DESIGN STANDARDS SECTION DS 7 STREET LIGHTING

Similar documents
5-1 Street Lights Required Street Lights on Private Roadways Developer s Responsibility...5-1

CONSTRUCTION STANDARDS SECTION CS 15 STREET LIGHTING

STREET LIGHTING. Springville City Power standard street lights will be installed in accordance with Springville City Power's Line Extension Policy.

SCHEDULE G REGULATIONS, STANDARDS AND SPECIFICATIONS FOR THE INSTALLATION OF STREET LIGHTING

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL

HALIFAX REGIONAL MUNICIPALITY MUNICIPAL DESIGN GUIDELINES

STREET IMPROVEMENTS (Refer to Title 18, chapter entitled "STREETS" of the Layton Municipal Code.)

DIVISION 1100 TRAFFIC

[Type text] Heber Light & Power. Developers & Excavators. Electrical Service Requirements Manual

CITY OF LAWRENCE RESIDENTIAL DRIVEWAY PERMIT CHAPTER 16, ARTICLE 3, ADOPTED BY THE CITY COMMISSION ON JULY 10, 1996.

Ivins City Standard Specifications for Design and Construction Part 2 Engineering and Design Standards

COUNTY OF YUBA DEPARTMENT OF PUBLIC WORKS IMPROVEMENT STANDARDS

TOWN of LAKESHORE SUBDIVISION DEVELOPMENT PLAN CHECKLIST

400 watt, high pressure sodium. Type C watt, high pressure sodium Collector Street Light Units

I. STREET CONSTRUCTION AND RECONSTRUCTION

City of Redding Construction Standards Index

DISTRICT OF HOPE SUPPLEMENTARY SPECIFICATIONS

GARDEN CITY STNANDARD REVISIONS FOR ISPWC DIVISION 1102 STREETLIGHTS

GENERAL NOTES ROADWAY CONSTRUCTION RD0001-1A ISSUED:2017 REVISED: --

SECTION 13 WATER SYSTEMS

PART II. - SPECIFICATIONS AND DESIGN STANDARDS TO CITY OF HEWITT, TEXAS SUBDIVISION ORDINANCE FOR PUBLIC WORKS CONSTRUCTION [TEXT]

T a b l e o f C o n t e n t s

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES

WHITE CITY LIGHTING DEVELOPER STANDARDS

City of Duluth Development Regulations

DESIGN STANDARDS SECTION DS 6 SANITARY SEWER SYSTEM

ROADWAY DESIGN AND CONSTRUCTION STANDARDS

TABLE OF DRAWINGS. Pierce County Public Works & Utilities

SECTION 1101 TRAFFIC SIGNALS AND APPURTENANCES END OF SECTION

TABLE OF CONTENTS PART III MINIMUM DESIGN STANDARDS Section 115 WATER DISTRIBUTION SYSTEM GENERAL SIZING LINES 115.

Tacoma Mall Office Building 4301 South Pine Street, Suite 446 Tacoma, Washington (253) Fax (253)

TABLE OF DRAWINGS. Pierce County Public Works & Utilities

Department of Building and Zoning Approaches and Sidewalks for ONE AND TWO FAMILY CONSTRUCTION

Recommended Technical Standards for Existing Roads UNH Technology Transfer Center

ENGINEERING DESIGN & IMPROVEMENT STANDARDS

Tacoma Mall Office Building 4301 South Pine Street, Suite 446 Tacoma, Washington (253) Fax (253)

CITY OF ROCKLIN STANDARD DRAWINGS

Chapter 3: Permit Procedures and Requirements

Section 7 Roadway GENERAL REQUIREMENTS I. TYPICAL SECTION...7-1

CITY OF LA QUINTA GENERAL NOTES GENERAL NOTES

CHAPTER 12 INSTALLATION OF UTILITIES AND OTHER SYSTEMS TABLE OF CONTENTS

PERMITTED USES: Within the MX Mixed Use District the following uses are permitted:

STREET LIGHTING GENERAL INFORMATION

CITY OF LA MARQUE, TEXAS CHAPTER 3 WATER SYSTEM DESIGN CRITERIA

SECTION 6. ROAD CONSTRUCTION STANDARDS

City of Clovis DESIGN GUIDELINES. To Be Used in the Preparation of CONSTRUCTION DRAWINGS. and other DOCUMENTS. Required in the processing of

SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES

Gainesville Technical Center 5399 Wellington Branch Drive Gainesville VA Phone (703)

Town of New Tecumseth Engineering Design Criteria and Standards for Subdivisions and Capital Works Projects

CHAPTER 13: RIGHT-OF-WAY LIGHT DESIGN AND CONSTRUCTION STANDARDS

Streets CHAPTER 4 STREETS General

Article 7 / Subdivision Sec. 7.4 / DEDICATION OF ROW FOR THOROUGHFARE PLAN STREETS AND HIGHWAYS Sec / Reasonable Relationship

Appendix C SPECIFICATIONS FOR DESIGN AND CONSTRUCTION (AMENDED 04/03/90)

CITY OF TACOMA RIGHT-OF-WAY RESTORATION POLICY. Guidance on restoration of City Rights-of-Way

Part 11: Lighting. Contents. Tables. Part 11: Lighting. Christchurch City Council Infrastructure Design Standard 11-1

CHAPTER 2. Restricted Residential ½ Street** Design Speed 25 MPH 25 MPH 25 MPH 25 MPH 40 MPH 50 MPH 55 MPH

CHAPTER 17: STORM SEWER STANDARDS Introduction Administration Standards 17.1

SPECIFICATIONS FOR STREET CONSTRUCTION WITHIN THE TOWN OF PLAINVILLE

Welcome to Douglas County PUD

General Legend Details...100

SECTION MAINTENANCE OF EXISTING CONDITIONS

MONTEZUMA COUNTY COLORADO ROAD AND BRIDGE STANDARD SPECIFICATIONS

UNIFORM STANDARD DRAWINGS CLARK COUNTY AREA, NEVADA YEAR 2015 REVISIONS

SPECIAL SPECIFICATION 7191 Illumination

Chapter 7. Street Drainage. 7.0 Introduction. 7.1 Function of Streets in the Drainage System. 7.2 Street Classification

SALEM CITY POWER ELECTRICAL REQUIREMENTS & STANDARDS MANUAL

PART 7 COMMUNICATIONS, LIGHTING, TRAFFIC CONTROL, POWER

SECTION 12 STANDARDS FOR CONSTRUCTION PLANS AND SPECIFICATIONS

Fence and Wall Guidelines

STREET LIGHTING SERVICE SCHEDULE SLR-45 (RESIDENTIAL SUBDIVISIONS)

This is only a general checklist; please refer to the CVWD Development Design Manual (DDM) for all requirements and regulations.

Bylaw 3847, 2016 Adopted Mar 21, 2016 SCHEDULE G - REGULATIONS, STANDARDS AND SPECIFICATIONS FOR THE INSTALLATION OF STREET LIGHTING

1.01 GENERAL. l.02 PIPELINE TRENCH EXCAVATION PIPELINES AND STRUCTURES REVISION: SECTION 1 PAGE : 1-1

PLANS. All plans shall be submitted on 24 x 36 sheets

CUYAHOGA COUNTY DEPARTMENT OF PUBLIC WORKS CUYAHOGA COUNTY ENGINEER TOWNSHIP SUBDIVISION STREET DESIGN STANDARDS AND IMPROVEMENT PLAN REQUIREMENTS

CONSTRUCTION SURVEY. Construction survey includes personnel, equipment, and supplies required for, but not limited to, the following:

CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING DEPARTMENT NON-NETWORK SYSTEMS SECTION

Ledges East Master Owners Association. Architectural Guidelines for the Community-Wide Areas

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT

CONSTRUCTION SPECIFICATION FOR SITE RESTORATION FOR UNDERGROUND UTILITIES

SECTION 7 STREET DESIGN

SUBDIVISION SECTION STREET DESIGN MANUAL

Standard Construction Specifications & Subdivision Regulations. Roswell, Georgia

TOWN OF AJAX DESIGN CRITERIA SECTION B ROADWAYS

1A-300 SCREENING AND BUFFERING REQUIREMENTS

ITEM NO. 824 SERVICE SUPPLY LINES (WATER)

Chapter WALLS AND FENCES

CITY OF ALBANY Public Works Department ADDENDUM #1 ST CROCKER LANE RECONSTRUCTION

San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER)

SUBDIVISION CHECKLIST. Subdivision Name. Prior To Review. Preliminary plan approved by Planning Commission / Council as required.

