Subject: Half yearly Report for the period of 1 st April 2013 to 30 th Sept., 2013 for Indmax Project

Similar documents
HALF YEARLY COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE CONDITIONS

DESCRIPTIVE REPORT ON STATUS OF COMPLIANCE TO THE CONDITIONS OF ENVIRONMENTAL CLEARANCE AND ENVIRONMENTAL MANAGEMENT

4. The ambient air quality monitoring stations We are monitoring the ambient air quality

6 th MONTHLY COMPLIANCE REPORT OF DIBRUGARH-BHOGPARA AREA

DESCRIPTIVE REPORT ON STATUS OF COMPLIANCE TO THE CONDITIONS OF ENVIRONMENTAL CLEARANCE AND ENVIRONMENTAL MANAGEMENT

COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF APRIL-2016 TO SEPTEMBER F. No. J-11011/309/2011-IA-ll (I)

Chambal Fertilisers and Chemicals Limited CFG3 Project Environment Clearance_ Compliance Report (Feb 28, 2018)

J-11011/45/2009- IA II (I)

Calcom Cement India Limited


COMPLIANCE STATUS REPORT

State Level Environment Impact Assessment Authority Madhya Pradesh Government of India Ministry of Environment & Forests

Environment protection measures / technology

Subject: Half Yearly Report for the period of 1 st October, 2013 to 31 st March 2014 for Refinery Expansion Project

Environmental Clearance; Letter No J / 152 / 2006-IA-II (I) Dt and corrigendum dated

Environmental Clearance; Letter No J / 152 / 2006-IA-II (I) Dt and corrigendum dated

Clearance Letter no. : MoEF Vide Letter no. J-11011/79/2003-IA-II (I) dated April 21, 2004

Annexure-A. Shall be complied with.

Six Monthly Reports for the period April, 2009 to September, Six monthly effluent quality (Point No. viii) Furnished in Appendix-A1

locations. The company shall use low sulphur fuel to minimize SO 2 emission.

SIX MONTHLY COMPLIANCE REPORT OF BORHAT-TITLAGARH AREA

High efficient ESP s has been provided to maintain an emission level below 100mg/Nm 3 in CPP. Modification of ESPs and.

Name of Project: J.K. Cement Works (Unit: J.K. Cement Ltd.), Muddapur (Karnataka)

Mangalam Cement Ltd.(Unit I)

Mangalam Cement Ltd. (Unit-II) Stack No.

Compliance of Conditions laid down by MoEF for Expansion of Cement Plant (2.0 MTPA to 2.6 MTPA Clinker) at Village Suli April 2017 to September 2017

Manufacture of Products like Phthalic Anhydride, Benzoic Acid and Power.

THE RAMCO CEMENTS LIMITED, KSR NAGAR COMPLIANCE REPORT - ENVIRONMENTAL CLEARANCE CEMENT PLANT 2.5 MILLION TPA CLINKER, 2

Ref: Environment Department, MS, SEIAA Letter SEAC 2010/CR.824/TC-2 Dated 2 nd Nov 2011

Telefax : 011: Dated 1 st November, 2011

Telefax: 011: Dated:10 th May, 2013

Shri Gurudatt Sugars Ltd., Gat No. 61/A, Akiwat - Takaliwadi Road, Takaliwadi , Taluka - Shirol, Dist Kolhapur, Maharashtra

Environmental Clearance Compliance Half Yearly Report

Overburden dumps are stacked separately as per the guidelines and the same will be used for backfilling in mined out area.

Janki Corp. Ltd., Six Monthly Compliance Report

COMPLIANCE TO THE CONDITIONS LAID BY MoEF VIDE CRZ CLEARANCE No.11/32/2009-IA.III dated

COMPLIANCE REPORT TO THE CONDITIONS LAID IN THE ENVIRONMENTAL CLEARANCE

Telefax: 011: Dated: 8 th March, 2013

Six Monthly Compliance status of Environment Clearance for Cement Plant (5300 TPD Clinker) at Village Lumshnong, Meghalaya January to June 2013

From : April 2015 To : October 2015 Status of conditions stipulated in Environmental and CRZ clearance. Adani Vizag Coal Terminal Private Limited

Bharat Petroleum Corporation Ltd., Mumbai Refinery

Six Monthly Compliance Status Report

Environmental Clearance Compliance Half Yearly Report

COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF APRIL 2013 TO SEPTEMBER M/s. Subham Planners Ltd.

