Green CCR Landfill. Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Landfill 2016 Annual Inspection Report

Similar documents
Green CCR Landfill. Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Landfill 2017 Annual Inspection Report

Big Rivers Electric Corporation Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Landfill Annual Inspection Report

Table of Contents. Attachments Attachment A Photos Attachment B Site Map. Pages 3 of 9

Jim Bridger Power Plant

Annual Inspection Report North CCR Surface Impoundment. MidAmerican Energy Company, Walter Scott Energy Center

D. B. Wilson Station CCR Landfill

VISUAL SITE INSPECTION REPORT 2018

Active Coal Combustion Residuals Landfill Annual Inspection Escalante Generating Station

CCR Rule Annual Inspection Report 2

Inspection Report. David Burton, Facility Manager (NRG Indian River Generating Station)

2018 JRPS LANDFILL INSPECTION REPORT CITY UTILITIES OF SPRINGFIELD, MISSOURI

Pleasants Power Station Landfill Coal Combustion Residual 2017 Annual Report

NRG BRANDYWINE ASH STORAGE SITE BRANDYWINE, MARYLAND 2015 ANNUAL CCR INSPECTION REPORT

Annual Inspection Report CCR Surface Impoundment. MidAmerican Energy Company, Louisa Generating Station

Inspection Report. Re: Keystone Ash Disposal Site Annual CCR Unit Inspection Report No. 1

VISUAL SITE INSPECTION REPORT

Annual Inspection Report

2017 Annual Landfill Inspection Report

VISUAL SITE INSPECTION REPORT 2017 HOOSIER ENERGY REC MEROM GENERATING STATION AREA 3 RESTRICTED WASTE LANDFILL MEROM, INDIANA

2016 LANDFILL INSPECTION REPORT CARDINAL PLANT BRILLIANT, OHIO

2017 Annual Landfill Inspection

Hunter Power Plant Coal Combustion Residuals Annual Inspection. Hunter CCR Landfill

December 21, Mr. Jeff Pittman, PE Cooperative Energy P.O. Box Hattiesburg, MS 39402

2017 Annual Surface Impoundment Inspection

DTE Energy Monroe Power Plant

Table of Contents. Attachments Attachment A Photos Attachment B Inspection Map. Pages 3 of 10

This annual inspection report has been prepared to meet the requirements of 40 CFR (b).

CCR Annual Inspection (b) for the West Ash Pond at the F. B. Culley Generating Station. Revision 0

DTE Energy St. Clair Power Plant

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

2017 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO S3N-R2 AFIN:

2017 Annual Inspection Report

AMERICAN ELECTRIC POWER (SWEPCO)

NC2 ASH DISPOSAL AREA

VICINITY MAP AND SITE MAP. Page 1 of 9

2018 Annual Inspection Report

2017 Annual Dam and Dike Inspection Report

2016 ANNUAL STRUCTURAL STABILITY INSPECTION REPORT

2018 Annual Dam and Dike Inspection Report

CCR Annual Inspection (b) for the Ash Pond at the A.B. Brown Generating Station. Revision 0

Annual Inspection Report Jeffrey Energy Center Flue Gas Desulfurization (FGD) Landfill

Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No

CCR Annual Inspection (b) for the Ash Pond at the A.B. Brown Generating Station. Revision 0

AMERICAN ELECTRIC POWER (SWEPCO)

Coal Combustion Residual Landfill Annual Inspection Report Corrective Actions Resolution. Boardman Generating Facility

ALLIANT ENERGY WISCONSIN POWER AND LIGHT COLUMBIA ENERGY CENTER CCR SURFACE IMPOUNDMENT ANNUAL INSPECTION REPORT. January 15, 2016

HOLLOW ROCK FACILITY 2016 ANNUAL LANDFILL INSPECTION REPORT FOR COAL COMBUSTION RESIDUALS (CCR) EXISTING LANDFILL

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY INDEPENDENCE PLANT CLASS 3N LANDFILL PERMIT NO S3N-R2 AFIN:

OPERATIONS AND MAINTENANCE MANUAL. Project: STORMWATER CONTROL STRUCTURE Wet Detention Pond. Cary, NC. Owners: Prepared By: Date:

POST CLOSURE PLAN. CFR (d) GERS Landfill. Mitchell Power Plant Marshall County, West Virginia. October, 2016

1.1 Background Facility Description REVIEW OF AVAILABLE INFORMATION Information Reviewed... 2

2015 LANDFILL INSPECTION REPORT CARDINAL PLANT BRILLIANT, OHIO

Construction Site Inspections

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY WHITE BLUFF PLANT CLASS 3N LANDFILL PERMIT NO S3N-R3 AFIN:

