Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District

Similar documents
Lemm Elementary. Restoring the Heart of the Community. Klein Independent School District

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Building Excellence IV Capital Levy Projects Under Construction

GREENVILLE ISD BID PACKAGES AND UPDATES 2014 Bond Program OCTOBER 2015

MARCH BOND & TIF PROJECT UPDATE. Grapevine-Colleyville ISD

Building Excellence IV Capital Levy Projects Under Construction

Update on FCPS Construction/Renovation Projects. June 2016

Upper Adams School District Facility Study Presentation Part 2 November 17, 2016

LLANO ISD SCHOOL BOARD MEETING. January 2016

BOND CONSTRUCTION UPDATE

RR Program Summary: Complete renovation with addition and code upgrades for a historic academic building

PRESENTATION JANUARY 24, 2017

Division 09 FINISHES TABLE OF CONTENTS

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012

DENNIS TOWNSHIP FEASIBILITY STUDY

C. Type of Selective Demolition Work: Demolition requires the selective removal and subsequent off-site disposal of:

APPLICATION AND CERTIFICATE FOR PAYMENT

6 Holub Middle School Overall Site Plan Gymnasium Floor Plan Exterior Perspective Before Exterior Perspective - After

Update on FCPS Construction/Renovation Projects. August 2015

Board Work Session Feasibility Study. January 9, 2017

Evansville Public Schools. Facility Assessment Report January 28, 2 , General Building Data

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5

STRATTON CENTENNIAL ARTS ACADEMY PROGRESS REPORT SEPTEMBER 7, 2016 CARROLL DANIEL CONSTRUCTION 509 CROWE DRIVE HIGHLANDS, NC

Fleet Elementary School

Seattle Public Schools Building Excellence IV Projects Under Construction

PROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations

Corsicana High School

SECTION ALTERNATES

Auxiliary Services 995 West Beardsley Place Salt Lake City, Utah Capital Projects Status Report October 1, 2018.

FACILITY ASSESSMENT PRESENTATION 11 October SCHRADERGROUP architecture

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

Manufacturing Facilities Proposal

CEFPI Monthly Meeting

Facilities Construction

Guam Adequate Education Act Trust Account - CIP/STEM: Formerly SFSF Federal ARRA Grant Year End Report FY

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

Stephen F. Austin State University Board of Regents - Building and Grounds Committee Construction Update July 23, 2018

Oconomowoc Area School District Facility Construction Update July 27, 2018

Subject: Lucretia Mott School No. 3 Rehabilitation. Figure 1 Figure 2 Figure 3

BOYERTOWN AREA SCHOOL DISTRICT February 28, Boyertown West Middle School Renovation Project

Initial Design & Size

A. Remove Table of Contents and insert new attached Table of Contents.

REQUEST FOR QUALIFICATIONS ARCHITECTURAL/ENGINEERING SERVICES

SECTION 6. Residential Warranty Corporation 10 Year, Limited Structural Warranty. Year One

REQUEST FOR PROPOSALS March 4, 2010 PROJECT OVERVIEW:

Project Status Update & Progress Report

Update on FCPS Construction/Renovation Projects. December 2015

Introduction & Project Background

A Program Summary: Complete renovation and addition with code upgrades for a historic academic building

SECTION ADDENDA

Health Life Safety Survey and Master Facilities Plan

Building Excellence IV Capital Levy Projects Under Construction

BRUCE-MONROE ELEMENTARY SCHOOL AT PARK VIEW MODERNIZATION HISTORIC PRESERVATION REVIEW

Facilities Construction

Christopher Glinski Construction Management. AE Senior Thesis Columbia Heights Community Center. Appendix B. Project Summary /Detailed Schedule


CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO

Collins Middle School

STRUCTURAL ABBREVIATIONS S-001 GENERAL NOTES CONCRETE MASONRY NOTES DESIGN NOTES SOF NSWG-10 UAS SUPPORT FACILITY FY 2016 MILCON P-225

Update on FCPS Construction/Renovation Projects. November 2015

Facilities Construction

ACCESSORY BUILDING. Building Permit Requirements: (must be completed before submitting application)

DISTRICT SERVICES BUILDING

STANMYRE + NOEL Architects, P.C Preston White Drive, Suite 104 Reston, VA v f

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project

Capital Projects Update

Update on FCPS Construction/Renovation Projects. September 2015

MCER Study for Little Powder K-8

Drexel Hill Middle School

BWA ENVIRONMENTAL CONTROL BOARD (ECB) APPLICATION

Cold Spring School District

Capital Projects Update

Chino Valley Unified School District Monthly Construction Update

NALLE ELEMENTARY SCHOOL

BALLOU SENIOR HIGH SCHOOL

HILLSIDE ELEMENTARY SCHOOL. Overview: Livingston School District Hillside Elementary School

