PG&E s Bidders Webinar

Similar documents
2018 Oakland Clean Energy Initiative Request for Offers Q&A

2018 Local Sub-Area Energy Storage RFO

PREFERRED RESOURCES PILOT

2017 Renewable Energy Sale - Request for Offers Solicitation Protocol

SCHEDULING COORDINATOR REQUEST FOR INFORMATION

2018 Open Season Request for Offers Procedural Overview & Instructions

Demand Response Auction Mechanism ( DRAM 3 ) Pre Bid (Bidders) Web Conference

Long Island Power Authority Seventh Revised Leaf No. 16

Pre-Bid (Bidders) 2019 Demand Response Auction Mechanism ( DRAM 4 ) Web Conference. February 1, Presentation will begin at 10:00 a.m.

MINIMIZING DISTRIBUTED ENERGY RESOURCES (DER) ACQUISITION COST THROUGH AUCTIONS

Long Island Power Authority Seventh Revised Leaf No. 16

SCE s Preferred Resources Pilot (PRP) Annual Progress Update

Business Practice Manual for Distributed Generation Deliverability. Version

Definitions O - P. Open Access Same-Time Information System (OASIS) or PJM Open Access Same-time Information System:

In the "Proforma_GenProfile tab, please populate the table with energy and ancillary services that are expected to be bid into the CAISO market.

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

Ordinance establishing a Community Choice Aggregation Program in accordance with

Photovoltaic Program Power Purchase Agreements Request for Offers 2012 Solicitation. Participants Forum. October 12, 2012

Distributed Energy Resource Management System (DERMS)

Appendix A. Glossary. For Request For Proposals For Long-Term Renewable Generation Resources For Entergy New Orleans, Inc.

Southern California Edison Preferred Resources Pilot Portfolio Design Report Revision 2

Integrating Renewables and Distributed Energy Resources into California s Electricity Markets

Renewable Market Adjusting Tariff (ReMAT) Feed-In Tariff (FIT)

CHAPTER 6 - Load Forecast & Resource Plan

1. Is there a preference between MW and MWh? RPS need for San Diego Gas & Electric is based upon a percentage of retail sales, which is in MWh.

Southern California Edison

CALL FOR COMBINED HEAT AND POWER (CHP) PROJECTS. Program Guide

Request For Offers. RFO Instructions

Southern California Edison Request for Offers Local Capacity Requirements. Transmittal Letter v 2.0

Joint Workshop on Multiple-Use Applications and Station Power for Energy Storage CPUC Rulemaking and CAISO ESDER 2 Stakeholder Initiative

Business Practice Manual for Reliability Requirements. Version 34

ATTACHMENT DD. Reliability Pricing Model

Carbon Free Energy with Storage

Smart Grid and Climate Change

Relevant changes will be made to corresponding sections of OA and RAA.

ELECTRIC SCHEDULE E-ECR-PDT Sheet 1 (N) E-ENHANCED COMMUNITY RENEWABLES PROJECT DEVELOPMENT TARIFF (N)

Distribution System Planning. Introduction and Overview Chris Villarreal <Month> <Day>, 2017

SCE s Renewable Market Adjusting Tariff (Re-MAT) Bidders Conference September 18, 2013

Expanding Capacity Eligibility

Calculating a Dependable Solar. Generation Curve for. SCE s Preferred Resources Pilot

Combined Heat and Power ( CHP ) Request for Offers. Participants Conference January 12, 2012

GRENLEC s Renewable Standard Offer

Energy Auction for the CPV Sentinel Generating Facility

Demand Response Availability Data Systems Definitions

Reliability Pricing Model (RPM) DRAFT Business Rules

NEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems

California s Approach to Designing a Feed-in Tariff. Sara Kamins California Public Utilities Commission June 19, 2014

effective date 1/8/01

PacifiCorp 2017R Request for Proposals. Pre-Issuance Bidders Conference May 31, 2017

QF Settlement Agreement Overview QF Meeting Rosemead, CA. July 22, 2011

SERVICE CLASSIFICATION NO. 14-RA STANDBY SERVICE

Locational and Temporal Values of Energy Efficiency and other DERs to Transmission and Distribution Systems

PG&E Demonstration A Dynamic Integration Capacity Revised Plan Overview

PASADENA WATER AND POWER MEMORANDUM. August 9, 2016

Current Language Proposed Revisions Rationale

CPA RFO - Q&A Response Form, Revision 1-11/2/18

SEPTEMBER 11, Renewable to Retail Technical Conference

Utility 2.0 Long Range Plan 2016 Annual Update Prepared for Long Island Power Authority. December 29, 2016

Water & Energy Consulting Lon W. House, Ph.D.