2016 DAM AND DIKE INSPECTION REPORT CCR PONDS COMPLEX

2017 Annual Inspection Report

2016 ANNUAL DAM AND DIKE INSPECTION REPORT. Bottom Ash Ponds. Rockport Plant Spencer County, Indiana. December 6 th, 2016

McElroy s Run Impoundment Coal Combustion Residual Annual Report

CCP Annual Inspection Report

POST CLOSURE PLAN. CFR (d) Pond 1. Clinch Power Plant Russell County, West Virginia. November Prepared for: Appalachian Power Company

2017 ANNUAL DAM AND DIKE INSPECTION REPORT

POST CLOSURE PLAN. CFR (d) GERS Fly Ash Pond. Big Sandy Plant Louisa, Kentucky. October, 2016

CCP Annual Inspection Report

ALLIANT ENERGY INTERSTATE POWER AND LIGHT OTTUMWA GENERATING STATION CCR SURFACE IMPOUNDMENT ANNUAL INSPECTION REPORT.

CLOSURE AND POST-CLOSURE CARE PLAN JAMES RIVER POWER STATION UTILITY WASTE LANDFILL CITY UTILITIES OF SPRINGFIELD, MISSOURI

2017 ANNUAL DAM AND DIKE INSPECTION REPORT

2016 Annual Dam and Dike Inspection Report

CCR Certification: Initial Written Post-Closure Plan (d) for the East Ash Pond at the F.B. Culley Generating Station.

2016 ANNUAL INSPECTION REPORT W.H. Sammis Coal Plant South Pond Stratton, Ohio

Coal Combustion Facility Assessment Report. October 20, 2010

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT MCMANUS ASH POND A (AP-1) 40 CFR (c)(1)(i)-(xii)

Written Closure Plan. Comanche Station - Active CCR Landfill Public Service Company of Colorado Denver Colorado. October 17, 2016

Green Station CCR Surface Impoundment

CCR Annual Inspection (b) for the Ash Pond at the A.B. Brown Generating Station. Revision 0

Dam Safety Inspection Checklist

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i)-(xii) PLANT WANSLEY ASH POND (AP-1) GEORGIA POWER COMPANY. Carrollton, Georgia 30116

POST CLOSURE PLAN. CFR (d) GERS Landfill. Pirkey Plant Hallsville, Texas. October, 2016

Practical Considerations for CCR Facility Design, Operations, and Maintenance

Green Station CCR Surface Impoundment Sebree Generating Station Address: 9000 Highway 2096 Robards, Kentucky 42452

CCR Annual Inspection (b) for the Ash Pond at the San Miguel Plant. Revision 0

December 19, GEI Project No Mr. Tim Muehlfeld, P.E. WEC Business Services, LLC 333 W. Everett Street, A231 Milwaukee, Wisconsin 53203

Sediment Control Practices

ANNUAL INSPECTION REPORT EXISTING COAL COMBUSTION RESIDUE (CCR) LANDFILL MUSCATINE POWER & WATER

Please print or type.

Green Station CCR Surface Impoundment Sebree Generating Station Address: 9000 Highway 2096 Robards, Kentucky 42452

4.4.6 Underground Detention

McElroy s Run Impoundment Structural Stability Assessment Report

Annual Landfill Inspection 2015

Closure Plan Brame Fly Ash Pond

Dry Swale Wet Swale Grass Channel Dry Well Permeable Pavement Bioretention DESIGN ELEMENTS

CCR Certification: Initial Written Post-Closure Plan (d) for the Ash Pond at the A.B. Brown Generating Station. Revision 0

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i)-(xii) PLANT MCDONOUGH ASH POND 1 (AP-1) GEORGIA POWER COMPANY

Extended Detention Basin Maintenance Plan for [[== Insert Project Name ==]]

POST CLOSURE PLAN. CFR (d) GERS East and West Bottom Ash Ponds. Pirkey Power Plant Hallsville, Texas. October, 2016


POST CLOSURE PLAN. CFR (d) Bottom Ash Pond Complex. Cardinal Plant. Brilliant, Ohio. September, 2016

ANNUAL LANDFILL INSPECTION REPORT. Sunflower Electric Power Corporation Holcomb Station Unit # Holcomb Lane / P.O. Box 430 Holcomb, KS 67851

Stormwater Management Training for MS4 Municipal Employees

INITIAL INSPECTION REPORT ASH LANDFILL AREA SPRINGERVILLE GENERATING STATION SPRINGERVILLE, ARIZONA

ALLIANT ENERGY WISCONSIN POWER AND LIGHT NELSON DEWEY GENERATING STATION CCR SURFACE IMPOUNDMENT ANNUAL INSPECTION REPORT.

