; Extending Pickering Nuclear Generating Station Operations: An Emissions and Economic Assessment for 2021 to 2024 in November 2015; and Ontario s Proposed Cap and Trade Design Option Consultation Feedback EBR 0122-5666 in December 2015. He can be reached at marc@strapolec.ca. Declaration of Interest The views expressed in this CCRE publication are based on the comprehensive analyses undertaken for Renewables and Ontario/Quebec Transmission System Interties: An Implications Assessment, June 2016, commissioned by the Power Workers Union. Editor Jan Carr Council Members Glen Wright, Chair Jan Carr Sean Conway Murray Elston David Hay Guy Holburn Allan Kupcis David McFadden Ian Mondrow Roy Mould Jatin Nathwani Paul Newall Laura Rees Ron Stewart Karen Taylor George Todd Robert Warren The Council for Clean & Reliable Energy The Council for Clean & Reliable Energy (CCRE) is a non-profit organization that provides a platform for public dialogue and analysis on subjects related to energy policy. The CCRE was formed by a group of volunteers from universities, public and private sector business leaders, and labour. The CCRE Members collaborate to broaden the public debate on energy issues. Energy leaders from around the world have been invited by the Council to facilitated conferences focused on sharing knowledge, experiences and expertise to create a better understanding of the challenges and potential solutions to common areas affecting energy in Canada and abroad. The Council has hosted conferences on distributed generation, biomass, coal and nuclear, public sector governance in the electricity sector and future of local distribution companies. Annually, the CCRE hosts the Energy Leaders Roundtable and the Innovation Technology and Policy Forum. The Council encourages energy experts to provide reasoned opinions and points of view about significant issues relevant to the sector. These CCRE Commentaries are published, distributed to opinion leaders and made available to the public. The Council understands the value of creating a broader and more inclusive public discourse. During the last decade, its efforts have been recognized and appreciated by decision-makers in government and the energy business as providing a neutral forum for the free exchange of ideas and opinions. The Council remains committed to continuing to facilitate debate on the generation, transmission and distribution of clean, affordable and reliable energy with a clear focus on finding effective solutions for Canada and abroad. While the Council subjects all papers to independent peer review, the views expressed are those of the author and do not necessarily reflect the opinions of the reviewers, the Council or its members. www.thinkingpower.ca

CCRE COMMENTARY 1 Buying Electricity from Quebec: The Case Against New Intertie Capacity Marc Brouillette Ontario s 2013 Long-Term Energy Plan (LTEP) suggested importing electricity from Quebec as an option for supplying Ontario s electricity demand (Ontario Ministry of Energy, 2013). Now, with preparation for the 2017 LTEP underway, this commentary re-examines the idea and finds that enhancing the capacity to import Quebec electricity involves substantial costs that exceed the anticipated benefits under the two provinces demand-and-supply forecasts. Infrastructure costs for Quebec imports outweigh the benefits. While the costs are not detailed in the 2013 LTEP, the posited benefits of importing Quebec electricity included: Exchanging peak-capacity reserves to balance the seasonal needs of the two provinces; Smoothing the intermittency of Ontario s wind generation by leveraging the storage capacity of Hydro- Quebec s large reservoirs; and Sourcing low-carbon firm hydroelectric imports while lessening Ontario s dependence upon higheremitting, natural-gas-fired generation. These potential benefits can be assessed by answering several questions: What are the characteristics and capacity of the transmission system interties 1 as they relate to demand and supply in Quebec and Ontario? How is Ontario s integration of renewable generation impacting its electricity system? How do Ontario s baseload options for the future compare; i.e., how does the chosen refurbished nuclear generation option compare to wind generation plus imports? This commentary discusses the transmission system, the Quebec-Ontario interties and the challenges related to upgrading their capacity. Future papers will consider the roles the interties play in integrating Ontario s renewable generating resources in the supply mix and in supporting arrangements for a firm baseload supply. QUEBEC AND ONTARIO: DIFFERENT DEMANDS Quebec and Ontario have different energy demand and supply characteristics (Figure 1). While the two provinces have offsetting seasonal peaks, Quebec s seasonal demand variation is more amplified than Ontario s. Historically, Ontario has exported and imported significant amounts of electricity to and from Quebec. These arrangements help Ontario ensure sufficient reliable energy and capacity to meet provincial demands. 2 Ontario s total annual energy requirement, including for exports, is ~160 Terawatt-hours (TWh) with peaks in the summer. However, the average difference between Ontario s summer and winter peak demand is only ~1.5 1 An intertie is a transmission facility that connects two separately operated transmission systems. 2 There is a distinction between energy and capacity. Energy is the cumulative amount of electricity over a period of time and, at the provincial scale, is measured in Gigawatt-hours (GWh) or Terawatt-hours (TWh). Capacity is the rate at which energy can be generated, delivered or used, and is measured in Gigawatts (GW) or Terrawatts (TW).

