Micropile Lateral Load Testing in the Charleston, SC Area

Similar documents
MICROPILE LATERAL LOAD TESTING IN CHARLESTON, SOUTH CAROLINA, USA

ISM 2007 Toronto, Canada Horst Aschenbroich Dipl. Ing. President & CEO of Con-Tech Systems LTD. Titan Hollow Bar

NPTEL Course GROUND IMPROVEMENT USING MICROPILES

Lesson 4. Construction Techniques and Materials. Learning Outcomes. Basic Construction

DESIGN-BUILD-TEST PROCESS FOR HIGH CAPACITY MICROPILES: CONSTRUCTION CASE STUDY ON DUTCHESS RAIL TRAIL BRIDGE FOUNDATIONS, POUGHKEEPSIE, NEW YORK

Non-destructive Testing of Installed Soil Nails Using Sonic Echo Test Method

METHOD STATEMENT for INSTALLATION OF MICROPILE

Case Study. The Challenge. Deep Micropile Installation Under Existing Multistory Building

Schnabel Foundation Company

Ground Improvement Prof. G. L. Sivakumar Babu Department of Civil Engineering Indian Institute of Science, Bangalore

Bond Strength of Hollow-Core Bar Micropiles

Over the last decade, drilled and postgrouted micropile foundations have

CONTINUOUS FLIGHT AUGER (CFA) PILES QC/QA PROCEDURES. Preferred QC/QA Procedures

HURRICANE SANDY LIMITED REEVALUATION REPORT UNION BEACH, NEW JERSEY DRAFT ENGINEERING APPENDIX SUB APPENDIX B-2 FLOODWALL PILE ANALYSES EAST WALLS

SECTION DUCTILE IRON PILES

INNOVATIVE SLOPE STABILISATION BY USING ISCHEBECK TITAN SOIL NAILS

CASE STUDY: LOAD TRANSFER ANALYSIS ON AN INSTRUMENTED AUGERCAST PILE USING EDC STRAIN GAUGES AND GEOKON REBAR STRAINMETERS

FLEXURAL AND SHEAR STRENGTHENING OF REINFORCED CONCRETE STRUCTURES WITH NEAR SURFACE MOUNTED FRP RODS

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DRILLED SHAFTS

10.5 ECCENTRICALLY LOADED COLUMNS: AXIAL LOAD AND BENDING.

MICROPILE FOUNDATIONS FOR RECONSTRUCTION OF HISTORIC LA LOMA BRIDGE IN PASADENA, CALIFORNIA. Casey Garneau 1

MASONRY WALL DATA: Wall Height = ft. Nominal Wall Thickness = 8.00 in. Depth to c.g. Steel, Wall = 3.81 in.

Design and Construction of Drilled Full Displacement Piles using the Penetration Resistance Method

SPECIAL SPECIFICATION 4401 Prestressed Ground Anchors

Soil Improvement by Compaction Grouting

Investigation of Hollow Bar Micropiles in Cohesive Soil

BORED MICROPILES. I.S.M 2009 London (10 th to 13 th may) 9 th International worksop on micropiles - by A. Jaubertou -

Figure 1. Horst Aschenbroich, President/CEO, Con-Tech Systems Ltd.

Determining the Bond-Dependent Coefficient of Glass Fiber- Reinforced Polymer (GFRP) Bars

TECHNICAL REPORT 1. Structural Concepts / Structural Existing Conditions. Penn State Hershey Medical Center Children s Hospital. Hershey, Pennsylvania

Outline of Presentation. Behavior of Laterally Loaded Piles in A Mechanically Stabilized Earth (MSE) Wall

Lateral Loads on Micropiles. Thomas Richards Nicholson Construction Company

SECTION VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT

SPECIAL SPECIFICATION 4492 Tie Back Anchors

SECTION 552 HELICAL ANCHORS AND HELICAL PILES

Design of Deep Foundations for Slope Stabilization

INNOVATIVE DEEP FOUNDATION SUPPORT USING DUCTILE IRON PILES

SECTION VIBRATION CONTROLS FOR PLUMBING PIPING AND EQUIPMENT

Upon speaking with the representatives with Technical Foundations as well as Walder Foundations, it was determined that:

