Condition of Improvements 30 December 2014 Cordova Harbor, Alaska (CWIS No , , )

Similar documents
1-6 CORDOVA HARBOR, ALASKA (CWIS NO ) (CWIS NO ) (CWIS NO ) Condition of Improvement 30 September 2011

Cook Inlet Navigation Channel

1-52 WRANGELL NARROWS, ALASKA (CWIS NOS & 65015) Condition of Improvement 30 September 2008

EAST WATERWAY HARBOR ISLAND SUPERFUND SITE CLEANUP CLEANING UP THE ENVIRONMENT, WHILE IMPROVING COMMERCE FOR THE PORT OF SEATTLE

Public Notice. Navigation Section Notice Date: May 23, 2018 PO Box 3755 Expiration Date: June 21, 2018

New Haven Harbor, Connecticut Navigation Improvement Feasibility Study and Environmental Impact Statement

Sediment Characterization Report

PROPOSED PLAN FOR CLEANING UP THE LOWER 8 MILES OF THE LOWER PASSAIC RIVER

Distribution Restriction Statement Approved for public release; distribution is unlimited.

Public Notice U.S. ARMY CORPS OF ENGINEERS, GALVESTON DISTRICT

30 DAY PUBLIC NOTICE MAINTENANCE DREDGING OF THE PLYMOUTH HARBOR FEDERAL NAVIGATION PROJECT PLYMOUTH, MASSACHUSETTS

30 DAY PUBLIC NOTICE MAINTENANCE DREDGING OF THE FEDERAL NAVIGATION PROJECT IN THE ROYAL RIVER, YARMOUTH, MAINE

New York- New Jersey Harbor Estuary. Lower Passaic River

GREAT KILLS HARBOR, STATEN ISLAND, NEW YORK FEDERAL NAVIGATION PROJECT MAINTENANCE DREDGING

NEW HAVEN HARBOR CONNECTICUT NAVIGATION IMPROVEMENT

30 DAY PUBLIC NOTICE MAINTENANCE DREDGING OF THE GUILFORD HARBOR FEDERAL NAVIGATION PROJECT GUILFORD, CONNECTICUT

15 DAY PUBLIC NOTICE. MAINTENANCE DREDGING OF THE FEDERAL NA VIGA TION PROJECT IN PA WTUXET COVE CRANSTON and WARWICK, RHODE ISLAND

Weldcraft Boatyard Clean-up and Redevelopment Project

PUBLIC NOTICE NO. FP13-AB03-05 August 30, 2013 CESAM-PD-EC JOINT PUBLIC NOTICE

Environmental Assessment and Finding of No Significant Impact. Bethel Harbor Improvements Bethel, Alaska

DOUGLAS HARBOR DREDGE MATERIAL DISPOSAL PRACTICABLE ALTERNATIVE ANALYSIS REPORT POA M3

30 DAY PUBLIC NOTICE MAINTENANCE OF THE NEW HAVEN HARBOR FEDERAL NAVIGATION PROJECT NEW HAVEN, CONNECTICUT

Grid Soil Sampling Outside of Source Areas

Public Notice 30 DAY PUBLIC NOTICE

FORUM ON USE OF CAD CELLS IN NEWARK BAY VS. OFF-SITE DISPOSAL

Public Notice of Application for Permit

Issuing Office: CELRB-PM-EA Published: 22 FEB 2019 Notice No: SANDUSKY-19 Expires: 25 MAR 2019

THIS IS NOT A PAID ADVERTISEMENT. Public Notice. Public Notice No. CENAP-OP-R September 20, 2018

SEPTEMBER 18, 2018 SUBMITTED TO: STATE OF NEW YORK DEPARTMENT OF STATE COASTAL ZONE MANAGEMENT PROGRAM

Collect deeper soil samples and groundwater from beneath site?

