TECHNICAL REPORT III LATERAL STRUCTURAL SYSTEM ANALYSIS

Similar documents
TECHNICAL REPORT II STRUCTURAL STUDY OF ALTERNATE FLOOR SYSTEMS

OVERALL STRUCTURAL SYSTEM

Technical Report #1. Matthew R Peyton

STRUCTURAL TECHNICAL REPORT 1

TECHNICAL REPORT 1. Structural Concepts / Structural Existing Conditions. Penn State Hershey Medical Center Children s Hospital. Hershey, Pennsylvania

Arlington, Virginia December 3, 2007 TECHNICAL REPORT III LATERAL SYSTEM ANALYSIS AND CONFIRMATION DESIGN

MOUNTAIN STATE BLUE CROSS BLUE SHIELD HEADQUARTERS

Structural Technical Report 1 Structural Concepts/ Structural Existing Conditions Report

1000 CONTINENTAL SQUARE

Technical Report #3. Matthew R Peyton

[TECHNICAL REPORT 3] Lateral System Analysis

Rutgers University Law School Building Addition and Renovation Camden, NJ

Technical Report 1. Seneca Allegany Casino Hotel Addition. Salamanca, NY

Christopher McCune Structural Option 2006 Senior Thesis Penn State Architectural Engineering. Eight Tower Bridge Conshohocken, Pennsylvania

William W. Wilkins Professional Building Columbus, Ohio

Technical Report #1. Indiana Regional Medical Center Indiana, PA. Cody A. Scheller. Structural Concepts & Existing Conditions Report

David A. Walenga Technical Assignment #1

Visteon Village Corporate Center

Traci Peterson Option: Structural Faculty Consultant: Memari. Executive Summary

Technical Assignment 3 December 3, 2007

Thesis Proposal. Matthew R Peyton

Letter of Transmittal

Dead Loads (psf): Concrete Floor Slab on Metal Deck 45 psf Mechanical and Ceiling 7 psf Miscellaneous 5 psf Exterior Wall 80 psf

Temecula Medical Center Temecula, CA

Technical Report #2. Matthew R Peyton

Technical Assignment #3 November 15, 2004 Lateral System Analysis and Confirmation Design

Design Criteria. Analysis and Design of a High Rise Steel Braced Frame Core 22

North Shore at Canton Baltimore, MD Beau Menard Technical Report 1

School of Engineering and Applied Science Building Miami University, Oxford, OH Technical Assignment 3 December 3, 2007

Executive Summary Building Description: Introduction... 13

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan

HIGH RISE CONDO SOHO, NEW YORK, NY

Table of Contents 2. Structural Systems.4 Foundations.4 Floor System...4 Columns..5 Lateral System...5

90% Design Submittal Structural Calculations Parking Garage CDRL

John Jay College Expansion Project

Thesis Proposal. La Jolla Commons Phase II Office Tower San Diego, California. December 13, 2013

The Harry and Jeanette Weinberg Center Mercy Hospital Medical Office Building Baltimore, MD. Thesis Proposal

Structural Engineering, Mechanics, and Materials. Preliminary Exam - Structural Design

CORPORATE HEADQUARTERS

Boyds Bear Country Pigeon Forge, TN

Simplified Building Schematic for Typical Floor (Levels 9 through 22):

Howard County General Hospital Patient Tower Addition Columbia, MD. Kelly M. Dooley Penn State Architectural Engineering Structural Option

Lateral System Analysis and Confirmation Design (S-3)

FINAL REPORT. Structural Redesign of Hershey Medical Center Children s Hospital. Penn State Hershey Medical Center Children s Hospital

Technic. Photo Courtesy of. Ryan

Structural Technical Report 1 Structural Concepts / Structural Existing Conditions Report

Executive Summary...2 Introduction...3 Structural System Overview Buffalo,...4 Foundation...4 Floor System...4 Gravity System...4 Lateral System...

Technical Report #3: Lateral System Analysis. Executive Summary

111 MORGAN ST. Ryan Friis

Technical Report 1. Kingstowne Section 36A 5680 King Center Drive Kingstowne, VA James Chavanic. Structural Option. Advisor: Dr.

Technical Report 1 Bed Tower Addition at Appleton Medical Center Appleton, WI

Technical Report 1. Residence Inn By Marriott. Structural Option September 29, Existing Conditions / Structural Concepts.

