Site Specific Hazardous Material Abatement Work Plan

Similar documents
HAZARDOUS MATERIALS SPECIFICATIONS

ADDENDUM NO.: 1 TO THE CONTRACT DOCUMENTS For SCC SWING SPACE FOR MOHR HALL MODERNIZATION (Existing Temps)

Hazardous Materials G

WORK INSTRUCTIONS COLORADO SPRINGS NNO FACILITY EQUIPMENT SALVAGE PLAN VERIZON WIRELESS PROJECT MANAGER PATRICK SKILLEN PREPARED FOR:

Pre-Demolition Hazardous Material Survey Report Administration Building, Building D Piedmont High School 800 Magnolia Street Piedmont, CA

LIMITED POTENTIALLY HAZARDOUS MATERIAL BUILDING INSPECTION REPORT AND ASBESTOS BUILDING INSPECTION REPORT. for

Asbestos and Lead Considerations in Construction Projects. Sean Purcer Senior Consultant Anthony Price Senior Consultant

A. Illinois Asbestos Abatement Act, as amended through Public Act , effective July 14, 1995.

COMMUNITY ACTION CHIP LEAD PROGRAM Bids due to Community Action ATTN: BERNADETTE JOHNSON 175 Main St. Battle Creek, MI 49014

SECTION DEMOLITION WASTE MANAGEMENT AND DISPOSAL

HAZARDOUS MATERIALS SPECIFICATIONS BID SUBMITTAL

Work Plan for Window Removal and Remediation Rooms: 200 Wing classrooms, Cafeteria and Kitchen Thomas Prince School Princeton, Massachusetts

Roseville OFFICE* 1911 Douglas Blvd, ste * Roseville, CA Phone (916) * Fax (916) *

Building Consent COMMERCIAL

APPENDIX A HAZARDOUS MATERIAL SPECIFICATIONS

DIVISION 02 EXISTING CONDITIONS 2010 Edition, Published January 1, 2010; Document Revision Date: February 7, 2017

Chabot - Las Positas Community College District. Chabot College Projects. Building Chabot College Hesperian Boulevard, Hayward, CA 94545

ALVARADO INTERMEDIATE SCHOOL - PARTIAL MODERNIZATION

Certification Number: NAT Lead Renovation, Repair and Painting Program

ABATEMENT PLAN FOR REMOVAL OF ASBESTOS, LEAD-BASED PAINT, PCB LIGHT BALLAST AND LIGHT TUBES

Alameda County Waste Management Authority Model Specification Update March 2004 SECTION CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

ABATEMENT PLAN FOR REMOVAL OF ASBESTOS-CONTAINING MATERIALS AND LEAD-BASED PAINT

1116 Willow Pass Court DESTRUCTIVE TESTING Concord, CA SFUSD PROJECT NO SAN FRANCISCO UNIFIED SCHOOL DISTRICT

HAZARDOUS MATERIALS SPECIFICATIONS

Abatement Scope of Work and Project Requirements for Library Painting Project Bay Shore Library Bret Harte Library Dana Library Long Beach, California

ALVARADO STREET SAN FRANCISCO, CA VARIANCE APPLICATION

Appendix J-29 Abatement Plan for Removal of Hazardous Materials, Men s Central Jail Project, Parking Lot 45: 725, 739, 747 North Spring Street

Asbestos Abatement Standard Procedures Indoor Environment Group, Inc.

REMOVAL AND DISPOSAL OF MATERIALS CONTAINING LEAD. A. General provisions of the Contract, including General and Supplementary Conditions.

Project 6668 Second beach Concession-Stanley Park Drive,Vancouver, BC Division 02080

Project Address Applicant: (Please Print) Plan review Engineer: Phone: Date

NORWELL PUBLIC LIBRARY 64 South St, Norwell, MA 02061

ABATEMENT PLAN FOR REMOVAL OF ASBESTOS AND LEAD-BASED PAINT

SCA FACILITIES DESIGN & CONSTRUCTION 135 VAN NESS AVENUE, ROOM 212 SAN FRANCISCO, CA 94102

PIER 26 and 28 BULKHEAD LIMITED ASBESTOS and LEAD SURVEY NTE Project No.: NT-3278

ABATEMENT PLAN FOR REMOVAL OF ASBESTOS, AND LEAD-BASED PAINT

Anticipated ICR 56 Revisions. Relating to Fire/Life Safety & Other Significant Issues

LOS RIOS COMMUNITY COLLEGE DISTRICT 1919 Spanos Court, Sacramento, CA Phone (916) FAX (916) Purchasing Department