Bethel Bank Stabilization

FACTS ABOUT: Former GE Power Systems Apparatus Service Center (Voluntary Cleanup Program) Site Location

WA Department of Ecology SEA Program Post Office Box Olympia, WA Telephone: (360) ATTN: Federal Permit Coordinator

Buffalo River, New York Great Lakes Restoration Initiative (GLRI) Dredging

30 DAY PUBLIC NOTICE MAINTENANCE DREDGING OF THE YORK HARBOR FEDERAL NAVIGATION PROJECT, YORK, MAINE

Milwaukee Harbor, Wisconsin

J O I N T P U B L I C N O T I C E

Design of CAD Pits in San José Lagoon, San Juan, Puerto Rico

30 DAY PUBLIC NOTICE MAINTENANCE DREDGING OF THE FEDERAL NAVIGATION PROJECT IN THE HOUSATONIC RIVER, STRATFORD AND MILFORD, CONNECTICUT

Hudson River PCBs Superfund Site

Lake Ontario Ordnance Works

Village Creek Harbor & Estuary

Appendix H: Construction Impacts H-5 Dredged Materials Management Alternatives Analysis

Honorable Louise Slaughter

ENVIRONMENTAL RESTORATION IN COASTAL MISSISSIPPI: MARSH RE-ESTABLISHMENT PROJECT HARRISON AND JACKSON COUNTIES, MISSISSIPPI

Appendix F Water Quality Monitoring Plan

2-14 LOWELL CREEK, ALASKA (CWIS NOS , 10140, & 12838) Condition of Improvement 30 September 2011

PROGRAMMATIC ESA 1 CONSULTATION Specific Project Information Form For Tideland Markers Version: May 2012

Public Notice of Application for Permit

APPENDIX A SECTION 404(B)(1) EVALUATION TYBEE ISLAND, GEORGIA SHORE PROTECTION PROJECT RENOURISHMENT

THIS IS NOT A PAID ADVERTISEMENT. Public Notice. Public Notice No. CENAP-OP-R February 2, 2018

Condition of Improvements 30 December 2014 Lowell Creek, Alaska (CWIS No , , )

Cleveland Harbor Open Lake Placement

JOINT PUBLIC NOTICE September 14, 2015

SECTION 404(b)(1) EVALUATION REPORT FOR THE FOR THE OPERATIONS AND MAINTENANCE OF THE FEDERALLY AUTHORIZED BILOXI HARBOR NAVIGATION PROJECT OTT BAYOU

Beneficial Reuse of Dredged Sediments in the Middle Harbor Slip 1 Fill

Environmental Assessment Appendix H: Section 404(b)(1) Guidelines Evaluation. U.S. Army Corps of Engineers New York District

SANDY HOOK CHANNEL, NEW YORK HARBOR FEDERAL NAVIGATION PROJECT MAINTENANCE DREDGING

Environmental Restoration in Harbor and Port Areas

Update on Lower Fox River Remediation Project, Green Bay, Wisconsin

March 24, 2016 Shaun Payne & Daniel Large, EAHCP

Identifying and Managing Key Cost Drivers During Investigation, Remedy Selection and Design at Contaminated Sediment Sites

FINDING OF NO SIGNIFICANT IMPACT

General Motors (Central Foundry Division) Cleanup Progress Update Massena, St. Lawrence County, NY

THIS IS NOT A PAID ADVERTISEMENT. Public Notice No. CENAP-OP-R In Reply Refer to:

CITY OF VALDEZ ALASKA REQUEST FOR PROPOSALS

Upper Mississippi River Floodplain Island Restoration Details

J O I N T P U B L I C N O T I C E

Excavation of petroleum-contaminated soil and tank removal sampling Petroleum Remediation Program

Galveston Harbor Channel Extension Feasibility Study Houston-Galveston Navigation Channels, Texas

EVALUATION OF ENVIRONMENTAL MONITORING DATA GATHERED DURING ASHTABULA RIVER DREDGING, ASHTABULA RIVER, OHIO

Public notice ER-12-03

Houston-Galveston Navigation Channels, Texas Galveston Harbor Channel Extension Project

