REPAIR OF AN 80-YEAR- OLD DRY STACK WALL. Ryan Eaves, E.I.T. Bridge Division Geotechnical Branch

Similar documents
PHASING CONSIDERATIONS FOR BRIDGES

FACING OPTIONS FOR SOIL NAIL WALLS. John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

STRUCTURAL STEEL INSPECTION

SLOPE FAILURES: REPAIR OPTIONS. Sean Yoon, Ph.D., P.E. Bridge Division Geotechnical Branch

CONCRETE RIPRAP VERSUS STONE PROTECTION RIPRAP. John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

DEMOLITION PLANS. Aaron Garza, P.E.

STANDARD OPERATING PROCEDURE FOR POST TENSIONING. Leon Flournoy, P.E. Bridge Division

BRIDGE DESIGN MANUAL UPDATES. Jamie F. Farris, P.E.

PIER PROTECTION (VEHICLE COLLISION) September 13, 2018

COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF TRANSPORTATION BUREAU OF DESIGN

Earth Retention Systems And Specialized Foundations

INSPECTION OF STEEL & TIMBER PILING

RELEASE STRENGTHS. Prestressed Girder Deterioration. March 2018 Date. Footer Text

City of Mesquite General Design Standards Revision Date:

ERECTION PLANS UT-BRIDGE & UT-LIFT. Kevin R. Pruski, PE July 27, 2017

ROCK SLOPE STABILIZATION PROJECTS LETCHWORTH STATE PARK PORTAGEVILLE, NEW YORK

Stone and Masonry Veneer

BRIDGE STANDARDS UPDATES. Amy Smith, Bridge Standards Engineer

Mechanical Engineer of Record: (Smoke Control Systems Only) Name & License Company. Others: Responsible Party Name & License Company

CONCRETE SPLICED GIRDERS IN TEXAS. Nicholas Nemec, P.E. TxDOT-BRG

CHAPTER 11: WALLS.

KORA_Req._for_Eng._Studies_on_Stouffer_Apts. KU Reference No

ENGINEERING DIRECTIVE

Rapid Axial Load Testing of Drilled Shafts

ERRATA SHEET FOR STANDARD SPECIFICATION BOOK FOR STATE ROAD AND BRIDGE CONSTRUCTION, EDITION 2007

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.

Special Provisions for Pavement Open Cuts

The Lewistown Narrows. State Routes 22/322

SEWER MANHOLE/WET WELL REHABILITATION, SEVERE SULFIDE (as provided by WBE Dorcas, Inc.)

DESIGNING TWIN TUB GIRDER BRIDGES TO BE NON-FRACTURE CRITICAL. Twin Tub Task Group (T3) Texas Steel Quality Council

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

MagnumStone Specifications Gravity

Subject: Amphitheater School District Reroofing Projects Amphi High School, Building 900 Roof Evaluation SCI Project Number:

Foundation/Site Work Code Requirements

CHAPTER B TABLE OF CONTENTS

A. Section includes temporary excavation support and protection systems.

STRENGTH AND DURABILITY OF THE INSTALLED STONE

Inlet Protection. Fe= (Depends on soil type)

Construction and Materials Tips

The Aizhai Suspension Bridge is

SPECIAL PROVISION Detours, Barricades, Warning Signs, Sequence of Work, etc.

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

Changes for the. TOHOPEKALIGA WATER AUTHORITY Standards, Specifications and Details

SECTION 39 - MANHOLES TABLE OF CONTENTS

Stevens & Associates, Inc. Tunnel Construction Projects. Fact Sheets

Specialty Applications. for Keystone Walls

NOTIFICATION OF ADDENDUM ADDENDUM NO. 1 DATED 7/07/2015

Widening the Harrods Creek Arch Bridge

Statement of Special Inspections Michigan Building Code 2012 (MBC 2012)

CHAPTER 11 CONDUITS AND FITTINGS

Earth Retention Systems

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR LOW-TENSION CABLE BARRIER. OPR:CT 1 of 5 APPR:JAR:DBP: FHWA:APPR:

PAY QUANTITY NOTES INCLUDES CU. YDS. FOR DRIVEWAYS, RETURNS, DIKES, AND MISCELLANEOUS EARTHWORK WHERE NO QUANTITY IS SHOWN ON P & P SHEETS.

