CITY OF PATERSON, NJ AND GREAT FALLS HYDROELECTRIC COMPANY JOINT AGENCY / STAKEHOLDER MEETING AUGUST 3, 2016

Similar documents
Grafton Hydro, LLC. 55 Union Street, 4 th Floor Boston, MA, USA Tel: Fax: October 9, 2015

FERC Relicensing of Hawks Nest Project (FERC NO. 2512) Glen Ferris Project (FERC NO )

TOLEDO BEND PROJECT FERC NO FINAL LICENSE APPLICATION EXECUTIVE SUMMARY

STUDY 7.0 FISH PASSAGE

Vegetation Cover Type Mapping Study Plan for Energy Northwest's Packwood Lake Hydroelectric Project FERC No Lewis County, Washington

ONTONAGON RIVER BOND FALLS HYDROELECTRIC PROJECT (P-1864)

Federal Energy Regulatory Commission. Scoping Meetings for the River Falls Hydroelectric Project (P-10489) November 15 & 16, 2018

Hydropower Project Summary YADKIN, NC W. KERR SCOTT HYDROELECTRIC PROJECT (P-12642) This summary was produced by the. Hydropower Reform Coalition.

SCOPING DOCUMENT 1 WEBER HYDROELECTRIC PROJECT UTAH FERC PROJECT NO. 1744

Takatz Lake Project - Alaska

Chakachamna Hydro. AEA Geothermal Conference

TOLEDO BEND PROJECT FERC NO DRAFT LICENSE APPLICATION EXHIBIT E - ENVIRONMENTAL EXHIBIT 2.0 PROPOSED ACTION AND ALTERNATIVES

Hydropower Project License Summary CHIPPEWA RIVER, WI JIM FALLS HYDROELECTRIC PROJECT (P ) This summary was produced by the

PARR. PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC JANUARY 2013

Prospect No. 3 Hydroelectric Project FERC Project No. P-2337 Initial Study Report: Ramping May 2015

PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC SEPTEMBER 19, 2012

Federal Energy Regulatory Commission

If any questions arise concerning this application, please contact us.

Kilarc-Cow Creek Hydroelectric Project Decommissioning FERC Project No Draft License Surrender Application. September 9-10, 2008

Saywatt Hydroelectric, LLC. Mechanicsville Hydroelectric (FERC Project No. 9611)

April 26, 2018 INITIAL STUDY REPORT MEETING

Federal Energy Regulatory Commission Washington, DC November 26, 2012

DEAD RIVER DEAD RIVER HYDROELECTRIC PROJECT (P-10855)

9:00 A.M. Welcome and Introductions Dan Corcoran, EID Environmental Manager. Brian Deason, EID Hydroelectric Compliance Analyst

Swinging Bridge Hydroelectric Project (FERC No ) Mongaup Falls Hydroelectric Project (FERC No ) Rio Hydroelectric Project (FERC No.

Federal Energy Regulatory Commission (FERC) Scoping Meetings for the Otter Tail River Hydroelectric Project

Prepared by: PacifiCorp 825 NE Multnomah Street Portland, OR 97232

Elko Project Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights

EXHIBIT B PROJECT OPERATIONS

Hydropower Project License Summary KERN RIVER, CA KERN CANYON HYDROELECTRIC PROJECT (P-178) This summary was produced by the

SOUTH FORK AMERICAN RIVER (CHILI BAR), CALIFORNIA

3.0 Proposed Action and Alternatives Proposed Action License Term Project Facilities to be Licensed...

KANAWHA RIVER, WEST VIRGINIA

Warm Springs Hydro LLC 5203 South 11 th East Idaho Falls, ID

Low Impact Hydropower Institute 34 Providence Street Portland, ME Tel. (207) Fax (206)

April 29, 2016 VIA ELECTRONIC FILING. Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

APPLICATION FOR PRELIMINARY PERMIT NOCKAMIXON PUMPED STORAGE HYDRO PROJECT

Project Information. Pursuant to Section 404 of the Clean Water Act (33 U.S. Code 1344), notice is hereby given that

Yale Hydroelectric Project FERC Project No APPLICATION FOR NEW LICENSE FOR MAJOR PROJECT Volume I

FINAL WILDLIFE and VEGETATION RESOURCES STUDY PLAN. Blue Lake Hydroelectric Project FERC No Expansion. Prepared by:

Village of North Bennington P.O. Box 427 North Bennington, Vermont 05257

Camp Far West Hydroelectric Project

Low Impact Hydropower Institute AMENDED Application for Low Impact Hydropower Certification: Island Park Hydroelectric Project

