Revised Mid-and-Long-Term Roadmap towards the Decommissioning of TEPCO s Fukushima Daiichi NPP Units 1-4

Similar documents
Mid-and-long-Term Roadmap towards the Decommissioning of Fukushima Daiichi Nuclear Power Units 1-4, TEPCO Digest Version

Nuclear Damage Compensation & Decommissioning Facilitation Corporation (NDF) and Strategic Plan for Decommissioning of Fukushima Daiichi NPS.

Mid-and-long-Term Roadmap towards the Decommissioning of Fukushima Daiichi Nuclear Power Station Units 1-4, TEPCO

Countermeasures for Contaminated Water at TEPCO s Fukushima Daiichi NPS

Mid-and-Long-Term Roadmap towards the. Decommissioning of TEPCO s Fukushima Daiichi. Nuclear Power Station

Implementation Plan of the measures to be taken at Fukushima Daiichi Nuclear Power Station designated as a Specified Reactor Facility (outline)

INTRODUCTION IN FUKUSHIMA WATER LEAK PROBLEM

Background Information of the Contaminated Water Management at TEPCO s Fukushima Daiichi NPS

Research and Development Programs for Decommissioning of Fukushima Daiichi Nuclear Power Station

Activities of Toshiba for Fukushima restoration

Progress of Medium- and Long-term Efforts to Decommission Fukushima Dai-ichi NPP of TEPCO (Statement)

NRA s Regulatory Perspectives on Decommissioning of TEPCO Fukushima Daiichi Nuclear Power Station

4. Current Status (1) Fukushima Daiichi Nuclear Power Station

Efforts for the restoration at Fukushima Daiichi Nuclear Power Plants

OVER VIEW OF ACCIDENT OF FUKUSHIMA DAI-ICHI NPSs AND FUTURE PLANNING TOWARD D&D

Regulatory Perspectives on Decommissioning of TEPCO Fukushima Daiichi Nuclear Power Station

Status of Fukushima Daiichi Decommissioning and Decontamination Project

Efforts to Decommission the TEPCO Fukushima Daiichi Nuclear Power Station

Approaches to the decommissioning and contaminated water management for Fukushima Daiichi Nuclear Power Station

Development of technologies for the processing and disposal of radioactive waste

2. Roadmap towards Restoration from the Accident

Immediate Countermeasures

Mid-and-Long-Term Roadmap towards the. Decommissioning of TEPCO s Fukushima Daiichi. Nuclear Power Station

X. Future Efforts to Settle the Situation regarding the Accident

Immediate Countermeasures

Unit 4. Storage and handling. Storage and handling. Fuel debris retrieval. Scenario development & technology consideration

F, 3 Toyokaiji Building, Nishi-Shimbashi, Minato-ku, Tokyo , Japan Published: March 2016

Unit 4. Storage and handling. Storage and handling. Fuel debris retrieval. Scenario development & technology consideration

Current Status and Challenges at Fukushima Daiichi Decontamination and Decommissioning

Progress Status Classified by Countermeasures

Executive Summary of Nuclear Safety Reform Plan Progress Report (FY2013 3rd Quarter)

Hironori Nakanishi Director-General for Energy and Technology Policy Agency of Natural Resources and Energy (ANRE), Ministry of Economy, Trade and

15 April 2015 Nuclear Regulation Authority, Japan. 1. Overview

Status of Radioactive Waste Management in Japan

Progress Status of Mid-and-long Term Roadmap towards the Decommissioning of Fukushima Daiichi Nuclear Power Units 1-4, TEPCO

Report: Good Practice in Radiation Exposure Control at the Fukushima Daiichi NPP

IAEA International Missions (2013) to Japan on Fukushima-D NPP decommissioning and on off-site remediation

Unit 4. Storage and handling. Fuel debris removal. Scenario development & technology consideration. Design and manufacturing of devices / equipment

Unit 4. Storage and handling. Fuel debris retrieval. Scenario development & technology consideration. Design and manufacturing of devices / equipment

IAEA INTERNATIONAL PEER REVIEW MISSION ON MID-AND-LONG-TERM ROADMAP TOWARDS THE DECOMMISSIONING OF TEPCO S FUKUSHIMA DAIICHI NUCLEAR POWER STATION

Unit 4. Storage and handling. Fuel debris retrieval. Storage and handling. Scenario development & technology consideration

Unit 1. Unit 2. Unit 3. PCV gas phase temperatures (recent quarter) * The trend graphs show part of the temperature data measured at multiple points.