V.S LIGNITE POWER Pvt. Ltd AT VILLAGE-GURHA, KOLAYAT, BIKANER, RAJASTHAN

Environmental Clearance Compliance Half Yearly Report

Health and safety norms of CPWD should be followed during construction.

Date: M/S Desh Bhakt Ratnappa Kumbhar Panchaganga SSK Ltd, Inchalkaranji, Kolhapur.

2 No. Continuous Ambient Air Quality Monitoring System (CAAQMS) installed in downwind & upwind direction and are connected to APPCB server.

Environmental Clearance Compliance Half Yearly Report

Name of the Project:- J&K Mineral Development Corporation Limited.

F. No. J-11011/480/2007-IA II (I) Government of India Ministry of Environment and Forests (I.A Division)

Torrent Pharmaceuticals Ltd. Indrad EC Compliance Report

PROJECT NAME: UTKAL ALUMINA INTERNATIONAL LTD. PERIOD OF COMPLIANCE: OCTOBER 2014 TO MARCH 2015.

(E.C. Letter No. F.No.J-11011/107/2013-IA II (I) Dated ) (For the Period 1 st October 17 to 30 th March 18)

PROJECT NAME: UTKAL ALUMINA INTERNATIONAL LTD. PERIOD OF COMPLIANCE: APRIL, 2013 TO SEPTEMBER, 2013.

Cement Manufacturing Company Ltd. Page 1

Environmental Clearance Compliance Half Yearly Report

BRGD Ingot Private Limited 4, D.L. Khan Road, Block-C, Flat No. 201, 2 nd Floor, P.S. Kalighat, P.O. Bhowanipur, Kolkata

INDIA: Dahej Liquefied Natural Gas Terminal Project

(Period April 2017 ~ Sept. 2017)

Your letter ref. no. J-11011/131/2005-IA.II (I) dated A. SPECIFIC CONDITIONS

Six Monthly Compliance Status Report

(A) Specific Conditions

J-11011/15/ IA II (I)

Environmental Clearance Compliance Half Yearly Report

M/s Deccan Cements Limited, Bhavanipuram,Janaphad, Palakeedu, Suryapet. Telangana MoEF No: J-11011/572/2007-IA II(I) Dated

SreeJayajothi Cements Limited (100% Subsidiary of M/s. My Home Industries Private Limited), Srinagar, Yanakandla , Kurnool Dist, Andhra

Compliance Status Report of Environmental Clearance No. J 11011/257/2008 IA II (I) dated 23/11/2010

Mangalam Cement Ltd.

F. No. J-11011/196/2007- IA II (I) Government of India Ministry of Environment and Forests (I.A. Division) Paryavaran Bhawan CGO Complex, Lodhi Road

Rajasthan State Pollution Control Board

Compliance Report of EC : Compliance Status

Environmental Clearance Compliance Half Yearly Report

.in Dated 9th August, Sharma ;

Chemplast Sanmar Limited Marine Terminal Facility, Chitrapettai Village Cuddalore District, Tamil Nadu

Shriram Vinyl & Chemical Industries, : Kota Compliance Report of Environmental Clearance dated 12 th July 2017 and amended on 23 rd November 2017

NATCO PHARMA LIMITED CHEMICAL DIVISION Mekaguda (Village), Nandigama (Mandal), Rangareddy (Dist.)

Ref: Online proposal no. IA/AP/IND2/57973/2016 dated 6th September, 2017

Ministry of Environment and Forests Telefax : 011: M/s Posco India Private Limited

Rajasthan State Pollution Control Board

NOC GRANTED FOR THE EXPANSION OF KASHLOG LIMESTONE MINES OF AMBUJA CEMENTS TIMITED

Monitoring the Implementation of Environmental Safeguards

Mill Expansion Cum Augmentation Project Compliance

MONITORING THE IMPLEMENTATION OF ENVIRONMENTAL SAFEGUARDS Ministry of Environment & Forests Regional Office (W), Bhopal Monitoring Report Part-I

J.K. Cement WORKS, NIMBAHERA (RAJ)

qqfq(ui qci CA' ~< Government of India Ministry of Environment & Forests (IA Division)

