Sources of Resource Risk

Similar documents
Overcoming Project Risk: Lessons from the PERIL Database. Tom Kendrick Program Manager, Hewlett-Packard Company. Introduction

Sources of Schedule Risk

Delivering contracts with teeth

Scheduling Principles and Problems

Why Managed Services and Why Not Staff Augmentation?

ITIL Intermediate Lifecycle Stream:

Service Center Organization

TABLE OF CONTENTS OBJECTIVE... 2 MARKET DRIVERS... 2 PROBLEM DEVELOPMENT... 2 A GENERIC INTRODUCTION TO THE SOLUTION... 3 BENEFITS... 3 EXAMPLES...

Workforce Solutions Guide

Those who cannot learn from history are doomed to repeat it. - George Santayana

Project vs Operation. Project Constraints. Pankaj Sharma, Pankaj Sharma,

Glossary 1. For a complete glossary of support center terminology, please visit HDI s Web site at HDI Course Glossary

The Need for a Collaborative Experience to Develop the Right Server Solution

Project Management. Kristian Sandahl

Session 2: A Phased Life Cycle for a modern system development project. COMP 377/477 Spring 2016 Conrad Weisert

2008 ERP REPORT. CONTACT: Panorama Consulting Group Part One in a Series

2018 Parking Services Cash Handling Review 8/3/2018. P.O. BOX 1027, SAVANNAH, GA

1. IDENTIFICATION. Freebalance coding: PURPOSE 3. SCOPE

Vendor Support Agreements: A Competitive Weapon for Optimizing Organizational Assets

The H igh C ost o f B usiness D isruption i n Modifying a nd M aintaining E RP

THE BIG STORY BENEFITS CASE STUDY. Client: Kelly Services Location: Troy, Michigan. Industry: Staffing and Recruiting

ICT Integration in Mergers & Acquisitions

RETAIL FOOD AMC-HACCP POLICIES, PROCEDURES AND STANDARDS MANUAL

SYSTEM MODERNIZATION BEST PRACTICES

PRINCE2 COURSE FOUNDATION. 1 Powered by POeT Solvers Limited

Improper Billing of Costs on Progress Payments 1

working with partnerships

AUDIT UNDP COUNTRY OFFICE JAMAICA. Report No Issue Date: 24 April 2015

Banks, Carson, Nelson & Nicol

PMP Practice Questions

Job Description. Carnival Corporate Shipbuilding. Principal Manager Naval Architecture. Reporting to (Job Title) : No of Direct Reports : 0

PAR Performance Factor Compendium Written Descriptors

Six Sigma Black Belt Week 3. Six Sigma Black Belt Week 3. Six Sigma Black Belt Week 3. Project Management. Chapter 3-4

19.3 Group Problem Solving L E A R N I N G O B JE C T I V E

COMPLYING WITH THE FMLA AND ADA WHEN YOUR EMPLOYEE IS DEALING WITH A MENTAL HEALTH CONDITION

7 Ways to Accelerate Your Go-to-Market Initiatives

Sources of Error in Software Cost Estimation

Chapter 8. Systems Development. Ralph M. Stair George W. Reynolds

The second procedure is called "Root Cause Analysis". It is used by specialists when they analyze a problem.

Metrics in Microbiology Monitoring Practices

This test is designed to provide information on your typical behaviour within work situations.

Getting Availability Right: Bringing Out-of-Stocks Under Control

Finding the Right Manufacturer for Your Design

JANUARY 2017 $ State of DevOps

The Core Structure of TOC Thinking Processes and their Applications to Improve Systems. Oded Cohen

QUESTION 1 What is known as a temporary solution that enables the user to continue working? A. Known Error B. Request For Change (RFC) C. Service Requ

ORION RESOURCES Solving the puzzle of smart hiring. Retained Search Quality A La Carte

Design & Detailing, or why every structural steel project is not profitable

Retail Deployment Management: The 7 Critical Challenges. The key issues that keep retail operations and project executives awake at night

I. POLICY FOR INTERNAL ALIGNMENT

Project Management for EnMS Implementation

LAND USE BOARD OF APPEALS (LUBA) Annual Performance Progress Report (APPR) for Fiscal Year

The Case for Code Quality Management

Top 5 finance processes that are the culprits of busy work. Automating your workflow to make your work flow.

The #1 Financial Mistake Made by Small-Business Owners

Need a Security Workforce Management Platform?

