Changes in Drilling Performance and Dust Suppression with the Use of a Water Separator Sub

Similar documents
Bearing capacity of a glass fibre reinforced polymer liner

Different modes of dust testing for bulk solids

A newly developed plaster stemming method for blasting

Optimisation of Overburden Blasts at Glencore Ulan Surface Coal Operations

Bengalla Mining Company Pty Limited. Particulate Matter Control Best Practice Implementation Monitoring Programs

The Influence of Concrete Sample Testing Dimensions on Assessing Cable Bolt Load Carrying Capacity

Drayton Management System Standard. Air Quality Management and Monitoring Plan

MT ARTHUR COAL U1 Particulate Matter Control Best Practice Implementation Report Wheel Generated Dust

KEEPS YOU DRILLING. KEEPS YOU DRILLING.

Environmental Aspects of Mine Planning

Work Program PRP4.2 Particulate Emissions from Coal Trains

Monetary Savings Opportunities of Electronic Blast Initiation Systems

A STUDY OF THE INFLUENCE OF DIFFERENT BLASTING MODES AND EXPLOSIVE TYPES ON GROUND VIBRATIONS *

Sand Mining and Transport: Potential Health Effects. Thomas M. Peters, PhD, CIH Associate Professor University of Iowa Iowa City, IA

The economics of extended pre-strip stripping

For personal use only

DEFINITIONS. A shallow bored hole under the derrick substructure in which the kelly is temporarily stored during tripping operations.

ABERGELDIE MINING PTY LTD

Improvements in long tendon support with pumpable resin

Some observations on the design data provided by three well known devices for measuring flow properties of bulk solids

Evaluation of structural component design in lifeof-mine

Development of a Prototype Key Performance Indicator in Large-Scale Drilling Operations

A Simulation Model for Roadway Development to Support Longwall Mining

Environmental Reclamation Practice in a Brazilian Coal Mine -- An Economical Approach

aêáääáåö=ó råçéêëí~åçáåö=cìåç~ãéåí~äë ^êåé=iáëäéêìç

AGA. Australia ANGLOGOLD ASHANTI AUSTRALIA. Fraser Clark Manager: Geology

Status Report on the Health Issues Associated with Pulverised Fuel Ash and Fly Dust. Introduction and Summary. Revision (Version 2.

Optimal Selection of Selective Mining Unit (SMU) Size

Monitoring and analysis of production waste blasts at the Cadia Hill Gold Mine

Drilling bit classification

Application of fault tree analysis to coal spontaneous combustion

Quantifying the creep behaviour of polyester resin and grout

An Experimental Study on the Contact Surface Area of Cabled Bolted Strata

Silica Dust: Quantifying The Problem

Experiences of the institute of occupational medicine foam respirable sampler use in mines

Managing the geotechnical aspects of longwall face recovery

FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) PART A

Radiation

Radiation

Investigations into the dustiness of bulk materials

Specialising in Ground Engineering & Slope Stabilisation

Concrete Deterioration in Mining Structures

LYNWOOD QUARRY AIR QUALITY MANAGEMENT PLAN FINAL

About the NSW Minerals Council

AIR QUALITY MANAGEMENT PLAN CORAKI QUARRY

Electronic detonators and the Gautrain rapid rail project

Contents OCCURRENCE ACTIONS AND COMMUNITY COMPLAINTS... 5 FIGURE 1 FIGURE 2. Quarterly. Spontaneous.

Investigating particle size distribution of blasthole samples in an openpit copper mine and its relationship with grade

THE APPLICATION OF NEW GENERATION SUPPORT PRODUCTS IN A TYPICAL SUB-LEVEL BLOCK CAVE MINING METHOD TO REDUCE SAFETY RISKS AND ENHANCE PRODUCTIVITY

SUBSURFACE ROTARY DRILLING INVESTIGATION SPECIFICATIONS

Sandvik TIM3D On top of accuracy. Advanced navigation system for surface top hammer drilling

Technology that works for you.

