CONSTRUCTION DUST AND NOISE MONITORING REPORT OFFICE DEVELOPMENT EXAMPLE LTD RP

Similar documents
19 RELOCATED BUILDINGS AND TEMPORARY ACTIVITIES

H28. Special Purpose Quarry Zone

NOISE MANAGEMENT PLAN

BSM SD PLN 0126 MANAGEMENT PLAN 1. COMMITMENT AND POLICY 2. BACKGROUND. 1.1 Purpose. 1.2 Scope. 2.1 Development Consent Requirements

Impacts of Dredging and Reclamation on Noise and Amenity

32 RULES FOR NOISE AND VIBRATION

Monitoring Solutions. Sound Environmental Solutions

8. Appendix F Acoustic Assessment

EDINBURGH TRAM LINES ONE AND TWO

SECTION 11: NOISE RULES

Use of long term monitoring data for defining baseline sound levels

6.0. Noise and Vibration.

The applicant has estimated a total of vehicle movements per day.

This report assesses the outward noise and vibration impact of the proposed development on its surrounding environment.

Victorian Desalination Project


Additional information relevant to Section 7 is presented in Appendix D in Volume 2 of 3 of the EIS.

Woodlawn Mechanical Biological Treatment Facility. Project Approval (06_0239) Condition 28 - Noise Audit Report. Report Number 610.

Status: Rev: Comments Date: Author: Reviewer:

8 Noise and Vibration

Appendix P. Construction Noise Assessment. (Prepared by Marshall Day Acoustics, November 2013)

Environmental Noise Compliance Assessment Bass Point Quarry

Sydney Port Botany Terminal 3 Project Out of Hours Works Protocol

1 18 August 2017 Version 2 (Noise and vibration)

SCHEDULE 17 Cultural Heritage Monitoring Program

CRANBOURNE LANDFILL. Environmental Noise Assessment. Rp ML. 10 May 2013

OBERON WHITE GRANITE QUARRY

October 2012 Air Quality Report Berry Lane Park

PART 7 - NOISE, SIGNS AND ARTIFICIAL LIGHTING

ASSESSMENT OF INWARD TRAFFIC NOISE IMPACT AT RESIDENTIAL DEVELOPMENT, WONDERFUL BARN, LEIXLIP, CO. KILDARE

Section 12: Noise & Vibration

Status: Rev: Comments Date: Author: Reviewer:

SELWYN PRIMARY SCHOOL, LONDON ENVIRONMENTAL NOISE SURVEY

USE OF LONG TERM MONITORING DATA FOR DEFINING BASELINE SOUND LEVELS

CONTENTS. For inspection purposes only. TABLES

Out of hours works protocol

100 Avenue Road, Swiss Cottage, London

Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018

VIRIDOR WASTE MANAGEMENT LIMITED. Lostock Waste Treatment Plant. Airborne Pollutant Management Plan. November 2009

NSL4 respectively. All survey measurement and nearest noise sensitive locations are illustrated in Figures 14.1.

MAINE MEDICAL CENTER

Section 4-7 Noise STUDY METHODS Acoustic Fundamentals Amplitude Frequency

Noise Impact Assessment

February/March 2015 Air Quality Report Burma Road Site

Final Revisions : Retention of Trommel in existing position and raising height of acoustic fence on western side of site.

Residential Impact Mitigation Guidelines for Construction

I335. Western Springs Stadium Precinct

Construction Noise Management Plan

HAINE ROAD, RAMSGATE NOISE ASSESSMENT

Ambient Air Quality and noise Measurements Report Gas pressure reduction station in Marsa Matrouh Governorate

BEST MANAGEMENT PRACTICES PLAN FOR FUGITIVE DUST Greenwood Aggregates Company Limited Violet Hill Pit > Town of Mono, ON

Gisborne District Council

Southlands Remediation and Development Project

E25. Noise and vibration

REQUEST FOR TENDER - SERVICES RFT HOUSE DEMOLITION 7958 BEAVERDAMS RD., NIAGARA FALLS, ON.

4.6 Noise and vibration from construction activities Methodology for measuring noise Wastewater Signs...

Oberon Quarries Pty Limited BLAST MANAGEMENT PLAN. Oberon Quarry FINAL

Waterview Operational Air Quality Monitoring Report November 2017

Appendix B Noise and Blasting Impact Assessment

Noise and Vibration Assessment Aurecon

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201

Ambient Air Quality and noise Measurements Report Gas pipeline network at Farshout- Naqada, Waqf, and Qeft - Qena governorate

Law enforcement on proactive protection of noise and vibration pollution for

Proposed District Plan Change 83: Kiwi Point Quarry. Plan Change Document: Alterations to the Wellington City District Plan

BLAST MANAGEMENT PLAN (BMP)