J-11011/371/2016-IA II (I) Government of India Ministry of Environment, Forest and Climate Change (Impact Assessment Division)

D:\My Documents\Legislative\Legislation BS\Consents\Six monthly compliance\cement\june 2017\COMPLIANCE STATUS.docx.docx

ANNEXURE 1 - THE DETAILS OF PRODUCTION QANTITIES

NATCO PHARMA LIMITED CHEMICAL DIVISION

Project Code: Clearance Letter No. : MoEF vide letter No: - J-11015/423/2005-IA-II (M) Dated 18 th May 2006

Project Code: Clearance Letter No. : MoEF vide letter No:- J-11016/202/2003-IA-II(M) Dated 6 th Jan 2005

Hope you will find the same in order. Thanking You, For EMAMI PAPER MILLS LTD. Authorized Signatory

COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF OCTOBER TO MARCH-2017

Chennai Petroleum Corporation Limited (A group company of IndianOil)

Application of Low and Non Waste Technology in the production process;

EXECUTIVE SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT

Hind Energy & Coal Beneficiation (India) Ltd.

Mangalam Cement Ltd. Clearance Letter No. :- F NO. J / 30/ IA II (I), dtd 17/07/2007

Transcription:

IOC/BGR/ENV/INDMAX/MoEF/2013-14/01 Date: 19.11.2013 To The Chief Conservator of Forests Regional Office, North East Region Ministry of Environment & Forests Law-U-SIB, Lumbatngen, Near M.T.C. Workshop, Shillong 793021 Subject: Half yearly Report for the period of 1 st April 2013 to 30 th Sept., 2013 for Indmax Project Dear Sir, With reference to above, we are enclosing the Six Monthly Report for the period of 1 st April 2013 to 30 th September, 2013 for your kind perusal. The reports are being sent as per EIA Rules 2006 on the Environmental Clearances issued by MoEF to Bongaigaon Refinery, (BGR) for Indmax Project. Thanking you, Yours faithfully, (A.K Agarwal) Senior Manager (HSE) Copy to: 1. Member Secretary, Pollution Control Board, Assam Bamunimaidam, Guwahati - 781 021 2. Zonal Officer, Central Pollution Control Board Eastern Zonal Office, TUM-SIR, Lower Motinagar, Near Fire Brigade H.Q., Shillong 793014 Page 1 of 5

Status of Indmax Project Six Monthly Status report for the period (1 st April 2013 to 30 th September, 2013) Environmental Clearance for Indmax Project (INDMAX FCC Unit along with Indmax Gasoline De- Sulphurisation Unit) to eliminate production of black oils (LDO, LVFO & LSHS) and Naphtha by M/s Bongaigaon Refinery & Petrochemicals Ltd. vide MoEF s letter No. J-11011/9/2008- IA II (I) dated 02/09/2008. S.N SPECIFIC CONDITIONS COMPLIANCE STATUS i ii. iii. M/s BRPL shall comply with new standards/norms for Oil Refinery Industry notified under the Environment (Protection) Rules, 1986 vide G.S.R.186(E) dated 18 th March 2008. The design of INDMAX FCC unit shall incorporate process features and equipments to comply with the emission and effluent standards for petroleum refinery. The process emissions (SO2, NOx, CO & HC) from various units shall conform to the standards prescribed by the Assam State Pollution Control Board from time to time. At no time, the emission levels shall go beyond the stipulated standards. In the event of failure of pollution control system(s) adopted by the unit, the unit shall be immediately put out of operation and shall not be restarted until the desired efficiency has been achieved. The company shall use sweet fuel gas and install low NOx burner in the furnace. Ambient air quality monitoring stations, [SPM, SO 2, NO x and NMHC, Benzene] shall be set up in consultation with SPCB, based on occurrence of maximum ground level concentration and down-wind direction of wind. The monitoring network must be decided based on modeling exercise to represent short term GLCs Continuous on-line stack monitoring equipment shall be installed for measurement of SO 2 & NO x. iv. Monitoring of fugitive emissions shall be carried out as per the guidelines of CPCB and reports shall be submitted to the Ministry s regional office at Shillong. For control of fugitive emission all unsaturated hydro carbon will be routed to the flare system and the flare system shall be designed for smoke less burning. v. Fugitive emissions of HC from product storage tank yards etc must be regularly monitored. Sensors for detecting HC leakage shall also be provided at strategic locations. vi The sour water containing H 2 S and NH 3 shall be treated in sour water stripper. The combined streams of strip sour water from the INDMAX FCC unit and INDMAX Gasoline Desulphurization unit shall be treated in the ETP followed by tertiary treatment plant to meet the prescribed standards for petroleum refinery. Efforts shall be made to recycle the treated effluent. Basic Design Engineering Package / Process Package have been prepared in line with the existing standards / norms for Oil Refinery Industry which will be further reviewed during Detailed Engineering, if required. Detailed engineering / implementation would start after approval of the project vii. The Company shall take necessary measures to prevent fire hazards, containing oil spill and soil remediation as needed. At place of ground flaring, the overhead flaring stack with knockout drums shall be installed to minimize gaseous emissions during flaring. All necessary measures have been considered to prevent fire hazards and oil spillage. Elevated flare system considered with KOD in the flare header. Page 2 of 5

