A684 Bedale, Aiskew and Leeming Bar Bypass Environmental Statement. Non Technical Summary. Business and Environmental Services

Similar documents
Affinity Water Draft Water Resources Management Plan. Strategic Environmental Assessment Environmental Report. Prepared by Jacobs for Affinity Water

A1 JUNCTION IMPROVEMENTS DROMORE ROAD, HILLSBOROUGH

Chapter 17 Cumulative Impacts

M1 Junction 19 Improvement Changes to Non-Technical Summary October 2012

18 Cumulative Impacts and Interaction of Effects

Non-Technical Summary

Western Rail Link To Heathrow

In-combination and Cumulative Effects Assessment

Northacre Renewable Energy

2 ENVIRONMENTAL IMPACT ASSESSMENT

Environmental Statement Non-Technical Summary Rectory Farm, Hounslow

VIRIDOR WASTE MANAGEMENT LTD

Strategic Environmental Assessment Environmental Report Non Technical Summary

Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell. Volume 2 NON TECHNICAL SUMMARY. December 2012 SLR Ref:

Greater Cambridge City Deal Executive Board. A428/A1303 Better Bus Journeys Scheme Public Consultation Outcomes and Next Steps

Non-Technical Summary

1. The impact of the new Environment (Wales) Act 2016 on how we address biodiversity issues in development John Ferry CIEEM Nov 201 6

Crossrail. Environmental Statement. Volume 9c. Appendices. Westbourne Park Bus Garage Extension. Volume 2 Appendices

Norfolk Minerals and Waste Local Plan. Sustainability Appraisal Report Non-technical summary

GC001: Lambert s Transport/Europa Tyres, Station Road, Gosberton Risegate

IEMA ES Review Criteria

Factor Potential Effects Mitigation Measures

Land to the South of Old Mill Road, Sandbach Environmental Impact Assessment Environmental Statement: Non-Technical Summary

For inspection purposes only. Consent of copyright owner required for any other use. EPA Export :23:33:57

Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until Non Technical Summary

The movement of construction vehicles is predicted to: give rise to some measurable increases in the early morning and evening;

Northacre Renewable Energy

Tullynahaw Wind Energy Project County Roscommon ENVIRONMENTAL IMPACT STATEMENT

8 Geology, Hydrology & Hydrogeology

Appraisal Summary Table (AST)

M42 Junction 6 Improvement Scheme. Preliminary Environmental Information Report - Non-Technical Summary

Broughton Bypass. Monitoring and Evaluation Plan Draft. August 2015

150Intr Transport and Strategic Regeneration Welsh Assembly Government New M4 Project Magor to Castleton WelTAG Appraisal Report Stage 1 DRAFT 3 WORKI

Arcow Quarry, North Yorkshire

M25 Junctions 27 to 30 Widening

Sustainability Statement

Wellington Dock Planning Application, Liverpool. Non-Technical Summary for Environmental Statement

Sizewell B Dry Fuel Store. Environmental Statement Non-Technical Summary

SEARs project justification and conclusion

GIS data classes used within the November 2013 Environmental Statement Environmental Maps

Environmental Statement Non Technical Summary. Anthony s Way Frindsbury June creative minds safe hands

Ponds Farm, Environmental Statement Non-Technical Summary

Marlow Flood Alleviation Scheme Environmental Statement Non-Technical Summary. Final. WNGLDC Environment Agency Title

RESOLUTION NO:

4 APPROACH TO THE ENVIRONMENTAL IMPACT ASSESSMENT

5 SCOPE OF THE ENVIRONMENTAL IMPACT ASSESSMENT. The scope of the EIA falls under three broad categories:

06/01851/MIN CONSTRUCTION OF A NOISE ATTENUATION BUND AT Hermitage Farm, Newport Road, Moulsoe FOR NGW and EF Richards

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton

Draft Code of Construction Practice

5. OTHER CEQA CONSIDERATIONS

Assessment of Landfill Footprint Alternatives West Carleton Environmental Centre. Option #4 Impact on Agriculture

ENVIRONMENTAL APPRAISAL NON-TECHNICAL SUMMARY

12.0 TRANSPORT AND ACCESS...

Last amended 3 May 2011 Earthworks Operative 27/07/2000

Devon County Council A382 Improvements. Non Technical Summary

Viridor Energy from Waste Facility. Environmental Statement Non-Technical Summary