4.11 NOISE ENVIRONMENTAL SETTING Characteristics of Noise

MATRIX 1: ENVIRONMENTAL MANAGEMENT PLAN TO BE IMPLEMENTED DURING THE SITE PREPARATION AND CONSTRUCTION PHASES

Salem, Massachusetts

APPENDIX A: AT: CRICKLEWOOD SIDINGS, LAND REAR OF BRENT TERRACE (SOUTH) CRICKLEWOOD LONDON NW2 1BX DRAFT PLANNING CONDITIONS

MAIN RESIDENTIAL ZONE RULES

PEAK GOLD MINES MONTHLY ENVIRONMENTAL SUMMARIES APRIL 2012

SECTIONAL DISTRICT PLAN REVIEW PLAN CHANGE 15 NORTH EAST INDUSTRIAL ZONE NOISE

Noise Impact Assessment. For Proposed Extension to Landfill Operations. Gowy Landfill Site Ince Lane Chester. For. FCC Environment

This Chapter contains rules managing land uses in the Main Rural Zone. The boundaries of this zone are shown on the Planning Maps.

Dun Laoghaire/Rathdown County Council. Longitude Festival 15 th to 17 th July Marlay Park, Dublin

UC Press Building 2120 Berkeley Way Berkeley, CA

Measurement of Airborne & Impact Sound Insulation. University of Durham, Pavilion H, Howlands Farm, Durham.

Power Plant Near-Field Noise Considerations

STATEMENT OF EVIDENCE OF CURT ROBINSON ON BEHALF THE AUCKLAND UTILITY OPERATORS GROUP

96(1A) Modification Application #2 DA The Sun Bistro Bayshore Drive, Byron Bay

THE WHARF TERRACES RENOVATIONS POLICY

APPENDIX 5.12-A PROJECT NOISE ANALYSIS: ARTESIAN SUBSTATION

PEAK GOLD MINES MONTHLY ENVIRONMENTAL SUMMARIES. April 2015

Management Plan: Hazardous Materials Removal & Demolition

ARCHITECTUS FEBRUARY 2010

Sydney Metro City and Southwest Sydney Yard Access Bridge Construction Noise and Vibration Management Plan (CNVMP)

Robinson Landing Condominium Pre- Construction Meeting

RIGHTMOVE PRODUCT GUIDELINES ESTATE AGENCY AND LETTINGS NEW JOINER

Regulations and Standards

Environment Protection Licence

Environmental Noise and Vibration Monitoring Report

Monthly Noise Monitoring Assessment

REPORT ON VIBRATION MONITORING GRANGEGORMAN CAMPUS CENTRAL & EAST QUAD, DUBLIN 7

Noise Survey. for. K & F Restaurant, 39 Camberwell Road, London SE5 0EN. Date of report: 30 th November 2012

Grande Prairie Generation, Inc.

SCHEDULE 17 Cultural Heritage Monitoring Program

FRINGE COMMERCIAL ZONE RULES

Content Copy Of Original

Exhibit G. Construction Mitigation Plan

Project: FONTERRA STIRLING. Prepared for: Fonterra Limited PO Box 459 Hamilton Attention: Brigid Buckley. Report No.

Transcription:

CONSTRUCTION DUST AND NOISE MONITORING REPORT OFFICE DEVELOPMENT EXAMPLE LTD RP01-19999

CONSTRUCTION DUST AND NOISE MONITORING REPORT PROJECT: OFFICE DEVELOPMENT CLIENT: EXAMPLE LTD CLIENT ADDRESS: EXAMPLE HOUSE EXAMPLE LANE LONDON COMPANY ADDRESS: CASS ALLEN ASSOCIATES BEDFORD I-LAB PRIORY BUSINESS PARK BEDFORD MK44 3RZ DOCUMENT CONTROL: REVISION ISSUE DATE REPORT BY CHECKED BY NOTES 0 Example date Adam Bamford, BSc MIOA DipIOA, Senior Acoustics Consultant Chris McNeillie, MSc CEng MIOA, Director Initial issue This report has been prepared by Cass Allen Associates Ltd with all reasonable skill, care and diligence, and taking account of the resources devoted to it by agreement with the client. Information reported herein is based on the interpretation of data collected and has been accepted in good faith as being accurate and valid at the time of collection. This report is for the exclusive use of the client named above; no warranties or guarantees are expressed or should be inferred by any third parties. This report may not be relied upon by other parties without written consent from Cass Allen Associates. Cass Allen Associates disclaims any responsibility to the client and others in respect of any matters outside the agreed scope of work.

