MONOLITHIC CONCRETE IRRIGATION PIPE INTRODUCTION CIPCP FOR IRRIGATION

Similar documents
SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

ITEM 432 TUNNEL CONSTRUCTION

SECTION TRENCHING

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

SECTION 39 - MANHOLES TABLE OF CONTENTS

17.0 CONSTRUCTION OF OPEN DRAINAGE SYSTEMS

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

GWINNETT COUNTY STORM SEWER PIPE STANDARDS

SECTION SPECIFICATION FOR STONEBRIDGE RETAINING WALL SYSTEM

ITEM 481 MONOLITHIC REINFORCED CONCRETE BOX SEWERS

SECTION A1 EXCAVATION AND BACKFILL GENERAL

Testing. Test drainage products according to the applicable AASHTO or ASTM specification, except as otherwise noted.

San Antonio Water System Standard Specifications for Construction ITEM NO. 848 SANITARY SEWERS

SECTION STORM DRAINAGE AND STORMWATER MANAGEMENT

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:

SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS

SPECIAL SPECIFICATION 5925 Polyvinyl Cloride (PVC) Sewer Pipe and Fittings

Specification for Cast-in-Place Concrete Pipe

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS

PUBLIC WORKS DEPARTMENT GENERAL NOTES

SECTION 44 SHOTCRETE, CAST CONCRETE CHANNEL LINING, AND GROUTED COBBLE TABLE OF CONTENTS

SECTION STORM SEWER PIPE

SECTION UTILITY MANHOLES AND STRUCTURES

FOX METRO WATER RECLAMATION DISTRICT MANHOLE / SEWER PIPE MATERIALS AND INSTALLATION SPECIFICATIONS MATERIALS 1. PIPE & FITTINGS

SRPE AASHTO Specifications.

SECTION STORM DRAIN

SPECIFICATION FOR REINFORCED SOIL WALL

SPECIFICATIONS - DETAILED PROVISIONS Section Controlled Low Strength Material C O N T E N T S

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS

SECTION RIGHT-OF-WAY DAMAGE REPAIRS PART 1 - GENERAL PART 2 - MATERIALS AND METHODS

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

SECTION 303 CULVERTS

Draft. Not Yet Approved SECTION 10.1 GENERAL SCOPE DEFINITIONS

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

C. Foundation stabilization for pipe and utility structures.

SECTION GRAVITY WASTEWATER LINES

CONCRETE WORK CONCRETE WORK. Underground Electric Distribution Standards I. SCOPE APPLICABLE STANDARDS

RETAINING WALL LEVEL BACKFILL

SECTION STORM DRAINAGE SYSTEM Excavating, Backfilling, and Compaction for Utilities Cast-in-place Concrete.

SECTION VITRIFIED CLAY PIPE SEWERS

SECTION IV. PIPELINE EXCAVATION AND BACKFILL

San Antonio Water System Specifications for Construction ITEM NO. 853 SANITARY SEWER GLASS-FIBER REINFORCED POLYESTER (FRP) MANHOLES

San Antonio Water System Standard Specifications for Construction ITEM NO. 808 REINFORCED CONCRETE VAULTS

CITY OF SAN ANGELO ITEM 275 PORTLAND CEMENT TREATED MATERIALS (ROAD MIXED)

TECHNICAL SPECIFICATION

SECTION 1 TERMS, DEFINITIONS, ABBREVIATIONS, UNITS OF MEASURE, AND SYMBOLS 1-3 ABBREVIATIONS Common Usage.

Tolerances- Section

B. Fiberglass for construction in back lot easements placed on cast-in-place base.

Z Z X X. Installation Instructions Bulletin Revision E Foundation Specifications. For 4.0 Meter Earth Station Antenna

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY CAST-IN-PLACE. Section CAST-IN-PLACE CONCRETE MANHOLES

TABLE OF CONTENTS

SECTION STORM DRAIN REHABILITATION. 1. Protection of environment; Section O Trench excavation, backfill, and compaction; Section

CHAPTER 6 - SANITARY SEWER

Public Works Manual. Revised September Concrete & Asphalt

***************************************************************************************************************

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL

VALLECITOS WATER DISTRICT SECTION PRECAST REINFORCED CONCRETE MANHOLES

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY. Section CEMENT STABILIZED BASE COURSE. 1. Foundation course of cement stabilized crushed stone.