THE ANTICIPATED SEQUENCE OF EVENTS ARE AS FOLLOWS, BUT THE CONTRACTOR IS RESPONSIBLE FOR ALL MEANS AND METHODS

Design-Build Selmon West Extension

Fence, Wall & Column Information Packet

WASHOE COUNTY COMMUNITY SERVICES DEPARTMENT GRAVITY SEWER COLLECTION DESIGN STANDARDS

OVERALL UTILITY PLANS 1. Provide a typical section depicting the roadway (proposed/future), utility locations, and separation for

APPENDIX A DESIGN SPECIFICATIONS FOR NEW ROAD CONSTRUCTION

Transcription:

DESIGN STANDARDS SECTION DS 7 STREET LIGHTING DS 7-01 GENERAL: A. INTENT: The intent of these Design Standards is to provide minimum standards for the design of street lighting to serve the ultimate level of development as defined on the City General Plan. These Design Standards describe typical practices for new or modified street lighting systems. The Street lighting system shall be owned and maintained by the City of Vacaville unless otherwise specified by these City Standard Specifications or determined by the Director of Public Works. B. GOVERNING CRITERIA: These Design Standards, in conjunction with the most current requirements of National Electric Code (NEC) and Pacific Gas and Electric (PG&E) company shall govern the design of all street lighting within the City of Vacaville. In the event that there is a conflict between these requirements or with other Current Standards so defined hereafter, the Director of Public Works shall determine which document governs. Additionally, if there are criteria or issues not addressed in these documents, the Director of Public Works will determine the criteria to be used in the design. All street lighting improvements shall be designed in accordance with current accepted engineering practices. These Design Standards are minimum standards and are intended to assist the Design Engineer, but not substitute for competent work. The City Engineer/Director of Public Works at their sole discretion may require more stringent requirements for unusual circumstances, special conditions, and/or environmental constraints. C. CURRENT STANDARDS: Street Light design shall be completed in accordance with all current applicable laws, standards, and regulations, including but not limited to the National Electric Code, California Electric Code, CALTRANS Standard Specifications, and the City of Vacaville Municipal Code, Storm Water Management Plan, Standard Drawings, and City Standard Specifications which include the Construction Standards, and the Design Standards. DS 7-02 APPROVED STREET LIGHT LUMINAIRES AND MOUNTINGS: A. The approved type of street light luminaires and mountings for use in the public right-of-way or that which is to be maintained by the City of Vacaville shall conform to the criteria shown in Table DS 7-1, paragraph B below and all other criteria included in Section CS 15, Street Lighting, of the Construction Standards. Street Light Design Standards Page DS 7-1 DS-SEC 07 REV: 11 March 2008

Luminaire and Mounting Type TABLE DS 7-1 APPROVED STREET LIGHT DESIGN TYPES 3 Cobra Head on single mast arm Cobra Head on single mast arm Cobra Head on dual mast arm Decorative Post Top Type Mount Decorative Post Top Type Mount Decorative Tear Drop Mount on single mast arm Decorative Tear Drop Mount on single mast arm Where allowed by street classification 2 Cul-de-Sac, Residential, and Collector Arterial Arterial within the median Cul-de-Sac and Residential Collector Arterial (64 foot wide) Arterial (80 feet wide) Locations 1 and Nominal Spacing 250 feet staggered 125 feet staggered See footnote 3 170 feet staggered 190 feet staggered 150 feet staggered 125 feet staggered 1 See Standard Drawing 7-01A & B for additional requirements for the placement of street lights at intersections, expanded corners and cul-de-sacs. 2 Industrial Streets shall use Cobra Head lighting with spacing based upon the street width which matches either a collector or arterial street classification shown in Table DS 7-1 and the lighting intensity shown on Table DS 7-2 unless otherwise approved by the City Engineer/Director of Public Works. 3 The design of street lighting systems using dual mast arms will be considered on a case by case basis and shall be subject to the approval of the City Engineer/Director of Public Works. See Construction Standards Section CS 15, Street Lighting, for details of approved luminaire fixtures, electrolier standards and arms, and other related equipment. B. ALLOWABLE USE OF DECORATIVE LIGHTING: Private development use of the Decorative lighting included in Table DS 7-1 is only allowed when a Lighting Assessment District is proposed or already established to maintain the lighting. The Lighting Assessment District shall be developed by the City Engineer and is subject to the Approval of the City Council. The selection of the type of Decorative Light shown in Table DS 7-1 proposed for use in the design shall be subject to the approval of the Director of Public Works. Only the approved Street Light luminaires, poles, and other related equipment included in Section CS 15, Street Light Design Standards Page DS 7-2 DS-SEC 07 REV: 11 March 2008