TABLE OF CONTENTS 1. INTRODUCTION 2. ADOPTED MONITORING METHODOLOGY 3. MONITORING RESULTS 4. CONCLUSIONS NOISE MONITORING RESULTS VIBRATION MONITORING RESULTS DUST MONITORING RESULTS Page: 1 of 7

1. INTRODUCTION 1.1 Cass Allen Associates has been instructed by Example Ltd to carry out continuous noise, vibration and dust monitoring during the construction works at the site of a new office development known as Example House located off Example Lane in London. 1.2 The construction monitoring started in February 2020 and is anticipated to last for 17 months in total. This report contains the results of the monitoring carried out between 1 st and 31 st August 2020. 1.3 The objective of the monitoring is to help client/contractor manage dust and noise emissions from the construction works in order to comply with the requirements of Condition 5 of the development planning consent. 1.4 Condition 5 states: The developer shall monitor the levels of noise, vibration and dust pollution using an objective method of measurement for each working site. The developer shall submit to the Local Planning Authority the proposed method, the frequency and location of monitoring. Baseline levels of dust and noise shall be agreed prior to the commencement of works of demolition and construction. The developer shall also agree action levels of dust pollution and noise with the Local Planning Authority. When these levels are exceeded the developer shall take action to ensure that the levels of dust and/or noise are reduce to comply with the agreed action level. 1.5 One noise, one vibration and one dust monitoring system has been installed on the site boundary at the position shown in Figure 1. The position was chosen to represent the nearest residential receptors to the construction works. 1.6 Appropriate noise, vibration and dust limits have been established to minimise the potential disturbance caused by the construction activities at the nearby sensitive receptors to the site. The limits are in line with guidance contained in the Local Planning Authorities Construction Practice document and were discussed and agreed with an Environmental Health Officer at the Local Planning Authority previously. 1.7 The noise monitoring system comprises a Class 1 (EC 61672 compliant) sound level meter; and vibration monitoring system comprises a Class 1 (DIN 45669 compliant) vibration meter and the dust monitoring system comprises an MCERTS (PM10) certified airborne particle monitor. 1.8 The systems are configured to send email and text message alerts to site management and staff at Cass Allen in the event that noise, vibration and/or dust levels at the monitoring position exceed pre-configured project limits (refer to Section 2 of this report). Page: 2 of 7

Figure 1 Annotated Aerial Photo Showing the Dust and Noise Monitoring Position Continuous noise, vibration and dust monitoring location: Nearest sensitive receptor Site Page: 3 of 7

2. ADOPTED MONITORING METHODOLOGY Limits 2.1 The noise, vibration and dust limits that have been adopted for the construction monitoring are set out in Table 1. Table 1 Monitoring Index Adopted Monitoring Limits Limits Action Reference Periods Noise 75 dba LAeq,1 hour If this level is exceeded for any significant proportion 0800-1900hrs (upper threshold limit) of a monitoring period, then site staff will be notified Monday and remedial measures should be taken to reduce through Friday emissions as far as practicable. The remedial actions 0800-1600hrs taken must be noted and reported on Saturdays 80 dba LAeq,1 hour) If this level is exceeded for any continued period of (action limit) time, then the operations identified as producing the noise should be stopped until it can be confirmed that remedial measures will be put in place to significantly reduce the noise emissions to an acceptable level. Vibration 5 mm/s Peak Particle If this level is exceeded for any significant proportion 0800-1900hrs Velocity (PPV) of a monitoring period, then site staff will be notified Monday (upper threshold limit) and remedial measures should be taken to reduce through Friday emissions as far as practicable. The remedial actions 0800-1600hrs taken must be noted and reported on Saturdays 10 mm/s Peak Particle If this level is exceeded for any continued period of Velocity (PPV) time, then the operations identified as producing the (action limit) noise should be stopped until it can be confirmed that remedial measures will be put in place to significantly reduce the noise emissions to an acceptable level. Dust 200 g m -3 15-minute If this level is exceeded for any significant proportion 0800-1900hrs mean for PM10 of a monitoring period, then site staff will be notified to Monday concentrations reduce dust emissions to an acceptable level through Friday (upper threshold limit) 0800-1600hrs 400 g m -3 15-minute If this level is exceeded for any continued period of on Saturdays mean for PM10 time, then the operations identified as producing the concentrations dust should be stopped until it can be confirmed that (action limit) remedial measures will be put in place to significantly reduce the dust concentration to an acceptable level. Page: 4 of 7

Alerts 2.2 The monitoring equipment has been configured to send alerts to site management and Cass Allen staff in the event that the upper threshold noise, vibration and/or dust limits given in Table 1 above are exceeded. If the noise, vibration and/or dust action limits are exceeded for any significant period of time then the work(s) causing the noise, vibration and/or dust emissions should be stopped and remedial measures incorporated to significantly reduce emissions to acceptable levels. 2.3 The alerts comprise SMS and email messages. The alerts will be sent to Cass Allen and site managers indicating that the dust and/or noise limits have been exceeded. The system is currently configured to send the alerts to the following managers: o o o example1@client.com; example2@client.com; and example3@client.com 2.4 The following actions should be taken in the event that either the upper threshold or action levels given in Table 1 are exceeded: A manager onsite will investigate the cause of the alert. The manager will ensure that the activity causing the exceedance is carried out in such a way as to minimise the noise or vibration emissions. Cass Allen will contact site to discuss the exceedance and available options for reducing the noise and vibration emissions. We will also document the cause for reporting purposes. Maintenance 2.5 The next scheduled site visit for maintenance is due in November 2020. Page: 5 of 7