134 FERC 61,195 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

DOMINION VIRGINIA POWER / NORTH CAROLINA POWER WITHIN DAY PEAKING PLAN LICENSE ARTICLE 414 Roanoke Rapids and Gaston FERC Project Number 2009

UNITED STATES OF AMERICA111 FERC 62,065 FEDERAL ENERGY REGULATORY COMMISSION. PPL Maine LLC Project No

Subject: La Grange Hydroelectric Project, FERC Project No Draft License Application

TERR 6 VALLEY ELDERBERRY LONGHORN BEETLE

Ceresco Dam Removal Project. Michigan Watershed Summit March 25, 2015 Luke Trumble, P.E., MDEQ-WRD Jay Wesley, MDNR-Fisheries

UNITED STATES OF AMERICA 138 FERC 62,093 FEDERAL ENERGY REGULATORY COMMISSION. Duke Energy Carolinas, LLC Project No

FEDERAL ENERGY REGULATORY COMMISSION Washington, DC November 8, Subject: Scoping Document 1 for the Lower Mousam Project, P

Kaweah Project (FERC Project No. 298)

APPLICATION FOR PRELIMINARY PERMIT BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. For The. Cascade Creek. Hydroelectric Project. Petersburg, Alaska

CONNECTING. Big Chino Valley Pumped Storage Project. Energy Infrastructure

Dear Ms. Bose, Thank you for the opportunity to comment on the application by Juneau Hydropower Inc. for a

HAWKS NEST-GLEN FERRIS HYDROELECTRIC PROJECT (FERC PROJECT NO. 2512)

WEST ROSEBUD CREEK, MONTANA

Final Tailrace Water Temperature Monitoring and Enhancement Plan for

ADAPTIVE MANAGEMENT PLAN

ATTACHMENT A QUESTION 3: PROJECT DESCRIPTION PROJECT MAP

WEST POINT PERTINENT DATA. GENERAL Location (damsite) Troup County GA, Chambers County AL, miles above mouth of Chattahoochee River

Stave River Water Use Plan (Stave Falls and Ruskin Projects) Revised for Acceptance by the Comptroller of Water Rights

JOINT PUBLIC NOTICE Savannah District/State of Georgia

FINAL LICENSE APPLICATION Exhibit C Construction History

New Hydro without a new Dam NWHA FEBRUARY 16, 2016

POINTE DU BOIS GENERATING STATION SHORT-TERM EXTENSION LICENCE APPLICATION

INTRODUCTION AND BACKGROUND

HYDROPOWER TRENDS. RMS/SORP, Boise, Idaho May 2016

Klamath River Renewal Project Dam Removal RFQ Informational Meeting August 29, 2018 Klamath Falls, OR

DRAFT FISHERIES MONITORING PLAN. BLUE LAKE HYDROELECTRIC PROJECT EXPANSION FERC No SITKA, ALASKA. Prepared By: City and Borough of Sitka

EXHIBIT B PLANT OPERATION AND RESOURCES UTILIZATION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Sacramento Municipal ) Project No Utility District )

GORDON BUTTE CLOSED LOOP PUMPED STORAGE HYDRO FACILITY BRIEFING DOCUMENT

PEND OREILLE RIVER, WASHINGTON

Lower Cherry Aqueduct Emergency Rehabilitation (44896) Scoping Package

Subject: October and November Fish Kill Incidents, Article 406

EXECUTIVE SUMMARY. Consultative Committee Report Jordan River Water Use Plan

Northwest Power and Conservation Council

Re: River Falls Hydroelectric Project, Project No Traditional Licensing Process and Kinnickinnic River Corridor Plan Intial Directed Studies

Comment. Section Title/ Paragraph. Technical Report. (initials/ agency)

Project Information. Pursuant to Section 404 of the Clean Water Act (33 U.S. Code 1344), notice is hereby given that

EAGLE MOUNTAIN Hydro Electric Pumped Storage Project

STUDY 4.0 WATER TEMPERATURE IN THE LOUP RIVER BYPASS REACH...4-1

MANZANITA LAKE PLANNING UNIT Willow Creek Watershed

NEW JERSEY DEPARTMENT OF ENVIRONMENTAL PROTECTION. Office of Coastal Management and Watershed Restoration

A guide to Chelan PUD s program for managing the lands and shorelines within the Rocky Reach Hydroelectric Project Boundary

Review of Application for LIHI Certification of the Newton Falls Hydroelectric Project St. Lawrence County, New York

CLEAN WATER ACT 401 WATER QUALITY CERTIFICATION APPLICATION FORM

Proposed Study Plans Alternative Study Plans Studies Not Proposed. Mason Dam Hydroelectric Project FERC No