S.N SPECIFIC CONDITIONS Compliance Status viii. To prevent fire and explosion at Oil and Gas facility, potential ignition sources shall be kept to a minimum and adequate separation distance between potential ignition sources and flammable material shall be in place. ix. Occupational health surveillance of worker shall be done on a regular basis and records maintained as per the Factory Act. x. Greenbelt shall be developed to mitigate the effect of fugitive emission all around the plant in a minimum 33% plant area in consultation with DFO as per CPCB guidelines. Equipment layout is based on OISD norms. Further, HAZOP study has been carried out on the P&IDs. Besides, HAZOP study will be carried out during Detailed Engineering also. Since the project is not yet approved, there is no worker under the project. However, regular health check-up is carried out for the employees of Bongaigaon Refinery which will be continued / extended for workers working under Indmax Project. Greenbelt is already existed. Green cover exists in 2/3 of the plant area. xi. M/s BRPL shall undertake measures for rain water harvesting to recharge the ground water and minimize fresh water consumption. i. The project authorities must strictly adhere to the stipulations made by the concerned State Pollution Control Board (SPCB) and the State Government and any other statuary body. ii. iii. S. No. iv. No further expansion or modification in the project shall be carried without prior approval of the Ministry of Environment and Forests. In case of deviations or alternations in the project proposal from those submitted to the Ministry for clearance, a fresh reference shall be made to the Ministry. At no time, the emissions should go beyond the prescribed standards. In the event of failure of any pollution control system, the respective well site should be immediately put out of operation and should not be restarted until the desired efficiency has been achieved. Provision of adequate height of stack attached to DG sets & flare is to be done. General Conditions Wastewater shall be properly collected and treated so as to conform to the standards prescribed under EP Act & Rules and mentioned in the Consents provided by the relevant SPCB. v. The overall noise levels in and around the premises shall be limited within the prescribed standards (75 dba) by providing noise control measures including acoustic hoods, silencers, enclosures etc. on all sources of noise generation. The ambient noise levels should conform to the standards prescribed under EPA Rules, 1989 viz. 75 dba (day time) and 70 dba (night time). BGR has implemented so far 7 No s roof top rain water harvesting projects in BGR campus in order to recharge the ground water table. Stipulations made in the environmental clearance of the project would be addressed during detailed engineering also. The same has been addressed in the Basic Engineering Design Package, wherever applicable. In case of requirement of expansion / modification of the project in future, prior approval of the Ministry of Environment and Forests shall be taken. In the event of failure of any pollution control system, the respective site shall be kept out of operation until the desired efficiency has been achieved. Height of stack attached to DG sets & flare is as per existing CPCB guidelines. Compliance Status Waste water shall be routed through pipeline to ETP for treatment. Action taken. Page 3 of 5