Appendix A Physical properties of rammed earth

underground coal mine delay data analysis system

Mining Services Low Density WALA Post blast fume resistant

Strength properties of grout for strata reinforcement

KEY PRODUCTION DRIVERS IN IN-PIT CRUSHING AND CONVEYING (IPCC) STUDIES

CAPABILITY STATEMENT RAISE BORE DIVISION CAPABILITIES FLEET SPECIALIST EXPERIENCE LEADERS IN UNDERGROUND MINING

CAPABILITY STATEMENT RAISE BORE DIVISION CAPABILITIES FLEET SPECIALIST EXPERIENCE LEADERS IN UNDERGROUND MINING

Environment Protection Licence

SECTION MAINTENANCE OF STONE ASSEMBLIES

Monitoring DPM Emissions in Underground Mines:

Office of Environmental Health and Safety 1.0 INTRODUCTION

Blast Dynamics POWER DECK OPTIMIZATION POWER DECK COMPANY MAY, 2004 PREPARED BY: improving productivity wi th the use of efficient blast designs

Minerals. WARMAN Centrifugal Slurry Pumps WBV Vertical Cantilever Slurry Sump Pump Series

2019 Semester Terms and Dates Summary

RESPIRABLE CRYSTALLINE SILICA

MODEL CRYSTALLINE SILICA EXPOSURE PLAN

Endurance performance of conical picks with hardfacing for improving wear resistance

Blast optimisation at limestone quarry operations good fragmentation, less fines

A Further Investigation of DIAjet Cutting. by:

Corrosion Protection of Rock Bolts by Epoxy coating and its Effect on Reducing Bond Capacity

Blast Management Plan. Pine Dale Coal Mine (Including the Yarraboldy Extension)

GLNG PROJECT - ENVIRONMENTAL IMPACT STATEMENT

Secoroc Rock Drilling Tools CASING ADVANCEMENT SYSTEMS

SURFACE ENGINEERING APPLICATIONS THAT EXTEND WEAR LIFE OF COMPONENTS 2 5 TIMES

Quality assurance programs for management excellence. Are they relevant to the coal industry?

Nowadays, there are several methods traditionally. Raise bored slot raises: A modern mining technique RAISE BORING

Dust Control on Longwall Faces by Fine Mist (Atomising) Sprays - Can They Really Work?

Drying of water treatment plant residuals

Macraes Phase III Vibration and Air Blast Assessment Oceana Gold (New Zealand) Limited March 30 th 2010

Stratford Extension Project

Environment Protection Licence

University of Wollongong. Research Online

Quantifying the Creep Behavior in Polyester Resin and Grout

Measuring Blast Movement to Reduce Ore Loss And Dilution

Evaluation of Rock Support Performance through Instrumentation and Monitoring of Bolt Axial Load

Gunlake Quarry. Air Quality Management Plan

New Silica Standard 11/16/2017. Construction: highway, masonry, concrete, rock drilling

The World s Most Versatile Filter System

Dust Management Procedure Environment

Construction. Sika FerroGard Method Statement for Application Corporate Construction. Scope:

Optimal Solutions for Mining, Material Handling and Processing

Bengalla Mining Company Pty Limited. Post Blast Fume Generation Mitigation and Management Plan

Line filters LINE FILTERS

Cardno is a leading provider in the mapping and management of underground utilities, and excavating within high-risk and sensitive environments.

Borehole Condition Assessment

Ambient Particulate Matter Monitoring - A Case Study at Tarkwa

Filters & Elements. People. Passion. Performance

water-powered drilling in ground engineering

Transcription:

University of Wollongong Research Online Coal Operators' Conference Faculty of Engineering and Information Sciences 2015 Changes in Drilling Performance and Dust Suppression with the Use of a Water Separator Sub Brianna Millgate University of New South Wales Paul Hagan University of New South Wales Publication Details Brianna Millgate, Paul Hagan and Jianhang Chen, Changes in Drilling Performance and Dust Suppression with the Use of a Water Separator Sub, 15th Coal Operators' Conference, University of Wollongong, The Australasian Institute of Mining and Metallurgy and Mine Managers Association of Australia, 2015, 330-336. Research Online is the open access institutional repository for the University of Wollongong. For further information contact the UOW Library: research-pubs@uow.edu.au

