Examining the Test Process: Predicting the Return on Investment of a Process Change

Similar documents
The ROI of CMMI: Using Process Simulation to Support Better Management Decisions

Software Process Assessment

Evaluating the Impact of New Tools and Technologies Using Simulation

A Global Overview of The Structure

Use of Competency Guidelines to Address CMMI GP 2.5

Update Observations of the Relationships between CMMI and ISO 9001:2000

CMMI for Technical Staff

Highlights of CMMI and SCAMPI 1.2 Changes

9/24/2011 Sof o tw t a w re e P roc o e c s e s s s Mo M d o e d l e s l 1 Wh W a h t t i s i s a Pr P oc o ess s 2 1

High Maturity Practices in Quality Assurance Mechanisms for Quantitative Management (QM) and Continuous Process Improvement (CPI)

Using Software Process Simulation to Assess the Impact of IV&V Activities 1

CMMI-DEV V1.3 CMMI for Development Version 1.3 Quick Reference Guide

Strategies for Transitioning to CMMI-SVC

USAF Software Technology Support Center (STSC) STSC SPI Help Desk COM , DSN

M. Lynn Penn Lockheed Martin Integrated Systems and Solutions November 2004

MTAT Software Engineering Management

DORNERWORKS QUALITY SYSTEM

Relationship between CMMI Maturity Levels and ISO/IEC Processes Capability Profiles

SCAMPI V1.1 Method Overview

Patricia A Eglin David Consulting Group

System Engineering Process Improvement using the CMMI in Large Space Programs

CC and CMMI. An Approach to Integrate CC with Development

CMMI SM Mini- Assessments

Generating Supportive Hypotheses

8. CMMI Standards and Certifications

The Issue of Performance Why Do you need a Maturity Level 5. Achieving the Organizational Business Objectives Through Optimized Operational Processes

Bill Smith, CEO Leading Edge Process Consultants LLC

Lesson Learned from Cross Constellations and Multi Models Process Improvement Initiatives

Managing a Project and Keeping Sane While Wrestling Elegantly With PMBOK, Scrum and CMMI (Together or Any Combination)

Ogden Air Logistics Center

SOFTWARE ENGINEERING SOFTWARE PROCESS. Saulius Ragaišis.

How to Assure your Subcontractors Quality with Cross Constellations and Multi Models Inspiration Continues Process Improvement Initiatives

Teuvo Suntio. Quality Development Tools. Professor of Power Electronics at University of Oulu. Electronic System Design A TS Rev. 1.

Leveraging Your Service Quality Using ITIL V3, ISO and CMMI-SVC. Monday Half-Day Tutorial

SCRUM and the CMMI. The Wolf and the Lamb shall Feed Together

High Maturity Misconceptions: Common Misinterpretations of CMMI Maturity Levels 4 & 5

Integrated Class C Process Appraisals (ICPA)

CMM,,mproving and,ntegrating

Process Maturity Profile

Implementing Systems Engineering Processes to Balance Cost and Technical Performance

Using CMMI. Type of Work. IT solution development Software development IT solution integration IT solution deployment

CMMI for Services (CMMI -SVC) Process Areas

CMMI Capability Maturity Model Integration [CMU SEI]

CMMI V2.0 MODEL AT-A-GLANCE. Including the following views: Development Services Supplier Management. CMMI V2.0 outline BOOKLET FOR print.

What is important in CMMI and what are the interrelations among its elements?

Chapter 26 Process improvement

A Real-Life Example of Appraising and Interpreting CMMI Services Maturity Level 2

Presentation Objectives

Practical Application of the CMMI for Building a Strong Project Management Infrastructure

High Maturity/Capability Appraisals

One if by Land, Two if by Sea

What s New in V1.3. Judah Mogilensky Process Enhancement Partners, Inc.

USING PILOTS TO ASSESS THE VALUE AND APPROACH OF CMMI IMPLEMENTATION. Goddard Space Flight Center (GSFC)

Engineering. CMMI for Development V.1.2 Module 3. M03/Engineering/v1.2

Software technology 3. Process improvement models. BSc Course Dr. Katalin Balla

Organizational Synthesis - CMMI, The Glue That Binds

2005 PSM Users Group Conference Keystone, CO. Topic Introduction

CMMI Version 1.2. Model Changes

Chapter 6. Software Quality Management & Estimation

A Practical Guide to Implementing Levels 4 and 5

Why Should you Care about CMMI?

There are 10 kinds of people in the world. Those who think in binary, and those who don t.