Specialising in Ground Engineering & Slope Stabilisation

SECTION VIBRATION CONTROLS FOR HVAC PIPING AND EQUIPMENT

Bi-Directional Static Load Testing of Drilled Shafts

Bi-Directional Static Load Testing of Drilled Shafts

Experimental Load Transfer of Piles Subject to Lateral Soil Movement

Direct Drilled New Micropile TITAN 127/111 for Underpinning Roman Bullring in Barcelona, Spain

SPECIAL INSPECTION AGREEMENT

Best Management Standards / Specifications. For Concrete Slab Raising. Prepared in conjunction with the Concrete Repair Association

Performance Objectives and the AASHTO Guide Specifications for LRFD Seismic Bridge Design

CONCRETE TECHNOLOGY CORPORATION

SECTION NONPRESTRESSED ROCK ANCHORS. 1. Placing drawings. 2. Bar details. 3. Manufacturer s data, and recommendations for grout.

penetrometer test (CPT) soundings were done to supplement the SPT data. Construction recommendations were made for most of the new buildings.

Structural Tests and Special Inspections Form. Inspection of Fabricators (1704.2)

Multi-Institutional Academic Health Science & Research Center Evansville, IN

How to Design a Singly Reinforced Concrete Beam

HAMMER GROUT PILES FOR THE BRONX WHITESTONE BRIDGE

STANDARD SPECIFICATION Section Auger-Grout Injected Piles Civil Engineering Group Revised: August, 2000

Reinforced Concrete Column Design

Strong Bolt 2 Wedge Anchor for Cracked and Uncracked Concrete

The ONLY Fast Cure ICC-ES Listed Adhesive for Water-filled Holes and Submerged Concrete

AC : STUDENT FEEDBACK AND LESSONS LEARNED FROM ADDING LABORATORY EXPERIENCES TO THE REINFORCED CONCRETE DESIGN COURSE

Studying of Floating Concrete Report Fall

MUD ROTARY TECHNIQUES. MUD Rotary Drilling Method 12/11/2017. Roger E. Renner, MGWC MUD ROTARY DRILLING. Rotary Well Rig

Lesson 7 & 8 Construction Inspection/ Quality Control (QA/QC) Load Testing. Learning Outcomes. Quality Assurance and Quality Control (QA/QC)

A. Installer Qualifications: A firm shall have a minimum of five projects successfully constructed in the last ten (10) years.

High-Strength Anchoring Epoxy

FB-MULTIPIER: P-Y MODEL VALIDATION

Moment curvature analysis of concrete flexural members confined with CFRP grids

STANDARD SPECIFICATION FOR MICROPILE CONSTRUCTION

VERIFICATION OF MASONRY DESIGN SOFTWARE NATIONAL CONCRETE MASONRY INSTITUTE PHASE III

CE 315: Design of Concrete Structures I

SEISMIC RETROFIT OF AN UNDERGROUND RESERVOIR. Robert Small 1, Rob Jameson 2

Advancements in the Use of Micropile Slab Brackets

SIMPLE CERTAINTY MAXIMUM VERSATILITY INCREASES ANCHOR RELIABILITY AND JOBSITE PRODUCTIVITY

Upgrading the shear strength of non-ductile reinforced concrete frame connections using FRP overlay systems

DUCTILE IRON PILES ARE HIGHLY EFFECTIVE, FAST AND VERSATILE MODULAR DRIVEN MICROPILE SYSTEMS

Table of Contents 18.1 GENERAL Overview Responsibilities References

A Brief History of Micropiling in

Learning Outcomes. Background Definitions. Lesson 2 & 3. Definitions, Background, Classification, Applications and Costs

The use of micropiles as a form of underpinning of existing commercial buildings development of IKEA hall in Gdańsk

Failure Mechanism for Large-Sized Grouted Anchor Bolt under Tensile Load

Reduced Required Strength since 2002 Code Live Load = 0.50 * Dead Load 11% Live Load = 1.00 * Dead Load 10% Live Load = 1.