South Bristol Link Sustainability Statement. May 2013

Western Rail Link to Heathrow (WRLtH) Environmental Impact Assessment: Preliminary Environmental Information Report Non Technical Summary March 2018

NON TECHNICAL SUMMARY OF THE ENVIRONMENTAL STATEMENT

PROPOSED EXTENSIONS OF EXISTING SAND AND GRAVEL WORKINGS ON TO LAND WEST OF ALDBOROUGH ROAD NORTH (PHASE E) AND WEST OF HAINAULT ROAD (PHASE F)

Ellerton. Ellerton. Non Technical Summary

5. ENVIRONMENTAL IMPACT ASSESSMENT

West Calf. Close. Water Point. Hazelbank Farm. Moss End Cottage. Oughtershaw C/13/187. Stone

Strategic Environmental Assessment (SEA) of the Bramley Neighbourhood Plan

Coleorton Parish Council Response to HS2 Draft Environmental Statement

subdivision WORKING ENVIRONMENT AND COMMUNITY ENVIRONMENT RULES ASSESSMENT CRITERIA

SECTION 6.0 Alternatives to the Proposed Project

M6 Junctions 16 to 19 Smart Motorway. Environmental Assessment Report Non-Technical Summary. FINAL, Rev.0. October 2014

introduction 1 On behalf of db symmetry we are pleased to welcome you to view our emerging plans for a new logistics park at Rugby.

Leaside to Main Infrastructure Refurbishment Project Strengthening the transmission system in your neighbourhood

EXHIBIT LIST No Exhibit Name Page 1 P3 Control of Environment Impacts Presentation.pdf (P3) 2-34

CONCLUSIONS 14 CONTENTS

Garvagh Glebe Wind Energy Project County Leitrim

Join the Conversation!

Napier Gateway Environmental Statement Non-technical Summary

MAGNA PARK Lutterworth. DHL SUPPLY CHAIN: Design and Access Statement. June

5. Environmental issues and methodology

Mid Wales (Powys) Conjoined Wind Farms Public Inquiry. Summary Proof of Evidence Kevin Martin BEng, CEng, MICE

Network Rail Romford Rail Operating Centre and Maintenance Delivery Unit Volume I: Environmental Statement Non-Technical Summary

The Nine Elms Vauxhall Partnership. London Borough of Lambeth London Borough of Wandsworth. Construction Charter. Summary SB15-22 APPENDIX 1

DELEGATED REPORT. Reason To ensure that any impermeable areas created during the filming process does not have a permanent impact on the site runoff.

Rural Living Environment

ENVIRONMENTAL IMPACT STATEMENT METRO NORTH BELINSTOWN TO SWORDS STOP AREA MN101 VOLUME 2 BOOK 1 OF 7

Community Update. Draft. North-South 400kV Interconnection Development. Application for Planning Approval to An Bord Pleanála

Longbridge Town Centre Planning Application

Division 15 Earthworks Code (including Lot Filling)

Excavated Material and Waste Management

Chapter 8 Natural Resources

5.0 LONG-TERM CEQA CONSIDERATIONS

Ironstone Quarry Wind Energy Project Environmental Statement

Environment Agency. Title. POI / Status: For File Storage / Archive Doc Title: Exeter Phase 1 NTS

Cambridgeshire s Culvert Policy. An explanation of our policy regarding applications to culvert ordinary watercourses.

Tees Valley Renewable Energy Facility

E13: MANAGEMENT OF TRAFFIC DURING CONSTRUCTION

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08

This Chapter contains rules managing land uses in the Main Rural Zone. The boundaries of this zone are shown on the Planning Maps.

LOSTOCK SUSTAINABLE ENERGY PLANT VARIATION OF CONSENT UNDER SECTION 36C OF THE ELECTRICITY ACT 1989

A465 Heads of the Valleys Dualling Sections 5 and 6 Dowlais Top to Hirwaun

1 INTRODUCTION 1.1 TERMS OF REFERENCE FOR THIS ENVIRONMENTAL IMPACT ASSESSMENT REPORT

ACEI Design Excellence Awards Nomination Form

Transcription:

A684 Bedale, Aiskew and Leeming Bar Bypass Environmental Statement Non Technical Summary Business and Environmental Services A responsive County Council providing excellent and efficient local services