Southern California Edison Request for Offers Local Capacity Requirements. Transmittal Letter Letter v 2.0

Power Saver TM Program

PREPARED FOR: ARIZONA PUBLIC SERVICE Updated Solar PV Value Report

DR Call. Friday, January 26, 2018

SERVICE AGREEMENT FOR WHOLESALE DISTRIBUTION SERVICE. Between SOUTHERN CALIFORNIA EDISON COMPANY. And TECHNI-CAST CORPORATION

2011 RFP for All Generation Sources Proposal Conference

Webinar: PG&E and Solar

SCE s Experience In Energy Storage


Dynamic Price, Product and Messaging Specification

Energy and Climate Report

LOAD SERVING ENTITIES PJM REGION

Appendix A. Glossary. For Request For Proposals For Long-Term Renewable Generation Resources for Entergy Louisiana, LLC DRAFT

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

Association of Energy Services Professionals (AESP) Request for Proposal Market Research Services

Stakeholder Comments Template. Subject: SCE Comments on Dynamic Transfer Revised Final Draft 2/18/11

Cluster Study Process

Demand Response Association of Energy Engineers. Presenter: David Wylie, P.E. ASWB Engineering

Locational Net Benefits Analysis Working Group Long Term Refinement Topics Scoping Document Prepared for the ICA Working Group by More Than Smart

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

Addendum 3: Additional Site Info plus continuation of Q&A November 11, 2016

California s Energy Storage Mandate

Distributed Energy Resources Roadmap

FY2017 SREC Registration Program (SRP) Final As-Built Technical Worksheet Instructions Page 1

The key features of the Town s municipal aggregation program will include:

SAN DIEGO GAS & ELECTRIC COMPANY

2016 Request For Proposals For Long-Term Renewable Generation Resources For Entergy Louisiana, LLC

What You Need to Know Before Requesting Interconnection

ONCOR INTERCONNECTION APPLICATION AND PROCESS FOR DISTRIBUTED RESOURCES

Demand as an Active Actor Day 2, Item 1. Presented by: Flora Flygt XM Medellin, Columbia December 12-13, 2012

Electrification and its Implications for the California Electricity System

Renewable Electricity Procurement in California

Southern California Edison Preferred Resources Pilot. Portfolio Design Report Revision 0

Entergy New Orleans, Inc Request for Proposals for Long-Term Renewable Generation Resources

First Revised Sheet No. 449 Canceling Original WN U-60 Sheet No. 449 PUGET SOUND ENERGY Electric Tariff G SCHEDULE 449 RETAIL WHEELING SERVICE

Revision: 67. Prepared by

Generator Interconnection Process. Wholesale Distribution Overview

Con Edison Non-Wires Solutions Response to RFP Clarification Questions

(2) isolated operation with standby service provided by the Company by means of a doublethrow

PG&E s General Comments on Demand Response Vision Update. January 11, 2008

Transcription:

PG&E s Bidders Webinar Distribution Resources Plan (DRP) Demonstration Project D RFO May 24, 2017

Agenda Topics Introduction Goals of DRP Demo D Overview Distribution Services Needed Solicitation Overview Eligibility Customer Engagement Support Term Sheet Evaluation Methodology Offer Submittal Process Offer Form Intermission Q & A Presenter Sandy Burns Michael Puckett Michael Puckett Michael Puckett Sandy Burns Sandy Burns Al Gaspari Jr Andrew Lee Andrew Lee Izzy Carson Izzy Carson Team 2