Transcription:

Green CCR Landfill Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Landfill 2016 Annual Inspection Report January 10, 2017 Prepared By: Project ID: 160122B

Big Rivers Electric Corporation Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Landfill 2016 Annual Inspection Report CCR Landfill Information Name: Operator: Green CCR Landfill Sebree Generating Station Address: 9000 Highway 2096 Robards, KY 42452 Qualified Professional Engineer Name: Company: Kentucky P.E. Number: 17822 Regulatory Applicability David A. Lamb Associated Engineers, Inc. Per 40 CFR 257.84(b), annual inspections by a qualified professional engineer must ensure that the design, construction, operation, and maintenance of the CCR landfill is consistent with recognized and generally accepted good engineering standards. Annual inspections of any CCR landfill must include, at a minimum: (1) a review of available information regarding the status and condition of the CCR unit, including, but not limited to, files available in the operating record (e.g., the results of inspections by a qualified person, and results of previous annual inspections); and (2) a visual inspection of the CCR unit to identify signs of distress or malfunction of the CCR unit. Additionally, following each annual inspection, the qualified professional engineer must prepare an inspection report which documents the following: (1) any changes in geometry of the structure since the previous annual inspection, (2) the approximate volume of CCR at the time of the inspection, (3) any appearances of an actual or potential structural weakness of the CCR unit, in addition to any existing conditions that are disrupting or have the potential to disrupt the operation and safety of the CCR unit; and (4) any other change(s) which may have affected the stability or operation of the CCR unit since the previous annual inspection. 1

Inspection Description This is the second annual inspection report for the Green CCR Landfill pursuant to the Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule which became effective April 17, 2015. The inspection was conducted on November 8 and 14, 2016 by Tim Brown P.E. and Matthew Lile of Associated Engineers, Inc. of Madisonville, Kentucky. Weekly (7-day) inspections conducted by Big Rivers Electric Corporation are kept in the facility operating record. The inspection consisted of a visual assessment of the landfill and associated drainage control features; and began on the south slope of the landfill. The inspection noted that the area between the toe and adjacent road (to the south) was rutted and saturated; red staining was visible. The slope and benches showed some erosion and bare areas with thick accumulations of grass clippings. Some very bare areas with poor cover and erosion were visible above the second bench. Some areas with longitudinal tracking and rutting from mowing equipment were visible and minimal small animal burrowing was present. A storm drain inlet on the southeast corner showed minimal erosion and small animal burrowing in exterior backfill. The inspection continued to the east slope which was in similar condition as the south slope. More specifically, standing water was present in places along the toe with some seepage of discolored water visible. Thick phragmites growth was prevalent in these areas although some areas had been mowed. Some erosion (areas of repaired erosion were also present) and bare areas were visible and some longitudinal tracking and rutting from mowing equipment was present. Areas of poor drainage and depressions with ponded water were visible although some areas showed surficial ground cracks from dry conditions. Some erosion extended from the top of the slope to the toe; a pile of CCR material was present on the third bench. On the northeast corner, the ditch located adjacent to the inactive area by the haul road was excessively eroded and contained a nonfunctioning pipe that had been washed out. Cover material had been recently placed above the third bench. On the fifth bench of the northeast corner, a new catch basin was nearly completed and the collection box contained significant silt from recently placed cover material. The collection box needs to be cleaned and adjacent sediment control provided. Large surficial cracks on the top edge of the landfill were visible along most of the east side; most likely due to dry conditions. Inspection of the north side of the landfill showed significant erosion in places with some top to bottom rills and gullies. An area of significant seepage and accumulation of discolored water is located centrally along the toe of the north slope and drains east in a ditch to a sediment control structure. Erosion and minor scarping has occurred in the upper cover material in the general area of seepage and the plunge pool west and adjacent to the haul road has become over steepened from erosion. Significant erosion and rills in bare soil were visible below the third bench. Some areas of small animal burrowing, longitudinal tracking 2