Structural Concepts and Existing Conditions Report

THE PARKING STRUCTURE PROTOTYPE II

Belmont Executive Center; Building A

Kevin Wigton Structural Option. Technical Report III. Simmons College School of Management, Boston, Ma

Structural System. Design Criteria Fire Resistance Concrete designed for 2 HR rating (worst case) Geotechnical Report Allowable Bearing Capacity

La Jolla Commons Phase II Office Tower

Lateral System Analysis and Confirmation Design

Brent Ellmann Structural Option 200 Minuteman Park, Andover, MA Structural Consultant: Dr. Hanagan

Executive Summary. Greg Kochalski. JW Marriott, Grand Rapids, MI

MCEER Hospital Demonstration Project

Best Buy Corporate Building D (4) Richfield, MN

TECHNICAL ASSIGNMENT 1 STRUCTURAL CONCEPTS / EXISTING CONDITIONS REPORT

Date: 'Comments' b Steel Quantity Takeoff. 'Quantities' b Design Loads and Parameters

Point Pleasant Apartments Point Pleasant, NJ Ryan P. Flynn Structural Option Faculty Consultant: Dr. Hanagan

Erie on the Park. Timothy Moore Penn State University Architectural Engineering Structural Emphasis Advisor: Prof. Ali Memari

MOUNTAIN STATE BLUE CROSS BLUE SHIELD HEADQUARTERS

CE 3150 Reinforced Concrete Design Design Project

Structural Design Engineers 120 Montgomery Street, Suite 1410 San Francisco, California / Fax 415/

Structural Technical Report #1 By Robert Whitaker

Office Building-G. Thesis Proposal. Carl Hubben. Structural Option. Advisor: Dr. Ali Memari

Jackson Crossing Located in Alexandria, VA. Technical Report 1 Michael Bologna

Southwest Housing, Arizona State University

Structural Option Indiana Regional Medical Center Indiana, PA

Butler Health System New Inpatient Tower Addition/Remodel. Dr. Ali Memari Technical Report #1. Architects Rendering. Technical Report #1

1000 CONNECTICUT AVENUE

TEMECULA MEDICAL CENTER PRESENTATION OUTLINE

SENIOR THESIS PROPOSAL STRUCTURAL REDESIGN USING STEEL FRAMING

La Jolla Commons Phase II Office Tower

Kaleida Health Global Heart and Vascular Institute University at Buffalo CTRC/Incubator. Buffalo, New York. Technical Report #2

Hilton Baltimore Convention Center Hotel Western Podium

Simplified Building Schematic for Typical Floor (Levels 9 through 22):

Hilton Baltimore Convention Center Hotel Western Podium

John Jay College Expansion Project

Boyds Bear Country Pigeon Forge, TN

PEER/CSSC Tall Building Design Case Study Building #1. J. Andrew Fry John Hooper Ron Klemencic Magnusson Klemencic Associates

STRUCTURAL TECHNICAL REPORT 3

MITRE 3 Building McLean VA

Structural Technical Report I October 5, 2006 Structural Concepts / Structural Existing Conditions Report

Park Potomac Office Building E

CORPORATE HEADQUARTERS

TECHNICAL REPORT 2 BUILDING CODES, SPECIFICATIONS, AND LOADS

Farquhar Park Aquatic Center. York, PA

UNION STATION EXPANSION AND RESTORATION TECHNICAL REPORT I

Trump Taj Mahal Hotel

BWI Hilton Hotel. Thomas Sabol The Pennsylvania State University Architectural Engineering Structural Emphasis Advisor: Dr. Ali M.

Franklin Square Hospital Center Patient Tower

September 26, 2014 Dr. Linda Hanagan Lhanagan.engr.psu.edu

Technical Report III

Transcription:

TECHNICAL REPORT III LATERAL STRUCTURAL SYSTEM ANALYSIS Chris Vanaskie Structural Peninsula Regional Medical Center Salisbury, MD January 10, 2009

TABLE OF CONTENTS Executive Summary... 3 Introduction... 4 Codes and Material Properties... 5 Structural System... 6 Gravity Framing System... 6 Lateral System... 7 Wind Loads... 9 Seismic Loads...10 Strength Check...11 Drift...11 Conclusion...12 2

EXECUTIVE SUMMARY In this report the lateral structural system of is analyzed and evaluated. A computer model was created using RAM Structural System, and using the Frame Module the braced frames of the building were analyzed for wind and seismic loading. Frames and individual members were evaluated for strength and drift. All members of the frames were found to be adequate to resist these lateral forces and it was found that the design of these members was governed by strength. 3

INTRODUCTION The is part of an expansion and renovation project at Peninsula Regional Medical Center. It is located at 100 East Carroll Street in Salisbury, MD. It is a 200,000 square foot facility that will house a new emergency/trauma center, pediatric unit, intensive care unit, cardiac and thoracic and vascular unit and a neurosciences and stroke unit. The building also features a helipad on the lower roof with access to the third floor of the main tower. There is a connection to the existing hospital at the northeast corner. Construction on was completed in 2008. The structure is divided into two parts: the east side (Area A) with three stories and the west (Area B) with one story. An expansion joint connects the two sections of the building. This report will analyze the lateral force resisting system of. Both wind and seismic loads will be considered. The results will be analyzed for strength and drift. 4