8 Critical Success Factors When Planning a CMS Data Migration

Optimizing the value of audit quality indicators Lessons we have learned

Using Demand Solutions APS for Effective Scheduling in the Food Process Industry

When Your People Are Engaged, Your Projects Really Move

Chapter 2: Project Management

Benefits and Limits to Performance Contracting

Effective Team Building

2017 Healthcare Compliance Benchmark Study

ESD264/1.264 Lecture 2 case study solutions Fall, A demand forecasting system

Strategic or Bust: Why Project Execution Needs to Change

How to Build a Solid Analytics Foundation

Cost of Quality. Appendix 2B. Copyright 2006, The McGraw-Hill Companies, Inc.

Retail Technology Roadmap Best Practices

Managerial Accounting and the Business Environment

Job Description. No of Direct Reports : 0. Titles of Direct Reports: Size of Department: 4. Budget Responsibility (direct) : 0

TOP FINANCE PROCESSES THAT ARE THE CULPRITS OF BUSY WORK. Automating your workflow. to make your work flow.

Enterprise Resource Planning Technical Assessment. Schools District of Manatee County. August 17, 2018

SESSION 607 Thursday, April 14, 2:45pm - 3:45pm Track: Metrics and Measurements. The Good, Bad and Ugly of Service Desk Metrics. Session Description

Introduction to Computer Integrated Manufacturing Environment

Cost of Poor Quality

ITIL Qualification: MANAGING ACROSS THE LIFECYCLE (MALC) CERTIFICATE. Sample Paper 2, version 5.1. To be used with Case Study 1 QUESTION BOOKLET

Contract Compliance: How Much Are Your Contracts Costing You? Written by: William Melville, Internal Audit Executive

QbD BASED SCALE UP SERVICES THE DPT LABS APPROACH

Price Electronics,LLC Quality Assurance Manual

The Impact of Agile. Quantified.

Contract Change Management

Job Description. No of Direct Reports : 0. Titles of Direct Reports: varied number in seconded project team. Budget Responsibility (direct) :

Requirements Gathering using Object-Oriented Models

Disruptive Technology Associates, Ltd.

Planning & Scheduling CSTM 102

Vehicle Operator I- Mail Courier (Existing position)

Information Outlook June, The Information Audit as a First Step Towards Effective Knowledge Management. Author: Susan Henczel

Define and Initiate SubPhase

Use of consultants and temporary staff

STRATEGIC ENVIRONMENTAL OUTSOURCING

FSC36 SAFE FEED/SAFE FOOD GUIDANCE DOCUMENT

Well Delivery Process A Proven Method to Improve Value and Performance While Reducing Costs. IADC/SPE

4. Which of the following statements are true regarding The Project Scope Statement based on the PMBOK 5h Edition?

Project Process Improvement

THE 2014 ERP REPORT:

A Guide for Employers Termination of Employment

KillTest *KIJGT 3WCNKV[ $GVVGT 5GTXKEG Q&A NZZV ]]] QORRZKYZ IUS =K ULLKX LXKK [VJGZK YKX\OIK LUX UTK _KGX

Transcription:

Sources of Resource Risk Like schedule risks, resource risks represent less than one third of the records in the PERIL database. Resource risks have an average impact of nearly seven weeks, intermediate between scope and schedule risks. There are three categories of resource risk: people, outsourcing, and money. risks arise within the project team. Outsourcing risks are caused by using people and services outside the project team for critical project work. The third category, money, is the rarest risk subcategory for the PERIL database, as very few of the problems reported were primarily about funding. Money, however, has the highest average impact and the effect of insufficient project funding has substantial impact on projects in many other ways. The root causes of people and outsourcing risk are further characterized by type, shown in this summary: Resource Root-Cause Subcategories Definition Count Cumulative Impact (Weeks) Average Impact (Weeks) Money: Limitation Motivation : Late Start Outsourcing: Late or Poor Output : Loss : Queuing Slip due to funding limits Loss of team cohesion and interest; often on long projects Staff available late; often due to delayed finish of earlier projects Deliverable late from vendor. Includes queuing, turnover Permanent staff member loss due to resignation, promotion, reassignment, health, etc. Slip due to bottleneck (includes specialized equipment) 17 228 13.4 8 69 8.6 15 115 7.7 34 260 7.6 40 277 6.9 27 117 4.3 Outsourcing: Delayed Start : Temporary Loss Contracting related delays 13 56 4.3 Temporary staff loss due to illness, hot site, support, etc. 33 128 3.9 1