from equipment and poor vegetation occur throughout the slope, although the upper slopes are in better condition than the lower slopes. Inspection of the west side began at the northwest corner where significant erosion in cover material was visible on the lower slope below the first bench. The west side is mostly disturbed for a width of approximately 50 feet along the length of the first bench where a vertical pile wall is being constructed to provide additional landfill capacity. Both the first slope and second bench are also disturbed due to ongoing wall construction. Several very wet areas were visible along the base of the wall and appeared to be seepage. Generally: some areas of erosion consisting of rills and minor washouts; bare areas; longitudinal tracking from equipment and trucks; and thick grass clippings were visible on the west side. More specifically in the area of the third bench: vegetation is poor and significant gullying was visible in the bench flow line near the south end; the area around the storm water collection box in the south west corner was eroded; and clumps of soil were visible from recent placement of soil cover. Most of the areas of recent cover on the upper slopes appear to have been seeded and mulched. In the area of the second bench near the south end, the storm water collection box inlet pipe extends towards the pile wall but appears to be disturbed by construction. The majority of CCR material placement was visible on the upper north slope and the top of the landfill, and to facilitate wall construction on the west side. Inspection Report Specifications (i) CCR Landfill Geometry The Green CCR Landfill is used for the placement of coal combustion residual material; currently fly ash, bottom ash and related material. The landfill is raised above adjacent ground to a maximum elevation of approximately 600 feet above mean sea level. The original ground surface within the landfill footprint was irregular and the predominant features were small stream valleys draining towards the Green River which is located just east of the landfill; and towards Groves Creek which is located just south of the landfill. Changes to the landfill geometry since the previous (2015) annual inspection include the ongoing construction of a vertical wall along the west side of the landfill to increase storage capacity for CCR material; and the continued placement of additional CCR and cover material on the landfill. (ii) CCR Landfill Volume The total volume of CCR material contained in the Green CCR Landfill at the time of inspection is approximately 20.7 million cubic yards. This volume was calculated from 3

available flight derived baseline topography compared to October 2016 flight derived topographic contours. (iii) CCR Landfill Structural, Operational, and Safety Items Noted Deficiencies 1. Erosion and minor scarping in upper cover material along toe and on lower slope of the landfill s north side caused by significant seepage of discolored water. (iv) CCR Landfill Changes A change to the Green CCR Landfill since the previous (2015) annual inspection that may have the potential to affect the stability or operation of the CCR unit is construction of the vertical expansion wall. The wall was designed per accepted engineering standards and if constructed as designed, should achieve required factors of safety. 4

Flight Date: October 23, 2016 BIG RIVERS ELECTRIC CORPORATION Green CCR Landfill 2016 Annual Inspection Aerial Photo Project Number: 12/122016 Scale: NOT TO SCALE Drawn By: 2740 North Main St. Madisonville, KY 42431 Phone: (270) 821-7732 Fax: (270) 821-7789 www.associatedengineers.com ENGINEERS GEOLOGISTS SURVEYORS 5 16-0122B Date: A.E.I.

BREC Final Rule CCR Landfill 2016 Annual Inspection Checklist Operator: Sebree Generating Station Weather: Overcast - 8 th, Clear - 14 th CCR Landfill: Green Temperature (Degrees F): 60 (average) 8 th & 14 th Date: November 8 & 14, 2016 Inspector/Qualified Person: Tim Brown P.E. & Matthew Lile (AEI) ITEM STATUS OBSERVATIONS 1 CONDITION OF INACTIVE AREA Access road deterioration (potholes, rutting, etc.) Any erosion Longitudinal cracks Transverse cracks Visual depressions Visual settlement Bulging or slumping Any drainage features obstructed or damaged Are drainage features flowing Is seepage present Is seepage or discharge carrying sediment Adequate vegetative cover Are trees growing on the slope Are there any animal burrows Any stone deterioration Adequate riprap/slope protection Debris or trash present Is there exposed CCR material 2 CONDITION OF ACTIVE AREA Access road deterioration (potholes, rutting, etc.) Any erosion Any cracks Any slides Visual depressions YES NO N/A 6 Surficial erosion/rills in cover material Minimal surficial cracking from dry conditions Minimal surficial cracking from dry conditions Some low areas in bench flowlines & longitudinal tracking/rutting from tractor & mower tires Minor slope failure in seepage zone along north side toe and lower slope Some catch basins obstructed by sediment Minimal sediment transport in seepage Isolated bare areas & invasive species monocultures Sporadic small animal burrows; primarily rodent Isolated areas Minimal depressions due to incomplete grading

Visual settlement Bulging or slumping Any drainage features obstructed or damaged Is seepage present Is seepage or discharge carrying sediment Debris or trash present 3 LINER AND LEACHATE COLLECTION SYSTEM Are liners intact and being installed correctly Is the leachate collection operating correctly Is the leachate collection pond/storage functioning correctly Is there any slope/bank erosion on pond Are there any animal burrows on pond Is the spillway functioning and discharging correctly 4 RUN-ON/RUNOFF-CONTROLS Are run-on/runoff controls in place Are run-on/runoff controls functioning Are run-on/runoff controls effective Are run-on runoff controls being maintained Signs of seepage or wetness Sediment transport or deposition DEFICIENCIES AND MAINTENANCE ITEMS STATUS YES NO N/A Along base of wall construction OBSERVATIONS 1. Erosion and minor scarping in upper cover material along toe and on lower slope of the landfill s north side caused by significant seepage of discolored water. 7