Presentation Overview. Background. Coast Crane Company Background. Coast Crane Company TOWER CRANE INSPECTIONS

Similar documents
Peter Juhren Corporate Service Manager Morrow Equipment Co. L.L.C. Salem, OR USA. What s New in Tower Crane Standards?

ASSEMBLY / DISASSEMBLY POWER LINES POWER LINES. Identify Work Zone. Work Zone

RECOMMANDATIONS TO MAINTAIN TOWER CRANES IN SAFE CONDITIONS

MOUNT RAINIER CHAPTER FEDERAL SAFETY AND HEALTH COUNCIL

Lifting Appliances of Ships and Offshore Installations

Cranes & Derricks in Construction. AIHA/ASSE September 17, 2010

EASTERN MICHIGAN U N I V E R S I T Y AERIAL WORK PLATFORMS PROGRAM

Standards Summary Sheet

Effective Date: 10-January Table of Contents

Guideline No.: G-01(201510) G-01 CRANES. Issued date: October 20,2015. China Classification Society

Dr. Ahmed Hussien Elyamany 2017 Questions

Could be remote control or cab operated.

Scaffolds. OSHA Office of Training & Education 1

Scaffolds. OSHA Office of Training & Education 1

Crane & Derrick Operation Procedures for Construction

ANSI/ ASME HST Performance Standard For Overhead Electric Wire Rope Hoists

Installation and Maintenance Manual for EMH Freestanding Workstation Jib Cranes

Economic concrete distribution with stationary booms

Lifting Operation Safety

Rapid Axial Load Testing of Drilled Shafts

PAGE 1 OF 10 HEALTH, SAFETY & ENVIRONMENTAL MANUAL PROCEDURE: S370 Mobile Cranes Procedure REV /14/2012

Crane Certification FAQs

Tower Cranes LN

This guide can be used to prepare a specification for incorporating free standing jib cranes into a competitively bid construction project.

Self-Erecting Tower Cranes

This guide can be used to prepare a specification for incorporating wall bracket jib cranes into a competitively bid construction project.

CRANES & MOBILE LIFTING EQUIPMENT

Presentation Title. OSHA Cranes & Derricks Subpart CC. October 1, Presenter Name Presenter Title Event Name

Document Revision Change Table Revision Number

Cranes and Derricks Standard Summary. April, 2010

MOBILE CRANE OPERATOR

Construction Safety Education Forum. 6 March Scaffolding. Dimitri Barlas, State Coordinator Construction Work Health and Safety Division DRAFT

Reliant Holdings Ltd Safety Management System

TLILIC3008A Licence to operate a slewing mobile crane (up to 20 tonnes)

ROOM-MATE. 3T - Through the Trapdoor USER GUIDE

Scaffolding and Raised Platforms

SCAFFOLDING SAFETY PROGRAM

STANDARD PRACTICE INSTRUCTION

600 SERIES FOUNDATIONLESS JIB CRANE MANUAL ADDENDUM

Safety First Mobile Towers - 3T Method INTRODUCTION

70 & 74. CMAA is an affiliate of the Material Handling Industry of America division of Material Handing Industry. Prepared by

RP 3.0: INSPECTION AND CERTIFICATION OF MASTS. A Recommended Practice (RP) for the Canadian Well Servicing Industry

A-Series Steel Gantry Crane

Span 300 Instruction Manual

Safety Instructions For Overhead Crane Operators

CEILING MOUNTED ARTICULATING JIB CRANE

Presentation Title. OSHA Cranes & Derricks Subpart CC. Washington Metropolitan Area Construction Safety Association.

