NTPC LIMITED. Bhadla, Rajasthan CASE STUDY

Similar documents
CASE STUDIES EPC NTPC LIMITED. Mandsaur, Madhya Pradesh CASE STUDY

We are pleased to quote our best price for 5 M W Solar Plant as appended. Annexure I : Price Schedule for 5 M W Solar Plant

HARTEK POWER PVT LTD SOLAR BUSINESS CATALOGUE (Formerly known as Amtek Energy & Power Pvt Ltd)

Environmental and Social Monitoring Report. THA: Provincial Solar Power Project Phase 2B Bang Pa-hun, Phranakorn Sri Ayutthaya

About NPS Green Energy

NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT

GLOBAL SOLAR EPC SUMMIT

A PV, diesel, ESS hybrid case study: The DeGrussa solar project

DSM Initiatives. Rajib Das Senior Manager (Distribution New Initiatives) December 2, 2013

7 Project Description

Solar Parks Concept, implementation and lessons learned. A Presentation by Agostinho Miguel Garcia SunBD Sun Business Development

White Rock Wind Farm Project update Community Consultative Committee 3 August 2017

TECHNICAL ASSISTANCE RAJASTHAN RENEWABLE ENERGY CAPACITY DEVELOPMENT AND IMPLEMENTATION SUPPORT

Jawaharlal Nehru National Solar Mission

PRE FEASIBILITY REPORT

Solar Energy Workshop

KINGSTON SOLAR LP. Sol-Luce Project Overview. August 13, 2014

Power Sector in Andhra Pradesh and Telangana during September 2014

790 sq miles / 2,038 sq kms

Local Vendor Opportunities. Darling Downs Solar Farm. Engineering Intelligence

Energy Generation, Transmission and Distribution (GTD) Mr. André Luís Rodrigues

SURINDER RAINA GM-I/C(RE & Nuclear)

Fringe-of-Grid PV Projects - Normanton Solar Farm

SOLAR SOLUTIONS PROVIDER

FLEXIBILITY HOW TO CONTRIBUTE TO THE STABILITY OF THE GRID THANKS TO THE FLEXIBILITY OF YOUR PRODUCTION PROCESSES?

Solar Energy - Securing Energy for Tomorrow Today. Dr. Vinay Hasabnis

Renewable Integration in India

Appendix A Technical Specifications Engineering Services for the Nocatee 230/26kV Substation

New York Community Solar Facility Decommissioning Plan

C&B Alberta Solar Development ULC

Pre- FEASIBILITY REPORT

Local Vendor Opportunities. Gannawarra Solar Farm. Engineering Intelligence

AFRICA. Transforming Africa s energy landscape today

Rykove Solar Project Non-Technical Summary

PFISTERER CrossPower

Private Sector Partnership for Inclusive Solar Park Development in Rajasthan Jaipur, 12th April 2016

(B) PREFEASIBILITY REPORT OF EXISTING BLACK TRAP PROJECT OF

INFRASTRUCTURE DEVELOPMENT IN GEOTHERMAL FIELDS: A CASE STUDY FOR MENENGAI GEOTHERMAL PROSPECT, KENYA

NERSA Public Hearing Dyason s Klip 1 (Pty) Ltd

Company Introduction and Information EPTCON LTD. 560 SHELDON DRIVE, CAMBRIDGE ONTARIO. PHONE:

Big Thunder Wind Park

Study of Using Energy Storage to Mitigate the Impact of High Renewable Energy Penetration to the Grid

BANKABILITY OF SOLAR PROJECTS HOW TO MAKE YOUR PV PROJECT BANKABLE? HOW TO SELECT EPC CONTRATCOR? ROLE OF TECHNLOGY SELECTION

A Shining Example of Project Success

TRAINING COURSES IN RENEWABLE ENERGY

Training: MED-SOLAR MODULE :4. Constructing and Starting-up Of a Solar Power Plant

Renewable energy. Sustainable investments. Summary PORTFOLIO HIGHLIGHTS SEPTEMBER Environmental Impact Calculator

project 36 MW 1.0 INTRODUCTION AND PROJECT INFORMATION

Dynamic Pricing. June 2, 2016 Harvard s Electricity Policy Group

Proposal Data. Submittal Form

E3072 v2. GEF Large City Congestion and Carbon Reduction Project. Environment Management Plan. Public Disclosure Authorized

PROJECT BRIEF. Noise environment: No Entrant noise generation sources exist in and around project area.