(August 2015) UNIFIED FACILITIES GUIDE SPECIFICATIONS **************************************************************************

ATTACHMENT A. Bid # 6793

Post Abatement Project Report - Sample Draft Form:

C. Type of Selective Demolition Work: Demolition requires the selective removal and subsequent off-site disposal of:

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 01 GENERAL REQUIREMENTS SECTION CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

Addendum Number One. USC Preston College Bathroom and Flooring Renovations Part II Project Number: H SG

Office of Design & Construction State University Plaza Albany, New York

Chico State- Siskiyou Hall EXHIBIT B REQUIREMENTS FOR DISTURBANCE OF LEAD IN CONSTRUCTION TABLE OF CONTENTS

SECTION 2080 ASBESTOS ABATEMENT

APPENDIX C SAMPLE ASBESTOS ABATEMENT SPECIFICATION

University of Akron. Addendum No. 2. For. Zook Hall Renovation Phase 2A Abatement & Demolition Project #: UAK120015

DUQUESNE UNIVERSITY ASBESTOS OPERATIONS & MAINTENANCE PROGRAM

SECTION ASBESTOS CONTAINING MATERIALS REMEDIATION

ABATEMENT PLAN FOR REMOVAL OF ASBESTOS AND LEAD-BASED PAINT

DSC BUILDING 1200 ALTERATIONS OCTOBER 2011 SECTION CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

SCA SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES DESIGN & CONSTRUCTION 135 VAN NESS AVENUE SAN FRANCISCO, CA 94102

BARR & CLARK Independent Environmental Testing Asbestos Lead Mold Phase I ASBESTOS REMOVAL SPECIFICATIONS

SECTION 2 DIVISION 01C DESIGN SERVICES PROJECT GUIDELINES (INFORMAL)

DIVISION 02 EXISTING CONDITIONS

Hazardous Materials Inspection Services Seekonk Public Library, Seekonk, MA

SECTION ALTERATION PROJECT PROCEDURES

PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

Asbestos Procedures. Asbestos Abatement and Repair

INSPECTION TIMING CHECKLIST FOR RESIDENTIAL FRAME BUILDING PRIOR TO INSPECTION REQUEST

Prepared for Florida State University Facilities Planning& Construction By Environmental Health & Safety Tallahassee, Fl

ADDENDUM NO. 1. TO SCOPE OF WORK: Section 0220, Form 01004/5

Carter's Oshkosh (SIS) # The Center at Pearland Parkway - Pearland, TX Scope Of Work / Bid Qualifications

Prepared for: Prepared By: Vista Environmental Consulting, Inc North Tustin Avenue Anaheim, California Phone: (714)

APPENDIX 1 PROJECT REQUIREMENTS

In general, the management plan development process consisted of:

CITY OF ANDERSON BUILDING AND CODES 601 South Main Street

SECTION POLYCHLORINATED BIPHENYLS (PCB) REMOVAL

PROJECT MANUAL ABATEMENT SPECIFICATIONS

SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS

A. Prior to commencement of any work, make a complete inspection of all of the facilities listed in this specification

DUQUESNE UNIVERSITY ASBESTOS MANAGEMENT PROGRAM

See attached answers to questions and requests for clarification received.

SECTION UNIT PRICES. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

REPORT OF HAZARDOUS MATERIALS CONSULTING SERVICES

BuildingName The Description of the Project P DOCUMENTS

Project 6668 Kerrisdale Senoirs Centre-5851 West Boulevard,Vancouver, BC Division 02080

16 GAGE, CONTINUOUS STAINLESS STEEL RESTRAINT METAL TO SUPPORT CUT TILE AT TERRACE EDGES. 24" x 24" PORCELAIN PAVERS WITH EDGE RESTRAINTS 1/2" MAX

ANNEX A.1 TECHNICAL SPECIFICATIONS. Open Call for Tender. No F/SE/10/05. Provision of Building Inspection, Maintenance, Alteration and Repair services

LEAD HAZARD CONTROL PROGRAM

Facility Condition Assessment

SECTION EXISTING HAZARDOUS MATERIALS CONDITIONS

TECHNICAL QUESTIONS FOR ITB-DOT-17/ LV DEMOLITION AND CONSTRUCTION OF DISTRICT SEVEN OFFICE SPACE

CHAPTER 34 ASBESTOS. Where is it Found? 34 ASBESTOS. What is Asbestos?