Scaffolding Procedures

Crane 101. An introduction to mobile cranes by Anthony Crane USA

Tower Crane Operator

Aerial Lift and Scaffolding Guidelines

Bulk Bag Unloader Installation, Operation and Maintenance Manual

PF-Series Gantry Crane

Aerial and Scissor Lift

Scaffolding Glossary of Terms A

MOBILE CRANE OPERATOR

SCAFFOLDING PROCEDURE

1450/850. Instruction Manual. Mobile Access Tower

OSHA S NEW CRANE STANDARD

CLIMA AGR. Mobile Aluminium Tower with Climbing Frames 1450/850 Camlock Advanced Guardrail USER GUIDE

Mobile Towers - 3T Method

WALL CANTILEVER WORK STATION JIB CRANE

Scaffold Inspection Procedures for the Competent Person. Merle Errthum

Load Handling (Hoisting) Policy

SafeDeck Supported Scaffold System

Scaffolding. Safety Guide. STOP! Before you climb

Scaffolding Safety. Scaffolding

References. EM , Sections 22 OSHA 29CFR (Subpart L ) UFGS [Latest] ANSI A

This guide can be used to prepare a bid specification for the incorporation of a Mast Jib Crane into a competitive bid project or application.

Part 3: Cranes Vocabulary. Tower cranes

This User Guide provides you with step by step instructions to ensure your system is erected easily and safely.

Contents. Technical Test Learning. Crawler Crane Tower Crane

Span 400 Instruction Manual

Walking & Working Surfaces / Back Safety and Ergonomics

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 7

CLIMA 3T. Mobile Aluminium Tower with Climbing Frame 1450/850 3T - Through the Trapdoor Method USER GUIDE

PART 22 POWERED MOBILE EQUIPMENT GENERAL. Application 22.1 This Part applies to every workplace where powered mobile equipment is used.

MODEL : TM-ZR566S(HEF)

Span 500. Elite Instruction Manual. DESIGNATION SPAN 500 Double Width EN /12 XXXD SPAN 500 Single Width EN /8 XXXD

SAFE WORK PROCEDURE: MOBILE ELEVATED WORK PLATFORMS (MEWP)

OCCUPATIONAL HEALTH AND SAFETY ACT SCAFFOLDING REGULATIONS

Tower Crane Erection and Use

WORKING AT HEIGHT. The company will comply with the Work at Height Regulations 2005, its schedules and Codes of Practice.

ADMINISTRATIVE BULLETIN

CLIMA 3T. Mobile Aluminium Tower with Climbing Frame 1450/850 3T - Through the Trapdoor Method USER GUIDE

Wall Mounted Jib Crane

PORTABLE LADDER SAFETY

BoSS Room-Mate. 3T - Through the Trap Method

This guide can be used to prepare a specification for incorporating free standing jib cranes into a competitively bid construction project.

Orientation to the Trade Annotated Instructor s Guide

Copies of the written program may be obtained at Where are copies of this written plan kept? (Insert building/room, etc.).

Golden Rule #5: Lifting & Mechanical Handling

BECx Construction Phase Safety

The following is Copyright 2009 The Queen s Printer, Saskatchewan

Regulations of dd Month 20yy on cranes and lifting operations on mobile offshore units

PS 02 PLANT AND EQUIPMENT

Title: Scaffolding Safety Policy. University Division/Department: Environmental Health & Safety Effective Date: October 6, 2017 Page: 1 of 15

T-Series Gantry Crane

WALL MOUNTED ARTICULATING JIB CRANE

Transcription:

TOWER CRANE INSPECTIONS Presented by Mike Heacock Coast Crane Company Presentation Overview Background of Coast Crane and Mike Heacock Review common tower crane types Pre-delivery inspections for new tower cranes. Required by manufacturers Storage and transportation of cranes and components Preassembly and jobsite delivery inspections On site preparations, inspections, calibrations and orientation Periodic inspections on site Background Graduate of U of W in Construction Management 15 years of experience working in the crane industry 10 years working with tower cranes While at Sunnen Crane Service I helped pioneer the use of self erecting tower cranes in the Northwest Currently the Tower Crane Division Manager for Coast Crane Company Coast Crane Company Background Elite Dealer for Manitowoc Crane Group Territory includes California, Oregon, Washington, British Columbia, Alaska - Manitowoc Crawler Cranes - Grove Mobile Cranes - National Boom Trucks - Potain Tower Cranes - #1 Self Erecting Tower Crane Dealer in North America - 1st MDT City Crane Dealer for MCG Dealer for Comansa Tower Cranes for California Dealer for Tadano Tractor Mounted Boom Trucks Coast Crane Company Coast Crane s Tower Crane Fleet - Approximately 100 Units 2/3 of fleet is Self Erecting Cranes 1/3 of fleet is Hammer Head Cranes 1