Advanced Technologies for Fuel Debris Retrieval towards Fukushima Daiichi Decommissioning

Current Status of Roadmap towards Restoration from the Accident at Fukushima Daiichi Nuclear Power Station, TEPCO (Revised edition)

Unit 4. Storage and handling. Fuel debris removal. Scenario development & technology consideration. Design and manufacturing of devices / equipment

Unit 4. Storage and handling. Storage and handling. Fuel debris retrieval. Scenario development & technology consideration

Technical Strategic Plan 2016 for Decommissioning of the Fukushima Daiichi Nuclear Power Station of Tokyo Electric Power Company Holdings, Inc.

6F Parkplace, Shimbashi, Minato-ku, Tokyo , Japan Phone :

Progress status of cooling (reactors) (Description)

Unit 4. Storage and handling. Fuel debris retrieval. Storage and handling. Scenario development & technology consideration

Great East Japan Earthquake and the seismic damage to the NPSs

Background and Current Situation of Restricted Areas and Areas to Which Evacuation Orders Have Been Issued

Strategy of the decommissioning of Fukushima Daiichi Nuclear Power Station and revitalization movement of the Hamadori

Strengthening safety by learning lessons from the accident at TEPCO s Fukushima Daiichi NPP. Akira OMOTO, Atomic Energy Commission

STATUS OF THE FUKUSHIMA DAIICHI SITE AND THE REMAINING RISKS

Unit 4. Storage and handling. Fuel debris retrieval. Storage and handling. Scenario development & technology consideration

Topics on Current Nuclear Regulation in Japan

EFFICIENCY OF FORTUM'S CSTREAT AND SRTREAT IN CESIUM AND STRONTIUM REMOVAL IN FUKUSHIMA DAIICHI NPP ABSTRACT

Unit 4. Storage and handling. Fuel debris retrieval. Storage and handling. Scenario development & technology consideration

November 17 th, 2011 Nuclear Emergency Response Headquarters Government-TEPCO Integrated Response Office

The 20 th N-20 Joint Statement

Great East Japan Earthquake and the seismic damage to the NPSs

Unit 4. Storage and handling. Storage and handling. Fuel debris retrieval. Scenario development & technology consideration

The Soundness of Unit 4 Reactor Building and Spent Fuel Pool at Fukushima Daiichi Nuclear Power Station

Current radioactive concentration of the seawater in Miyagi, Fukushima, Ibaraki and Chiba

Chapter 15 Radioactive Waste Management After Fukushima Daiichi Accident

Technical Strategic Plan for Decommissioning of the Fukushima Daiichi. Nuclear Power Station of. Tokyo Electric Power Company Holdings, Inc.

Outline & Prospect of IRID. September 16, 2013 Hajimu Yamana President International Research Institute for Nuclear Decommissioning

Presentation Outline. Basic Reactor Physics and Boiling Water Design Sequence of Events Consequences and Mitigation Conclusions and Lessons Learned

PRELIMINARY SUMMARY REPORT

Unit 4. Storage and handling. Fuel debris retrieval. handling. Design and manufacturing of devices / equipment

IAEA OSART review-results-list Recommendations

The Strategies of Research and Education on Decommissioning of Nuclear Facilities in the University of Fukui

Japan s Challenges for Fukushima Daiichi D&D

Current Situation of Fukushima- Daiichi Nuclear Power Plants and Difficulties in the Defueling Plan

Importance of Innovation for D&D at Fukushima Daiichi NPS

Information on Status of Nuclear Power Plants in Fukushima

Progress Status of the Groundwater Bypass Construction and Preparation for Operational Commencement

Information on Status of Nuclear Power Plants in Fukushima

Lessons Learned from the Fukushima Daiichi Nuclear Power Plant Accident

Information on Status of Nuclear Power Plants in Fukushima

Toru OGAWA. Overview of Radioactive Waste Management in Japan And R&D Activities for Fukushima Daiichi

Fukushima Daiichi Status Report

TOPICS Fukushima No. 78

Technical Volume 1 Description and Context of the Accident. R. Jammal P. Vincze

Information on Status of Nuclear Power Plants in Fukushima

Information on Status of Nuclear Power Plants in Fukushima

Japan s Energy White Paper 2017

Information on Status of Nuclear Power Plants in Fukushima

Japan s Current Nuclear Energy Policy

Unit 4. Storage and handling. Fuel debris removal. Scenario development & technology consideration. Design and manufacturing of devices/ equipment