3. FIELD INVESTIGATION PROGRAM

SECTION VIBRATION CONTROLS FOR HVAC PIPING AND EQUIPMENT

NCMA TEK. TEK 14-5A Structural (2006) LOADBEARING CONCRETE MASONRY WALL DESIGN

Trutek TCM380 PRO. Trutek Fasteners Polska Al. Krakowska 55 Sekocin nowy Rasxyn Poland T:

Pier Pressure in Natchez, Mississippi Post Grouted Drilled Shafts Pass Test

Design, Manufacture, and Installation Guidelines of Precast Concrete Segmented Piles for Foundation Underpinning. by The Structural Committee

SUDAS Revision Submittal Form

Extended Working Time Epoxy

S T R U C T U R. Technology. magazine. Software for the Structural Design of Masonry. The Design Basis. Copyright

CHAPTER 3 BEHAVIOUR OF FERROCEMENT HOLLOW SLABS

MODEL SPECIFICATIONS: Hydraulically Driven Steel Underpinning Pile Specifications

Settlement Control in Soft Soils. Jonathan Bennett, PE, D.GE Chief Engineer Earth Support Division Saturday, September 25, 2010

The first national micropile guideline in Finland

Structural Technical Report 1 Structural Concepts/ Structural Existing Conditions Report

SECTION VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

Distribution Restriction Statement Approved for public release; distribution is unlimited.

Repair of Metal Culverts Using ECC Bendable Concrete. Celik Ozyildirim, Ph.D., PE., Virginia Transportation Research Council

SECTION DRILLED CONCRETE PIERS AND SHAFTS

Post-installed reinforcement bars in structural connections

Transcription:

Micropile Lateral Load Testing in the Charleston, SC Area A special thanks to: William B. Wright, PE, Bryan T. Shiver, PE, Kenneth J. Zur, PE, Jackson C. Gosnell, PE, Theodore G. Padgett, PE, and William L. Snow, Sr. 1

2 Background Micropiles are being used more frequently in the Charleston, SC area Limited space or overhead Noise or vibration considerations Rehabilitation of an existing older structures Additions to existing structures in close quarters Underpinning Upgrading of foundation support due to seismic and wind load requirements

3 Purpose of Presentation 1. Provide a limited understanding of the lateral design factors and the use of cased and uncased sections. 2. Provide 5 case histories in Charleston, SC that indicate the lateral loads possible using both cased and uncased upper micropile sections. 3. Provide a starting point for the economical use of micropiles to resist lateral loads 4. Continue load testing and design processes to increase case history data base.

4 Geotechnical Test Methods The following test methods have been used to verify & refine Micropile Design with Load Testing ASTM D-1143 (Axial Compression) ASTM D-3680 (Axial Tensile) ASTM D-3966 (Lateral Loading)

5 Background for Design Methods Specifications that govern design may include the current International Building Code

6 Background for Design Methods Performance based on local conditions Cost & Anticipated installation difficulties Photo Differences in LPILE design analysis vs. test modeling

7 Background for Design Methods FHWA-NHI-05-039 (Micropile Design and Construction) has become widely used as a more specific requirement in addition to IBC requirements. It is specific to micropile design and construction It recognizes four micropile construction types. A newer Type E exists that is incorporates a hollow bar with a bit to self drill the hole. This is the type used for tests

8 Micropile Equipment Information The typically used micropile in the Charleston, SC area are comprised of TITAN Injection Bore (IBO) 40/20 steel rods The TITAN IBO steel rods are comprised of StE460 micro-alloy construction steel Bit size x factor = hole size. Common factors in Charleston soils is 1.1 to 1.4

Titan Micropile Reinforcing Size 9

10 Method of Installation MicroPile Installation Use appropriate rotary drilling technique which is normally wet wash drilling, driven casing or other acceptable means. Mix sufficient flushing grout (W/C=0.70) and pump into holding tank. Start pumping to assure that grout will exit drill bit. Start rotary drilling while pumping grout continuously out of the holding tank. When final depth is reached, change to W/C ratio of 0.44 and recirculate until the flushing grout replaced. Based on the measured grout volumes (number of bags of cement and water per bag) taken during installation, the average pile diameter and crosssectional can be back calculated.

11 Method of Installation The contractor normally uses a neat cement grout w/ a minimum of 28 day unconfined compressive strength of 5000 psi. The grout plant equipment is a ChemGrout CG600 Pneumatic Plant or similar used for both mixing and pumping the mixture.