Document control sheet BPP 04 F8 Client: Project: Document Title: North Yorkshire County Council A684 Bedale, Aiskew, Leeming Bar Bypass Non-Technical Summary Job No: B1055900 Originator Checked by Reviewed by Approved by ORIGINAL NAME NAME NAME NAME A Robinson S Woodruff S Woodruff S White DATE SIGNATURE SIGNATURE SIGNATURE SIGNATURE March 2010 Document Status Draft REVISION NAME NAME NAME NAME DATE SIGNATURE SIGNATURE SIGNATURE SIGNATURE Document Status REVISION NAME NAME NAME NAME DATE SIGNATURE SIGNATURE SIGNATURE SIGNATURE Document Status Jacobs Engineering U.K. Limited This document has been prepared by a division, subsidiary or affiliate of Jacobs Engineering U.K. Limited ( Jacobs ) in its professional capacity as consultants in accordance with the terms and conditions of Jacobs contract with the commissioning party (the Client ). Regard should be had to those terms and conditions when considering and/or placing any reliance on this document. No part of this document may be copied or reproduced by any means without prior written permission from Jacobs. If you have received this document in error, please destroy all copies in your possession or control and notify Jacobs. Any advice, opinions, or recommendations within this document (a) should be read and relied upon only in the context of the document as a whole; (b) do not, in any way, purport to include any manner of legal advice or opinion; (c) are based upon the information made available to Jacobs at the date of this document and on current UK standards, codes, technology and construction practices as at the date of this document. It should be noted and it is expressly stated that no independent verification of any of the documents or information supplied to Jacobs has been made. No liability is accepted by Jacobs for any use of this document, other than for the purposes for which it was originally prepared and provided. Following final delivery of this document to the Client, Jacobs will have no further obligations or duty to advise the Client on any matters, including development affecting the information or advice provided in this document. This document has been prepared for the exclusive use of the Client and unless otherwise agreed in writing by Jacobs, no other party may use, make use of or rely on the contents of this document. Should the Client wish to release this document to a third party, Jacobs may, at its discretion, agree to such release provided that (a) Jacobs written agreement is obtained prior to such release; and (b) by release of the document to the third party, that third party does not acquire any rights, contractual or otherwise, whatsoever against Jacobs and Jacobs, accordingly, assume no duties, liabilities or obligations to that third party; and (c) Jacobs accepts no responsibility for any loss or damage incurred by the Client or for any conflict of Jacobs interests arising out of the Client's release of this document to the third party. A684 Bedale Aiskew Leeming Bar Bypass i

Contents Non-Technical Summary: Contents Document control sheet BPP 04 F8 Contents i ii 1 Introduction 1-1 2 Methods of Assessment 2-1 3 Types of Impact 3-1 Appendix 1 Figure 1 3-1 A684 Bedale Aiskew Leeming Bar Bypass ii

[Blank page] A684 Bedale Aiskew Leeming Bar Bypass iii

1 Introduction 1.1 Introduction 1.1.1 North Yorkshire County Council wishes to apply for planning permission for a new road to bypass the communities of Bedale, Aiskew and Leeming Bar. As part of the planning process, an Environmental Impact Assessment (EIA) has been carried out to understand the effects that the bypass would have on the environment. The results of the assessment are available in the Environmental Statement, and are summarised in this Non-Technical Summary (NTS). 1.1.2 The bypass is intended to relieve traffic congestion in the communities of Bedale, Aiskew and Leeming Bar. This congestion currently causes problems relating to road safety, air quality and noise. 1.1.3 The road would start in the west at a new roundabout on the A684, north of Bedale near Bedale Golf Club, and would end in the east at another new roundabout on the A684, east of Leeming Bar, between Holmfield Farm and Spring House to the south of Scruton. The road would be 4.8km long, and would be a single-carriageway, designed for a 60 mile per hour speed limit. The road would cross over Bedale Beck, Rectory Wood and the Wensleydale Railway at two locations, as well as passing beneath the new A1(M) upgrade at the new Leeming Bar junction. Trees and shrubs would be planted to help to blend the road in to the surrounding area. Figure 1 in Appendix 1 of this NTS, illustrates the landscape and environmental design proposed to integrate the Bypass into its surroundings and to mitigate significant adverse environmental impacts where feasible. A684 Bedale Aiskew Leeming Bar Bypass 1-1

