Background Information Document

Similar documents
Background Information Document

Background Information Document

Purpose of this Document

INITIAL PUBLIC MEETING

PUBLIC MEETING B3.1 ATTENDANCE REGISTERS. A record of attendance from the provided in the following pages.

Background Information Document and Invitation to Comment

Click to edit Master title style

1 INTRODUCTION 1.1 PROJECT APPLICANT

ENVIRONMENTAL IMPACT ASSESSMENT (BASIC ASSESSMENT) PROCESS: PROPOSED REVERSE OSMOSIS PLANT, IRON ORE HANDLING FACILITY, PORT OF SALDANHA

BACKGROUND INFORMATION DOCUMENT PROPOSED HAZARDOUS SUBSTANCE STORAGE FACILITIES AT THE SALDANHA BAY INDUSTRIAL DEVELOPMENT ZONE

BASIC ENVIRONMENTAL IMPACT ASSESSMENT for the BEER PROPERTY MANAGEMENT FILLING STATION

TEMA LIQUEFIED NATURAL GAS PROJECT ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT

The Project will consist of the following key components: PV solar panels/modules (arranged in arrays); DC-AC current inverters and transformers;

Annex B2.3. Background Information Document

Environmental and Social Impact Assessment [ESIA] for Proposed Liquefied Natural Gas (LNG) Project at Tema in the Greater Accra Region of Ghana

EXECUTIVE SUMMARY 1. INTRODUCTION

ENVIRONMENTAL IMPACT ASSESSMENT: PROPOSED PHOTOVOLTAIC ENERGY PLANT ON FARM KLIPGATS PAN NEAR COPPERTON, NORTHERN CAPE

BOLAND ENVIRONMENTAL CONSULTANTS CC

1 INTRODUCTION 1.1 PROJECT BACKGROUND

Abeokuta, Nigeria Greenfield Power Generation Plant Environmental Impact Assessment (EIA) Background Information Document (BID) January 2015

BACKGROUND INFORMATION DOCUMENT AND INVITATION TO COMMENT

4 ADMINISTRATIVE FRAMEWORK 4.1 INTRODUCTION

Figure 4. The proposed location of the Zalu Dam a) basin and b) wall.

NOTICE OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

The Phase Gas Pipeline Strategic Environmental Assessment (SEA) November 2017

CHAPTER 3: GENERAL DESCRIPTION OF THE PROPOSED COEGA INTEGRATED POWER PROJECT

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS AND WASTE MANAGEMENT LICENSE APPLICATION PROPOSED EXTENSION OF ASH DAMS AT HENDRINA POWER STATION, MPUMALANGA

Amended Background Information Document

SECTION 1: INTRODUCTION 1.1 BACKGROUND TO THE PROJECT

BIOMASS POWER PLANT NEAR MKUZE, KWAZULU-NATAL

BACKGROUND INFORMATION DOCUMENT:

Figure 1.1: Location of Majuba Power Station within the Pixley Ka Seme Local Municipality

Annex C. Port Zoning and Operational Opportunities and Constraints

FULL SCOPING AND ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

BACKGROUND INFORMATION DOCUMENT SEPTEMBER 2014 MDEDET REF NUMBER: 17/2/3N-389

Appendix A: Project Characteristics

PROPOSED WAAIHOEK WIND ENERGY FACILITY UTRECHT KWA-ZULU NATAL

Background Information Document

NOTICE OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS: APPLICATION FOR THE MINING OF SAND AT BORROW PIT MR771/8.6/R/80, VAN WYKSVLEI, NORTHERN CAPE.

13 July

DEA Reference Number: To be announced

The aim of the public participation process undertaken as part of this Scoping phase is to:

1 INTRODUCTION. Figure 1.1: Steve Tshwete Local Municipality

PROPOSED VOLSPRUIT MINE, MOKOPANE DISTRICT, LIMPOPO PROVINCE. Background Information Document (BID) ESCIENCE ASSOCIATES (PTY) LTD.