2015 Coal Operators Conference The University of Wollongong CHANGES IN DRILLING PERFORMANCE AND DUST SUPPRESSION WITH THE USE OF A WATERW SEPARATOR SUB S Brianna Millgate and Paul Hagan ABSTRACT: Drill and blast is a key excavation process in open pit mining systems. Rock fragmentation due to drilling results in the production of fine dust particles that can be detrimental to the environment. There are different methods to manage the dustt make often based on some form of wet drilling which can cause further issues. The water separatorr sub is a device aimed at overcoming some off these issues. This paper outlines a study undertaken of the effect of a water separator sub on drill performance and dust suppression. The study involved collecting dust measurements throughh a real time dust monitor, and analysing drill performance data from a mine site, in particular drill penetration rate data and bit life. INTRODUCTION Depending on the type of rock being drilled, drilling can be a source of harmful dust that is detrimental to human health (Kalestone Environmental, 2011) ). Current dust suppression techniques have pitfalls in terms of productivity, health and safety and environmental sustainability. The water separator sub shown in Figure 1 is a device thatt replaces the bit sub in the drill string. It is designed so the combination of water and compressed air that is directedd down through the centree of the drill string takes a sudden sharp turn before the drill bit. Due to the higher inertia of water particles, the water is unable to negotiate the turn and is physically separated from the air (USBM, 1988). The air continues its flow and makes it way through the U-turn flowing through slots to the bit. The water accumulates in a small reservoir and the air pressure forces it to be ejected out of weep holes located l above the bit as a fine spray as shown in Figure 2 (NIOSH, 2012). The compressed air that exits the t drill bit forces the fragmented drill cuttings up the hole and then mixes it with the water r spray carrying the wetted material to the surface (Listak and Reed, 2007). Figure 1: Schematic of water separator sub inn a blasthole (NIOSH, 2012) 2 (left) and, installation of the sub (right) The water separator sub has the potential to utilise the advantages of o wet drilling in terms of dust suppression. This contributes to sustainability of the mining industry byy allowing drilling operations to occur, without posing a threat to human healthh and the environment. Minimising M dust also benefits a mining operation s social license to operate. Dust can be irritating and worrying to surrounding 330 11 13 February 2015

2015 Coal Operators Conference The University of Wollongong communities, even if the particular dust particles are not harmful. It can result in complaints and resistance from communities to any future development or extension of operations. Dust can also be extremely problematic for visibility. It can cause operations to be halted, resulting in lost production. Suppressing dust at drilling operations will help reduce dust make at a mine site and contribute to ensuring production is maintained. Figure 2: Water spray from weep holes in side of the sub above the drill bit The water separator sub also has the potential to lower drill bit costs. Preventing water from coming into contact with the drill bit can extend bit life by preventing corrosion and premature bit wear that is associated with standard wet drilling. If drill bit life is extended, bits do not need to be replaced as often reducing downtime and therefore lowering costs. This contributes to sustainability as companies are always looking for ways to lower operating costs in order to mine economically in deep pits and in tough markets. METHODOLOGY The project involved a field study at an openpit coalmine operating in the Hunter Valley of Australia. Data related to bit life and penetration rate and, measurements of dust levels were analysed over a period of several months before and after a water separator sub was installed. RESULTS Dust levels Dust monitoring was conducted to compare the effect of wet drilling on dust suppression with and without use of the water separation over a six-day period. A Dust Trak II Aerosol Monitor mounted on the surface near to the drillhole collar as shown in Figure 3 was used in the study. The unit utilises a light-scattering laser photometer to provide real-time aerosol mass readings every 30 seconds and reports the instantaneous dust concentration in air in units of mg/m 3. Figure 4 shows a plot comparing the dust readings for the same time period for the three days before and after sub installation that indicates there were more instances of high peaks readings before sub installation. Figure 3: Dust monitor in use during drilling operations 11 13 February 2015 331