CCRE COMMENTARY 2 Gigawatt (GW). 3 In some years, such as 2014 when the province experienced a cold winter and mild summer, peak summer demand can be less than in winter. Adequate firm supply for electricity exchange evaporates by 2028. Summer electricity demand is very similar in the two provinces. However, due to the extensive use of electrical heating in Quebec, its winter peak can be ~15 GW or 65-per-cent higher than its summer peak a seasonal variation tenfold greater than in Ontario. Quebec s vast developed hydro reservoirs provide it with a globally unique and flexible hydroelectric capability that helps Hydro-Quebec meet the 222 TWh annual provincial demand. Reservoirs such as the James Bay La Grande complex provide a provincial grid-level seasonal storage that is essential for meeting winter demand. In contrast, Ontario has only limited and short-term daily storage. Currently, Quebec has an energy surplus (Hydro-Quebec Distribution, 2014). However, this surplus is expected to evaporate by 2028 as demand increases (Figure 2 4 ) (Brouillette, 2016; Hydro-Quebec Distribution, 2014; Lanoue, 2014). Notwithstanding this current energy surplus, Quebec s winter generating capacity is insufficient to meet demand and the province must import electricity from Ontario. Similarly, Ontario has a surplus of low-carbon electricity supply that will disappear with the retirement of the Pickering Nuclear Generating Station in 2024 (IESO, 2016). 3 Based on 2013 LTEP data tables. 4 Forecast to 2028 extrapolated from Hydro-Quebec projected trends to 2023.

CCRE COMMENTARY 3 These emerging supply-and-demand dynamics suggest that when Ontario needs sustained energy from Quebec in the future, Quebec s hydroelectric resources won t be able to meet the demand. Conversely, when Quebec needs winter supply from Ontario in less than a decade, Ontario won t have low-carbon generation available. The recent agreements between Ontario and Quebec (Office of the Premier, 2016) are near term only, potentially reflecting these realities. QUEBEC S TRANSMISSION SYSTEM AND INTERTIES WITH ONTARIO Quebec s transmission network operates asynchronously and is physically distinct from those in Ontario and the United States. Quebec is one of four interconnections that supply North American electricity needs. They are: (1) the Eastern Interconnection; (2) the Western Interconnection; (3) the Electric Reliability Council of Texas Interconnection (Ercot); and (4) the Quebec Interconnection (Figure 3). The four interconnections are independent in that they are not synchronized with each other, but are linked through limited direct current (DC) interties. 5 The Eastern and Western interconnections extend into Canada. The Eastern Interconnection has six different Regional Coordinating Councils. Quebec has a distinct electricity network with limited cross-border connections. The northeastern states, Atlantic provinces along with Ontario and Quebec despite Quebec s asynchronous system operate within the context of the Northeast Power Coordinating Council (NPCC). The Quebec Interconnection is connected to New York and New England by DC interties. Quebec and Ontario are connected by nine interties grouped operationally into three regions with a combined capacity of 2,775 Megawatts (MW) (Figure 4) (IESO, 2015): 1. Quebec North connections have modest capability, generally less than 100 MW. 2. Quebec South (Ottawa) has two classes of connections: (a) Bi-directional 1,250 MW high-voltage, directcurrent (HVDC) line that came into service in 2009 and (b) Three interties in the Ottawa region with a total of 660 MW into Ontario and 220 to 240 MW from Ontario to Quebec. 5 Within each interconnection, all generators are synchronized so that the entire system appears to be a single large alternating current (AC) generator. A direct current link between two AC systems allows them to operate separately without synchronizing (i.e., asynchronously).