Webinar Format PG&E will not take questions during the webinar Participants should email questions to DRPRFO@pge.com during the presentation Questions will be answered at the end of the webinar PG&E might not address all questions during the Q&A portion of this webinar After the webinar, PG&E will compile and post a Q&A document on PG&E s DRP RFO website, accessed via www.pge.com/rfo/drp2017 PG&E may post a list of attendees on PG&E s website If you do not want your name or the name of your company published, please send an email to DRPRFO@pge.com by May 25, 2017 PG&E plans to post a recording of the webinar on PG&E s DRP RFO website 3

Webinar Overview This presentation is intended to provide a summary of the information and requirements set forth in the RFO materials Participants should carefully review the DRP Solicitation Protocol and all RFO materials, available on PG&E s DRP RFO website To the extent that there are any inconsistencies between information provided in this presentation and the requirements in the RFO materials, the RFO materials published on PG&E s website shall govern 4

Communications and Website RFO website (www.pge.com/rfo/drp2017) provides everything you need to submit an Offer, including (but not limited to) the following: RFO materials Detailed instructions for submitting Offers(s) using Power Advocate and to the IE Announcements, additional resources, and Q&A All solicitation communications should be directed to: DRPRFO@pge.com with a copy to the Independent Evaluator at Alan.Taylor@sedwayconsulting.com 5

DRP Demo D RFO Schedule Date/Time May 16, 2017 May 24, 2017 July 17, 2017 by 1:00 PM PPT July 18, 2017 September 29, 2017 Event PG&E issues DRP Demonstration Project D RFO Participants webinar Deadline for Participants to submit Offers via Power Advocate Deadline for IE to receive a flash drive of Offers Participants Notified of Eligibility for Shortlisted Offer Negotiations October 13, 2017 Participants notify PG&E whether they accept Shortlist status June 2018 Target Advice Letter filing with the CPUC 6

Independent Evaluator (IE) Primary role of the IE is to: Monitor RFO processes to ensure fair and equal treatment of all Participants Monitor evaluation processes to ensure PG&E has implemented methodology as described and that offers are treated consistently Report on RFO process and proposed transactions to CPUC when filed for CPUC approval The IE may review all Offer data and communications with Participants 2017 DRP RFO IE is Sedway Consulting. Contact is: Alan Taylor (Alan.Taylor@sedwayconsulting.com) 7

Goals of DRP 8

Goals of DRP Modernize distribution system to accommodate expected DER growth through two way power flow Enable customer choice of new electric DER technologies and services Identify and develop opportunities for DERs to realize grid benefits 9

What are Distributed Energy Resources? Distributed Energy Resources (DER) means: Distributed Renewable Generation Energy Storage Energy Efficiency Demand Response Electric Vehicles 10

Demo D Overview CPUC has directed IOUs to procure distribution services from third party owned DERs in order to demonstrate DER capabilities in deferring traditional wires investments for two demonstration projects beginning in 2020: Demo C and Demo D Per CPUC filing, Demo D is focused on integrating high penetrations of DERs into utility distribution planning and operations PG&E has selected Huron Substation as the location for Demo D Objectives include: Operation of Aggregated Fleet of Dispersed DERs Multiple Applications of DERs Competitive Solicitation of DERs 11

Huron Substation Location Overview Location: Huron Substation, Fresno County 1,840 electric service points Summer Peaking Area Electrical Service: Four (4) electric distribution feeders powered at 12 kilovolts (kv) from Huron Substation provides service to end users Two (2) dedicated generation tie feeders interconnecting 20 megawatts (MW) of utility photovoltaic (PV) plant 1 Huron Substation Transformer Bank (70/12 kv) Customer Base: Agricultural (97 service points) Residential (1513 service points) Commercial and Industrial (236 service points) PV Capacity: 20 MW of utility PV tied directly to Huron Substation Symbols: Huron Feeders: = Huron Bank 1 1112 = 1106 = 1116 = 1108 = 207 kilowatts (kw) at Feeder Number (No.) 1116 Distribution feeder configurations as of May 1, 2017 886 kw at Feeder No. 1112 12