Street Lighting, of the Construction Standards are allowed for use in the design. DS 7-03 LIGHTING FIXTURE INTENSITY: A. The street light design shall include high pressure sodium luminaries conforming to the criteria for lighting intensity shown in Table DS 7-2: TABLE DS 7-2 LIGHTING INTENSITY Street Classification Lighting Intensity (Luminaire Wattage) Cul-de-Sac and Residential 70 Collector and Industrial 100 Arterial 200 DS 7-04 STREET LIGHTING LAYOUT A. GENERAL: 1. Street light layout shall be in accordance with the spacing and layout requirements shown in Table DS 7-1 and the Standard Drawings. 2. Street lights shall be normally located on property lines and whenever possible, at least five (5) feet from driveways or any above ground facility, and at such locations to maximize their separation from trees. The Design Engineer shall review the utility joint trench plan and coordinate the location of street lighting to ensure conformance to these requirements. 3. Street lights should be located on the outside edge of the curve for horizontal curvilinear street alignment. B. STREET INTERSECTION, EXPANDED CORNER, AND CUL-DE- SAC LOCATIONS: Street lighting for intersections, Expanded Corners and Cul-de-Sacs shall be located at the locations shown on Standard Drawing 7-01A and 7-01B and the lighting within the limits of the street shall also conform to the spacing requirements shown in Table DS 7-1. C. LOCATION RELATIVE TO SIDEWALK, CURB AND GUTTER The electrolier location shall conform to the following: Street Light Design Standards Page DS 7-3 DS-SEC 07 REV: 11 March 2008

1. Where the sidewalk is contiguous to the curb and the sidewalk width is seven (7) feet or less, the street light pole shall be centered two (2) feet behind the back of the sidewalk. 2. Where the sidewalk is contiguous to the curb and the sidewalk width is more than seven (7) feet, or when the sidewalk is separated from the curb, the street light pole shall be centered two (2) feet from the gutter flow line. DS 7-05 DESIGN COORDINATION: A. For all projects which will include the construction of street lights, the developer should contact PG&E early in the design process regarding providing service to the expanded street light system. The developer/ Design Engineer shall be responsible for processing the PG&E application for electrical service for the proposed lighting system. B. It shall be the Developer s responsibility to install all new PG&E facilities to provide service to the development site. C. Existing street lights which must be relocated or repositioned as a result of the developer s construction shall be the responsibility of the developer. D. Once the street light locations have been established and approved by the City Engineer/Director of Public Works, copies of the Street Lighting Project Plans shall be sent to PG&E by the Design Engineer. The following data should be requested: 1. Service Point Location 2. Street Light Numbers DS 7-06 CONDUIT: The conduit design shall conform to the following criteria: A. Conduits shall be sized in accordance with the National Electrical Code but shall not be less than 1½ inches in diameter. B. The street light conduit shall be installed at least 24 from the joint trench location and within the public right-of-way. C. The minimum depth of the conduit shall conform to the following criteria in addition to the requirements of Section CS 15, Street Lighting, of the Construction Standards: 1. Outside the street pavement: Conduit installed outside of street pavement shall be placed not less than twenty four (24) inches below the surface of the ground or sidewalk. 2. Within the existing street pavement: Conduit installed within existing street pavement (asphalt concrete paved) areas shall be placed not less than twenty-four (24) inches when the trench is not excavated Street Light Design Standards Page DS 7-4 DS-SEC 07 REV: 11 March 2008