San Jacinto River Waste Pits Superfund Site Technical Document Review: Remedial Alternatives Memorandum (RAM)

DEPARTMENT OF THE ARMY US ARMY CORPS OF ENGINEERS SOUTH ATLANTIC DIVISION 60 FORSYTH STREET SW, ROOM 10M15 ATLANTA, GA

Cleveland Harbor Interim Dredged Material Management Plan Environmental Assessment Scoping Information Packet

Public Notice of Application for Permit

The release of the Final Environmental Impact Statement (FEIS) for the Bogue

PUBLIC NOTICE. Maintenance dredging with upland placement of dredged material Arthur Kill Road, Staten Island, Richmond County, New York

APPENDIX A Application Form for Regional General Permit 7 (RGP-7) Valid: July 26, 2011-July 26, 2016

Assessing Potential Contaminant Removal from Sediments and Biota within the First Wetland Mitigation Bank in New York City

Ashtabula Harbor, Ohio Great Lakes Restoration Initiative (GLRI) Dredging

DEPARTMENT OF THE ARMY CORPS OF ENGINEERS, MOBILE DISTRICT P.O. BOX 2288 MOBILE, AL

BAPTISTE COLLETTE BAYOU NAVIGATION CHANNEL DEEPENING SECTION 203 FEASIBILITY STUDY

DRAFT SECTION 404(b)(1) EVALUATION REPORT CONTINUED MAINTENANCE DREDGING OF THE FEDERALLY AUTHORIZED EASTPOINT NAVIGATION PROJECT

Great Lakes Sediment Testing Manual Evaluating the Suitability of Dredged Material for Beneficial Use

AR No. IR No. EIELSON AFB ALASKA. Administrative Record Cover Sheet NOTES:

Morris Cove as a Confined Aquatic

PROFESSIONAL SERVICES DESCRIPTION FOR THE POSITION OF: Paulsboro Marine Terminal Sediment Sampling Survey of Mitigation Site

Alaska Deep-Draft Arctic Ports Navigation Feasibility Study. U.S. Army Corps of Engineers Bruce Sexauer P.E. Chief of Planning, Alaska District

Port Gravina Quarry Operating Plan

J O I N T P U B L I C N O T I C E

Charleston Harbor Deepening Feasibility Study (Post 45 Study) Public Meeting

Public Notice: Application for Permit

Public Notice of Application for Permit

Mobile Bay National Estuary Program Project Implementation Committee Meeting

DRAFT. Point Hudson. Marina Breakwater Rehabilitation Task 1 Design Refinement. Port of Port Townsend. August 30, 2017

Dredging Project Update

THIS IS NOT A PAID ADVERTISEMENT. Public Notice. Public Notice No. CENAP-OP-R June 27, 2017

NOTICE DATE: December 20, U.S. Army Corps of Engineers

Transcription:

Cordova Harbor

Condition of Improvements 30 December 2014 Cordova Harbor, Alaska (CWIS No. 087136, 087186, 087711) Authorization Rivers and Harbors Act, 30 August 1935 (R & H Committee Doc. 33, 73rd Congress, 2nd Session) as adopted, provides for a sheltered small boat harbor of 8.26 acres with a depth of -10 feet MLLW protected by north and south breakwaters of 1,100 feet and 1,400 feet respectively, with provision for a future expansion of 10.4 acres to -14 feet MLLW. Table 1 Existing Project Length (max) Width (max) Depth ft. Entrance & Access Channel 1750 ft 125 ft -16 Entrance Breakwater 183 ft Western Breakwater 1902 ft Silt Barrier (contained) 1450ft 650 ft Mooring Basin (maintained by others) 19.55 acres 19.55 acres Varies Project Usage Cordova is a community on Prince William Sound in the Gulf of Alaska. The project is used as a base of operations for commercial fishing and provides moorage for 727 vessels, making it one of Alaska s largest single-basin harbors. Seaplane moorage is also available. The Cordova canning season is one of the longest and most diversified in the state. In 2011, nearly 400 residents held commercial fishing permits and nearly half of all households had someone working in the industry. Progress of Work 1938 The original basin and breakwaters are completed in October of this year. 1951 Maintenance dredging is accomplished to a depth of -12 feet MLLW. 1962 Dredging to -12 feet from September October removes 41,347 cubic yards of material from the harbor. 1964 The area is uplifted 6.2 feet by the 27 March 1964 earthquake causing major damage to the project. Restoration work begins in June. Basin expansion is approved on 19 August 1964 and begins in November. 1965 Restoration and expansion phases are completed in June. Cordova Harbor Page 3 of 9