SCA SAN FRANCISCO UNIFIED SCHOOL DISTRICT FACILITIES DESIGN & CONSTRUCTION 135 VAN NESS AVENUE SAN FRANCISCO, CA 94102

SECTION COPPER/ SOLDERED RF SYSTEM SPECIFICATIONS

Asbestos, Lead and Hazardous Materials Pre-demolition Survey Report

SURVEY FINDINGS Building: 1101

LEAD-BASED PAINT ABATEMENT SPECIFICATIONS

Project Monitoring & Air Sampling

ASBESTOS-RELATED DOCUMENT REVIEW of Eight Properties For City of San Leandro

Chabot Las Positas Community College District 5020 Franklin Drive Pleasanton, California (925)

RENOVATION OF THE VIA BUILDING FOR THE GUELPH TRANSIT TERMINAL FROM THE PRE- QUALIFIED GENERAL CONTRACTORS Reference Number:

INFORMATION SHEET. To demolish the entire building to the foundation will require a demolition permit (Form 6).

SCA ENVIRONMENTAL, INC.

PRICING DOCUMENT FOR REQUEST FOR APPLICATIONS FOR APPOINTMENT TO A MULTI-PARTY FRAMEWORK AGREEMENT FOR ASBESTOS REMOVAL AND DISPOSAL CONTRACTORS FOR

Section Asbestos Removal

Transcription:

Site Specific Hazardous Material Abatement Work Plan Jobsite Location: Pier 31 Building and Roof Repair Project Port of San Francisco San Francisco, California Prepared By: North Tower Environmental, Inc. 1485 Bayshore Boulevard, #185 San Francisco, CA 94124 April 16, 2015 I. SUMMARY This work plan is issued for the hazardous material scope work for Pier 31 Building and Roof Repair Project. The scope of work encompasses Pier 31, the adjoining Pier 29 ½ and rear apron. Building designations and a full description of project requirements and scope of work can be found in the project construction documents and plans. Contractor is responsible for reviewing the project construction document and plans. In general, the scope of construction work consists of selective demolition of building elements, repair of structural framing, roof and roof elements, windows, doors, ladders, restrooms; upgrades to power, mechanical, and plumbing, interior and exterior lighting and painting. A limited asbestos, lead and PCB survey, in preparation for the planned construction, was conducted and by North Tower Environmental, Inc. and the report was issued on April 15, 2015. Asbestos was identified throughout the roof as well as in drywall systems, flooring, sink undercoat, window caulk and window sealants. Lead Based Paint (LBP) and Lead Containing Paint (LCP) were identified on surfaces throughout the exterior and interior of the buildings. The scope of work covered by this abatement work plan includes the removal, handling, and disposal of hazardous materials. This work plan does not include non-hazardous material work performed as part of the overall project scope of work. The Contractor shall complete the abatement work in full accordance with this work plan and meet all applicable requirements of the Port of San Francisco contractor documents for this project including Hazardous Abatement and Controls and Selective Demolition sections Site Specific Asbestos Abatement Work Plan Page 1 of 8

II. PROJECT CONTACTS Contractor: Main Office: Project Manager: To Be Determined Environmental Consultant: North Tower Environmental Project Manager: Carolyn Henry: cell: (415) 740-8969 Field Supervisor: Gary Lowe: cell: (415) 577-9207 San Francisco Department of Carol Krop Public Works Representative: Main Office: (415) 554-8376 Port Of San Francisco Tim Felton Representative: Main Office: (415) 274-0582 III. CONTRACTOR REQUIREMENTS A. See Construction architectural plans and document for all project requirements including all general notes and sheet notes. B. In accordance with Hazardous Abatement and Controls (Section 02130) of the contract documents, contractor must submit a Hazardous Materials Management Plan (HMMP) that provides the Contractor s comprehensive plan for the management of hazards encountered during the work of this project. C. Portions of the building will remain occupied during the project. D. Contractor is responsible for protecting all areas adjacent to the work area from being impacted by hazardous material (i.e. lead or asbestos). E. Contractor is responsible for protecting the building interior during roof and roof gravel removal, including isolating any occupied areas in the building while work is taking place. F. The Contractor must take special care must be taken to avoid any debris falling into the San Francisco Bay. These precautions and measure must be outlined in a written work plan. G. The Port will disconnect existing utilities and provide water and power. The Abatement Contractor is responsible for providing, installing, and removing temporary connections to these services, without damaging the building s equipment or disrupting these services to the facility. Site Specific Asbestos Abatement Work Plan Page 2 of 8