2 Methods of Assessment 2.1 Method of Assessment 2.1.1 The Environmental Impact Assessment has been carried out in line with the relevant legislation and has followed best practice guidance. This includes guidance contained in the Highways Agency s Design Manual for Roads and Bridges, as well as more specialist guidance where necessary, including that published by the Landscape Institute and the Institute for Ecology and Environmental Management. 2.1.2 Impacts have been assessed by considering the sensitivity of the different parts of the environment and the magnitude (size) of impacts that would occur. These two considerations together allow the significance of an impact to be understood. 2.1.3 Environmental impacts may be adverse or beneficial. Wherever possible, if adverse impacts are identified, ways of reducing those impacts have been identified, and so the scheme design has developed during the period of the EIA. 2.1.4 Impacts may occur during construction or after the road is open to traffic, and they may be temporary or permanent. A684 Bedale Aiskew Leeming Bar Bypass 2-1

3 Types of Impact 3.1 Types of Impact 3.1.1 Impacts have been considered for a range of environmental topics. The impacts for each topic are summarised below: 3.2 Community and Private Assets 3.2.1 The scheme would not affect the use of private property or facilities used by the community. This is because the bypass would not take land from such properties, and also because the bypass would not cut people off from facilities that they use. For example, schools, doctors surgeries and libraries serve local residents in the communities of Bedale, Aiskew and Leeming Bar, and the road would not cut through these communities. However, the road would pass through farmers fields, and so farms would be affected. 3.3 Air Quality 3.3.1 The construction of the bypass could release dust which could cause a nuisance within a few hundred metres of the construction site. However, the risk of this would be kept to a minimum by taking care to keep loose material damp. 3.3.2 Once the bypass opened to traffic, there would be reduced numbers of vehicles passing through Bedale, Aiskew and Leeming Bar, as large numbers would use the bypass instead. Vehicle exhaust emissions in the communities would reduce, and so local air quality would improve in those areas. 3.3.3 Close to the bypass, air quality would be worse than it would be without the bypass, but there are fewer people living and working in those areas, and no properties would be immediately next to the new road, so fewer people would be affected. The increases in pollution levels at properties near to the bypass would be slight, and would be well within acceptable limits. 3.4 Noise 3.4.1 Noise from construction activities would be heard at properties close to the construction site. This noise would be temporary, and would be likely to be restricted to normal working hours, generally avoiding evenings and weekends. 3.4.2 The pattern of long term noise impacts would be similar to that for air quality impacts. Properties in the communities would benefit from lower noise A684 Bedale Aiskew Leeming Bar Bypass 3-1

levels, as traffic would be re-routed to the bypass. The small number of properties closer to the bypass route would experience more noise, and for some of these, the change would be significant. 3.5 Water Environment 3.5.1 Construction activity can pose a risk to water quality in rivers and streams, as sediments, fuel and chemicals could be spilt and could run off into watercourses. However, good site practice will reduce this risk to an acceptable level. 3.5.2 Once the road opened to traffic, the risk to the quality of surface waters would be low, and there would be no impacts on groundwater. Ponds would be used to slow down the flow of water running off the road, and so there would be no change to the risk of flooding. 3.5.3 Oil interceptors would provide pollution protection. 3.6 Cultural Heritage 3.6.1 The bypass would cut through three sites of archaeological importance, causing adverse impacts on each. It would not be possible to preserve the archaeology of the affected parts of these sites in their current location, but detailed records would be made. In two cases, the resulting impacts would be large adverse, and in the third, the impact would be of moderate adverse significance. Once the road opened to traffic, there would be no further impacts on archaeology. 3.6.2 The impacts on historic buildings have also been considered. During construction, five sites would experience adverse impacts as a result of changes to their views and to noise and disturbance. Once the road opened to traffic, three of these sites would experience slight adverse impacts in relation to changes to their setting. On the other hand, two of these sites would experience slight benefits from reduced traffic in the local area. 3.7 Nature Conservation 3.7.1 The construction of the bypass would cause areas of habitat to be lost, as woodland and hedgerows would be cut through, open land would be lost, and minor water courses would be put into culverts under the road. These impacts would continue after the opening of the road. Areas of habitat creation have been identified to offset these impacts, but the impacts would remain significant locally. 3.7.2 Various species would be affected by the introduction of the bypass and the related changes to habitats, at a level that would be significant locally. These A684 Bedale Aiskew Leeming Bar Bypass 3-2