CCRE COMMENTARY 4 3. Quebec South (East) connections support up to 800 MW into Ontario and 470 MW to Quebec. Other than the HVDC interface, the interties are associated with specific generating stations located either in Ontario or Quebec. To enable flows across the interties, these generators are connected (segregated) by physically switching them onto one system or the other, depending on system and market conditions. The HVDC is thus the primary intertie for real-time energy flow between the provinces and was the focus of the IESO 2014 assessment of firm imports to Ontario, discussed below. Ontario exports to Quebec 42% of the time and imports 58%. TAPPING INTERTIE CAPACITY In 2015, the HVDC intertie was used 42 per cent of the time to export off-peak surplus energy from Ontario to Quebec, generally at night, and 58 per cent of the time to import energy from Quebec to Ontario during the day (Figure 5) (IESO, 2016). Imports from Quebec during daytime hours supplement Ontario s use of natural-gas-fired generation to meet peak needs.

CCRE COMMENTARY 5 The intertie peak usage in 2015 exceeded 90 per cent of capacity only four per cent of the time. The average capacity usage was ~33 per cent. This operating profile suggests that if Quebec wanted more Ontario energy at different times, the interties would allow for it, and vice versa. However, exchange profiles of higher and more constant flow in one direction or the other would reflect a baseload power exchange rather than the peakingexchange service the interties currently provide. Indeed, the IESO s 2014 intertie assessment states that the interties were not designed to be used to replace significant amounts of baseload power (IESO, 2014). INTERTIE UPGRADING COSTS Increased Quebec import capacity would be 50% more expensive than in-province alternatives. The 2013 LTEP identified a need for imported energy after the retirement of the Pickering Nuclear Generating Station. In 2014, the IESO assessed the alternative viability of expanding the capacity of the interties to meet this need (IESO, 2014). The IESO s analysis reflected existing plans to address the anticipated transmission constraints in the Ottawa area by 2020 and enable a 1,000-MW firm import flow from Quebec within the capacity of the existing interties. It found that providing an additional 2,300 MW of firm import capacity across the HVDC intertie and enabling onward delivery of the resulting 3,300 MW to the Greater Toronto Area would cost approximately $1.9 billion. The IESO analysis also suggested that related investments in Quebec could be similar. Quebec s cost for the existing HVDC intertie project validated this suggestion to yield a combined total estimated investment of approximately $3.3B (Hydro-Quebec, 2009; Brouillette, 2016) A further analysis of Quebec s cost for the existing HVDC intertie project confirmed a combined total estimated investment of approximately $3.3 billion (Hydro-Quebec, 2009; Brouillette, 2016). IS IT WORTH IT? The cost implications of intertie upgrades can be viewed from two perspectives: (1) as they relate to providing peak reserve capacity and (2) how they would accrue under a firm import arrangement. For peak reserve capacity purposes, investing in a 2,300-MW intertie upgrade represents a financed cost of ~$450 million/year. 6 The IESO found that for peak reserve supply a Simple Cycle Gas Turbine (SCGT) capacity is more cost effective than upgrading the interties (IESO, 2015). An SCGT has a capacity charge of approximately $130,000 per MW per year, which is about $300 million annually for 2,300 MW. Upgrading the interties is thus approximately 50 per cent more expensive than solving peak reserve capacity challenges with SCGT plants. For firm imports, the incremental consumer cost is a function of the energy that the interties transport: the higher the usage, the lower the per-megawatt-hour (MWh) cost and vice versa. For a fully utilized line, the IESO estimated the intertie upgrade would add between $20/MWh and $30/MWh to the cost of electricity. As an independent check, U.S. Energy Information Administration financing assumptions (U.S. Energy Information Administration, 2015) were used to estimate the per-mwh cost 7 at about $25/MWh. This figure is consistent with the IESO s estimate. The IESO s analysis concluded that upgrading the interties would not be cost effective for the purpose of addressing the firm import needs projected in the 2013 LTEP. 6 The U.S. Energy Information Administration suggested a pre-tax weighted average capital cost of 14 per cent with a 30-year life. $3.3 billion equates to $456 million annually. 7 2,300 MW could support up to 20 TWh of energy transfer. Based on the derived $456 million per year, the yield is $25/MWh at a 90-per-cent-capacity factor.