A Pareto chart of overall impact by type of risk is in Figure 5-1. Although risks related to internal staffing dominate the listed resource risk subcategories, both outsourcing and money risks are included in the top three. Weeks of Project Impact 300 250 200 150 100 50 0 Loss Outsourcing Late or Poor Output Money Limitation Temp loss Queuing Late start Motivation Outsourcing Delayed start Figure 5-1: Total Project Impact by Resource Root-Cause Subcategories risks Risks related to people represent the most numerous resource risks, comprising almost 20 percent of the entire database and nearly two thirds of the resource category. risks are subdivided into five subcategories: Loss: Permanent staff member loss to the project due to resignation, promotion, reassignment, health, or other reasons Temporary loss: Short-term staff loss due to illness, hot site, support priorities or other reasons Queuing: Slip due to other commitments for needed resources or 2

expertise Late start: Staff not available at project start; often due to late finish of previous projects Motivation: Loss of team cohesion and interest; typical of long projects Loss of staff permanently had by far the highest overall impact, resulting in an average slip of almost seven weeks. Permanent staff loss represented about one third of the people risks. The reasons for permanent staff loss included resignations, promotions, reassignments to other work or different projects, and staffing cutbacks. Discovering these risks in advance is difficult, but good record-keeping and trend analysis are useful in setting realistic project expectations. Temporary loss of project staff was the next most common people-related risk, with roughly another third of the total. Its overall impact was lower than for permanent staff loss, causing an average slip of nearly four weeks. The most frequently reported reason for short-term staff loss was a customer problem (a hot site ) related to the deliverable from an earlier project. Other reasons for short-term staff loss included illness, travel problems, and organizational reorganizations. Queuing problems were about 20 percent of the people-related risks in the PERIL database. The average schedule impact due to queuing was just in excess of four weeks. Most organizations optimize operations by investing the bare minimum in specialized (and expensive) expertise, and in costly facilities and equipment. This leads to a potential scarcity of these individuals or facilities, and contention between projects for access. Most technical projects rely on at least some special expertise that they share with other projects, such as system architects needed at the start, testing personnel needed at the end, and other specialists needed throughout the project. If an expert happens to be free when a project is ready for the work to start, there is no problem, but if he or she has five other projects queued up already when your project needs attention, you will come to a screeching halt while you wait in queue. Queuing analysis is well understood, and it is relevant to a wide variety of manufacturing, engineering, system design, computer networks, and many other business systems. Any system subject to queues requires some excess capacity if it needs to increase throughput. Optimizing organizational resources needed for projects based only on cost drives out necessary capacity and results in project delay. Late starts for key staff unavailable at the beginning of a project also caused a good deal of project delay. While the frequency was only a little more than 10 percent of the people-related resource risks, the average impact was nearly eight weeks. Staff joining the project late had a number of root causes, but the most common was a situation was aptly described by one project leader as the rolling sledgehammer. Whenever a prior project is late, some, perhaps even all, of the staff for the new project is still busy working to get it done. As a consequence, the next project gets a slow and ragged start, with key people beginning their contributions to the new project only when they can 3

break free of an earlier one. Even when these people become available, there may be additional delay, because the staff members coming from a late project are often exhausted from the stress and long hours typical of an overdue project. The rolling sledgehammer creates a cycle that self-perpetuates and is very hard to break. Each late project causes the projects that follow also to be late. Motivation issues were the smallest subcategory, at only a bit more than 5 percent of the people-related resource risks. However, these risks had an average impact of nearly nine weeks, among the highest for any of the subcategories in the PERIL database. Motivation issues are generally a consequence of lowering interest on very long duration projects, or due to interpersonal conflicts. Thorough planning and credible scheduling of the work well in advance will reveal some of the most serious potential exposures regarding people. Histogram analysis of resource requirements may also provide insight into staffing exposures a project will face, but unless analysis of project resources is credibly integrated with comprehensive resource data for other projects and all the non-project demands within the business, the results will not be very useful. Aligning staffing capacity with project requirements requires ongoing attention. One significant root cause for understaffed projects is little or no use of project planning information to make or revise project selection decisions at the organization level, triggering the too many projects problem. Retrospective analysis of projects over time is also an effective way to detect and measure the consequences of inadequate staffing, especially when the problems are chronic. Outsourcing risks Outsourcing risks account for more than a quarter of the resource risks. Though the frequency in the PERIL database is lower than for people risks, the impact of outsourcing risk was nearly seven weeks, about equal to the database average. Risks related to outsourcing are separated into two subcategories: late or poor outputs and delayed start. Late or poor output from outsource partners is a problem that is well represented in the PERIL database. The growth of outsourcing in the recent past has been driven primarily by a desire to save money, and often it does. There is a trade-off, though, between this and predictability. Work done at a distance is out of sight, and problems that might easily be detected within a local team inside the organization may not surface as an issue until it is too late. Nearly three quarters of the outsourcing risks involved receiving a late or unsatisfactory deliverable from an external supplier, and the average impact for these incidents was nearly eight weeks. These delays result from many of the same root causes as other people risks turnover, queuing problems, staff availability, and other issues but often a precise cause is not known. Receiving anything the project needs late is a risk, but these cases are compounded by the added element of surprise; the problem may be invisible until the day of the default (after weeks of reports saying, Things are going just fine ), when it is too late to do much about it. Lateness was often exacerbated in cases in the PERIL database because work that did not meet specifications caused further delay 4