Customer Sited Solar PV & The Impact of Grid Interactive Systems

REQUEST FOR BID (TURNKEY SOLUTION) 1MW GRID TIE SOLAR PV POWER PLANT. Location:

Additional Information on Project Components

The world s leading sustainability consultancy

Community Clean Energy Resiliency Initiative PON-ENE BESS Request for Proposals Question and Answer Log

ENVIRONMENT MANAGEMENT PLAN. For Excavation of Brick Earth (Total Mining Area Ha.) (for Manufacturing of Bricks)

EXPRESSION OF INTENT FOR 100 MW SOLAR PV PROJECT ON EPC BASIS AT KHARAGHODA

THE DISTRIBUTION SYSTEM SECURITY AND PLANNING STANDARDS. Asset Management & Regulation, ESB Networks

INGENIA ASLAT Our experience at your service

Modernization of the Power System

AMENDMENTS TO BAYFIELD COUNTY ZONING ORDINANCE. Lake Superior Shoreland Lot Development Requirements.

Environmental Management Plan

International Innovations Awards CAPAM GUJARAT STATE ELECTRICITY CORPORATION LIMITED. A new direction to green,clean and inclusive

SOLAR. Ground, Rooftop, Water, Space. Think Solar Think BHEL

UNIVERGY AROUND THE WORLD

Making Renewable Energy Integration Compatible with the Security of the System

EMPOWERING HUMANITY BY ADDRESSING THE TOUGHEST CHALLENGES OF ENERGY DELIVERY

The Jeffreys Bay Wind Farm

DETAILED NOTICE INVITING TENDER WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY LIMITED. (A Govt of West Bengal Enterprise)

RAPID. RELIABLE. REMOTE.

EXECUTIVE SUMMARY ON ENVIRONMENTAL IMPACT ASSESSMENT REPORT

Design and Development of Hybrid Power Generation System

The Energy Supply and Purchase Agreement (ESPA) was signed between Solar Energy Ltd and the Central Electricity Board on 28 November 2014.

Ref. No.: SRMU/NDP-I/VBMPS-II/ INVITATION FOR QUOTATION FOR SUPPLY OF GOODS UNDER SHOPPING PROCEDURES

NIAGARA REGION WIND FARM. By Hugues Girardin and Michael Weidemann. ENERCON Forum 2016 The Global Energy Revolution November 16, 2016


The women in our village want solar panels so their children can study at night.

Regional Rusumo Falls Hydroelectric Project. Terms of Reference for the Project Manager

FAQs on ESIA of CASA-1000

Massachusetts _Lowell Renewable Energy Sources / Brief World Wide Renewable Energy. Impact of Renewable Energy on Utility Grids

SOLAR POWER STATEMENT OF QUALIFICATIONS. experience matters

NT Solar PV Commercialisation Pilot Project --- Information Package ---

Welcome Old Jackson Solar Project Public Open House

INDIA S LEADING ROOFTOP SOLAR SOLUTIONS PROVIDER

Technical considerations for integration of distributed renewables on the grid

Action Plan along with the budgetary allocation for the queries raised in the public hearing is given below:

TECHNICAL SPECIFICATION DESIGN, PROCUREMENT, INSTALLATION AND MAINTENANCE OF PHOTOVOLTAIC SOLAR POWER PLANT AT AZRAQ REFUGEE CAMP

New Reclaim Tunnel at Coal Fired Plant

PROJECT TECHNICAL DESCRIPTION

Northumbria Research Link

Progress Report for the Renewable Energy Training Centre (June 2012)

NERC Lessons Learned and Industry Recommendation

PV + Storage for Load-Shifting in the Cook Islands

BRYPAAL SOLAR POWER (PV) PROJECT AND ASSOCIATED INFRASTRUCTURE

Peterborough City Council Energy from Waste Facility Fengate, Peterborough. Phase 1 Energy Stury

More than ONE GIGAWATT

Transcription:

NTPC LIMITED Bhadla, CASE STUDY

NTPC LIMITED Bhadla, PROJECT OVERVIEW R Site Co-ordinates 27.5N, 72.0E R Plant capacity 130 MW (2 blocks of 65 MW each) R Connection Type & Connected to Grid connected - Bhadla 220KV Pooling Station -1 R Rated System Power 130 MW R Total Site Span 3.5 km length & 1.0 km wide R Number of Modules About 4,40,000 nos. R Inverter Solar Grid Connected Inverter (104 nos.) R Power Evacuation At GSS-1 pooling station (132kV) Bhadla Solar Park Phase-II, Village Bhadla, Tehsil Bap, District Jodhpur, R Total Land Area 663 acres

Local Manpower: The project s major problem lied with local unskilled manpower. Mitigation: We had to engage and train local workers for temporary works and hire tractors, trolleys and other small machineries locally to aid the process. CASE STUDIES EPC NTPC Limited Bhadla, CHALLENGES & SOLUTION Soil & Land Strata: The land strata of the project site varied extensively with presence of small dunes in a sandy terrain. Naturally, the project team faced immense difficultly in moving the construction equipment and machineries. The project team encountered rocks at depth of 0.5 m, 1.5 mm and complete sand due to which the pilling work was done at 3 different depths in Zone A, Zone B & Zone C. Mitigation: Temporary murram road was built to access the site for construction and moving of machineries. Weather: Extreme weather conditions at the project site posed a problem. The summer temperature was as high as 500 C; from April to July, cyclonic storm ensued with prevalence of strong wind between 11 am to 4 pm and work came to a halt. Similarly, the temperature during winter was as low as 50 C (night). Mitigation: Controlled working hours along with a dynamic work schedule allowed us to deliver the project on time. Continuous hydration of the workers ensured better productivity. Construction Power and Water: This project had a multitude of problems. Firstly, there was an absence of a continuous power source. But arranging for it with immediacy was quite difficult considering the remoteness of the area. Also, quality of the available bore well water was not suitable for going ahead with the construction work in an uninterrupted way. Mitigation: We procured power from RRECL for construction site and used Diesel Generator sets to get uninterrupted power. For civil works, we had to arrange for canal water from nearby areas. Murram Sourcing: Sourcing of murram was a challenge in the area. The process of getting approval from the mining department was tough and required extensive compliances and certificates from our side. Mitigation: We provided all the backings and fulfilled the compliances for getting the permission from the mining department for sourcing the murram.

PROJECT USP The 130MW NTPC project is the largest solar PV plant ever executed by Vikram Solar since its incorporation. The project is located inside the Bhadla Solar Park, built by RRECL, with basic infrastructural support like GSS, pooling station, bitumen road, approach road, street lights, construction water and land lease. Permissions from multiple government bodies were acquired and statutory norms were diligently followed during the installation and commissioning of the plant. This was the first-of-its-kind project under our supervision. In order to avoid soil erosion, murram spreading was done up to 1 sq. m. of the pile area for each of the 73,000 piles. Commissioning of 2 x 65MW blocks was done in 4 phases (40MW, 25MW, 25MW & 40MW). The solar plant was commissioned prior to the scheduled time and generation started about two months in advance, which is considered as an achievement on its own owing to the size of the project. The work started from 8th February and continued up to 24th March. Vikram Solar was the first among all the other bidders to commission the project successfully. Total 4,40,000 solar PV modules (approx.) were installed in the 130MW plant. Total 7500MT of steel were used for the mounting of the module structure. Each 65MW block has a unique switchyard which steps up the plant voltage from 33kV level to 132Kv level with the help of 63MVA grid transformer. One of the first helipads in the region was developed inside this project area block. CASE STUDIES EPC NTPC Limited Bhadla, 9

STEP BY STEP DEVELOPMENT Structure mounting Structure mounting Module mounting Switch yard

CASE STUDIES EPC NTPC Limited Bhadla, Weather monitoring station Inverter 11

STEP BY STEP DEVELOPMENT Control room Control room: inside view Fencing

ENVIRONMENTAL BENEFITS Expected Annual Energy Yield 212.44 million unit. The plant is also expected to reduce CO 2 emissions to the tune of 203942.4 metric tonnes annually. CASE STUDIES EPC NTPC Limited Bhadla, 13