The Quality Paradigm. Quality Paradigm Elements

Buy:

Software Quality Assurance Framework (SQA) Yujuan Dou 窦玉娟 2008/11/28

Using the Equity in AS9100C to Implement CMMI-DEV Maturity Level 3

CMMI-SVC V1.3 CMMI for Services Version 1.3 Quick Reference Guide

Q.A. Осигуряване на качество на софтуера (2016/2017, редовно/задочно)

CMMI for Acquisition Quick Reference

CMMI v1.1 for a Service-Oriented Organization. By Steve Hall, Jeff Ricketts, Diane Simpson 16 November 2005

Marilyn Ginsberg-Finner Northrop Grumman Corporation

CMMI Re-Appraisal Moving Barriers & Making Strides

CMMI-SVC: A Cost-Effective Approach to Early Use

PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3)

Measuring Performance: Evidence about the Results of CMMI

Who needs that process stuff anyway? A practical example of process discipline to improve deployment

Achieving Excellence In Software Engineering

Applying PSM and Insight within a Small Organization

Leveraging Quality For Competitive Advantage

Lockheed Martin Benefits Continue Under CMMI

Transition from SW-CMM to CMMI : The Benefits Continue!

CMMI Implementation at Korestone Technologies, LLC

Fast Track Your CMMI Initiative with Better Estimation Practices

Presented By: Mark Paulk

Quality Management of Software and Systems: Software Process Assessments

Do s and Don ts of Appraisal Preparation

Maturity Models - CMMI

PM Architecture Design as a Critical Success Factor in CMMI Model Implementation

SOFTWARE QUALITY IN 2005 A SURVEY OF THE STATE OF THE ART SOURCES OF SPR S QUALITY DATA. SPR clients from 1984 through 2005 BASIC DEFINITIONS

Two Branches of Software Engineering

Process Improvement: CMMI

Quest 2015 Webinar Series:

Techniques for Shortening the Time and Cost of CMMI Appraisals

Capability Maturity Model the most extensively used model in the software establishments

Using Pilots to Assess the Value and Approach of CMMI Implementation

CMMI for Services Quick Reference

Q.A. Осигуряване на качество на софтуера (2016/2017, редовно/задочно)

Analyzing Resonance of Motivation in Software Development Process Training by Using FRAM (Work-in-progress)

Transcription:

Pittsburgh, PA 15213-3890 Examining the Process: Predicting the Return on Investment of a Process Change David M. Raffo, Ph.D. Associate Professor, Visiting Scientist, Software Engineering Institute Sponsored by IBM Centre for Advanced Studies page 1 Agenda 1. Motivation 2. What are Process Simulation Models 3. Benefits of Process Simulation 4. Examining the ing Process 5. Goals, Questions, Performance Measures and Data 6. Model Results 7. Conclusion page 2 1

Motivation Competition within the U.S. and abroad is putting pressure on software firms to improve performance in terms of: Reducing costs Reducing cycle time Reducing defects In order to compete, organizations need to incorporate new methods and tools into their development operations quickly page 3 Introducing - Process Simulation One area that can help companies improve their processes is Process Simulation. Process Simulation supports organizations at all levels of the CMMI Designing and defining processes Quantitative process management Continuous process improvement page 4 2

What is Process Simulation? Simulation is a computerized model (not a maturity model) designed to display significant features of the dynamic system it represents. Process simulation models focus on the dynamics of software and systems development, maintenance and acquisition activities. Process Simulation models represent the process - as currently implemented (as-is), or - as planned for future implementation (to-be) page 5 Company Strategy Competitive Advantage Customer Value Improving Operations Industry Standards CMMI, Six Sigma, ISO Many choices. Which one(s) to choose? Need to focus efforts to be successful. Set of Potential Process Changes Process Simulation Evaluate Impact on Process Performance Performance Measures Cost, Quality, Schedule Which change will provide the greatest improvement? What is the financial impact? Financial Benefits - NPV, ROI page 6 3