MANDATORY SUPPLEMENTAL SPECIFICATIONS FOR CONTRACTOR QUALITY CONTROL Contractor Quality Control - is replaced with the following:

CITY OF SCHERTZ TEXAS ENGINEERING AND PUBLIC WORKS

ACCELERATED BRIDGE CONSTRUCTION: TECHNIQUES. Kevin Pruski TxDOT Bridge Division 2018 Transportation Planning Conference

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it.

Flood Hazard Assessment Report Falls Gulch, Larimer County, Colorado January 16, 2013

CONTRACT PROPOSAL/CONTRACT ACCEPTANCE HIGDON LOOP ROAD BRIDGE

BRIDGE DECK CONCRETE OVERLAYS

Installation Manual. ArchCast Bridge. 3-Sided Precast Concrete Bridge Structure

CONDUITS AND FITTINGS

Final Estimates Level 2

Bi-Directional Static Load Testing of Drilled Shafts

Bi-Directional Static Load Testing of Drilled Shafts

ATTACHMENT 50-1: PERFORMANCE AND MEASUREMENT TABLE

MOA Project # Golden View Drive Intersection & Safety Upgrades

IMPLEMENTING NEW MATERIALS

SUPPLEMENTAL TECHNICAL SPECIFICATION

VOLUME 2 TECHNICAL SPECIFICATIONS BID NO PROJECT MANUAL FOR BONDS RANCH ROAD WIDENING PROJECT BIDS DUE JULY 9, :00 P.M.

SECTION Temperature Change: 120 deg F, ambient; 180 deg F, material surfaces.

DIVISION 4100 SITEWORK

Special Provision No. 799F01 March 2012 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF NOISE BARRIER TABLE OF CONTENTS

Topic: Site Formation

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT EXIT 44 SOUTHBOUND ON RAMP IMPROVEMENTS MILE 44.3

RFB for Wastewater Force Main #3. October 2, Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered

Canal 3. Geocomposite for Canals & Water Containment Applications

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR CONCRETE FORM LINERS AND COLOR STAIN COATING

CONSTRUCTION SPECIFICATION FOR NOISE BARRIER SYSTEMS

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

TABLE OF CONTENTS. Chapter 3 - WATER MAIN, VALVES, HYDRANTS AND APPURTENANCES. Chapter 4 - SANITARY SEWER. Chapter 5 - STORM SEWER

5-20 FOUNDATION REPORT/GEOTECHNICAL DESIGN

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards...

Special Provision No. 599F01 May 2004 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF NOISE BARRIER TABLE OF CONTENTS

SUDAS Revision Submittal Form

Section 7 Roadway GENERAL REQUIREMENTS I. TYPICAL SECTION...7-1

Index to Technical Specifications

SECTION UNIT PRICES. A. This Section specifies administrative and procedural requirements for the unit prices.

Lecture 13: Practical Design, The Future of Prestressed Concrete, and Concluding Thoughts...

City of Rohnert Park Building Department Inspection Descriptions

UPRR INDUSTRIAL LEAD BRIDGE T-WALL RETAINING WALL SYSTEM 5.0 x 7.5 UNITS DESIGN UNIT 018 WORK PACKAGE 04

RECONSTRUCTION OF DISTRESSED PAVEMENTS Full-Depth Rehabilitation (FDR) (Portland cement)

Houston Community College 3200 Main Parking Garage November 15, 2010 Houston Community College

Maine Turnpike Authority

Presented by: Taya Retterer BRG Webinar July 30, 2012

Specialising in Ground Engineering & Slope Stabilisation

ST. TAMMANY PARISH PATRICIA P. BRISTER PARISH PRESIDENT

SECTION mil thickness COLD FLUID-APPLIED WATERPROOFING

Construction Requirements for Installation of Utilities in the Public Right-of-way of McPherson County, Kansas October 2011

Transcription:

REPAIR OF AN 80-YEAR- OLD DRY STACK WALL Ryan Eaves, E.I.T. Bridge Division Geotechnical Branch October 2015

Project Location Located on Texas 290 90 miles southwest of San Angelo Remote area 10 miles west of Sheffield 2

Dry Stack Wall Construction Initial construction in 1930s From 10 feet to 25 feet in height and 400 feet in length Repair of an 80-Year-Old Dry Stack Wall October 2015 3

Existing wall cross section Gravity wall relies entirely on self weight of stacked rock to resist lateral load Battered wall face common to dry stack walls Sensitive to erosion weathering of rock can result in instability 4