Cape Environmental Assessment Practitioners(Pty) Ltd

BRYPAAL SOLAR POWER (PV) PROJECT AND ASSOCIATED INFRASTRUCTURE

INTRODUCTION PROJECT DESCRIPTION

EIA FOR THREE 10MW PHOTOVOLTAIC (SOLAR) ENERGY FACILITIES PROPOSED FOR MARIENTAL, OMARURU AND OKAHANDJA BACKROUND INFORMATION DOCUMENT

Proposed Sea-Based Aquaculture Development Zone in Saldanha Bay. TNPA Port of Saldanha Planning Workshop

Photovoltaic Power Generation Facility, Prieska EXECUTIVE SUMMARY

Proposed Expansion of the existing Natal Solvent Recovery facility on ERF 7590, Pinetown (10 Clubhouse Place, Westmead) REF: 12/9/11/L44704/4

SEA FOR STRATEGIC GRID PLANNING IN SOUTH AFRICA: Enabling the efficient and effective roll out of strategic electricity transmission infrastructure

30-YEAR LONG-TERM PLANNING FRAMEWORK

PIPED-GAS REGULATION FEBRUARY 2017

Liquefied Natural Gas to Power IPP Procurement Programme

Overview of the South Africa s Independent Power Producers Procurement Programme

TEMA LIQUEFIED NATURAL GAS PROJECT ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT

Nxuba Wind Farm NERSA PUBLIC HEARINGS. 10 September 2015

INVESTMENT POTENTIAL INVEST IN PORT TERMINALS AT THE PORT OF WALVIS BAY NORTH PORT PROGRAM DATE: 29 AUGUST 2016 REVISION: 1

Steps in Building a Wind Farm

Liquefied Natural Gas to Power IPP Procurement Programme

Basic Assessment for the Vopak Efficiency (Growth 4) Project, Durban, South Africa

Positioning Nelson Mandela Bay for Renewable Energy Manufacturing Opportunities

Construction of a 600 MW independent power plant and associated infrastructure. BACKGROUND INFORMATION DOCUMENT July 2011

Appendix A1 NOTES OF PRE-APPLICATION AUTHORITIES MEETING

ENVIRONMENTAL IMPACT ASSESSMENT: PROPOSED REVERSE OSMOSIS PLANT AT HENDRINA POWER STATION, MPUMALANGA EXECUTIVE SUMMARY: FINAL BASIC ASSESSMENT REPORT

Opportunities in South Africa s Oceans Economy

VLAKVARKFONTEIN COAL MINE

BACKGROUND INFORMATION DOCUMENT

June Prepared for Eskom Holdings Limited PO Box 1091 Johannesburg Prepared by ENVIRONMENTAL IMPACT ASSESSMENT PROCESS DRAFT SCOPING REPORT

BACKGROUND INFORMATION DOCUMENT FOR A PROPOSED SEWER IN GROOT DRAKENSTEIN, WESTERN CAPE

BACKGROUND INFORMATION DOCUMENT & INVITATION TO COMMENT JULY 2015

Ministry of Energy and Water Government of Lebanon

The following buildings/facilities are included in the design of this Project:

ATLANTIC ARRAY OFFSHORE WINDFARM INITIAL CONSULTATION AVIATION INTERESTS

2010 EIA Regulations GNR 543 of 18 June 2010, effective 2 August 2010

BACK GROUND INFORMATION DOCUMENT

PUBLIC PARTICIPATION REPORT

PROPOSED LIBODE & NGQELENI BULK WATER SUPPLY CONVEYANCE CORRIDORS OR TAMBO DISTRICT MUNICIPALITY, EASTERN CAPE

Draft Scoping Report. Delivering sustainable solutions in a more competitive world

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS PROPOSED CONCENTRATING SOLAR POWER (CSP) PLANT AND ASSOCIATED INFRASTRUCTURE IN THE NORTHERN CAPE AREA

BACKGROUND INFORMATION DOCUMENT

Soetwater Wind Farm NERSA PUBLIC HEARINGS. 09 September 2015

UNDERGROUND COAL GASIFICATION - POWER OPPORTUNITIES

11 CONCLUSIONS, RECOMMENDATIONS AND WAY FORWARD Need for the project 11-1

NERSA Public Participation Process Klipheuwel Dassiesfontein Wind Energy Facility March 1, 2012

ESKOM HOLDINGS SOC LIMITED: WATER USE LICENCE APPLICATION AT THE MEDUPI AND MATIMBA POWER STATIONS, LEPHALALE LOCAL MUNICIPALITY, LIMPOPO PROVINCE

FINAL ENVIRONMENTAL SCOPING REPORT (DEAT APPLICATION NO. 12/12/20/806)