12 Method of Installation The grout is injected from the lowest point of the hollow steel reinforcing bar into the drilled hole. The mixer and pump are monitored continually to control the quality and quantity of the grout. When the grouting is completed, the hollow bar remains in the hole and is filled with high strength grout. Normally after grouting the grout compressive strength can exceed 5000 psi after 3-5 days. At that time the pile can be load tested based on structural strength.

13 Installation Equipment Casagrande C-4 XP, Casagrande S.P.A

14 Installation Equipment PD 1011HD Grout Mixer, PennDrill Manufacturing

15 Installation Equipment TEJ model WD 50 Skid Steer tracked loader with hydraulic drill mounted as attachment

16 Micropile Case Histories Our 5 detailed case histories include

17 Load Test Overview The following table summarizes specific information about each of the five test locations

18 Load Test Overview 1 2 Project Name MUSC HVAC Pad Galliard Auditorium Renovations 3 Citadel Mechanical Pad 4 Roper Cardiac Center Bar Size Micropile Information Diamete r (in.) Case Study Summary Length (ft.) 40/20 8.6 85 Cased/Uncase d Cased ( 7.625 x 14 ) 40/20 8 53 Uncased Surface Soil Conditions Medium Dense Sands Medium Dense to Dense Sand 40/20 8.6 60 Uncased Dense Sands 40/20 9.5 75 Uncased Medium Dense Sands Design Loads Axial (kips) Lateral (kips) Test Results Axial (kips) Lateral (kips) 60 7.5 125 45 80 7.6 157 24 22 2 50 10.5 40 2 105 23 5 Morris Square 40/20 8.6 31.25 Uncased Medium Dense to Dense Sand 30 7.6 102 11.5

19 Geotechnical Design Methods Compression and Tensile Capacity LCPC Method - Laboratoire Central Ponts et Chaussees Alpha - Composite LCPC/Alpha Beta Local Cooper Marl Design Method - Composite Safety Factors used range from 2.0 to 3.0 depending on data quality and QC/QA

20 Geotechnical Design Methods Lateral Capacity Initially determined using generalized soils information, structural loads or deflection ranges and the LPile software.

Case History Locations 1-5 21

Case History 1: MUSC HVAC Pad 22

Case History 1: MUSC HVAC Pad 23

24 Case History 1: MUSC HVAC Pad Pertinent Pile Information Cased (diameter: 7 5 inches, length: 14 ft. ) 8 Pile length 85 feet Titan IBO 40/20 Pile Diameter - ~ 8.6 inches Design Axial Capacity 60 kips Available Capacity 120 kips Design Lateral Capacity 7.5 kips Available Lateral Capacity 45 kips

Load Testing 25

Case History 1: MUSC HVAC Pad - Site Plan 26

Case History 1: MUSC HVAC Pad - Axial Load Test 27

Case History 1: MUSC HVAC Pad - Lateral Load Test 28

Case History 1: MUSC HVAC Pad - LPILE Results 29

Case History 2: Gaillard Center 30

Case History 2: Gaillard Center 31

32 Case History 2: Gaillard Center Pertinent Pile Information Uncased Pile length 53 feet Titan IBO 40/20 Pile Diameter - ~ 8 inches Design Axial Capacity 80 kips Available Capacity 157 kips Design Lateral Capacity 7.6 kips Available Lateral Capacity 24 kips

Case History 2: Gaillard Center - Site Plan 33

Case History 2: Axial Compression Load Test Gaillard Center 34

Case History 2: Lateral Load Test - Gaillard Center 35

Case History 2: Gaillard Center Theoretical LPILE Results 36

Case History 2: Gaillard Center Modified LPile Results 37

Case History 3: Citadel Mechanical Pad 38

Case History 3: Citadel Mechanical Pad 39

40 Case History 3: Citadel Mechanical Pad Pertinent Pile Information Uncased Pile length 60 feet Titan IBO 40/20 Pile Diameter - ~ 8.6 inches Design Axial Capacity 22 kips Available Capacity 50 kips Design Lateral Capacity 2 kips Available Lateral Capacity 10 kips