Customer Composition Served by Huron Substation Total Service Points by Sector Peak Day Demand by Sector 2% 11% 5% 53% 40% * Service point count as of February 1, 2017 82% *Total Peak Day Customer Sector Service Points Demand (MW) Residential 1513 6.58 Commercial 204 0.76 Industrial 32 0.37 Agricultural 97 8.54 2% 5% 13

Historical Peak Load: Day Shape by Customer Type Peak Load: 16.25 MW Time of Peak: 7 PM [July 1, 2016] 14

Historical Minimum* Load: Day Shape by Customer Type Peak Load: 6.92 MW Time of Peak: 7 AM [October 29, 2016] * Minimum load day within the Summer months defined by distribution planning cycle 15 15

Solar and DR Customers Served by Huron Substation PV Interconnections* #of Customer PV Installations Total PV Capacity (MW) 79 1.1 Demand Response #of Customers Participating in BIP and PDP Reduction to Peak Demand (MW) 128 2.27 * Customer interconnection values based on total number of customers interconnected as of May 1, 2017 16

Distribution Capacity Need: Huron Substation Loading Forecasts Reverse Flow Reverse flow overload is forecast beginning in 2020 Overload occurs during middle of the day in summer and shoulder months, driven by low customer load and high PV generation 2022 forecasts for reverse flow through the bank shown below to illustrate DER procurement need assuming 3 year contract (beginning of 2020 end of 2022) 2022 Summer Reverse Flow 2022 Winter Reverse Flow 10 10 5 5 0 0 Bank loading (MW) 5 5 10 10 15 15 Bank loading (MW) 20 20 25 25 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 1 2 3 4 5 6 7 8 9 101112131415161718192021222324 April May November December June July January February August September 17 October 95% Summer Bank Limit March 95% Winter Bank Limit

Distribution Capacity Need: Huron Substation Loading Forecasts Peak Load Peak load is forecast to hit the bank limit in 2022 Peak occurs in evenings in June and July, driven by pumping and AC load 2022 forecasts for peak load shown below to illustrate DER procurement need, assuming 3 year contract (beginning of 2020 end of 2022) 2024 forecasts are also shown for peak Winter months are well within bank limits throughout the 2020 2024 period 25 2022/2024 Summer Peak Load 2022 Winter Peak Load 25 20 20 Bank loading (MW) 15 10 Bank loading (MW) 15 10 5 5 0 0 1 2 3 4 5 6 7 8 9 101112131415161718192021222324 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 April May November December June 2022 July 2022 June 2024 July 2024 January February 18 August 95% Summer Bank Limit March 95% Winter Bank Limit

Distribution Services Procurement Summary Participants may Offer one or both products: 1. Hosting capacity 10 Reverse flow: February October Total procurement of 4 MW 5 Need exists February October, every day of each month 0 Participants will be required to offer either 3 or 6 hour blocks 10am 1pm; or 1pm 4pm; or 10am 4pm 2. Load capacity 20 Total procurement of 2 MW Need exists for June and July, every day of each 25 month Participants will be required to offer either 3 or 6 hour blocks 20 6pm 9pm; or 9pm 12am (midnight); or 6pm 12am (midnight) Participants cannot operate in certain ways during Restricted Periods No load increase from 5pm to 7am every day, April through October No load decrease from 9am to 5pm every day of 0 the year Bank loading (MW) 5 10 15 Bank loading (MW) 18 16 14 12 10 8 6 4 2 1 2 3 4 5 6 7 8 9 101112131415161718192021222324 10am-4pm 4MW load increase Peak load: June & July 2MW load decrease 6pm-12am 19 1 2 3 4 5 6 7 8 9 101112131415161718192021222324

Solicitation Overview 20

RFO Design (1/4) Product PG&E is purchasing distribution services only: hosting capacity and load capacity No RA, energy, ancillary services, RECs, other attributes PG&E is looking for delivery terms of 3 or 5 years Initial Delivery Date February 1, 2020 for hosting capacity June 1, 2020 for load capacity Project size Minimum size of 0.5 MW Maximum size of 2 MW for load capacity and 4 MW for hosting capacity Offers must be in increments of 0.5 MW Offers must be the same size for all the delivery months, delivery hours, and for the length of the delivery term Offers There are no limits on the number of offers Offers may be mutually exclusive/inclusive of each other 21