Our Activities, Our Commitment

LNG Importation Initiative. Saldanha Cape Town Corridor. Fossil Fuel Foundation 21 May 2014

Click to edit Master title style

BACKGROUND INFORMATION DOCUMENT FOR THE ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED ELECTRICITY GENERATION PLANT HERNIC FERROCHROME

SOCIAL IMPACT ASSESSMENT FOR

EXECUTIVE SUMMARY: SCOPING REPORT ENVIRONMENTAL IMPACT ASSESSMENT (EIA) PROCESS FOR VISSERSHOK NORTH LANDFILL WASTE MANAGEMENT LICENCE

This is a working draft report provided for information purposes only, and may be modified prior to finalisation. It has been prepared on the basis

INSTALLATION OF A SOLAR PHOTOVOLTAIC POWER PLANT AT ESKOM S DUVHA POWER STATION: ENVIRONMENTAL IMPACT ASSESSMENT

The Republic of South Africa. Department of Energy REQUEST FOR INFORMATION IN RESPECT OF THE DESIGN OF A GAS TO POWER PROGRAMME

Proposed Acetylene Gas Production Facility

NERSA Public Hearing Dyason s Klip 1 (Pty) Ltd

Transcription:

Background Information Document Independent Power Producer Programme: EIA for a Floating Power Plant and EIA for LNG Import Facilities, Port of Saldanha: ERM Ref Number: 0320754 Purpose of this Background Information Document and ERM s Role The Department of Energy (DoE) plans to procure power from a Floating Power Plant to be located within the Port of Saldanha Bay to help meet South Africa s electricity requirements. Transnet will need to grant the rights in the port for this project and also plans to enable the development of Liquefied Natural Gas (LNG) import facilities within the Port of Saldanha to support the DoE s gas-to-power programme. The DoE and Transnet are considering similar projects in the Ports of Richards Bay and Ngqura. The Floating Power Plant and LNG Import Facilities each require Environmental Authorisation through Environmental Impact Assessments (EIAs) from the National Department of Environmental Affairs (DEA) in terms of the National Environmental Management Act (NEMA), 1998 (Act No. 107 of 1998), as amended. This document provides background information on both projects and EIA processes. It aims to assist interested and affected parties to understand the background to the projects, and to provide guidance on getting involved. Interested and affected parties can play a very important role in the EIA processes and therefore we encourage you to register as an interested and affected party. This will help us to keep you informed throughout the EIA processes. You will have opportunities to engage in discussions on issues, provide comment on the draft Scoping Reports, various specialist study findings as well as the draft EIA Reports that will be produced through the EIA processes. Your input will inform the report s content, and will also be included in the final submissions to DEA, the body that will take a decision on the proposed developments.