Information on Status of Nuclear Power Plants in Fukushima

Information on Status of Nuclear Power Plants in Fukushima

Information on Status of Nuclear Power Plants in Fukushima

The 4th Progress Report

MISSION REPORT TO THE GOVERNMENT OF JAPAN

Summary on Fukushima Related Activities in Japan

Shunsuke Kondo. Chairman Japan Atomic Energy Commission

Chapter 28 Consideration of Treatment and Disposal of Secondary Wastes Generated from Treatment of Contaminated Water

Information on Status of Nuclear Power Plants in Fukushima

Transcription:

Revised Mid-and-Long-Term Roadmap towards the Decommissioning of TEPCO s Fukushima Daiichi NPP Units 1-4 Tatsuya Shinkawa Director, Nuclear Accident Response Office, Agency for Natural Resources and Energy, METI July 2013 1

Overview of the Mid-and-Long-Term Roadmap March 11, 2011 The Great East Japan Earthquake December 21, 2011 The Government and TEPCO Council adopted the Mid-and-Long-Term Roadmap towards the Decommissioning of TEPCO s Fukushima Daiichi NPP Units 1-4 (Mid-and-Long-Term Roadmap ver. 1.0) July 30, 2012 Mid-and-Long-Term Roadmap was revised (ver. 1.1). February 8, 2013 The Nuclear Emergency Response Headquarters established The Council for the Decommissioning of TEPCO's Fukushima Daiichi NPP Enhance the further collaboration between on-site work and R&D through involvement relevant R&D bodies into Government of Japan and TEPCO. June 10, 2013 The draft of concept for the revised Mid-and-Long-Term Roadmap was released. Opinions from Fukushima Prefecture, local governments, and experts. June 27, 2013 The Council adopted the revised Mid-and-Long-Term Roadmap ver. 2.0. 2

Three Major Points of the revised Roadmap 1. Reviewing the schedule based on the condition of each unit To pursue the possibility of the acceleration of the target data for fuel debris removal With multiple option plans for the removal of the fuel rods and fuel debris to fit the on-site situation 2. Strengthen communications with local stake holders and across all levels of society Establish the Fukushima Advisory Board (provisional title), with the participation of Fukushima Prefecture, local governments, relevant local organizations, and experts in order to strengthen the provision of information and communications. 3. Developing a comprehensive structure to gather international expertise Appoint international advisors who provide advice to the R&D management organization Establish an international collaboration department in the R&D organization and an international decommissioning expert group consisting of foreign experts in various fields 3

Basic Principles of Mid-and-Long-Term Roadmap Principle 1: Systematically tackle the issues while placing top priority on the safety of local citizens and workers. Principle 2: Move forward while maintaining transparent communications with local and national citizens to gain their understanding and respect. Principle 3: Continuously update the roadmap in consideration of the onsite situation and the latest R&D result. Principle 4: Harmonize the efforts of TEPCO and Government of Japan to achieve the goals indicated in this Roadmap. The Government of Japan should take the initiative in promoting the efforts to implement decommissioning measures safely and steadily. 4

Basic Concept for Ensuring Safety Ensuring safety as Specified Nuclear Power Facilities (under regulation by NSA) Efforts to ensure safety To set the priority on the removal of the hazards such as fuel rods in Spent Fuel Pool (SFP) and fuel debris as soon as possible To set the urgent action for the contaminated water treatment To consider on safety, gain the understanding of the local and other citizens, consider the holistic plan for the decommissioning, use the best available technologies, and employ the most rational and achievable measures Preparations for the Development of New Standards and Regulatory Response Actions 5

Targets of Roadmap December 2011 (Step 2 Achieved) December 2013 December 2021 30 to 40 years in the future Efforts to stabilize the NPP Phase 1 Phase 2 Phase 3 Cold shutdown achieved Achieve cold shutdown (Step 1) Significantly reduce radiation releases (Step 2) Period up to the commencement of the removal of the fuel from the spent fuel pool (within 2 years) Period up to the commencement of the removal of the fuel debris (within 10 years) Period up to the completion of decommissioning measures (30 to 40 years in the future) Now: Under preparation of first fuel rods removal from Unit 4 SFP as target of Phase 1 6