1. Payment for concrete sidewalks is on square foot basis. a. Limits for measurement for trench excavation as follows:

TYPICAL INSTALLATION INSTRUCTIONS

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES

Special Provision No. 421F01 April 2006

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

Rural Servicing Guidelines

SECTION MEASUREMENT AND PAYMENT

2001 SCOPE. This section covers all cast-in-place concrete, including reinforcing steel, forms, finishing, curing, and other appurtenant work.

San Antonio Water System Standard Specifications for Construction ITEM NO. 853 SANITARY SEWER GLASS-FIBER REINFORCED POLYESTER (FRP) MANHOLES

SECTION ROCK REMOVAL

Foundation Specifications

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR LOW-TENSION CABLE BARRIER. OPR:CT 1 of 5 APPR:JAR:DBP: FHWA:APPR:

SECTION STORM DRAINAGE

ICRI Concrete Surface Repair Technician s Performance Examination Rubric

SECTION SANITARY SEWER SYSTEM

SECTION BORING AND/OR JACKING PIPE

SECTION SOILS REPORT

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS

(B). Plan. The plan shall be defined as colllectively all of. storm sewers, drains and drainage ways shall be determined by using

DIVISION 300 TRENCHING SECTION 308 BORING AND JACKING 2.2 STEEL CASING PIPE

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS

1. Division 01 Section General Requirements - Temporary Facilities and Controls. 2. Division 31 Section Earthwork.

SPECIAL SPECIFICATION 4425 Thermoplastic Pipe

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SPECIAL SPECIFICATION 6664 Level (3) Communications System

SPECIAL SPECIFICATION 6658 Time Warner Communications System

Repair of Metal Culverts Using ECC Bendable Concrete. Celik Ozyildirim, Ph.D., PE., Virginia Transportation Research Council

This type of masonry shall consist of brick laid in full beds of cement mortar.

SECTION PRECAST CONCRETE BIOSOLIDS STORAGE TANK

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

ITEM 461 STRUCTURAL PLATE STRUCTURES. Galvanized steel plates shall conform to AASHTO M167 and aluminum plates shall conform to AASHTO M219.

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

Union County Vocational - Technical Schools Scotch Plains, New Jersey

ITEM NO SLIPLINING SANITARY SEWERS

Transcription:

MONOLITHIC CONCRETE IRRIGATION PIPE Charles M. Burt 1 and John M. Wegener 2 INTRODUCTION Monolithic concrete pipe (also known as "Cast-In-Place Concrete Pipe (CIPCP) or Cast-In-Place Pipe (CIPP)) is widely used in some regions for purposes such as storm, sewer, or irrigation pipelines. The earliest use of CIPCP was in 1922 in the Turlock Irrigation District of California. It is reported by The Sierra Group (Sierra, 1991) that there are over 15 million linear feet (4.6 million linear meters) of CIPCP under various applications. Nevertheless, many irrigation engineers, especially outside the U.S. are unaware of CIPCP. Monolithic concrete irrigation pipe is seldom mentioned in irrigation design literature. This paper has been written to familiarize irrigation engineers with an additional design option. Cited references can be used to obtain technical and installation details. CIPCP FOR IRRIGATION CIPCP is a cast-in-place pipe which is underground, continuous non-reinforced concrete having no joints or seams except as necessitated by construction requirements (ACI, 1990). Pressures in CIPCP, including surge, are recommended in ACI 346R-90 to be less than 15 feet (4.5 m), and in practice most pressures are much lower than this. Common irrigation CIPCP diameters range from 30" - 84" (762 mm - 2134 mm), with minimum wall thicknesses of 3.5" - 8" (89 mm - 203 mm), respectively. With such large diameters, CIPCP is almost exclusively used for water conveyance and distribution systems in irrigation districts, rather than on-farm. Most buried low pressure on-farm pipelines in California were originally non-reinforced mortar jointed pipe. In the past 15 years, the use of non-reinforced mortar jointed pipe for on-farm use has been eclipsed by PVC pipe. CIPCP is selected over other pipeline designs because of the low cost. It is suitable for very low pressure installations. The quality of the pipelines and the anticipated life appear to be highly dependent upon the amount of attention paid to trench compaction, concrete mixes, and curing. Some installations also have extremely shallow or deep covers, both of which can cause failure. The success may also be dependent upon the amount of soil settling and movement; these are significant in some areas with seismic activity or subsidence due to ground water extraction. Some irrigation districts have abandoned the use of CIPCP because of chronic leakage and cracks in older CIPCP installations, while other irrigation districts expand their use of CIPCP. 1 Director, Irrigation Training and Research Center (ITRC), Agricultural Engineering Dept., California Polytechnic State University, San Luis Obispo, CA 93407. (805) 756-2379. 2 Construction Administrator, Water Dept., Imperial Irrigation District, P.O. Box 937, Imperial, CA 92251. (619) 339-9431. 1