RFO Design (2/4) Project eligibility DERs: Renewable distributed generation, energy storage, energy efficiency, demand response, electric vehicles For hosting capacity, Projects cannot be strictly an increase in load Participants may be either in front of the meter or behind the meter Participants may offer one technology or a portfolio If offering a portfolio, Participants must identify the composition of the portfolio Participants may offer one resource or an aggregation Measurement and verification Participants must submit a measurement and verification plan with their offers Behind the meter Projects using a baseline methodology may require a customized approach 22

RFO Design (3/4) Interconnection Project must connect to specified lines/feeders No specific interconnection milestone required, but Participants must demonstrate they can meet the online date Participants can utilize the Integration Capacity Analysis (ICA) map on PG&E s DRP RFO website to get an indicative understanding of current capacity on the distribution lines in the Huron area Double payments/double counting Projects must be fully or partially incremental to PG&E s programs, tariffs, and solicitations Examples and links to PG&E s programs are provided on the PG&E DRP RFO website Participants must submit Appendix B5 of the RFO materials to demonstrate how their Offer is incremental Submit any questions on incrementality to DRPRFO@pge.com 23

RFO Design (4/4) Examples of fully incremental, partially incremental, and nonincremental Projects Resources can be: Fully Incremental Partially Incremental Not Incremental Examples Add on s to existing DERs; New programs; EE Technology not included in Portfolio Enhanced uptake of DER over base Rooftop PV compensated under NEM; DG or ES compensated under SGIP; EE or DR portfolio resources without enhancement 24

Customer Engagement Support 25

Customer Engagement Support PG&E is offering support to Participants with behind the meter Projects to improve the chances of success in acquiring customers For all Participants, PG&E will provide a customer facing website to enable customers in the area to validate that this is a PG&E solicitation PG&E is also offering additional resources to support customer acquisition: Offers should reflect Participant s value of such support Participants must include in their Offers the number of hours of PG&E Customer Relationship Manager support it wants Final scoping of support is subject to negotiation Example of services for 50 hours Assist in evaluating and executing co branding opportunities Customer engagement support for Participants identified targets Example of services for 200 hours Same as 50 hours plus: Assist with development of outreach plans Assist in identifying high potential customers 26

Term Sheet Overview 27

Transaction Product: Distribution Services in accordance with Operating Parameters Distribution hosting capacity: increase load or reduce generation during specified hours Distribution load capacity: decrease load or increase generation during specified hours Sellers are free to monetize other revenue streams Seller is free to operate the resource how it wants outside of the Restricted Periods Seller commits to provide Product at Contract Quantities Seller may sell excess amount of Product from Project to third parties Seller may sell other attributes of the Project to third parties Sellers will be instructed on whether they are required to provide hosting capacity or load capacity by 8 am day ahead No limit to number of dispatches per month Seller will provide PG&E with real time visibility into DER performance Sellers are required to install a communications system and equipment for PG&E to be able to remotely monitor Project status on an aggregate and individual unit basis 28

Payment and Delivered Energy Compensation: Fixed price ($/kw month) Variable price ($/kwh) for amount of Distribution Services Project provides when required If Contract Quantities are not delivered, fixed payment will be reduced Ratio Reduction 1.00 100% 0.90 and < 1.00 Ratio 0.80 and < 0.90 Ratio x 50% 0.75 and < 0.80 0 < 0.75 Ratio 75% (Seller will pay PG&E) 29

Project Site and Customers Sellers are solely responsible for acquiring Customers Sellers may remove or replace Sites/Customers, provided that changes are in accordance with safety provisions Seller must provide PG&E a list of Customers and satisfy incrementality criteria prior to Initial Delivery Date Changes to initial Customer list must continue to satisfy incrementality criteria Seller s marketing materials that reference PG&E are subject to written approval by PG&E Seller is responsible for all marketing activities, provided that PG&E may provide specified type of assistance and number of hours of customer representative time 30