species have been identified as amphibians, bats, birds, otters and aquatic invertebrates. 3.8 Landscape and Visual Amenity 3.8.1 Elements of the local landscape would change adversely during the construction of the bypass, for example because of the creation of raised embankments and bridges as well as the removal of trees. Areas of land on the edges of the scheme may benefit from integration into the landscape. 3.8.2 The views from several properties would be made worse during the construction period. These visual impacts have been assessed as large adverse using a standard description. 3.8.3 Once the road opened to traffic, adverse impacts would reduce, as trees and hedgerows planted during construction would start to mature. By the design year (15 years after opening), the impacts on the landscape character would be slightly adverse. 3.8.4 The impacts on visual amenity, once the road opened to traffic, would be slight beneficial overall, as views from properties in the communities would be improved by the reduction in traffic. However, two receptors would continue to experience large, adverse impacts in the design year. 3.9 Geology and Soils 3.9.1 Impacts on soils and geology would occur during the construction phase, but their significance would be only slight. These relate to the extraction of minerals and the possibility of encountering contaminated land. 3.9.2 The assessment also considered earthworks balance (meaning how much excavation is required, and whether any material needs to be brought to site to create areas of raised embankments), geology, landforms, and changes to soil quality. Impacts of these types were assessed as being of neutral significance. 3.10 Effects on all Travellers 3.10.1 The assessment considered the impact on people using footpaths and other public rights of way, and on drivers using roads in the local area. 3.10.2 The bypass would not cut across or join any public rights of way, and so there would be no impact on the use of any such routes. The bypass includes proposals to improve non-motorised links for pedestrians, cyclists and horse riders to the east of the A1(M). A684 Bedale Aiskew Leeming Bar Bypass 3-3

3.10.3 Overall, drivers stress would be reduced by the bypass, once it opened to traffic, as congestion would be reduced, although drivers along the A684 north of Bedale would experience increased stress when negotiating the new roundabout, compared to the situation without the scheme. 3.10.4 Vehicle travellers would experience changes in their views during the construction period, as well as once the road was open to traffic. There would be adverse impacts on the views experienced by drivers on the A684 at both ends of the scheme, although the significance would reduce as landscape planting became mature. Views from the A684 to the west of Bedale Roundabout would continue to be of large adverse significance in the design year (15 years after opening). 3.11 Cumulative Effects 3.11.1 Some locations would be affected in a number of different ways by the scheme. For example, properties in Bedale would experience a number of beneficial impacts, whilst properties close to the bypass would experience a number of adverse impacts. Similarly, risks to water quality are linked to risks to aquatic ecology. 3.11.2 Some of the impacts of the scheme should be considered together with similar impacts that are expected from the current improvements to the A1 in the area. This has been done, and the combined effects of the two schemes are summarised here: Local air quality would improve due to reduced congestion in built-up areas, although greenhouse gas emissions would increase, due to increased speeds on the A1(M); The A1(M) improvements would reduce noise levels at neighbouring properties, but would not alter the assessment of noise impacts for the bypass scheme; Surface water quality would be improved by the two schemes together, as pollution prevention measures would be included for the first time on the A1(M); There would be no cumulative impacts of the two schemes on cultural heritage, as they do not affect the same sites; There would be no cumulative impacts of the two schemes on ecology; The combined effects of the two schemes on landscape and visual amenity would be broadly similar to those of the bypass scheme alone; A684 Bedale Aiskew Leeming Bar Bypass 3-4

Drivers using both the bypass and the improved A1(M) would experience less stressful journeys on both of these roads than they would on either of the existing routes. A684 Bedale Aiskew Leeming Bar Bypass 3-5

Appendix 1 Figure 1 A684 Bedale Aiskew Leeming Bar Bypass 3-1

FIGURE 1 A1(M) 0 MAR 10 Original creation AD AR SW Rev Rev. Date Purpose of revision Drawn Checked Approved Client Leeds Office, 1 City Walk, Leeds, West Yorkshire, LS11 9DX Tel: 0113 2426771 Fax: 0113 3891389 www.jacobs.com Project Bedale - Aiskew - Leeming Bar Bypass Drawing Title Non Technical Summary Drawn By AD Checked By AR Authorised By SW Drawing Status Scale NOT TO SCALE Job no. B1055900 Client no. Drawing Number B1055900_NTS_01 DO NOT SCALE Rev 0 This drawing is not to be used in whole or part other than for the intended purpose and project as defined on this drawing. Refer to the contract for full terms and conditions.