Project Background San Angelo District contacted Bridge Division in spring 2014 Found two severely voided zones spanning 55LF and 33LF along the wall Barrier undermined and void extends to roadway surface Rock on surface shows signs of significant deterioration 5

Project Background 6

Project Background Smaller of the two severely weathered areas 7

Project Background Resulted in pavement and barrier distress on the surface above the wall 8

Project Background As a result, traffic control measures were put in place Two way traffic was condensed into one lane Signalized system managed traffic Project was let as a Routine Maintenance Contract 9

Design Considerations Preserving historic value both barrier and retaining wall 10

Design Considerations Weathering/deterioration present throughout wall Decided to treat the entire wall with soil nails Made most economic sense to cover entire wall with permanent shotcrete and sculpt to match original 11

Design Considerations Remove barrier original materials and set aside After retaining wall repair is completed, a masonry expert can reassemble the barrier using the original materials Concrete cap on top would then be recast 12

Design Considerations Soil nails minimally invasive to existing structure Provided option to use hollow core self drilling soil nail anchors to help with hole stability 13

Design Considerations Installed anchors on existing face of the voided zones Coupled on to the nails to lengthen to proposed wall face Build up section with welded wire wall 14

Pre-Construction Contractor recommended 2-inch flash coat of shotcrete Shotcrete to be fiber reinforced Fiber reinforcement allowed for decrease in face thickness 15

Pre-Construction Site equipment access issues were a concern Decided to build a temporary berm at the bottom of the wall to allow small equipment access Two methods used to install nails 16

Wall Construction Drill by reaching over the top of the wall with an excavator Used for the top couple of rows of nails Could not reach the bottom few rows 17

Wall Construction Wagon Drill Frame that orients and holds drill Able to scale and attach to wall Used for the lower portion of the wall 18

Construction Soil nail testing verification testing to verify soil strength assumptions and evaluate drilling methods done before construction began did not reach rock material shown in the boring logs 19

Wall Construction Initially the test holes took 20 times the theoretical volume of grout to fill grout seeped into voids in the stacked rock volumes Decided to ensure at least 5-foot minimum tag into rock layer grout added 20% 30% more than theoretical 5 volume Contractor verified that corrosion due to the unbonded portion would not affect the 75-year design life of the wall 20

Sculpted Face Small shotcrete layer added on top of flash coat to create smooth surface Application of final shotcrete layer and sculpting completed in increments 21

Sculpted Face Man-lift from roadway above used to reach the top portions of wall Shotcrete face was then stained to reflect original rock color after shotcrete cured 22

Project Completed Wall repair finished in eight weeks Only delay was acquiring water for the grout mixture Approximate total project cost: 23

Finished Barrier Barrier reconstructed and new concrete cap cast Pavement damage repaired 24

Cost Summary RW(temp) $ 166,500.00 RT(soil nailed) gunite $ 398,255.00 Soil Nail Anchors $ 268,561.00 Additional gunite $ 29,996.23 Horizontal Drains $ 60,486.00 Stone Wall $ 7,455.12 Wall Base Benching $ 7,576.21 Pavement Repair (Removed) $ (25,400.00) Retaining Wall Total $ 913,429.56 Mobilization $ 92,250.00 Barricades $ 32,500.00 Mobilization Total $ 124,750.00 Project Total $ 1,038,179.56 25

Final Thoughts Contractor and TxDOT able to: work together to swiftly handle challenges as they arise in construction come up with solutions to unique problems complete the project quickly with minimal effect on the travelling public 26

Copyright Notice Copyright 2015 Texas Department of Transportation All Rights Reserved Entities or individuals that copy and present state agency information must identify the source of the content, including the date the content was copied. Entities or individuals that copy and present state agency information on their websites must accompany that information with a statement that neither the entity or individual nor the information, as it is presented on its website, is endorsed by the State of Texas or any state agency. To protect the intellectual property of state agencies, copied information must reflect the copyright, trademark, service mark, or other intellectual property rights of the state agency whose protected information is being used by the entity or individual. Entities or individuals may not copy, reproduce, distribute, publish, or transmit, in any way this content for commercial purposes. This presentation is distributed without profit and is being made available solely for educational purposes. The use of any copyrighted material included in this presentation is intended to be a fair use of such material as provided for in Title 17 U.S.C. Section 107 of the U.S. Copyright Law. 27