Performance Assurance Performance Assurance Project Development Security is due to PG&E within five (5) business days following CPUC approval of the agreement and must be in the form of a letter of credit or cash and in the following amounts: $60 per kw for all new resources $25 per kw for existing resources Delivery Term Security is due to PG&E before the Initial Delivery Date and will be held by PG&E throughout the delivery term Maximum of $125/kw or 10% of the sum of the highest 36 months of fixed payments Damage Payment/Termination Payment In an event of default, defaulting party will owe non defaulting party an amount equal to the performance assurance 31

Conditions Precedent If CPUC Approval has not occurred on or before 180 days from the date on which PG&E files the agreement with the CPUC, then either party may terminate the agreement Initial Delivery Date shall not occur until Seller: Has constructed the Project and provided certification from an independent engineer that Project is commercially operable and constructed in accordance with the safety requirements Has passed an initial Performance Test demonstrating that the Project is capable of delivering Distribution Service Has provided PG&E with a list of Sites and Customers and PG&E has verified that such Sites/Customers are incremental Has provided Delivery Term Security 32

Events of Default Failure to meet a Critical Milestone Failure to meet Initial Delivery Date Monthly Distribution Services Factor for any calendar year is less than 75% Results of Performance Test shows that the Project provides less than 85% of Contract Capacity Seller does not operate in accordance with the Restricted Periods for more than 3 days per year 33

Evaluation Methodology 34

Evaluation Criteria: Least Cost, Best Fit Quantitative Factors Distribution deferral value Contract payments Customer engagement/support costs Administrative costs Qualitative Factors Project viability (including interconnection and site control assessment and developer experience) Credit Technology, counterparty diversity Small business enterprise 35

Offer Submittal Process 36

Offer Submittal Offers must be submitted via the online platform at Power Advocate. Only accepted registrants are permitted to submit Offers. Register through Power Advocate at: https://www.poweradvocate.com/pr.do?okey=69550&pubevent=true PG&E strongly encourages you to register well in advance of Offer due date of July 17 th at 1:00 PM (PPT). Offer materials must also be submitted to the IE on a USB flash drive, no later than July 18 th at the following address: Sedway Consulting, Inc. 821 15 th Street Boulder, CO 80302 PG&E will only consider Offers that, as of the submittal deadline, are complete and conforming Offers. 37

Keys to a Successful Proposal Sellers may choose to submit multiple Offers. Variations include: Term (3 or 5 year) Time block With or without customer engagement support Pricing 38

Required Offer Submission Forms Offer package must be in the format as specified in the 2017 DRP RFO Protocol. Introductory Letter. Format: MS Word Fully Completed Offer Form (Appendix A). Format: MS Excel Supplemental RFO Appendix Document (Appendices B1 through B7). Format: MS Word or PDF as noted Interconnection Studies, if applicable. Format: PDF or MS Word Note: Incomplete documentation will require additional communication to resolve any issues. 39

Offer Form 40

Offer Form Structure Instructions Validation Worksheet Participant Information Project Description Pricing Sheet Supply Chain Responsibility 41

Offer Form Instructions Be sure to ENABLE MACROS when opening the Offer Form. Instruction tab provides clear directions on completing the offer form. Please make sure you save and submit the form in Microsoft Excel.xlsb format. No other formats will be accepted. Each cell with a yellow background must be filled out. Once completed the yellow background will disappear. Grayed out cells are auto calculated cells. If the word Complete does not appear at the top of the page the form will be deemed invalid and returned to you. 42

Offer Form Participant Information Complete legal entity name At least one authorized contact Read through each attestation and affirmation on the Participant Information tab. A number of these items are specific to and/or new to this RFO. 43

Offer Form Product Description Name file to match bid ID Offer Variant Exclusions 44

Offer Form Product Description 1. Select Term 2. Select Time Slot 3. Select Contract Capacity 4. Select Technology and Time Slot 45

Offer Form Product Description 1. Select Term 2. Select Time Slot 3. Select Contract Capacity 4. Select Technology and Time Slot 46

Offer Form Pricing *Customer Engagement Support for Behind the Meter Projects only Enter Fixed Capacity Price in $/kw Month Enter Variable Price in $/kwh 47

Intermission 48

Q & A 49