General Approach Software Development Process Better Process Decisions Process Performance Cost, Quality, Schedule SW Process Simulation Model Project Data Process and Product Model Parameters Project is Approved FS Development Unit Release to Func Spec Complete Complete Customers HLD H Lev Design LLD L Lev Design Field Code Unit Support Functional Code Dev and Maintenance Proposed Create System Process UT Follow UT Change UT Pln Plan Plan Project is Approved FS Development Unit Release to Func Spec Complete Complete Customers HLD H Lev Design LLD L Lev Design Field Code Unit Support Functional Code Dev and Maintenance Proposed Create System Process UT Follow UT Change UT Pln Plan Plan page 7 Process Tradeoff Analysis Method (PTAM) Based on extensive research into Software Process Modeling conducted in academia, SEI and industry. Graphical user interface and models software processes Integrates SEI methods to define processes and to support CMMI PAs Integrates metrics related to cost, quality, and schedule into understandable project performance picture. Predicts project-level impacts of process improvements in terms of cost, quality and cycle time Support business case analysis of process decisions - ROI, NPV and quantitatively assessing risk. page 8 4

Process Tradeoff Analysis Method (PTAM) Reduces risk associated with process changes by predicting the probability of improvement Saves time, effort and expertise over other methods page 9 What are the Benefits of Process Simulation? Project Option 0 Base Case Total Effort (PM) Dev Eff + Dev Rwk Rework Effort Devel Defects (PM) Project Duration (Calendar Months) Projected Cost or Revenue delta due to Duration Change Total Injected Corrected Escapted Defects Defects Defects Rework Effort for Field Defects (PM) Impleme ntation Costs ($) NPV ROI 200 90 18 $0.00 1150 990 160 40 $0.00 n.a. n.a. 1 Implement QFD 190 75 17.5 $0.00 1150 1020 130 30 $100,000 $165,145 15% 2 Implement VOC 185 75 17 $ 100,000 1150 1050 100 20 $120,000 $185,231 29% 3 Add QuARS Tool 175 65 16 $ 300,000 1150 1090 60 10 $ 80,000 $289,674 88% 4 Eliminate 230 130 22 $(400,000) 1150 900 250 80 $0.00 -$378,043-129% 5 Additional Process page 10 5

Benefits of Process Simulation Decision Support and Tradeoff Analysis Sensitivity Analysis What if Supports Industry Certification and process improvement programs including CMMI, Six Sigma, and others Benchmarking Design and Define Processes Bring Lessons Learned Repositories Alive Can save cost, effort, and expertise Can be used to address project manager questions page 11 Software Project Manager Concerns What development phases are essential? Which phases could be skipped or minimized to shorten cycle time and reduce costs without sacrificing quality? Are inspections worthwhile? What is the value of applying automated tools to support development activities? How do we predict the benefit associated with implementing a process change? How do we prioritize process changes? How to achieve higher levels of the CMMI? What is the level of Risk associated with a change? page 12 6

NASA IV&V Questions What is the optimal IV&V strategy for a given NASA project or NASA project type? What combination(s) of IV&V techniques enable us to meet or exceed the quality assurance goals for the system? Which alternative is best? Given a budget of X dollars, what IV&V activities should be conducted? What if the complexity or defect profiles for a particular project were different than expected? How is the duration of the IV&V effort impacted by the overall staffing level for the project? How will this affect the total project duration? What would be the impact if selected V&V techniques are handled as IV&V services? page 13 Potential Questions What would be the costs and benefits associated with implementing an IV&V technique on a selected software project? How would the IV&V technique contribute to the development process and quality assurance? How would IV&V activity X work in conjunction with other V&V or IV&V techniques? At what point in the process does this technique provide the greatest benefit (e.g. before or after testing)? What would be the impact if a IV&V technique X is applied at different portions of the process or applied multiple times? page 14 7

Supports CMMI Based Process Improvement CMMI Levels 4 and 5 Process simulation helps to fulfill PAs (OID, CAR, OPP and QPM - Sub Goals and Generic Goals) CMMI Levels 2 and 3 Process simulation can be used to evaluate alternative process choices (RD, TS, PI, V&V, RM, SAM, PPQA, and CM) Process simulation helps to fulfill PAs (OPF, OPD, OT, IPM, Risk, DAR, PP, PMA, MA, PPQA Multiple Sub Goals and Generic Goals ) page 15 Examining the Process: Organizational Setting Leading software development firm Peak staffing of 60 developers on project Assessed at strong Level 2 of CMM/CMMI Experienced development staff 5 th release of commercial project Data available in electronic and paper form: quantitative and qualitative; professional estimates used to fill in gaps Active SEPG page 16 8