Public Notice. Public Notice No. Date: April 8, 2016 CENAP-PL-E Comment Period Closes: May 9, 2016

Mr. Rob Matthews Manager, Water Use Licensing Manitoba Conservation and Water Stewardship Box Saulteaux Crescent Winnipeg MANITOBA R3J 3W3

CLARK FORK HYDROELECTRIC PROJECT LIHI APPLICATION FOR CERTIFICATION INTRODUCTION

Aquatic Restoration Through Hydropower Licensing, Bond Falls Project, Michigan

Klamath Hydroelectric Project (FERC Project No. 2082) PacifiCorp Portland, Oregon. Version: February 2004

U.S. ARMY CORPS OF ENGINEERS BUILDING STRONG LOS ANGELES DISTRICT

RECORD OF PLAN CONFORMANCE AND CATEGORICAL EXCLUSION (CX) DETERMINATION

LAND 2 Multiple Use Opportunity Assessment

Solutions through Science. Hydropower. Services and Solutions for Environmental Compliance

MIEL I Hydroelectric Power Plant

AU SABLE RIVER. a. Foote (P-2436) A dam containing two existing earth fill embankment sections, a concrete

Transcription:

CITY OF PATERSON, NJ AND GREAT FALLS HYDROELECTRIC COMPANY JOINT AGENCY / STAKEHOLDER MEETING AUGUST 3, 2016 1

EAGLE CREEK RENEWABLE ENERGY - BOB GATES - MICHAEL SCARZELLO - SUSAN GIANSANTE CITY OF PATERSON YOUNG ENERGY SERVICES (YES) - KEVIN YOUNG - ADAM CONNOLLY AGENCY PERSONNEL 2

TO INFORM AGENCIES AND THE PUBLIC ABOUT THE PROJECT AND TO SEEK FEEDBACK JOINT MEETING IS REQUIRED BY 18 CFR 4.38(B) OF THE FEDERAL POWER ACT OPEN TO THE PUBLIC AND RECORDED 3

PROJECT OVERVIEW DESCRIPTION OF THE PROJECT FERC LICENSING PROCESS OVERVIEW OF PAD FILED WITH THE FERC DISCUSS ANY ISSUES AND REQUESTED STUDIES TO BE CONDUCTED BY THE CO-LICENSEES SCHEDULE AND DOCUMENT DEVELOPMENT TIMEFRAME COMMENTS 4

5

1791 PIERRE L ENFANT SOCIETY OF USEFUL MANUFACTURERS 1794 PETER COLT RESERVOIR BASED SYSTEM 1846 SUM RETURNS TO L ENFANT PLAN OF AQUEDUCTS 1914 END OF SUM; BEGINNING OF THOMAS EDISON S 4,849 KW HYDRO PLANT 1969 4 UNIT STATION OPERATIONS ENDS 1976 DECLARED A NATIONAL HISTORIC LANDMARK 1986 PLANT RESTORED W/ 3 TURBINES; TOTAL 10,950 KW 2011 DECLARED A NATIONAL HISTORIC PARK 2013 EAGLE CREEK PURCHASES GREAT FALLS HYDRO COMPANY, LLC INTERESTS 2016 RELICENSING PROJECT INITIATED W/ FEDERAL ENERGY REGULATORY COMMISSION 2021 FEDERAL LICENSE RENEWAL EXPECTED 6

S.U.M. Dam Great Falls Powerhouse Project Boundary 7

GREAT FALLS S.U.M. Dam Walkway Bridge /Trash Diverter Forebay Inlet 8 Project Powerhouse

THE PROJECT WORKS APPROVED IN 1986 AS PART OF THE CURRENT FERC LICENSE CONSIST OF: - (A) AN OVERFLOW GRANITE STONE GRAVITY DAM APPROXIMATELY 315 FEET LONG, WITH A MAXIMUM HEIGHT OF 15 FEET AND HAVING A CREST ELEVATION OF 114.6 FEET MEAN SEA LEVEL (MSL) AND 27 INCH BREAKAWAY FLASHBOARDS; - (B) A FOREBAY INLET STRUCTURE; - (C) A RESERVOIR WITH NEGLIGIBLE STORAGE AT SPILLWAY CREST ELEVATION 116.85 FEET (MSL); - (D) A WALKWAY, BRIDGE, AND A TRASH DIVERTER; - (E) A HEADGATE CONTROL STRUCTURE CONTAINING ONE SET OF TRASHRACKS WITH AN AUTOMATIC CLEANER AND THREE STEEL HEAD GATES; - (F) THREE PENSTOCKS, EACH 8.5 FEET IN DIAMETER AND APPROXIMATELY 55 FEET LONG; - (G) A CONCRETE POWERHOUSE CONTAINING THREE TURBINE/GENERATORS WITH A TOTAL RATED CAPACITY OF 10.95 MW; - (H) A 37 FOOT-LONG, 4.16 KV UNDERGROUND CABLE CONNECTING THE POWERHOUSE TO A 4.16/26.4 KV STEP-UP TRANSFORMER, TYING INTO THE CITY OF PATERSON'S PUBLIC SERVICE ELECTRIC AND GAS COMPANY (PSE&G) SUBSTATION VIA A 1,500 FOOT-LONG, 26.4 KV UNDERGROUND AND AERIAL CABLE; 9