S. No. vi. vii. viii. Ix. General Conditions The project authorities must strictly comply with the provisions made in Manufacture, Storage and Import of Hazardous Chemicals Rules 1989 as amended in 2000 for handling of hazardous chemicals etc. Necessary approvals from Chief Controller of Explosives must be obtained before commission of the expansion project, if required. Requisite On-site and Off-site Disaster Management Plans will be prepared and implemented. Disposal of hazardous wastes shall be as per the Hazardous Wastes (Management and Handling) Rules, 2003. Authorization from the State Pollution Control Board must be obtained for collections/ treatment/storage/disposal of hazardous wastes. The project authorities will provide adequate funds as nonrecurring and recurring expenditure to implement the conditions stipulated by the Ministry of Environment and Forests as well as the State Government along with the implementation schedule for all the conditions stipulated herein. The funds so provided should not be diverted for any other purposes. The company shall develop rain water harvesting structures to harvest the run off water for recharge of ground water. Compliance Status On-site and Off-site Disaster Management Plans are already in place which shall be reviewed and modified (if required) at appropriate time of implementation of the project. x. The stipulated conditions will be monitored by the concerned Regional Office of this Ministry /Central Pollution Control Board/State Pollution Control Board. A six monthly compliance report and the monitored data should be submitted to them regularly. It will also be displayed on the Website of the Company. xi. xii. xiii. The Project Proponent should inform the public that the project has been accorded environmental clearance by the Ministry and copies of the clearance letter are available with the State Pollution Control Board/ Committee and may also be seen at Website of the Ministry of Environment & Forests at http://www.envfor.nic.in. This should be advertised within seven days from the date of issue of the clearance letter at least in two local newspapers that are widely circulated in the region of which one shall be in the vernacular language of the locality concerned and a copy of the same should be forwarded to the concerned Regional office of this Ministry. A separate environment management cell with full fledged laboratory facilities to carry out various management and monitoring functions shall be set up under the control of a Senior Executive. The project authorities shall inform the Regional Office as well as the Ministry, the date of financial closure and final approval of the project by the concerned authorities and the date of start of the project Published in 3 local newspaper viz. The Assam Tribune (English Daily), Dainik Agradoot (Assamese Daily) and Sanseyari Bodosa (Bodo Daily) on 26.09.2008 BGR is already having a separate environmental management cell and full fledged laboratory to carry-out environment management and monitoring functions. BGR Environment Laboratory is accredited by NABL Page 4 of 5

APPENDIX: Status of Indmax Project Six Monthly Status report for the period (1 st April, 2013 to 30 th September, 2013) Following are some of the important mile stones towards implementation of the Indmax project: 1. Grant of Environment Clearance from the Ministry of Environment & Forest: The Ministry of Environment & Forests has accorded Environment Clearance for Indmax Project (INDMAX FCC Unit along with Indmax Gasoline De-Sulphurisation Unit) to eliminate production of black oils (LDO, LVFO & LSHS) and Naphtha at Dhaligaon, Chirang, Assam by Bongaigaon Refinery of IOCL (Earstwhile Bongaigaon Refinery & Petrochemicals Ltd.) vide MoEF s letter No. J-11011/9/2008- IA II (I) dated 02/09/2008. 2. Press Advertisement for grant of Environment Clearance : BGR had advertised Public Notice in three local news papers that are widely circulated in the region namely The Assam Tribune English Daily, Dainik Agradoot Assamese Daily & Sanseyari Bodosa Bodo daily on 26 th September, 2008 in order to inform the public that the project has been accorded Environmental Clearance by the Ministry and copies of the clearance letter are available with the State Pollution Control Board/ Committee and may also be seen at Website of the Ministry of Environment and Forests at http://www.envfor.nic.in. 3. Application for NOC from State Pollution Control Board: BGR had applied No Objection Certificate (NOC) to the Pollution Control Board, Assam vide our letter No. BGR/ENV/INDMAX/NOC/08-09/01 dated 14 th November, 2008. NOC has been obtained from PCBA on 27 th April, 2009 and 31 st July, 2009. 4. Project Status: Detailed Feasibility Report: I. The Basic Design Engineering Packages (BDEP) for the Indmax project has been prepared keeping in view of various standards/norms for Oil Refinery. Detailed Feasibility Report for the project has been prepared and is under review for investment approval. II. After investment approval, Detailed Engineering will be done during implementation. During Detailed Engineering, the basic design of the process units and other offsite facilities will be further reviewed and necessary changes, if any, will be made to comply with the new environment standards/norms with respect to process emissions, fugitive emissions, ambient air quality, noise levels, quality & disposal of effluents and disposal of hazardous wastes. As informed earlier, the above status will remain unchanged till project approval accorded. Page 5 of 5