H. The Port will provide up to 2000 square feet of lay down area. I. Debris bins will be stored near and need to be stored/loaded over approved locations. J. Load limits are 3000 pounds per wheel for vehicles. Any equipment over 10,000 pounds must be approved by Port. K. The Contractor is responsible for determining site conditions, quantities and location of all work to be performed, prior to submitting bid for completing the work. L. By submitting a bid, the Contractor acknowledges investigation (through a site visit) and acceptance of the conditions affecting the work. These conditions include, but are not limited to, physical conditions of the site that may affect access; handling and storage of tools and materials; access to water and electricity or other utilities that may otherwise affect the performance of required activities. Staging areas and parking are be limited at the site. Locations of sanitary facilities, storage areas, parking and other Contractor facilities shall be subject to the prior approval of the Port of San Francisco. M. All abatement work must be conducted following all applicable federal, state and local regulations including, but not limited to, California Code of Regulations Title 8, Section 1529; Bay Area Air Quality Management District Regulation 11; and the San Francisco Municipal Code. N. The Abatement Contractor is responsible for all required notifications to regulatory agencies and other parties and to submit all required notification forms to applicable regulatory agencies within required time frames. Any variances requested from regulatory agencies must be reviewed and approved by SAR and NTE prior to submittal to the regulatory agency. IV. SECURITY A. The Contractor to provide temporary fencing until demolition the project is complete. B. Containment structures and work areas shall be secured to restrict access. All work areas are to be clearly marked with caution tape and appropriate signage. The Abatement Contractor shall ensure that full access to emergency exits and to entrances to the structures and to surrounding facilities is maintained at all times. C. The abatement contractor shall be responsible for keeping work areas secured at all times, particularly during off-hours. D. Abatement Contractor is responsible for securing its own equipment, supplies, and facilities, including lifts, trucks, ladders, and job boxes. Site Specific Asbestos Abatement Work Plan Page 3 of 8

V. SCHEDULE A. Work hours, schedule and phasing to be determine by project schedule. B. The Contractor and its subcontractors will be provided access to the work areas on a date to be determined by the Port of San Francisco. The scope of work for the project duration shall include all mobilization, abatement, repair, clearance and demobilization. C. Port of San Francisco personnel and their contractors are to have full access to the facilities during the work period. Access into the regulated area, where abatement is to take place, will not be available until clearance has been granted by NTE. VI. DESCRIPTION OF WORK A. Remove asbestos containing materials identified in the Scope of Abatement Work listed below. B. Perform lead-related construction as identified in the Scope of abatement Work Listed below including. C. Perform other hazardous material work as identified in the Scope of abatement Work Listed below including. D. In accordance with Hazardous Abatement and Controls (Section 02130) of the contract documents, contractor must submit a Hazardous Materials Management Plan (HMMP) that provides the Contractor s comprehensive plan for the management of hazards encountered during the work of this project. E. The quantity below is presented as an Approximate Amount. The Contractor is responsible for determining the actual quantity to be removed. F. Lead waste generated from stabilization of deteriorated painted surfaces, and other tasks where paint and lead-contaminated dust is a significant component of the waste stream (i.e. paint chips, roof gravel and associated dust and debris, sludge, solvent residues from strippers, liquid waste, etc.) should be expected to be hazardous waste. Note that the contractor is responsible for lead waste stream characterization. Site Specific Asbestos Abatement Work Plan Page 4 of 8

SCOPE of HAZARDOUS MATERIAL ABATEMENT WORK Asbestos Containing Materials Building Material Location % Asbestos Approximate Amount Drywall/Taping Mud Wall and Ceiling Systems 1 st Floor Restroom Beneath Stairs And 2 nd Floor North Restrooms 0.25-0.50% (composite point count) 1,000 sf Vinyl Floor Tile Restrooms on 1 st Floor Restrooms and 2 nd Floor North Restrooms 2% 350 sf Sheet Vinyl Flooring (black debris) 2 nd Floor South Restroom 40% 75 sf Sink Undercoat Sink outside of 2 nd Floor North Restroom 15% 10 sf Roofing Mastics, Flashings, Penetrations Throughout Roof Field (including Roof Monitor Roofs), Perimeter, Parapet, Parapet Caps, Flashings and around base of Roof Monitors 5-15% 142,259 sf Window Caulk and Sealant Throughout Roof Monitor Windows (caulk at glass and sealant between frame and building) >1-5% 800 sf Caulk 300 sf - Sealant Window Caulk Pier Building Windows-Remove where required to install new fan units (see project drawings) >1-5% 3 Windows (12 window panes and associating framing) Fire Core Doors Pier 31 Building Assumed ACM 5 doors Lead-Related Construction Work Site Specific Asbestos Abatement Work Plan Page 5 of 8