10

11

OPERATIONS -RUN-OF-RIVER OPERATION WITH A MAXIMUM OPERATING FLOW CAPACITY OF 2,130 CFS. -UNDER NORMAL FLOW CONDITIONS THE PROJECT RESERVOIR WILL NORMALLY VARY BETWEEN 114.5-115.9 MSL WITH ALL FLOWS BETWEEN 200 CFS AND 2,130 CFS DIVERTED THROUGH THE TURBINES. -LICENSE ARTICLE 27 REQUIRES THE CO-LICENSEES TO DISCHARGE AN INTERIM CONTINUOUS MINIMUM FLOW OF 200 CFS OR THE INFLOW TO THE PROJECT RESERVOIR, WHICHEVER IS LESS, OVER THE GREAT FALLS FOR THE PURPOSE OF MAINTAINING WATER QUALITY, THE SCENIC VALUES OF THE GREAT FALLS, AND THE LOCAL FISH AND WILDLIFE RESOURCES. 12

13

PROPOSED PROJECT OPERATIONS: THE CO-LICENSEES ARE PROPOSING NO CHANGES TO THE CURRENT PROJECT S LICENSED OPERATIONS. 14

15

16

GEOLOGY, TOPOGRAPHY, AND SOILS WATER RESOURCES FISH AND AQUATIC RESOURCES WILDLIFE AND BOTANICAL RESOURCES WETLANDS, RIPARIAN, AND LITTORAL HABITAT RARE, THREATENED, AND ENDANGERED SPECIES RECREATION AND LAND USE AESTHETIC RESOURCES CULTURAL AND HISTORIC RESOURCES SOCIOECONOMIC RESOURCES TRIBAL RESOURCES 17

18 C.F.R. 5.6(D)(3)(II) REQUIRES DESCRIPTIONS AND MAPS SHOWING THE EXISTING GEOLOGY, TOPOGRAPHY, AND SOILS OF THE PROPOSED PROJECT AND SURROUNDING AREA. PAD Figure 5.3: Shaded Relief and Physiography 18

18 C.F.R. 5.6(D)(3)(III) REQUIRES A DESCRIPTION OF THE WATER RESOURCES OF THE PROPOSED PROJECT AND SURROUNDING AREA. PAD Figure 5.6: Passaic River Watershed 19

THE PROJECT WAS ISSUED A CONDITIONAL 401(A)(1) WATER QUALITY CERTIFICATE (80-4 - 5) BY THE NJDEP ON JULY 30, 1980. THE NJDEP DETERMINED THE PROJECT WOULD BE CONDUCTED IN A MANNER, WHICH WILL NOT VIOLATE APPLICABLE WATER QUALITY STANDARDS OF THE STATE OF NEW JERSEY, AS LONG AS THE SPECIFIC CONDITIONS WITHIN THE 401 ARE SATISFIED. 20

18 C.F.R. 5.6(D)(3)(IV) A DESCRIPTION OF THE FISH AND OTHER AQUATIC RESOURCES, INCLUDING INVASIVE SPECIES, IN THE PROJECT VICINITY. Project Fish Passage Device 21

18 C.F.R. 5.6(D)(3)(V) REQUIRES A DESCRIPTION OF THE WILDLIFE AND BOTANICAL RESOURCES, INCLUDING INVASIVE SPECIES, IN THE PROJECT VICINITY. 22

18 C.F.R. 5.6(D)(3)(VI) - DESCRIPTION OF FLOODPLAINS, WETLANDS, RIPARIAN, AND LITTORAL HABITAT 23

18 C.F.R. 5.6(D)(3)(VII) REQUIRES A DESCRIPTION OF ANY LISTED RARE, THREATENED AND ENDANGERED, CANDIDATE, OR SPECIAL STATUS SPECIES THAT MAY BE PRESENT IN THE PROJECT VICINITY. 24