CMMI Level 3 PAs: Validation and Verification Problem: Releasing defective products, had high schedule variance. Why? Unit was main defect removal stage. They did it unreliably. Built a model of Large-Scale commercial development process Based on actual project data Predicted project performance in terms of effort, task duration and delivered defects. Part of a full business case analysis - determined financial performance of the process change page 17 Process Overview - 1 Project is Approved FS Func Spec 1 HL Design HLD Development Complete Unit Complete Release to Customers Tasks Affected By Process Change Change LL Design Code LLD Code Unit Execution Functional Field Support and Maintenance 1 Plan TP System Case TC Diagram of the Field Study Life Cycle AS-IS Process page 18 9

Process Overview - 2 Begin Code Development Code Development is Complete Code ection is Complete Code Dev Code Unit Execution Unit Complete; Begin Functional ing Conducted during Code Development Create Unit Plans Prep,, and RWK UT Plans Conducted as part of regular Code ection Follow UT Plan Followed while conducting Unit page 19 Questions Investigated Will the process change improve project performance? What is the cost the firm is currently paying by conducting Unit s incorrectly? Is partial implementation of the proposed process change possible? How would potential learning curve effects affect the performance of the process change? Would alternative process changes offer a greater improvement? Can the project benefit from reusing process artifacts? page 20 10

Performance Measures Cost Person-Months of Development, ection, ing and Rework effort Equivalent Manpower (Staffing levels) Implementation costs Quality Number of delivered defects by type Schedule Months of Effort page 21 Input Data CMM/CMMI Level 2+ organization Process documents and assessments Project Size Productivity Earned Value by phase Total number of defects injected Defect injection, detection and correction rates Effort and schedule data Defect detection and rework costs page 22 11

Graphical Model Project is Approved FS Func Spec 1 HL Design HLD Development Complete Unit Complete Release to Customers Tasks Affected By Process Change Change LL Design Code LLD Code Unit Execution Functional Field Support and Maintenance 1 Plan TP System Case TC Diagram of the Field Study Life Cycle AS-IS Process page 23 Simplified Error Model Undetected errors from previous phase Errors injected in this phase Errors detected (and removed) Perform Work Verify Work Rework Detected Errors Verification Efficiency = Errors Detected Total Errors Present Undetected errors to next phase page 24 12

More Detailed Error Model Errors injected Preliminary Design Dev TA TA Rev Rwk Errors undetected Errors detected Dev UA UA Rev Errors injected Rwk Errors undetected Errors detected Code Code Rev Errors injected Errors detected Rwk Errors detected Errors undetected UT Rwk Errors undetected PT Rwk Errors undetected Errors detected Int Errors detected Rwk SW Req. Analysis & Preliminary Dsn SW Detailed Design Coding Unit Process Integration & Formal page 25 Unit Planning Process Change Estimate Localized Impacts Effort and schedule to develop test plans Early detection and removal of defects while creating test plans ection effort for inspecting and reworking test plans Improved efficiency during Unit due to following the plans page 26 13

Key Parameters for the Process Change Model Parameters Create Unit Plan Effort (Hours per KLOC) Percentage of Current Errors Removed before Code ections while creating the Unit Plans Percent Unit Effort Decrease due to following the plan Percent Increase in Unit Error Detection Capability Effort to Prepare for the ection of the Unit Plan Effort to ect the Unit Plan (hours per meeting) Effort to Rework the Unit Plan (hours per plan error) AS-IS Observed TO-BE Estimated 0.0 Min=47.6 Mode= 72.2 Max = 144.3 0.0% Min = 9.0% Mode=15.7% Max = 22.5% 0.0% Min = 5% Mode=10% Max = 15% 0.0% Min = 10% Mode=15% Max = 20% 0.0 added 10% to the time of the Code ection TO-BE (Observed) Pilot Study Value Min=83.3 Mode= 110.1 Max = 200.0 Min = 0.0% Mode=6.4% Max = 28.6% Min = 15% Mode=30% Max = 40% Min = 8% Mode=10% Max = 15% Min=11.4 Mode= 17.5 Max = 25.0 0.0 Min=0.25 Min=0 Mode= 0.25 Mode= 0.25 Max = 0.25 Max = 0.40 0.0 0.0 Min=0.0 Mode= 2.0 Max = 3.0 page 27 Unit Planning Process Change Model Predicts Project Level Impacts Cost, quality, and schedule impacts by phase for all phases of development Overall cost, quality, and schedule impacts for the project Implementation costs Post deployment quality page 28 14