USE OF CIPCP FOR IRRIGATION IN THE U.S. CIPCP usage for irrigation is concentrated in Arizona and California. A major user in Arizona has been the Salt River Project. In California, some irrigation districts, primarily on the eastern side of the San Joaquin Valley, have used the pipe extensively. In California and Arizona there is little new construction of irrigation district mainlines or laterals. Present construction with CIPCP almost always occurs as conversions of existing open ditches or canals into pipelines. Typical justifications cited by irrigation districts include: Water savings due to less seepage Easier operation than with canals Reduction in maintenance costs Increase in land area available for agricultural production Increase in land area available for commercial developers, as agricultural land shifts to urban uses Improved safety in and near cities. Drownings in canals occur annually in some irrigation districts. The Irrigation Training and Research Center (ITRC) at Cal Poly, San Luis Obispo, CA, sent an informal mail survey to approximately 80 irrigation districts in California regarding their usage of CIPCP. Of the 41 districts which responded, 14 indicated that they have CIPCP and of those, 9 are currently installing more CIPCP. The authors are aware of other districts which have also installed CIPCP recently. The informal ITRC survey indicated that the majority of pipe sizes used are in the 30" - 42" (762 mm - 1067 mm) range. Table 1 summarizes the results reported by the districts. Table 1. CIPCP in irrigation districts responding to the survey. Pipe Diameter Lengths of CIPCP inches millimeters feet meters 18 457 244,200 74,432 24 610 3,960 1,207 30 762 2,016,115 614,512 36 914 2,906,059 885,767 42 1067 1,708,608 520,784 48 1219 395,155 120,443 54 1372 175,718 53,559 60 1524 5,280 1,609 72 1829 2,904 885 84 2134 3,960 1,207 Totals 7,461,959 2,274,405 Table 2 presents reported costs for CIPCP in various California irrigation districts. The installation costs which were reported by the districts were variable, and no attempt was made to verify the accuracy of the values or to determine why they might differ. However, there are wide 2

ranges of installation techniques and equipment. Some districts use their own labor crews with outside equipment; some use outside contractors for the complete work; and other districts have their own crews and equipment. Personal observations indicate that there are also differences in the quality of the pipes. The costs of 72" (1829 mm) pipe reflect the true cost to Imperial Irrigation District (IID) in 1993 for pipe installed by contractors to conform to rigorous specifications which included frequent on-site concrete testing, over-excavation and bed compaction, and a special concrete mix. Table 2. Reported costs for CIPCP for California irrigation districts. Pipe Diameter Reported Costs inches millimeters $/foot $/meter 18 457 22 72 24 610 23 75 30 762 15-17 48-54 36 914 17-38 56-125 42 1067 17-45 56-148 48 1219 35-50 113-164 54 1372 40 132 60 1524 47 154 72 1829 185 607 84 2134 85 279 CIPCP CONSTRUCTION Casting requires the construction of a trench with a semicircular bottom, which serves as the outer form for the bottom and sides of the pipe. There are several different techniques available to form the side walls and top of the pipe. Original pouring techniques favored a two-step pour process (first the bottom, and later the top) by hand. This two-step process resulted in a weak horizontal construction joints either because of dirty joints or insufficient plasticity of the concrete on the lower half (and therefore weak bonding) when the top half was poured. For over 40 years there have been a variety of improved single-stage (hence the term, "monolithic") construction techniques. Some have used an inflated bladder as a form which is pulled down the trench. Most contracted installations now use a pipe casting machine or "boat" which winches itself along a pre-formed trench, continuously receiving concrete from trucks. ACI346R-90 (ACI, 1990) provides a good description of various techniques and equipment. The process used at the Imperial Irrigation District in 1993 for the construction of 0.55 miles (.88 km) of 72" (1829 mm) pipe is described briefly as follows (IID, 1993a, 1993b; Tremont, 1990): A trench is over-excavated by a minimum of 2 feet (.61 m) on each side of the pipe outside diameter (OD) and 4 feet (1.21 m) below the pipe bed. It is backfilled, and compacted to 85% of maximum Proctor density up to the top of the proposed pipe. A trench is excavated to the desired outside diameter of the pipe with round bottom buckets to provide a three-sided mold. Bucket movement is assisted by laser guides. 3