Self Erecting Tower Cranes Pendants Tower Top Counter Hammer Head Tower Cranes Pendants No tower top and pendants reduces the topless crane s overall height. This is advantageous on multi-crane projects or around airports. The jib also does not have to be completely assembled on the ground because it does not rely on Trolley pendants for support. Trolley Hammer Head cranes slew at the top of the tower Counter Self erecting cranes can be operated from a cab located at the top of the crane but quite often they are operated from the ground via wireless remote control. Hammer head cranes require an additional crane for erection / disassembly. Pieces are erected individually or as component groups. Back stay or back pendant As their name implies, self erecting cranes have the ability to completely assemble themselves without the aid of an additional crane. This significantly reduces the erect / disassembly cost. The tower of most self erecting cranes turns with the jib. Some towers telescope out to predetermined heights giving the user multiple tower heights to choose from. Other towers fold half way up and only allow one tower height to work at. Operators typically control the crane from a cab at the top of the crane which swings with the jib. Tower Tower sections range in length but are generally 15-20 tall and can be erected either one at a time or in multi-section groups to save erection time on site. Cranes equipped with self climbing gear have the ability to add tower sections under their own power. This enables the crane to be erected at a lower tower height and grow with the building. Most self erecting cranes swing at the bottom of the tower Self erecting cranes are free standing on an outrigger type base. Drive bogies can be attached so the crane can move around a job site on rails. TRADITIONAL HAMMER HEAD Ballasted Cross Frame Base These bases require a smaller concrete footing but require enough space for Static base the cross frame and ballast. These These bases require a large bases work well outside the building concrete footing but only require footprint. These bases require extra enough space for the tower. These assembly time and trucking. Traveling bases work well in elevator shafts bogies can be attached and the crane or where space is limited. can move around a job site on rails. TOPLESS HAMMER HEAD Luffing Tower Crane Luffing tower cranes are advantageous when working in cities or other areas where buildings or other structures would obstruct 360 swing of a traditional tower crane. Luffing cranes are also useful on multi-crane projects where hammerhead crane jibs would not have clearance. Drawbacks to luffing jib cranes are high monthly rental rates and erect / disassembly cost. Boom Hoist Bridle Pendant Gantry Machinery Platform Fixed Unlike other tower cranes which utilize a trolley system, the jib on luffing tower cranes is configured like a lattice boom mobile or crawler crane. The crane uses a gantry and boom hoist to raise and lower the boom with the load block always suspended from the jib / boom tip. Swinging Many luffing tower cranes have both fixed and swinging counterweights. Swinging counterweights move away from the center of rotation as the operator booms down and towards the center of rotation as the operator booms up. Greater maximum radius capacities can be achieved with this system. Most luffing cranes slew at the top of the tower Tower Tower sections range in length but are generally 15-20 tall and can be erected either one at a time or in multi-section groups to save erection time on site. Operators typically control the crane from a cab at the top of the crane which swings with the jib. Cranes equipped with self climbing gear have the ability to add tower sections under their own power. This enables the crane to be erected at a lower tower height and grow with the building. Base Luffing tower cranes can be put on both static and ballasted cross frame bases. Static bases (as shown) require only enough room for the tower but have a large concrete footing. These bases work well in elevator shafts or where space is limited. Ballasted cross frame bases (not shown) require smaller concrete footings but occupy much more room and are generally used outside the building footprint. Traveling bogies can be attached and the crane can move around a job site on rails. Pre-delivery Inspections for New Cranes New crane components are unloaded from containers or trucks Inspected for shipping damage All components are assembled (ie jib sections pinned together) & then disassembled into subassemblies for shipping to the jobsite All electrical components are connected, energized and tested as a complete unit Testing checks for electrical shipping damages that may not be noticeable from a visual inspection Self erecting tower cranes are erected in our yard. The cranes are function tested and load tested both static and dynamically to loads that exceed on site testing (required by manufacturer) 2