Background Information Document ERM s Role in the FPP and LNG Facilities The DoE has appointed Environmental Resources Management Southern Africa (Pty) Ltd (ERM) as the independent Environmental Assessment Practitioner for the EIAs for both the Floating Power Plant and the LNG Import facilities in Saldanha Bay. The EIA will be undertaken in several steps, scoping issues and alternatives, coordinating specialist studies and compiling Environmental Impact Reports that set out the anticipated impacts and how these might be mitigated. The EIA reports are prepared to inform an environmental authorisation decision to be taken by the DEA, the competent authority. A further crucial part of ERM s role is to facilitate the active involvement of interested and affected parties in the process. All of this activity must be conducted to the highest standards of independence and professionalism. Get involved. Register as an interested and affected party. Please complete the enclosed registration/comment sheet or contact ERM to register as an I&AP. The Gas to Power Programme Tougheeda Aspeling of ERM Southern Africa: Tel: 021 681 5400; Fax to email: 086 719 5869 Postnet Suite 90, Private Bag X12, Tokai, 7966 Email: G2Psaldanhabay.eia@erm.com Project Website: www.erm.com/gastopower The National Development Plan (NDP) identifies the need for South Africa to invest in a strong network of economic infrastructure designed to support the country s medium- and long-term economic and social objectives. This requires the development of 10,000 MWs of additional electricity capacity to be established by 2025. To achieve this, the DoE has developed a 20-year energy plan for South Africa, the Integrated Resources Plan 2010-2030 (IRP 2010), which encourages the participation of independent power producers (IPPs) in electricity generation in South Africa. The Independent Power Producers (IPP) Office was established by the DoE, the National Treasury and the Development Bank of Southern Africa (DBSA) to facilitate the involvement of IPPs in the generation of electricity. The IPP Office has to date successfully procured 6327 megawatts (MW) under the Renewable Energy IPP Procurement Programme. It is currently intended that a further 3126 MW of new generation capacity wil be generated from natural gas. For the Gas IPP Procurement Programme, the DoE through the IPP Office has, in collaboration with Transnet, developed a two-phased approach. The first phase is to introduce Floating Power Plants in three of South Africa s commercial ports Saldanha Bay, Ngqura and Richards Bay. The second phase is to facilitate the import of Liquefied Natural Gas (LNG) to allow for the development of medium- to long-term gas power plants in the same three ports. Separate applications and studies are being undertaken by private parties for gas power plants and related infrastructure near the Port. Following a competitive bidding process to be conducted by the DoE through the Independent Power Producers (IPP) Office, the DoE plans to select only one of these applicants to develop a gas power plant. The competitive bidders need to conduct EIAs for their respective project proposals. Project Description Floating Power Plants are special purpose marine vessels which incorporate power generation equipment and only require a land based switchyard to distribute power. The proposed Floating Power Plant Project has both land-based (terrestrial) and marine-based components, including the following: Floating Power Plant which may be a power barge or a selfpropelled powership (marine); Mooring infrastructure in the form of anchors, dolphin structures and a piled temporary access jetty; Floating fuel storage facilities (marine); Connection of the fuel storage facility to the Floating Power Plant for the transfer of liquid fuel/gas on board (marine); 2 Underground or aboveground power lines connecting the Floating Power Plant to a floating or terrestrial switchyard for the conversion of the power to a higher voltage (marine and terrestrial); Transmission line to Blouwater substation for distribution into the national power grid (terrestrial).

EIA for a Floating Power Plant and LNG Import Facilities Several Floating Power Plants could be moored within each port depending on the power generation capacity, the capacity of the relevant substation to distribute this power and space within the Port. There is currently 332 MW capacity available at the Blouwater substation. The Floating Power Plant will be powered by liquid fuel and may be converted to a gas powered facility at a later date. Fuel is typically supplied from a bunker barge or tanker vessel moored close to the Floating Power Plant. Refuelling the fuel storage vessel typically takes place once a week via a fuel supply vessel. The Floating Power Plant will operate 24 hours per day for 365 days per year. The Floating Power Plant would be moored within the Port of Saldanha to the north of the bulk iron ore loading facility on the western side of this causeway. Power would be evacuated via a switching yard and a 132 kv transmission line (approximately 7.5 km) to the Blouwater substation, which is managed by Eskom An illustration of the proposed FPP LNG Import Facilities The proposed LNG Import Facilities aim to secure gas supplies to feed to land-based gas power plants, other industrial users and FPPs. The facilities will provide for the importation, storage, regasification and the transmission of natural gas to a distribution hub, and will include both land-based (terrestrial) and marine-based components. There are currently two (2) infrastructure technologies under consideration for this, including the following: Floating Regasification This would consist of the following components: A marine import facility consisting of a loading quay, berthing and mooring dolphins, access and services trestle and pipeline; A permanently moored Floating Storage and Regasification Unit (FSRU) (marine); and A gas pipeline connecting the fuel storage and regasification facility to a common gas distribution hub from which the gas will be distributed to the power plant and domestic users via pipeline. An illustration of the floating regasification technology 3

Background Information Document Land-based Regasification The would consist of the following components A marine import facility consisting of a loading quay, berthing and mooring dolphins, access and services trestle and pipeline; A dock at an existing facility in the port or a special purpose docking facility to be constructed for an LNG transport ship; A cryogenic gas pipeline connecting the LNG carrier to storage and regasification facilities on land; A gas pipeline from the regasification unit to a gas distribution hub which will then distribute the gas further to a power plant and other gas users. Electricity is connected from the power plant to the national grid. An illustration of the regasification technology Once operational, LNG carriers will supply the LNG Import Facility which will discharge the LNG load to the FSRU/FSO over a period of approximately 24 hours. It is envisaged that the LNG Import Facility will operate for 24 hours per day for 365 days per year. The location of the LNG import facility would be within the Port of Saldanha. Project Inputs, Outputs and Potential Concerns There are a number of activities associated with the construction and operation of a Floating Power Plant and an LNG Import Facility that may result in environmental and social impacts. At this stage the issues of concern shown below will be addressed as part of the EIA process. Additional issues and concerns will be identified during the public participation process. The potential impact of noise and air emissions associated with each Project, and what this means for people and the broader environment in the area. The potential impact of the Projects on terrestrial animals and plants. The potential impact of the Projects on marine life. The management of waste during the Project lifespan. The benefits associated with the Projects, such as increased energy production for the country, and employment creation. 4