Current Status of Fukushima Daiichi NPP 7

Plan under the Revised Roadmap (example: Unit 2) Existing reactor building Rooftop crane Plan 1 Fuel Handling When the existing reactor Machine (FHM) building can be decontaminated and the FHM can be restored Upper container Separate container Plan 2 When the reactor building has sufficient seismic resistance for a container to be constructed on its upper level Plan 3 When the reactor building lacks sufficient seismic resistance, necessitating the construction of a separate container First half of FY2020 (one-and-a-half years earlier than the initial plan) Commencement of the removal of the fuel debris First half of FY2021 (6 months earlier than the initial plan) Commencement of the removal of the fuel debris First half of FY2024 Commencement of the removal of the fuel debris Future plans will be narrowed down in the first half of FY2014 based on the results of analysis of the likelihood of the existing reactor building s decontamination or restoration of the FHM, as well as the results of the assessment of the seismic resistance of the existing reactor building. 8

Planned Schedule for Each Unit (Summary) Fuel rods removal from SFPs (Target schedule) Fuel debris removal (Target schedule) Initial Target December 2013 (the earliest unit) December 2021 (the earliest unit) Unit 1 Unit 2 Unit 3 First half of FY2017 (the earliest case) Second half of FY2017 Second half of FY2017 (the earliest case) First half of FY2023 First half of FY2015 First half of FY2020 (one-and-a-half years earlier than the initial plan) Second half of FY2022 First half of FY2020 (one-and-a-half years earlier than the initial plan) First half of FY2024 Second half of FY2021 (the earliest case) Second half of FY2023 Unit 4 November 2013 (one month earlier than the initial plan) 9

Fuel Rods Removal from SFP 1. Rubbles in the upper level of the reactor building needs to be removed(unit 4: completed, Unit 3: ongoing) 2. A cover or a container for the entire reactor building is to be constructed and the Fuel Handling Machine is to be installed (Unit 4: Under construction) 3. The fuel rods stored in the common pool is to be moved to the temporary cask custody area to make vacancy in the common pool for the fuel removed from the spent fuel pool (SFP) 4. The fuel rods removed from the spent fuel pool of each damaged units will finally be packed into transport containers after confirming the soundness and transported. Transportation of the fuel rods removed from Unit 4 is scheduled to commence in November 2013. Fuel Removal Cover on Unit 4 Safety barrier Cask Pit Common Pool Storage area Ensuring vacancy Temporary Cask Custody Area Crane Cask Pit Modules 10

Work Processes to the Removal of the Fuel Debris The most reliable method of fuel debris removal is to remove the fuel debris in keeping them covered with water in terms of reducing the risk of radiation exposure during work processes. The fuel debris will be examined and the primary containment vessel (PCV) will be examined and repaired for filling the PCV with water. Furthermore, R&D for the removal and storage of fuel debris will be implemented. In addition to the submerged method, backup plans have been considered. Ceiling crane Container Spent fuel pool Penetration RPV Penetration Pressure vessel lid Spent fuel pool Transp ort Fuel debris can Filling the bottom of the vessel with water PCV RPV Water flow Torus stoppage room Rough picture of the process from repairing the bottom of the RCV (water flow stoppage) to filling the bottom of the vessel with water PCV Torus room PCV Torus room Rough picture indicating the process of removing the fuel debris 11

Continuous Monitoring Cold Shutdown State of the Reactors and Cooling Plan Keep the cold shutdown state Improve backup system of the monitoring temperatures in the PCVs and RPVc Improving to small circulation loop Completion of constructing circulation loop in buildings by the end of FY2014 Study of constructing a small circulation loop (containment vessel circulative cooling) of the reactor water injection line Circulative water injection line (large circulation) Circulation loop in building 12

Contaminated Water Treatment 1/2 Overview of the System Reactor cooling water: About 400 m3/day Reactor Building About 800 m3/day Ground water About 400 m3/day Ground water Injection water tank Re-use Residual water About 400 m3/day Desalination devices Turbine Building Cesium removal devices Main process building High temperature incinerator building Temporary storage AREVA (France) Stand-by Kurion (US Backup Sarry (Toshiba) In operation Low-to-mid-level tank Multi-nuclide removal device (ALPS) Storage tank 13

Discharging of contaminated water into the ocean will not be implemented lightly. 1. Bypass of the under ground water Construction is completed. Waiting for the local public acceptance. 2. Restoring the sub-drain Under construction (for clean-up) 3. Frozen-soil shielding walls Feasibility Study Contaminated Water Treatment 2/2 4. Improvement of the capacity and stable operation of contaminated water Approx. treatment facilities 200m Operation of multi-nuclide removal equipment 5. Construction of new tanks to manage contaminated water Increase the capacity to 0.8 million m 3 by FY2016 Shielding walls on the seaward side Frozen-soil shielding walls on the landward side Units 1 to 4 Approx. 500m [Plan to construct shielding walls on the landward side] 14