2015 Coal Operators Conference The University of Wollongong Figure 4: Variation in dust readings beforee and after sub s installation Table 1 shows a summary of the mean and maximum readings on each day of monitoring. While use of the water separator sub in wet drilling resulted in a slight reduction in the mean daily dust readings of 12%, there was a near halving in the maximum daily dust readings. Table 1: Comparison of dust readings over a six-day period no water separator water separator installed Day 1 1.99 2 4.24 3 2.08 mean 2.77 5 3.65 6 1.16 7 2.48 mean 2.43 Dust reading (mg/m 3 ) mean maximumm 65.3 159.0 98.6 107.6 On Day 4, dust monitoring commenced at 8:00 am with wet drilling prior to installation of the water separation and continued until the water separator was installed at approximately 9:30 am. Dust monitoring then continued until 3:30 pm, utilising water separated wet drilling. d Theree was a noticeable reduction in the dust levels after the sub installation with more consistentt and fewer peaks in dust make post installation as shown in Figure 5.The resultss in Table 2 compare the mean, minimum and maximum readings before and after the sub was installed. The significance of this data set is that it appliess to the same set of conditions in terms of rock type, drill machine, drill bit, operator and weather conditions. As the data indicates there wass a reduction in the mean reading by 0.81 mg/m 3 or 25% %, the minimum reading decreased by b 0.027 mg/ /m 3 or 47%, and the maximum reading decreased significantly by 17.9 mg/m 3 or 37%. This shows that on this day with all other variables being the same, use of the waterr separatorsub increased the effectiveness of wet drilling in reducing dust make. 70.3 49.1 35.0 51.5 332 11 13 February 2015

2015 Coal Operators Conference The University of Wollongong Figure 5: Variation in dust readings beforee and after sub s installation on Day 4 Table 2: Effect of water separator installation on dust make Dust reading (mg/m 3 ) mean minimum maximumm before installation after installation percentagee change 3.19 2.38 25% 0.057 0.03 47% 47.6 29.7 37% Dust monitoring limitations While it was planned to maintain similar conditions with the water separator sub during the t study, in reality a number of changes occurred and differences in operating conditions c that may have impacted on the measurements. First, the drill rig used in the study was fitted with a dust curtain and collection system. It was observed that there were differences between drill operators in the use of thiss system. Second, the water flow rate was not fixed but varied by the operatorr depending on the ground conditions and the amount of visible dust present. Third, the drill rig was moved between drill sites after three days into the study. It was initially planned thatt the drill rig would remain in the same location for the duration of testing, however due to scheduling changes, drilling was completed prematurely and the rig relocated. This is likely to have introducedd differences in geological ground conditions. This factor does not apply to thee data in Table 2.Finally, weather conditions such as temperature, wind and humidity can also affect the amount of dust generation. Dry, hot and windy days will see an increase in the amount of dust present in the air. It was observed during the period of study that drilling operations occurred on fine, sunny days with minimal wind. Even so any small gust of wind may y have affected the readings depending on the location of the dust monitor and wind direction. For example, if a wind gust was in the direction of the dust monitor it may have temporarily resulted in a higher measurement, conversely if the wind gust t was away from the dust monitor it would have reduced the dust measurement. Drill penetration rate The mean daily drill penetration rate per shift was analysed over a nine n month period prior to installationn of the water separator sub and six months post installation. Histograms of the respective performance are shown in Figure 6 and various statistics summarised in Table 3. A comparison of the results for both cases shows there were reductions of 10.4% and 8..8% in the median m and mean penetration rates respectively. The use of the water separator sub had been expected to increased penetration rate by 11 13 February 2015 333

2015 Coal Operators Conference The University of Wollongong removing water from the point of rock breakage, however the data indicates the opposite seemed to t have occurred. Figure 6: Mean daily drill penetration rate before sub installation (left) and after sub installation (right) Table 3: Comparison of the drill bit penetration rate before and after sub installationn Daily penetration rate (m/hr) median mean s.d. before installation 71.2 after installationn 63.8 percentage change 10..4% 70.4 64.2 8.8% 16.9 16.4 Penetrationn rate data limitations A problem in analysing penetration rate data is that it is reliant on operator efficiency. Each operator s experience and drilling performance will influencee penetrationn rates. This factor could have accounted for 334 11 13 February 2015