Case History 3: Citadel Mechanical Pad - Site Plan 41

Case History 3: Citadel Mechanical Pad-Axial Load Test 42

Case History 3: Citadel Mechanical Pad - Lateral Load Test 43

Case History 3: Citadel Mechanical Pad LPile Results 44

Case History 4: Roper Cardiac Center Entrance 45

Case History 4: Roper Cardiac Center Entrance 46

47 Case History 4: Roper Cardiac Center Entrance Pertinent Pile Information Uncased Pile length 75 feet Titan IBO 40/20 Pile Diameter - ~ 7.9 inches Design Axial Capacity 61 kips Available Capacity 120 kips Design Lateral Capacity 4 kips Available Lateral Capacity 45 kips

Case History 4: Roper Cardiac Center Entrance Axial Load Test 48

Case History 4: Roper Cardiac Center Entrance Lateral Load Test 49

Case History 5: Morris Square 50

Case History 5: Morris Square 51

52 Case History 5: Morris Square Pertinent Pile Information Uncased Pile length 31.25 feet Titan IBO 40/20 Pile Diameter - ~ 8.6 inches Design Axial Capacity 15 kips Available Capacity 50 kips Design Lateral Capacity 7.6 kips Available Lateral Capacity 11.5 kips

Static Load Test - Morris Square 53

Lateral Load Test - Morris Square 54

55 Initial Geotechnical Conclusions Lateral load test results varied from xx.x for uncased to xx.x for case Test results indicate a higher capacity than normally assumed significant increase in lateral capacity when using properly designed casings Lateral loads of 8-10 kips do not require the use of casings

56 Initial Conclusions of Testing Successful use of modified P-Y parameter curves for site specific design Installation method is extremely important for Coastal SC Steady grout pressure Proper centering of drill rod Over sizing hole based of soil type, depth, rotation speed and cuttings removal Can be used in close quarters

57 These initial case histories provide a basis for: Structural Design of Uncased Micropiles

58 Federal Highway Administration Micropile Design and Construction Considers Only Cased Piles

59 Federal Highway Administration Micropile Design and Construction

2006 International Building Code 60

61 2006 International Building Code 1810.8.1 Construction. Micropiles shall consist of a grouted section reinforced with steel pipe or steel reinforcing. Micropiles shall develop their load-carrying capacity through a bond zone in soil, bedrock or a combination of soil and bedrock. The full length of the micropile shall contain either a steel pipe or steel reinforcement.

62 2006 International Building Code 1810.8.4.1 Seismic reinforcement. Where a structure is assigned to Seismic Design Category D, E or F, the pile shall be considered as an alternative system. In accordance with Section 104.11, the alternative pile system design, supporting documentation and test data shall be submitted to the building official for review and approval.

63 2006 International Building Code 1810.8.4.1 Seismic reinforcement. Where a structure is assigned to Seismic Design Category D, E or F, the pile shall be considered as an alternative system. In accordance with Section 104.11, the alternative pile system design, supporting documentation and test data shall be submitted to the building official for review and approval.

There are no direct references to Micropiles in ACI 318 64

65 So We know that Design as Alternative System with Testing Compression and Tension- No Problem! But Lateral forces induce flexural stresses What about Bending?

66 Technical Treatises and Research Papers on Bending of Circular Concrete Sections with Center Reinforcement: ZERO!

67 ACI 318 10.2.6 The relationship between concrete compressive stress distribution and concrete strain shall be assumed to be rectangular, trapezoidal, parabolic, or any other shape that results in prediction of strength in substantial agreement with results of comprehensive tests.

Actual vs. Whitney Stress Block 68

69 ACI 318 a = β 1 c 10.2.7.3 For fc between 2500 and 4000 psi, β 1 shall be taken as 0.85. For fc above 4000 psi, β 1 shall be reduced linearly at a rate of 0.05 for each 1000 psi of strength in excess of 4000 psi, but β 1 shall not be taken less than 0.65.

70 So Back to Basic Reinforced Concrete Design 2 Failure Modes: Compression- Concrete Crushes And Tension- Steel Yields

71 Basic Reinforced Concrete Design 2 Failure Modes: Compression- Catastrophic! And Tension- More Desirable

72 Basic Reinforced Concrete Design Designs where Compression Failures occur are considered Over-Reinforced Designs where Tension Failures occur are considered Under-Reinforced

73 Basic Reinforced Concrete Design Balanced Failures when the concrete crushes at the same loading as the reinforcing yields

QUESTIONS? 74