Progress of Work 1966 Contract for construction of the 183 foot entrance breakwater is awarded in September and completed in October. 1968 13,170 cubic yards of material are dredged in February. 1970 A shoal at the entrance channel is dredged to -15 feet MLLW. 1972 The entrance channel and basin are dredged from September to October with 13,646 cubic yards removed. 1977 Maintenance dredging removes 11,313 cubic yards from September to October. 1981 Under the River and Harbor Act of 14 July 1960, Section 107, P.L. 86-645, authorized by the Chief of Engineers, 29 June 1978, harbor expansion is approved to 20 acres by the removal of the 1,400 foot breakwater, the construction of a 2,000 foot breakwater, and an increased depth for the entrance and access channel to -16 feet MLLW. 1983 1985 1988 1991 Harbor expansion contract is successfully completed. A condition survey is conducted in April and May. The entrance channel and portion of the basin are surveyed in September. Sampling and testing is carried out followed by maintenance dredging in December 1991 with 3,900 cubic yards removed from the Federal project. A project condition survey of the entrance channel is conducted in June. The entrance channel, basins, and breakwaters are surveyed in June. 1994 1997 2000 A condition survey of the harbor is completed in June. 2002 Vertical aerial photography is obtained of the harbor in June. 2003 A condition survey of the harbor is conducted in June. 2006 A condition survey is completed in May. E&D begins for a new maintenance dredging contract to be awarded in 2008. Contaminated sediments found in both the entrance channel and maneuvering area require upland disposal. 2008 A Department of the Army permit authorizing the construction of a breakwater extension and to raise the height of the north breakwater is issued. 2009 Maintenance dredging of the small boat basin from September to November removed 33,206 cubic yards of material. Contaminated material was disposed at the city landfill and non-contaminated material was disposed using the in-water site. 2010 A Project Condition Survey was conducted in June. 2014 A Project Condition Survey was conducted in May. Table 2 Cost to Date Project Description Cost $ 87136 O&M Appropriation 2,516,670 O&M Costs 2,513,716 O&M ARRA Appropriation 1,221,613 O&M ARRA Costs 1,221,613 Cordova Harbor Page 4 of 9

Project Description Cost $ 87186 CG Appropriation 10,341,656 CG Costs 10,341,656 CG Contributed Appropriation 4,811,891 CG Contributed Costs 4,811,891 Rehab Appropriation 675,000 Rehab Costs 675,000 Table 3 Range of Tides in feet Tide Station Mean Range Diurnal Range Extreme Range 945 4050 Cordova AK 10.17 12.59 22.36 Controlling Depth A depth of -15.7 feet MLLW controls along the centerline at the mouth of the entrance channel; a depth of -9.0 feet MLLW controls along the northern toe of fill/rock placed near the channel. Depths along the transient float are adequate with some soundings directly beneath the float above project depth. Nearly all the north basin (local) is above project depth and approximately half of the south basin (local) is above project depth. Conditions are based on the 2014 survey. Approximately 1-2 feet of shoaling has occurred throughout the entrance channel since the 2010 survey. Maintenance Dredging Supplement A. General 1. The Federal access and entrance channel requires dredging activity approximately every 12 years, as indicated by our records. 2. The harbor entrance is subject to shoaling activity, is within the Federal project, and thus requires periodic survey and ultimately dredging. 3. Sediments are typically removed with a clamshell and barge during the open dredging window from 8 September to 1 April. B. Sampling & Testing Seven samples (including a duplicate) were collected from six locations within the Federal project area in July 2006. A summary of the sampling activities is provided in the following table. Cordova Harbor Page 5 of 9