The pipe machine (boat) is placed into the trench. The boat is equipped with a hopper to receive concrete from trucks, an auger and assembly of vibrators to force the concrete between the forms (the bottom outside form is the trench soil), room for a person to stand inside to adjust inside forms, and a winch for self-propulsion. The rear of the machine has an upper trowel plate which forms the outside crown of the pipe, and a lower trowel plate which forms the inside bottom (invert) of the pipe. A person working outside the machine feeds aluminum sheets and support brackets to another person working inside the machine. These aluminum sheets temporarily support the upper 270 of the concrete. Low slump concrete is fed into a hopper on the machine from trucks positioned alongside the trench. The concrete is tamped and vibrated to ensure uniform density and high pipe strength. The concrete at IID was reinforced with a minimum of 1.5 pounds per cubic yard (.82 kg/m 3 ) of collated, fillibrated polypropylene fibers. The concrete met the requirements of ASTM designation C150 for Type II cement and met the low alkali and false-set limitations specified therein. Concrete was tested a minimum of once per every 50 cubic yards (42 m 3 ) of concrete placed. As the pipe is formed, the machine winches itself along with a cable attached to a deadman positioned ahead in the trench. In practice, lengths of pipe poured per day range from about 100' to 400' (30.5 m - 122 m) for 120" - 24" (3048 mm - 610 mm) diameters. The newly cast pipe is immediately covered with a thin (.0015 in;.038 mm) polyethylene sheet for moisture retention and optimum curing. No longer than six hours after casting, a 6" (152 mm) layer of loose moist soil is placed on the top of the pipe, without damaging the polyethylene film or pipe. The soil is kept moist until backfill operations are completed. Backfill operations are not completed until the concrete attains the 28 day strength specified (3000 psi or 20.7 MPa). A special joint is installed at the end of the day in order to obtain a good bond with the next day's pour. The pipe end is covered to enhance curing. Forms are removed within 2 to 18 hours and are re-positioned along the trench for the next day's pour. Various agencies have special requirements that need to be placed in the writing of the specifications such as water deliveries, road closures, etc. The concrete design mix can be altered, by a qualified geotechnical lab, to achieve early compression strengths of 3000 PSI (20,685 kpa) in 24 hours. This allows early water deliveries, and backfilling of the trench can start the next day. SUMMARY Cast-In-Place Concrete Pipe (CIPCP) is traditionally about 33% cheaper to install than comparable pre-cast concrete pipe. In these days of tight construction budgets and urban expansion into existing farm lands, CIPCP is an economical approach to putting open working irrigation and drainage conveyance systems underground. REFERENCES 4

ACI, 1990. ACI 346R-90. Recommendations for cast-in-place non-reinforced concrete pipe. American Concrete Institute. Detroit, Michigan 48219. IID, 1993a. Dogwood canal cast-in-place concrete pipeline. Imperial Irrigation District. Imperial, CA 92251. IID, 1993b. Video of cast-in-place dogwood canal. Imperial Irrigation District. Imperial, CA 92251. Sierra, 1991. Quality construction of cast-in-place concrete pipe. Southern Sierra Contracting, Inc. Sun City, CA 92355. Tremont, 1990. Cast-in-place concrete pipe process. Tremont Equipment Co., Inc. Dixon, CA 95620. 5