Building Material Lead-Contaminated Gravel and Associated Dust and Debris Metal Roll-Up Doors New Door Opening at West Exterior Steel Infrastructure Lead-Containing Paint Stabilization 1 Location Remove Throughout Roof (including Roof Monitors Roofs) Spot Abate LBP on metal doors at cut lines (both interior and exterior paint). Spot Abate LBP at cut lines for new door opening (both interior and exterior paint). Spot Abate LBP on steel infrastructure for purpose of welding Throughout: Stabilize LCP in all work areas. Extend stabilization out in a 2 radius from the boundary of each work area (i.e. trusses, structural framing, ceilings, columns, etc.) Roof Monitors: Stabilize Exterior LBP walls and interior LCP walls and ceilings Stabilize all surfaces in work area (interior and exterior) where painting is planned Approximate Amount 142,259 sf 5 doors (cut lines only) 1 door (cut lines only) 15 sf Field Verify Field Verify Field Verify Lead-Related Construction 2 LBP and LCP are present on all interior and exterior painted surfaces including: -Walls, Ceilings, Columns, Trim -Trusses and Structural Framing -Ladders -Ground surfaces (where painted) -Pipes, conduit, mechanical, vents, louvers, fire safety fixtures, devices and equipement (where painted) -Steel Infrastructure, Metal Angles Irons, Brackets, Bolts, etc. 1 : Stabilization is the process of preparing a surface for repainting by which the areas of deteriorated paint are removed and an encapsulation coating (specifically made for application over lead-based paint) is applied to the area. 2 : Perform work throughout project work areas in a manner that conforms with Cal/OSHA Construction Safety Orders-Lead, Section 1532.1, Title 8; California Code of Regulations and the California Department of Public Health (CDPH) Title 17; and the San Francisco Exterior Lead- Based Paint Ordinance Other Hazardous Material Work Site Specific Asbestos Abatement Work Plan Page 6 of 8

Building Material Light Fixtures, Mercury -Containing Fluorescent Light Tubes, Universal Waste Lamps and PCB Ballasts, Non- PCB Ballasts (assume DEHP Ballasts); Location Remove in work area (interior and exterior) where removal is planned Approximate Amount Field Verify VII. SUBMITTALS The following items shall be submitted to, and approved by the Environmental Consultant before commencing abatement and stabilization work outlined in this work plan. Pre-job Submittals (as designated): BAAQMD Notification (10 working days in advance); Cal/OSHA Asbestos Abatement Notification per 8 CCR 1529 (twenty four (24) hours in advance); Cal/OSHA Lead Hazard Notification per 8 CCR 1532.1 (twenty four (24) hours in advance); DHS Notification Form DHS 8551 (12/97) for Abatement of Lead Hazards Notifications per San Francisco Exterior Lead-Based Paint Ordinance Copy of current Contractors State Licensing Board (CSLB) License; Copy of Cal/OSHA Asbestos Registration Certificate; Proof of all required permits or variances; Abatement work schedule; Abatement work plan(s); Copies of workers' asbestos training certificates, including the Competent Person; Copies of DHS Certified Lead Worker's and Supervisor's training certificates, as applicable; Copies of workers' lead awareness training certificates; Copies of workers' annual medical exam and respirator approval; Copies of workers' twelve (12) month respirator fit testing records; Copies of workers' blood lead test within past ninety (90)]days; Material Safety Data Sheets (MSDS) for chemicals used; Emergency phone and pager listing; Independent third-party DOP testing of negative pressure units and vacuums; Proposed location of locked dumpster; and Rotometer calibrations within past six (6) months. Periodic Submittals (as designated): Site Specific Asbestos Abatement Work Plan Page 7 of 8

Personal air monitoring (daily); Updated worker documentation (as needed); Boundary access logs (daily); Negative pressure records (daily); and Copies of updated notification to regulatory agencies (as needed). Project Close-out Submittals (as designated within two (2) weeks of completion): Certificate of Completion; Receipt and weight tickets from landfill operator or recycler (as applicable); Copies of completed uniform waste manifests, including hazardous and non-hazardous waste; Abatement Contractor Waste profiling data (TCLP, WET and SW846, as applicable); Filter change logs for all filtration units, water filtration units (as applicable) and respirators; Foreman s daily job reports; Employee and visitor entry/exit logs for all containments; Manometer printouts for all applicable containments; and Air sample results for all personnel, work areas and air filtration units. Site Specific Asbestos Abatement Work Plan Page 8 of 8