3. MONITORING RESULTS 3.1 The results of the monitoring between the 1 st and 31 st August 2020 are shown in the graphs in: Appendix 1 (noise monitoring results); Appendix 2 (vibration monitoring results); and Appendix 3 (dust monitoring results). 3.2 It can be seen from the noise monitoring results that: There were a total of 4 exceedances of the noise upper threshold but no exceedances of the action limits during the monitoring period. 3.3 It can be seen from the vibration monitoring results that: There was 1 exceedance of the vibration upper threshold but no exceedances of the action limits during the monitoring period. 3.4 It can be seen from the dust monitoring results that: There were a total of 39 exceedances during the monitoring period. Of these: o o 14 exceedances were above the upper threshold dust level 8 of which were outside of construction hours and have therefore been discounted; and 25 exceedances were above the dust action level 12 of which were outside of construction hours and have therefore been discounted. Discussion and Remedial Measures Taken 3.5 All exceedances of the 75 dba LAeq,1 hour (upper threshold noise limit), were brief incidents (i.e. the noise source exceed 75 dba for less than 60 seconds). 3.6 Generally noise levels are well below the noise limits so we recommend that site staff continue to investigate any alerts to ensure that noisy activities are minimised in close proximity to the nearby residential receptors, as far as practicable. 3.7 The vibration exceedance is believed to have been caused by a heavy roller operating in close proximity to the vibration monitor. It is worth pointing out that this exceedance was a brief, isolated incident and generally vibration levels are well below the adopted limits. We recommend that site staff continue to investigate alerts to ensure that vibration generating activities in the vicinity of the sewer are minimised as far as reasonably practicable. 3.8 Site management confirmed that the decoupling of articulated trailers takes place in the area where the noise, vibration and dust monitors are located. This causes dust to lift at high pressure from the floor which could account for the majority of the exceedances. In order to demonstrate Best Practicable Means, site staff are regularly wetting down this area to minimise future occurrences as far as reasonably practicable. 3.9 The vast majority of the exceedances were isolated, brief incidents (less than 15 minutes in duration) and typically, dust emissions are generally well below the upper threshold limit the average PM10 dust concentrations for the monitoring period was 23 g m -3. Page: 6 of 7

4. CONCLUSIONS 4.1 Continuous construction noise, vibration and dust compliance monitoring is being carried out to protect nearby existing residential amenity surrounding the site. 4.2 The monitoring being provided by Cass Allen commenced in February 2020 and is anticipated to last for approximately 17 months. 4.3 The monitoring location was previously discussed and agreed with the Environmental Health Department at the Local Planning Authority for the demolition works and the limits are in line with the guidance given in the Local Planning Authorities Construction Practice document. 4.4 This report provides the results of the monitoring for the period between 1 st and 31 st August 2020. During this period: There were some exceedances of the adopted noise upper threshold but no exceedances of the action limit during the monitoring period. It is recommended that site staff continue to investigate any alerts to ensure that noisy activities are minimised in close proximity to the nearby sensitive receptors, as far as practicable; There was one exceedance of the adopted vibration upper threshold but not exceedances of the action limit during the monitoring period. It is recommended that site staff continue to investigate any alerts to ensure that vibration activities are minimised in close proximity to the nearby sensitive receptors, as far as practicable There were some potential construction related exceedances of the adopted dust upper threshold and action limits as described in Section 3.4 above. Site have commenced washing down of the area to minimise future occurrences and demonstrate Best Practicable Means. 4.5 Construction noise, vibration and dust levels will continue to be monitored for the remainder of the construction phase and reported via monthly reports. Page: 7 of 7

Noise Monitoring Results Sound Pressure Level (dba) Upper threshold noise limit, 75 db LAeq, 1hr Action noise limit, 80 db LAeq, 1hr Noise level, LAeq, 1hr

Vibration Monitoring Results Upper threshold vibration limit, 5 mm/s PPV Action vibration limit, 10 mm/s PPV

Dust Monitoring Results Upper threshold dust limit, 200 g m -3 15-minute mean for PM10 concentrations Action dust limit, 400 g m -3 15-minute mean for PM10 concentrations Dust level, g m -3 15-minute mean for PM10 concentrations

www.cassallen.co.uk