18 C.F.R. 5.6(D)(3)(VIII) REQUIRES A DESCRIPTION OF THE EXISTING RECREATIONAL AND LAND USES AND OPPORTUNITIES WITHIN THE PROJECT BOUNDARY. 25

18 C.F.R. 5.6(D)(3)(VIII) REQUIRES A DESCRIPTION OF THE OF THE VISUAL CHARACTERISTICS OF THE LANDS AND WATERS AFFECTED BY THE PROJECT. 26

18 C.F.R. 5.6(D)(3)(X) REQUIRES A DESCRIPTION OF THE KNOWN CULTURAL OR HISTORICAL RESOURCES OF THE PROPOSED PROJECT AND SURROUNDING AREA. 27

18 C.F.R. 5.6(D)(3)(XI) REQUIRES A GENERAL DESCRIPTION OF SOCIO-ECONOMIC CONDITIONS IN THE VICINITY OF THE PROJECT. 28

18 C.F.R. 5.6(D)(3)(XII) REQUIRES A DESCRIPTION OF INDIAN TRIBES, TRIBAL LANDS, AND INTERESTS THAT MAY BE AFFECTED BY THE PROJECT. 29

THE PROJECT WILL CONTINUE TO OPERATE WITH RUN-OF-THE RIVER OPERATIONS AND NO CHANGES TO LICENSED CONDITIONS PROPOSED. STUDIES CONSIDERED TO DATE INCLUDE: ASSESSMENT OF AESTHETIC FLOWS OVER THE FALLS RECREATION USE OF THE PARKS AREA 30

DESCRIBE THE GOALS AND OBJECTIVES OF EACH STUDY PROPOSAL AND THE INFORMATION TO BE OBTAINED IF APPLICABLE, EXPLAIN THE RELEVANT RESOURCE MANAGEMENT GOALS OF THE AGENCY OR INDIAN TRIBE WITH JURISDICTION OVER THE RESOURCE TO BE STUDIED IF THE REQUESTER IS NOT A RESOURCE AGENCY, EXPLAIN ANY RELEVANT PUBLIC INTEREST CONSIDERATIONS IN REGARD TO THE PROPOSED STUDY DESCRIBE EXISTING INFORMATION CONCERNING THE SUBJECT OF THE STUDY PROPOSAL, AND THE NEED FOR ADDITIONAL INFORMATION 31

EXPLAIN ANY NEXUS BETWEEN THE PROJECT OPERATIONS AND THE EFFECTS (DIRECT, INDIRECT AND/OR CUMULATIVE) ON THE RESOURCE TO BE STUDIED AND HOW THE STUDY RESULTS WOULD BE USED IN RELICENSING OF THIS PROJECT EXPLAIN HOW ANY PROPOSED STUDY METHODOLOGY IS CONSISTENT WITH GENERALLY ACCEPTED PRACTICE IN THE SCIENTIFIC COMMUNITY DESCRIBE CONSIDERATION OF LEVEL OF EFFORT AND COST, AS APPLICABLE, AND WHY ANY PROPOSED ALTERNATIVE STUDIES OR MITIGATION WOULD NOT BE SUFFICIENT TO MEET THE STATED INFORMATION NEEDS. 32

GREAT FALLS HYDROELECTRIC PROJECT P-2814 NOI/PAD FILED WITH FERC FEBRUARY 26, 2016 FERC RECOGNIZED NOI/PAD AND GRANTED REQUEST TO USE TLP APRIL 28, 2016 PROVIDED FERC NOTICE OF JOINT AGENCY/STAKEHOLDER MEETING BY JULY 20, 2016 CONDUCTED JOINT AGENCY/STAKEHOLDER MEETING AUGUST 3, 2016 FILE COMMENTS ON THE PAD AND STUDY REQUESTS, IF ANY, WITH GREAT FALLS HYDRO 60 DAYS AFTER JOINT MEETING 33 BY OCTOBER 3, 2016

CONDUCT STUDIES, AS NEEDED (2017) ISSUE STUDY REPORT(S) TO STAKEHOLDERS (2017) ISSUE DRAFT LICENSE APPLICATION TO STAKEHOLDERS (EARLY 2018) FILE COMMENTS ON DRAFT LICENSE APPLICATION WITHIN 90 DAYS (MID 2018) FILE FINAL LICENSE APPLICATION WITH THE FERC ON OR BEFORE FEBRUARY 28, 2019 34

PLEASE SEND ANY COMMENTS OR QUESTIONS TO: KEVIN YOUNG KYOUNG@YOUNGENERGYSERVICES.COM (617) 645-3658 35