and backfilled in accordance with the City s Standard for Rockwheel Trench. However, the conduit may be installed with 18 inches of cover provided that the trench is excavated and backfilled in accordance with Section CS 3-07, Rockwheel Trench, of these City Standard Specifications. 3. Within the proposed street pavement: Conduit installed within areas of proposed street pavement shall be installed at a depth lot less than the subgrade elevation or twenty-four (24) inches, whichever is greater. DS 7-07 CONDUCTORS: The conductors shall conform to the following criteria: A. The conductors shall be stranded copper wire conforming to the requirements included in Section CS 15, Street Lighting, of the Construction Standards. B. The size of the conductors shall be determined by voltage drop calculations prepared in accordance with the National Electric Code except as amended by this Section DS 7, Street Lighting, of the Design Standards. The conductor shall be sized such that the voltage drop in the circuit from the service point to the last Street Light on the circuit will not exceed 5% of the nominal voltage which is normally 120 volts. However, in any case, the minimum size of the conductors shall conform to the following: 1. The minimum size of any conductor within the conduit from the pull box adjacent to the electrolier to within the electrolier shall be #10. 2. The minimum size of conductor within all other conduit runs is #8. DS 7-08 PULL BOXES: Pull boxes shall be located at the base of all lights, where two or more conduits intersect, at angle points, street crossings, and 90 degree bends. Pull boxes shall also be located where conduit runs are more than 150 feet in length from the service point to the first street light location. DS 7-09 CIRCUIT: The circuit shall be designed for 120 volts with a connection to an underground 120 volt service point connection unless otherwise approved by the Director of Public Works. No more than six street lights shall be included on a circuit without designing a multiple circuit. The multiple circuits for staggered lighting layout shall include a separate hot leg for each side of the street from the branch in the circuit to the service point. The neutral conductor may be shared between the two sides of the street from the branch of the circuit to the service point. Street Light Design Standards Page DS 7-5 DS-SEC 07 REV: 11 March 2008

DS 7-10 PROJECT PLAN REQUIREMENTS: A. The Design Engineer shall include full details of the proposed street lighting system design on the Project Plans which conforms to the City of Vacaville Standard Specifications. B. A Street Lighting Plan shall be shown on a separate plan sheet of the Project Plans unless an exception is granted by the City Engineer/Director of Public Works. C. The Design Engineer shall prepare and submit voltage drop calculations in accordance with Section DS 7-07, Conductors, of these Design Standards to the City Engineer/Director of Public Works for review. D. The Project Plans shall show the following information: 1. The street light and associated conduit shall be shown in plan view and in the typical section for the street. 2. The size and quantity of all conduits and conductors shall be identified in tabular form or be noted next to each conduit run. 3. Luminaire and Mounting type (see Table DS 7-1). 4. Wattages of the luminaires and Lighting Distribution Pattern (Type) if different from Type III. 5. Location and size of all pull boxes. 6. The location of the PG&E service point and notes specifying the requirements for making the connection from the service point to the proposed Street Lighting system. 7. Street Light Numbers as assigned by PG&E. 8. Location of existing street lighting including size and depth of conduit and size and quantity of conductor and pull boxes that are impacted by the proposed project construction. 9. Any other pertinent information required for construction. E. On Private Development projects, if the Design Engineer has not been able to obtain the PG&E service point and City Street Light numbers in a timely manner from PG&E, the City Engineer may at its discretion approve the subdivision or other development Project Plans designating the Street Lighting Plans as Incomplete. The following note will then be added to the plans: The Street Lighting Plan included herein is not approved with these plans. Approval of this plan will only occur after the service points and City Street Light numbers have been established by PG&E and are reflected as a revision to these plans. Street subgrade shall not be approved for paving until the Street Lighting Plan has been revised and approved by the City Engineer and all conduit street crossings are installed. The Sheet Index included on the Title Sheet for the Project Plans shall also designatethe Street Lighting Plan as Incomplete. Street Light Design Standards Page DS 7-6 DS-SEC 07 REV: 11 March 2008