Baseline Results The process change offered significant reductions in remaining defects, staff effort to correct field detected defects, and project duration. The expected ROI was 56% for a typical 30 KLOC release. Pilot implementations indicated that the process change provided a 37% ROI even under worst case conditions. page 29 Model Results PERFORMANCE AS-IS TO-BE MEAN PCT CHG P-VAL PROB MEASURE DIFF CHG STD IMPR REMAINING 10.21 8.51 1.70 16.65% 0.93 0.000 97% ERRORS LIFE CYCLE 52.42 52.49-0.07-0.12% 1.02 0.446 49% EFFORT (PM) TOTAL 62.00 60.47 1.53 2.47% 1.43 0.000 85% EFFORT(PM) LIFE CYCLE 18.05 16.44 1.61 8.92% 1.75 0.000 79% DURATION (Mo) page 30 15

Sensitivity Analysis Results Compressing Unit causes significant increases in schedule (+18%) and effort costs (+8%) during the later testing phases and reduces overall product quality(+48% increase in defects). Partial implementation of the process change is possible for complex portions of the code. Estimated ROI is 72%. Potential learning curve effects significantly enhance the performance of the process change. Expected ROI of 72% assuming only moderate improvements. page 31 Mean Cost, Quality, and Schedule Impacts for Changes in Unit Error Detection Capability COST (Hours of Staff Effort) MODE = 0.200 MODE = 0.351* TO-BE MODE= 0.403 Total Effort 66.62 62.00 60.47 Life Cycle Eff 52.43 52.42 52.49 UT Effort 7.06 9.19 8.45 FVT Effort 8.22 6.55 6.01 SVT Effort 3.89 3.40 3.23 QUALITY (Number of Remaining Errors) Remaining Err 15.13 10.2133 8.51333 Corr E-UT 57.28 101.727 85.4867 Corr E-FVT 82.29 57.18 48.1333 Corr E-SVT 29.81 20.8267 17.5133 SCHEDULE (Hours of Task Duration) Life Cycle Dur 21.21 18.05 16.44 UT Duration 1.80 2.34 2.15 FVT Duration 16.71 12.73 10.47 SVT Duration 10.50 7.71 6.54 page 32 16

Sensitivity Analysis Results Improving inspections would be a more effective process improvement than the Creating Unit Plans process change. Reusing the Unit Plans on the next development cycle provided an overall ROI of 73% (compared to 56% expected improvement without reuse) page 33 Impact on the Company Supports strategic process improvement goals of for higher CMMI levels Provides a framework and direction for metrics program (made improvements) Supports business case analysis of process changes Provides quantitative risk assessment prior to the introduction of process changes Obtains Management buy-in for process change and collection of further metrics page 34 17

Rapidly Deployable Software Process Simulation Models Goal: To create a flexible decision support tool that can be easily used to support better project management, planning and tracking by quantitatively assessing the economic benefit of proposed process alternatives. Motivation: Companies need to get useful results from simulation models quickly. page 35 Rapidly Deployable Process Models Software Development Process Project is Approved FS Func Spec H Lev Design HLD Development Complete Unit Complete Release to Customers LLD L Lev Design Code Code Dev Unit Functional Field Support and Maintenance Proposed Process Change Create UT UT Plan Plan Follow UT Pln System Life Cycle Model REQ DES IMP TEST CUST Generic Process Blocks TP TCG Generalized Equations page 36 18

Conclusions Process simulation modeling has been used successfully to quantitatively address a variety of issues from strategic management to process understanding. Key benefits include: Decision Support and Tradeoff Analysis Sensitivity Analysis What if Supports Industry Certification and process improvement programs including CMMI, Six Sigma, and others Supports CMMI at all levels 2 through 5 Design and Define Processes Benchmarking Can address project manager concerns Supports project management and control page 37 Conclusions This study provided turnkey analysis and recommendations for making a Go/No go decision on the process change Expected benefit Partial Implementation Learning curve impacts Impact of bad behavior Alternative process changes Re-estimate based upon pilot study results Not a silver bullet Focus on RAPID DEPLOYMENT Reducing costs and making models easier to use No simulation expert needed page 38 19

The End Questions? page 39 Contact Information David M. Raffo, Ph.D. Associate Professor College of Engineering and Computer Science School of Business Administration Visiting Scientist Software Engineering Institute Carnegie Mellon Raffod@pdx.edu 503-725-8508 page 40 20

6 th International Workshop on Software Process Simulation and Modeling (ProSim 2005) May 14 and 15, 2005 Held in conjunction with ICSE 2005 in St. Louis, Missouri, USA Sponsors:, International Software Process Association, and Fraunhofer Institute E-mail: davidr@sba.pdx.edu Web: http://www.prosim.pdx.edu/ page 41 21