Technical Assignment 2

10 Year Plan. Facilities Planning Guide. December 15, 2014

BRUCE MONROE AT PARK VIEW ELEMENTARY SCHOOL MODERNIZATION PROPOSED MAIN ENTRY - EXTERIOR RENDERING

Structural Condition Assessment

Cheldelin Middle School

Architectural Services

Michael Teller, CBI Consulting Inc. Gymnasium & Auditorium Restoration at South Middle School

4.1.3 Project Manual

PROJECT UPDATE SEPTEMBER 11, 2014

Building Inspection Report

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District

1.1 THE ARCHITECT S SPECIFICATIONS AND DRAWINGS 1.2 THE BIDDING CONTRACTORS

Exhibit B TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS. September 9, Design Collective Project Number

AN OFFERING OF 1661 EAST OGLETHORPE HIGHWAY FLEMINGTON, LIBERTY COUNTY, GEORGIA PRESENTED BY WHITLEY AND ASSOCIATES, INC.

DeKalb County School District/Elementary Schools Clifton Elementary Final School Assessment Report May 19, 2016

PROJECTS COMPLETED WITH DIVERSIFIED EMPLOYEES (COMMERCIAL)

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

BOARD OF EDUCATION OF HARFORD COUNTY INFORMATIONAL REPORT

Coos Bay Best Bond Cost Breakdowns

SEATON ELEMENTARY SCHOOL

Estimating & Scope. Additional Lessons Tools / Measuring / Masonry / Framing/

RAYMOND EDUCATION CAMPUS

Existing Site Aerial Frederick High School Feasibility Study September 5, 2012

Transcription:

Lemm Elementary Restoring the Heart of the Community

Target Date: August 2018

June Work Update - Project is on schedule Exterior brick is ongoing in Area A addition Area A walls have been covered Main entry vestibule natural stone is almost done Multi-purpose room deck and structure will be painted Resinous flooring being installed in all main student restrooms and wash stations Wall finishes being finalized in Area B Area B wainscot has been completed All restroom tile work has been completed A/C has been turned on in Area C Ceiling tiles have been installed in Area C Glass sectional doors have started to be installed in Area A Air is turned on in Area B Operable glass wall has been installed in the covered play collaboration area Carpet has started to be installed in Area C Casework installation has commenced in Area C Door frames are being painted

June Work Examples

May Work Update - Project is on schedule Exterior sheathing has commenced at new addition Concrete saw cutting has commenced for sanitary line replacement New exterior brick installation to start at covered play area Exterior building envelope remediation work is ongoing at designated areas Interior wall framing is ongoing at Area A New windows are being sealed Interior door frames have been installed at Area A Area B wall finishes have commenced Area C tile installation is ongoing Gymnasium floor preparation has started Exterior Wall Mock-up First wall paint coat has started at Area C Window frame installations have started at Area C Solatube roof curbs have been installed

May Work Examples

Lemm Construction Photographs (May Work)

Lemm Construction Photographs (May Work)

Lemm Construction Photographs (May Work)

Lemm Construction Photographs (May Work)

Lemm Construction Photographs (May Work)

Lemm Construction Photographs (May Work)

Lemm Construction Photographs (May Work)

Lemm Construction Photographs (May Work)

April Work Update - Project is on schedule Stage Wave work Area A grade beam preparation Area A concrete pad has been poured Steel erection started Exterior punch openings complete and prepped for new windows Area C ready for inspection Area B metal framing and masonry ready for inspection & interior door frames installed Operable partition track installed at cover play area & music room Area B & C ceiling framing commenced Furrdowns at collaboration spaces commenced Area C tile installation begin this week

April Work Examples

Lemm Construction Photographs (April Work)

Lemm Construction Photographs (April Work)

Lemm Construction Photographs (April Work)

Lemm Construction Photographs (April Work)

Lemm Construction Photographs (April Work)

Lemm Construction Photographs (April Work)

March Work Examples

Lemm Construction Photographs (March Work)

Lemm Construction Photographs (March Work)

Lemm Construction Photographs (March Work)

Roofing (March Work)

Lemm s Legacy Lemm is committed to high-quality and innovative teaching and learning. We focus on the success of every child! Although Hurricane Harvey affected us in many ways, Lemm will be restored with educational space for our current students and those that will continue the Lemm tradition of greatness for years to come.