CCRE COMMENTARY 6 SUMMARY The electricity systems of Quebec and Ontario balance very different energy needs and constraints. The interties are rarely used to maximum capacity and that use is highly correlated with Ontario s demand profile higher demand during the day and lower demand at night. Costs for upgrading the intertie capability have been assessed to be around $3.3 billion for 2,300 MW of additional intertie capability. For peak reserve capacity purposes, upgrading the intertie costs 50 per cent more than the SCGT option recommended by the IESO. The current low utilization of the intertie, the planned capacity upgrades in the Ottawa area to enable 1,000 MW of firm imports and the available capacity in the two provinces over the next 15 years makes new investment in enhanced intertie capacity unwarranted under the 2013 LTEP flat demand forecast. REFERENCES Load and supply forecasts do not justify increased intertie capacity. Brouillette, M. Rethinking Ontario s Long Term Energy Plan, CCRE Commentary, December 2014. Retrieved from http://www.thinkingpower.ca/commentary.cfm. Brouillette, M. Strategic Policy Economics. Renewables and Ontario/Quebec Transmission System Interties: An Implications Assessment. June 2016. Canadian Academy of Engineering. Canada s Low Carbon Electricity Advantage: Unlocking the Potential of Inter-Regional Trade, Chapter 6 of CANADA: Becoming a Sustainable Energy Powerhouse. 2014. Hydro-Quebec Distribution. État D Avancement 2014 Du Plan D Approvisionement 2014-2023. November, 2014. Hydro-Quebec. 2008 Annual Report. 2009. Hydro-Quebec. 2015 Annual Report. 2016. Hydro-Quebec. Reliability Model for North America. 2017. Retrieved from http://www.hydroquebec.com/transenergie/reliability/modele.html. IESO. Ontario Transmission System. 2015. IESO. NUG Framework Assessment. September 1, 2015. IESO. Preliminary Outlook and Discussion: Ontario Supply/Demand Balance to 2035. March 23, 2016. IESO. Review of Ontario Interties. October 2014. Lanoue, R., and Mousseau, N. Maîtriser Notre Avenir Énergétique. February, 2014. Office of the Premier. Ontario and Québec Working Together to Drive Economic Growth. October 21, 2016. Retrieved from https://news.ontario.ca/opo/en/2016/10/ontario-and-quebec-working-together-to-driveeconomic-growth.html. Ontario Ministry of Energy. Achieving Balance: Ontario s Long Term Energy Plan. December 2013. Retrieved from http://www.energy.gov.on.ca/en/files/2014/10/ltep_2013_english_web.pdf. Pineau, P-O. Can Ontario and Quebec Benefit from more Electricity Market Integration? A Long-Term Perspective. January, 2015. Retrieved from http://sei.info.yorku.ca/files/2015/01/pineau-on-qc_electricity- 9jan2015.pdf U.S. Energy Information Administration. Annual Energy Outlook 2015. April 2015. Retrieved from http://www.eia.gov/forecasts/aeo/pdf/0383(2015).pdf.