To maintain integrity of tower crane components, and prolong the life of these expensive tools, tower cranes and their components must be stored, transported and handled properly to ensure they stay safe for a long period of time. STORAGE IN YARD Components must always be bunked on wood or steel blocking to keep the components from being damaged Components must also be stored in a manner so water cannot pool in the surface of the components promoting corrosion Some electrical components should be either covered or stored indoors to ensure their longevity by reducing their exposure to moisture. RIGGING & HANDLING Most manufacturers supply information on proper lift points or methods. These instructions must be followed in order to ensure the components are not damaged while handling the crane components. TRANSPORTATION Chain tie downs should always be avoided for securing equipment on the trailer. If possible, use nylon straps to secure the loads. Chain must never be used to secure lattice type equipment (ie. jib, tower etc.) If chains must be used on non-lattice equipment, softener must be placed between the chain and the component being tied down to ensure the chain links do not dig into the component during transportation. All components loaded on trucks should be able to sit on the trailer without being tied down or rigged to a crane. Performed prior to shipment to project site Must be performed by competent person Documentation must be kept. See sample documents for periodic checklist for hammer head tower cranes SUMMRAY OF INSPECTIONS Visual inspection of structural components Looking for damaged lacings, cracked welds, bent or damaged components Components with suspect welds or cracks must be NDT tested All repairs must be made by a certified welder experienced in performing repairs of this type All materials must either be supplied by manufacturer or must be approved by manufacturer 3

SUMMRAY OF INSPECTIONS (cont) Clean and Inspect all pins and bolts that are removed during assembly / disassembly Cleaning should be done with solvent or other degreaser Cleaning with a wire brush or wheel should be avoided as it may remove protective coatings and over time reduce the diameter of the pin or bolt. Pins or bolts with suspect cracks must be NDT tested and replaced if cracks are present SAFETY ITEMS Check the condition and installation of all ladders platforms, ladders and handrails Check to see all warning signs and safety decals are in good condition and in their proper place Check to see the fire extinguisher, operating manual and log book are in the cabin or operators station WIRE ROPE Inspect wire rope as per ANSI B30.3 instructions for tower cranes Damaged wire rope must be replaced or shortened by removing the damaged section of rope Proper procedures must be followed by an experience individual when shortening wire rope (Cutting with an oxyacetylene torch is generally not an approved method for shortening tower crane hoist ropes) ELECTRICAL COMPONENTS The inspections required will vary by model and manufacturer Primary components Electrical slip ring clean & inspect for abnormal wear Cabin / remote controls clean & check functions Limit switches check condition Motors test conditions of windings (megger test) - check brake adjustments, pads or linings Electrical supply cable inspect for damage (ie. cuts, cracks etc) - Electrical cabinet components - check for signs of wear on contactors, timers, etc. On Site Customer responsibilities Foundation Engineer must evaluate soil (self erecting crane) or design concrete footing Provide survey instrument and qualified person to plumb the base tower section when it is set Break concrete cylinder from footing prior to erecting tower crane Industry Standard for tower crane plumb tolerance is L/500 example: Δ=96 /500 Δ=.192 max. 4

On Site Assembly / Disassembly Provide unobstructed work area for assembly of components Restrict access for other trades to assembly areas and areas under overhead work Have licensed electrician on site to connect or disconnect the crane to the electrical and grounding service Turnover report (see sample documents) Technician and operator checklist which double checks all components and systems of the crane have been properly assembled In Service Certification (load test report see sample document) Functional tests of the crane are performed checking all systems Calibration of all movement limits and capacity limits as well as testing the support structure or footing On Site OPERATOR ORIENTATION It is extremely important that all operators (regardless of qualifications) review the functions, features and safety items of each tower crane with a qualified crane technician Periodic Inspections On Site Operator inspections (see sample documents) Daily logbook visual inspections and functional checks of crane systems Weekly logbook detailed visual inspections and routine maintenance Coast Crane Inspections (see sample documents) Periodic 3 month visual inspections and routine adjustments of crane systems Annual detailed visual inspections and major adjustments and checks of crane systems 5