Table 5 Chemical Testing Method Chemical analysis Results SW846 8270C Semi-Volatile Organic Compounds (SVOCs) Low Level 0.97 to 19,000 ppb (35 analytes detected) SW846 8260B Volatile Organic Compounds 2.1 to 120 ppb (10 analytes detected) (VOCs) AK-101 Gasoline Range Organics 0.61 to 0.76 ppm (GRO) AK-102 Diesel Range Organics (DRO) 9.9 to 75 ppm AK-103 Residual Range Organics 20 to 68 ppm (RRO) SW846 8082 Polychlorinated Biphenyls Non-Detected (PCBs) SW846 8081A Pesticides (PEST) 0.20 to 25 ppb SW846 6010, 6020 CLP Target Analyte Metals 23 Metals detected or 7471 EPA 160.4 Total Volatile Solids (TVS) 2.3 to 2.8 % [sediment only] SW846 9060 Total Organic Carbon (TOC) 1.8 to 7.5 g/kg EPA 350.3 Ammonia N 62 to 120 ppm EPA 376.2 Sulfides 210 to 560 ppm ASTM D422 Grain Size Distribution (Sediment Only) *See Cordova Harbor Report 2007 (06-059) for complete analytical data 7.1 to 11.8 % Sand 88.2to 92.9 % Silt/Clay C. Disposal 1. Dredged material is transported by barge and tug to a deep water site, dumped, and dispersed by tidal activity. 2. A rectangular site is located approximately 500 yards west of Spike Island. Corners have the following geographic coordinates: Table 6 Disposal Area Corner Latitude (N) Longitude (W) 24 60 33 04.7 145 46 37.5 25 60 33 03.0 145 46 30.3 26 60 32 55.9 145 46 46.2 27 60 32 54.1 145 46 39.0 Cordova Harbor Page 6 of 9

3. The previous disposal site has met the approval of various agencies; other options may be available for future operations. D. Environmental Permits and Reports 1. The most recent Environmental Assessment (EA) was completed by the Corps in February 2008 for maintenance dredging that was conducted the following year. An EA was also completed by the Corps in July 1991. A Final Environmental Impact Statement (FEIS) was previously circulated in 1979 for harbor expansion. A Finding of No Significant Impact (FONSI) was signed in May 2008 and September 1991 for the most recent maintenance dredging events. 2. The following permits or authorizations are listed by agency below: Table 7 Environmental Permits Agency Name Date of Issue Date of Expiration US Fish and Wildlife Service January 25, 2008 n/a AK Department of Natural Resources (ACMP) April 25, 2008 n/a AK Department of Environmental Conservation May 12, 2008 May 12, 2013 AK State Historic Preservation Office February 14, 2008 n/a 3. Water Quality: Four physical parameters were measured through the water column at three locations in the federal project and one location at the disposal site, May 1991; temperature, ph, oxidation reduction potential (ORP), and conductivity were measured in the field. No chemical analysis was conducted. Cordova Harbor Page 7 of 9

Cordova Small Boat Harbor, Cordova, Alaska Aerial of the Cordova Small Boat Harbor, April 2014. Cordova Small Boat Harbor, 20 May 2014. Cordova Small Boat Harbor Page 8 of 9

Cordova Small Boat Harbor, Cordova, Alaska View of the entrance breakwater extension in May, 2014. Condition of the western breakwater during May, 2014. Cordova Small Boat Harbor Page 9 of 9