Lemm Aerial View

Covered Entry & Walkways Lemm Front Entry

Natural Light via Windows Lemm Next Generation Classroom

Natural Light via Solar Tubes Lemm Collaboration Space Shared Flex Space

Classroom Doors Garage-Type Doors Glass walls Flexible Spaces Lemm Bird s Eye View of a Classroom Module

Acoustical Tiles Stage Lemm Cafeteria & Stage

Green Room Makerspaces Learning Commons Library Flexible Seating Lego Wall & Dry Erase Wall

Timeline Key Emergency Services Roofing Procurement Klein ISD Lemm Roof Setback Educational Architect Programming Development Construction Punch List FEMA

8/29-9/28 8/31 & 9/1 9/1 9/18 9/19 & 21, 28 Emergency Services Roofing Project Emergency Planning Procurement Process Step One Document Collection/Inventory Discussion regarding bond, insurance, FEMA, etc. regarding the Lemm restoration Board approved project initiation for Lemm restoration project with PBK Architects using CSP method 1) As-built documents compiled by KISD for the PBK architect team; 2) Lemm inventory review and planning meeting with KISD purchasing department; 3) Lemm Post-Debris Survey with PBK; 4) KISD met with insurance claims adjuster Debris Removal and Preliminary Demolition 1) Board approves resolution to authorize emergency services to procure roofing project; 2) Roofing consultant begins preparation of construction documents August - September Timeline

10/13 & 20 FEMA Requirements Notification 1) Received FEMA letter indicating normal procurement processes must be adhered to after emergency clean-up; 2) FEMA recovery scoping 10/17, & 31-11/17 10/18 Roofing MEP Survey 1) Roofing bids accepted; 2) Roofing contract negotiations and document verification process KISD surveyed Lemm with SOBE (MEP) 10/20 & 27 Educational Programming Lemm restoration programming meeting to start discussion of educational space needs 10/25 & 26 Funding 1) Discussion of estimated expenditures for bond funds; 2) Preliminary discussion of repair estimate; 3) Lemm walkthrough with Vericlaim and Insurance consultant 11/1 & 22 11/3 & 9 11/7 11/3, 17 & 27/17 Architect Development Detention Requirements FEMA Requirements Progress Planning PBK internal meeting with consultants Oct. - Nov. Timeline 1) Inquiry into detention FEMA Program Delivery requirements but HC flood Manager (PDM) meeting control regulations unclear; 2) Lemm restoration progress meeting with discussion about requirements to bring building up to current Fire and Energy Code Lemm restoration progress meeting 10/26 Architect Development PBK internal meeting with consultants

12/1, 5, 8,15, 19 & 21 12/6 & 18 12/11 & 12 12/11 12/27 Progress Planning FEMA Roofing Project Procurement Process Steps Two & Three Architect Meeting 1) Board approved the roofing contract; 2) General contractor mobilization Board approved the schematic design and design development for the Lemm restoration process 1) Lemm restoration progress 1) FEMA PDM meeting; 2) Meeting meeting including Klein Cain with HC.; 3) HC notified KISD of interior design students helping requirement to raise Lemm by three with color selections; 2) Bond feet; 4) Clarification of HC expenses discussion; 3) PBK regulations coordination with consultants, 4) PBK 50% document review PBK project milestone meeting with consultants 1/5 1/12, 19 & 23 1/16, 23, 24, 29 & 31 1/22-24 1/26 Roofing Project Progress Meeting Architect Meeting FEMA KISD Internal Review Roofing work begins Lemm restoration progress meeting PBK coordination meetings with consultants & 75% set review FEMA Site Inspections with final walk-through on 1/24 Lemm restoration department review with maintenance/it and review of architectural changes Dec. - Jan. Timeline

2/5 2/5 2/10 & 17 2/12 Procurement Process Steps Four & Five Progress Meeting Architect Meeting Procurement Ad Lemm restoration progress meeting PBK coordination meeting with consultants Required advertising released in The Chronicle Board approval of construction documents & approval authorizing the superintendent to negotiate and execute the construction contract 2/13 2/20 2/27 Procurement Process Pre-proposal Conference Procurement Process 1) Construction plans released for competitive sealed proposal (CSP); 2) Plans submitted for permitting and accessibility (ADA) Pre-proposal conference for interested general contractors Competitive sealed proposals (CSP) due and evaluation process begins February Timeline

3/1 3/2 3/5-19 March 20 March August Procurement Process Procurement Process Contractor Roofing Project Construction 1) CSP evaluation continues; 2) Recommendation of contractor to superintendent Construction contract negotiation and execution Contractor permitting process & mobilization Roofing substantial completion Construction restoration to commence on or about March 19 August Sept. Construction & Move-In Final Construction Construction Restoration; Substantial Completion; Move-In Punch List Items March - Project Completion Timeline