Reducing Radiation Doses of Entire Plant and Preventing Expansion of Contamination In order to prevent expansion of ocean contamination, the shielding walls on the seaward side will be constructed by the middle of FY2014. Countermeasure for increased concentration of radionuclides in groundwater near the seawall Strengthening monitoring (including investigation of contamination routes, land improvement to prevent the expansion of contamination, and removal of contaminated water in the trench on the seaward side. Waste management and radiation dose reduction at the boundaries of the site will be continued. 15

Radioactive Waste Management and Decommissioning Scenarios Proper Management and Reduction of Radioactive Waste Proper waste management in consideration of environmental effect in and outside the site Priority of waste management: Reduce the amount carried in Minimize waste generation Reuse Recycle Processing and Disposal of Radioactive Waste R&D for characterizing and analyzing waste properties will be promoted to explore processing and disposal methods. Decommissioning Scenarios Decommissioning scenarios will be considered and established through gathering worldwide information on how to ensure safety of decommissioning in consideration of end state of facilities. 16

Personnel Plan and Improvement of Working Environment and Condition Personnel Plan The number of personnel required is estimated at a same level for the next three years. Because it will be necessary to work under much higher dose rates in the mid-and-long-term, personnel plans will be reviewed when the Roadmap is revised. Improving Work Environment and Conditions Work safety and health management: Improvement of rest area, heat stroke preventive measures, ensuring of the medical system, etc. Radiation control: Expansion of areas where a full-face mask is not required, improving exit/entrance bases, etc. Efforts to ensure appropriate working conditions: Education concerning the ensuring of working conditions, survey on efforts made by prime contractors concerning working conditions, etc. 17

Coexistence with Local Communities and Communication with All Levels of Citizens Coexistence with Local Communities Provide opportunities to participate in the decommissioning work Foster local companies that supply required equipment and machinery on a long-term basis Promote to set up new companies to revitalize local economies. Strengthen the provision of information and communications Establish the Fukushima Advisory Board (provisional title), with the participation of Fukushima Prefecture, surrounding local governments, relevant local organizations, and experts in the field of regional development and communications Enhance the PR activities for citizens and society 18

R&D Plan and Structure to promote R&D Systematic promotion of R&D Plan Removal of the fuel from the spent fuel pool Preparation for the removal of the fuel debris Processing and disposal of radioactive waste Establishment of an organization to manage R&D activities Establish an organization to manage R&D activities in an integrated way Gathering international expertise international advisors, international decommissioning expert group Human resource development Promote human resource development by setting priority fields and core bases from mid-and-long-term perspective. 19

Structure to promote R&D Council for the Decommissioning of TEPCO s Fukushima Daiichi Nuclear Power Station Fukushima Advisory Board (provisional title) Secretariat of the Council Committee on Countermeasures for Contaminated Water Treatment Presentation and report on the concept for the facility Presentation and report on the R&D plan Research base facilities (JAEA) Radioactive material analysis and research facility Remote-controlled equipment and device development facility Collaboration Utilization Organization to manage R&D Candidate members: JAEA, National Institute of Advanced Industrial Science and Technology, Toshiba, Hitachi GE, Mitsubishi Heavy Industries, TEPCO and other power companies, etc. Appointment of international advisors who provide advice on the operation and structure of the organization Establishment of a group consisting of foreign experts in various fields 20

R&D for preparation of fuel debris removal Development of remote decontamination technology on the reactor buildings Development of investigation technology of inside PCV High water pressure Dry-ice blasting Blasting and vacuuming 21

International Cooperation Gathering the knowledge and expertise from Japan and abroad Sharing information and implement the decommissioning in transparent manner with international community Recognize responsibility of this accident occurred country Gathering international expertise for the R&D management organization Appoint international advisors Establish an international collaboration department Establish an international decommissioning expert group Improving an environment that encourages participation of overseas research institutions and businesses Multilateral and bilateral international cooperation 22

Thank you for your attention! Tatsuya Shinkawa Director, Nuclear Accident response Office, Agency for Natural Resources and Energy, METI shinkawa-tatsuya@meti.go.jp 23