CODES AND MATERIAL PROPERTIES Codes The structural design of the conforms to the requirements of the Maryland Building Performance Standards (MBPS) which has adopted the 2003 International Building Code (IBC) and ASCE 7-02. Structural steel design used the AISC Manual of Steel Construction Load and Resistance Factor Design, Second Edition, 2003. Concrete design used American Concrete Institute, ACI 318-02. For this report, the latest versions of these codes were used. IBC 2006 and ASCE 7-05 were used for design loads and structural analysis. ACI 318-08 was used for structural concrete design and AISC Manual of Steel Construction, Load and Resistance Factor Design, Fourth Edition 2007 for structural steel. Material Properties Steel Members W-Shapes ASTM A992, Grade 50 Channels, Angles, Plates, Bars ASTM A36 or A572, Grade 50 HSS Sections ASTM A500, Grade B Structural Pipe ASTM A53, Type E or S, Grade B Braced Frame Members ASTM A992 or A36 Steel Reinforcement Grade 60 Concrete Footings 3000 psi 145 pcf Slab-on-grade 3500 psi 145 pcf Foundation walls 4000 psi 145 pcf Suspended slabs 4000 psi 145 pcf Slabs on Metal Deck 3000 psi 115 pcf Building frame members 4000 psi 145 pcf Building walls 4000 psi 145 pcf Precast panels 5000 psi 145 pcf or 115 pcf 5

STRUCTURAL SYSTEM Gravity Framing System The main structural system is made up of structural steel W-shape members. Most connections are shear connections. The typical beam size in Area A (Figure 1) is W18x35 space at 10-0 on center and in Area B (Figure 2) it is W 18x35 also spaced at 10-0 on center(beams are running east-west in figures below). Girders are typically W21x50 in both areas(running north-south in figures below). Columns in Area A are various W12 sizes. In Area B the typical column size is W12x53. The most typical bay is 30 0 by 30 0, but there are also column spacings of 28 0, 27-8, and 26 0. Area B Figure 1, Area A 6

Area A Figure 2, Area B Lateral System The lateral structural system is composed of braced frames, one in each direction. W12 s are the typical members for the braced frames. All of the main frames are one bay wide, extending the full height of the building, and most are located along the perimeter walls of both Areas A and B. In Area A there is one near the elevator shafts located in the center of the building. Figures 3 and 4 show the locations of the braced frames by the orange highlighted lines. In Area B all frames are K-frames. All penthouses as well as the heliport are braced along all sides. 7

26'-0" 26'-0" 26'-0" Frame A Frame C 26'-0" Chris Vanaskie Frame D Frame B Figure 3, Lateral Braces Area A 27'-8" 28'-0" 28'-0" 28'-0" 28'-0" Figure 4, Lateral Braces Area B 8

Figure 5, Braced Frames Wind Loads Wind loads were determined using RAM Structural System Basic Wind Speed, V = 110 mph Wind Directionality Factor, K d = 0.85 Building category = IV Importance Factor = 1.15 Exposure Category = C Topographic Factor, K zt = 1.0 External Pressure Coefficient, C p,w = 0.8 External Pressure Coefficient, C p,l = -0.5 External Pressure Coefficient, C p,s = -0.7 Wind Forces Force Level Pressure Applied (psf) (kips) Roof 39.35 53.86 5 38.06 114.73 3 36.06 117.88 2 32.88 101.18 Wind Story Shears Level East-West North-South Roof 54.72 46.87 5 170.51 145.94 3 289.42 247.46 2 391.68 333.54 Base 13.96 75.3 9

Seismic Loads Seismic Loads were designed in accordance with sections 11 and 12 of ASCE 7-05. The geotechnical information was unavailable for this report so the site class was assumed to be site class D because that is what was used in the original design of the building. Ss = 0.124 S1 = 0.045 SDS = 0.132 SD1 = 0.072 Seismic Design Category C Response Modification Factor, R = 3 Importance Factor, I = 1.5 Area A Area B Base Shear 630 kips 592 kips Overturning Moment 79061 ft-kips 24234 ft-kips Seismic Story Shear Level East-West North-South Roof 96.63 98.23 5 169.71 172.6 3 214.42 217.93 2 232.62 235.87 Base 5.73 74.41 10

Strength Check A strength check of all frame members was performed using RAM. Members were first analyzed as W12x50 s and found that the sizes had to be increased on floors one through three. When sizes were changed to the actual sizes of the members according to plans, all members were found to satisfy strength checks. Below is a figure from RAM showing the frames and the members in question. All blue members are ok while red are not. The red beams are that way most likely because they are not considered in part of the frame for lateral force resistance and are only sized according to gravity loading. Drift Building drift and story drift were found with RAM. These values were to be less than h/400 where h is the height of the building or height of the floors. h/400 for the building is 70 /400 = 2.1. For story drift h/400 is either 16 /400 = 0.48 or 19 /400 = 0.57. drift story Wind Seismic Wind 0.61483 2 0.1472 0.0994 Seismic 0.5262 3 0.1709 0.1349 5 0.1688 0.1563 Roof 0.1279 0.1357 11

CONCLUSION The lateral system in place on is satisfactory to resist both wind and seismic loads. The design was controlled by strength and found to be adequate for drift. 12