while it was being redone correctly. Delayed starts are also fairly common with outsourced work, causing about one quarter of the outsourcing problems. Before any external work can begin, contracts must be negotiated, approved, and signed. All these steps can be very time consuming. Beginning a new, complex relationship with people outside your organization can require more time than expected. For projects with particularly unusual needs, just finding an appropriate supplier may cause significant delays. The average impact from these delayed starts in the database was just over one month. Outsourcing risks are detected through planning processes, and through careful analysis and thorough understanding of all the terms of the contract. Both the project team and the outsourcing partner must understand the terms and conditions of the contract, especially the scope of work and the business relationship. Money risks The third category of resource risks was not very common in the PERIL database, representing less than 10 percent of the resource risks and about 2 percent of the whole. It is significant, however, because when funding is a problem, it is often a big problem. The average impact was the highest for any subcategory, at over 13 weeks. Insufficient funding can significantly stretch out the duration of a project, and it is a contributing root cause in many other subcategories (people turnover due to layoffs and outsourcing of work primarily for cost reasons, as examples). Black swans The worst 20 percent of the risks in the PERIL database are deemed black swans. These large-impact, hard-to-predict, rare events caused at least three months of schedule slip, and 33 of these most damaging 127 risks were resource risks. As with the black swans as a whole, the most severe of the resource risks account for about one half of the total measured impact. The details are: 5

Resource Risks Total Impact (Weeks) Black Swan Impact (Weeks) Black Swan Percentage Money Limitation 228 174 76% Outsourcing Delayed start 56 12 21% Late or poor output 260 152 58% Late start 115 58 50% Loss 277 101 36% Motivation 69 53 77% Queuing 117 50 43% Temp loss 128 12 9% Totals 1,250 612 49% As can be seen in the table, the black swan resource risks were distributed unevenly. The money category represents a much higher portion of the total, with outsourcing about as expected and people-related risks much lower. Not surprisingly, money issues were a substantial portion of the black swan resource risks. Eight cases, more than half of the risks reported in this category, were in this group, including such problems as: Project budget was limited to the bare minimum estimated. Important parts of scope were missed due to insufficient resources. Not enough staff was funded to cover the workload. Major cut backs delayed fixes that lost time and ultimately also cost a lot of money. Only half the resources required were assigned to the project. There were also ten outsourcing black swan risks. Nine were due to late or poor output, with these among them: 6

The vendor was unable to control the subproject and the work had to be redone. The supplier was purchased and reorganized; the project had to find a new supplier. Outsourced research work was not managed well, and all work was ultimately redone. Changes were agreed to, but the supplier shipped late and it failed. The subcontractor failed to understand technology and requirements. The partner on the project defaulted. The supplier was not able to meet deadlines. There was also a black swan outsourcing risk due to a delayed start when settling the terms of the agreement and negotiating the contracts took months and caused the project to begin very late. There were 15 additional black swan people risks. This category had a smaller proportion of severe risks but did have the largest total number of these severe risks. The three black swan risks associated with motivation were over one third of all the motivation risks, and they account for nearly 80 percent of the impact form this category of risk. These risks were: Management mandated the project but never got team buy-in. Staff got along poorly and frequently quarreled. The product manager disliked the project manager. Permanent staff loss also caused a lot of pain and led the list of black swan people risks with five examples: A key staff member resigned. The committed medical expert was no longer available. Staffing suffered cutbacks. Specialists were lost, including designers, business analysts, and QA/testers. There was a company-wide layoff. 7

There were also three black swan project risks due to queuing, where projects were slowed by lack of access to specific resources: Insufficient QA resources were available to cover the auditing tasks and training tasks. Key decisions were stalled when no system architect was available. Several projects shared only one subject matter expert There were three more major people risks caused by late staffing availability. All were due to people who were trapped on a delayed prior project. Temporary loss of people caused only one back swan risk, due to an unexpectedly early start of conflicting peakseason responsibilities that resulted in a protracted loss of project staff. 8