2015 Coal Operators Conference The University of Wollongong some variance in the results. On the other hand, considering the size of the two data sets, this is less likely to be a contributing factor. Nevertheless during the period of study, a number of new drillers were employed and, due to the large number of operators at the mine as well as the number of drill rigs, there may have been differences in the actual operators between the two periods. Another issue is variation in ground conditions. Numerous drill sites can result in variations in the material properties of the overburden material. Factors such as strength, hardness and abrasivity of the rock and moisture content all present the potential to alter penetration rates. Drill bit life Bit life was examined over similar periods as penetration rate before and after installation of the water separator sub. The data analysed for drill bit life was based on the metres drilled per bit from the time a bit was first mounted to being dismounted. This was chosen as simply measuring the period during which a bit was used and does not take into account time delays for crib breaks or maintenance, nor does it consider lower penetration rates due to harder rock beds. Table 4 shows a comparison of the mean, minimum and maximum metres drilled per bit before and after sub installation. The mean bit life was found to have increased significantly by 58% after the water separator sub was installed. The improvements in the minimum and maximum values were 78% and 71% respectively. Table 4: Comparison of the drill bit life before and after water sub installation Number of bits Bit life (m/bit) mean minimum maximum before installation 13 13,326 6,743 26,230 after installation 8 21,060 12,039 44,854 percentage change 58% 78% 71% Drill bit life limitations A limitation on the reliability of the data is the variation in ground conditions. As is the case for penetration rate, drilling operations would have occurred between locations in the pit resulting in different drilling conditions with changes in rock strength, hardness and abrasivity. Another factor that may have impacted on bit life is the operator decisions on what constitutes a worn-out drill bit. Although there are strict guidelines on what constitutes a worn bit, if a bit was used past its optimum point then it would have skewed the results towards appearing to have improved drill bit life and conversely if changed too early. CONCLUSION The impact of a water separator sub was examined in terms of changes in dust make, drill penetration rate and drill bit life. Water is injected into the compressed air line that is used to bail rock fragments from the bit face in order to reduce the amount of fine dust produced at the drillhole collar. Over a three-day period both before and after installation of the sub, there was little significant change in the measured dust levels. As the drill rig was moved before and after installation this may have consequently resulted in changes in drilling conditions and may have masked any improvements. Interestingly, a 25% reduction in dust make was measured post installation on the actual day the sub was installed. It is recommended that a further study be undertaken over a much longer time period to confirm the impact on dust levels. The average daily drill bit penetration rate and bit life were analysed over a nine-month period before installation of the sub and a six-month period after installation. It was found that there was a reduction in the median and mean penetration rates by 10.4% and 8.8% respectively. Conversely, the sub had a marked beneficial effect of increasing bit life over the period studied of 25%. Overall, while installation of the water separator sub was not found to have had any significant impact in the measured dust levels on the surface near the drillhole collar, it had a slight detrimental impact on penetration rate while it had led to a significant improvement in extending bit life. 11 13 February 2015 335

2015 Coal Operators Conference The University of Wollongong REFERENCES Kalestone Environmental. 2011, NSW Coal Mining Benchmarking Study: international best practice measures to prevent or minimize emissions of particulate matter from coal mining [online]. Available from: <www.epa.nsw.gov.au> [Accessed: 15 May 2014]. Listak J and Reed W. 2007, Water separator shows potential for reducing respirable dust generated on small-diameter rotary blasthole drills, International Journal of Mining, Reclamation and Environment, 21(3):160 172. National Institute of Occupational Safety and Health (NIOSH). 2012, Dust Control Handbook for Industrial Minerals Mining and Processing, pp. 79-108 (Department of Health and Human Services: Pittsburgh). United States Bureau of Mines (USBM). 1988, Impact of drill stem water separation on dust control for surface coal mines. US Bureau of Mines Technology 308 p1-2. 336 11 13 February 2015