EIA for a Floating Power Plant and LNG Import Facilities INPUTS OUTPUTS Project Inputs and Outputs for the FPP INPUTS OUTPUTS Cool Water Project inputs and outputs for the LNG Facilities using a Floating Storage and Regasification Unit INPUTS OUTPUTS Cool Water Project inputs and outputs for the LNG Facilities using land-based regasification 5

Background Information Document The Environmental Impact Assessment Processes The two (2) Environmental Impact Assessments (EIA) for the proposed Floating Power Plant and LNG Import Facility are being conducted in terms of the National Environmental Management Act, 1998, (Act No. 107 of 1998), as amended (NEMA). The proposed Projects trigger listed activities in EIA Regulations Listing Notice 1 (GNR R983), Notice 2 (GNR 984) and Notice 3 (GNR 985), as well as activities listed in the National Environmental Management: Waste Act, 2008. Therefore, these Projects will require full Scoping and EIA Processes to support any environmental authorisation decisions. A typical full Scoping/EIA Process is explained below. Scoping Phase The purpose of the scoping phase is to communicate the proposed project to interested and affected parties, to identify possible positive and negative impacts, alternatives, as well as to determine the terms of reference for specialist studies to be conducted in the EIA phase. This will be set out in the Scoping Report. The Draft Scoping Reports for the projects will be made available for a thirty (30) day public comment period. EIA Phase The possible positive and negative impacts identified in the scoping reports will be assessed in the EIA Reports. The significance of the impacts will be rated using a prescribed methodology. As the preferred design and technology has not been selected for the projects, an envelope of project description options and impacts will be assessed. The Environmental Impact Reports arising from this phase will include Environmental Management Programmes, which will detail proposed management measures to minimise negative impacts and enhance positive impacts. The draft EIAs will be made available for a thirty (30) day public comment period. The DoE is the current applicant for environmental authorisations for these Projects. Once the DoE is awarded, the environmental authorisations will need to be transferred into the names of the winning companies once they are identified. In addition to environmental authorisation being applied for through NEMA, the following permits may be required: Water Use Licences in terms of the National Water Act, 1998 (Act No. 36 of 1998); Air Emissions Licences in terms of the National Environmental Management: Air Quality Act, 2004 (Act No. 39 of 2004); and Coastal Water Discharge Permits in terms of the National Environmental Management: Integrated Coastal Management Act, 2008 (Act No. 24 of 2008). The National Department of Environmental Affairs (DEA) is the competent authority for both EIAs. The Final Scoping Reports and EIA Reports, along with all stakeholder comments, will be submitted to the DEA for decision making. 6 lbhsouthafrica.com

the environmental impact assessment processes ENVIRONMENTAL APPROVAL PROCESSES Pre-application Activities Pre-application consultation with Competent Authority Public Engagement (including Notifications, Advertising, BID and Public Meetings Formal application Draft SCOPING REPORT & PLAN OF STUDY FOR EIA (Scoping Phase: 44 days from acceptance of application) I & AP Comment Period 30 days Final SCOPING REPORT & PLAN OF STUDY FOR EIA Authority Review Authority Acceptance 30 days Draft ENVIRONMENTAL IMPACT REPORT (EIA) & ENVIRONMENTAL MANAGEMENT PROGRAMME Public Meetings I & AP Comment Period 30 days Final ENVIRONMENTAL IMPACT REPORT (EIA) & ENVIRONMENTAL MANAGEMENT PLAN (EMP) Grant or Refuse Authorisation Notify Applicant of Decision NOTIFICATION TO ALL I & APs Appeal Period INTEGRATED ENVIRONMENTAL AUTHORISATION 60 days 5 days 14 days Appeal 20 days Appeal Process 90 days 7

17 54'0"E 17 56'0"E 17 58'0"E 18 0'0"E R399 Small Bay SAS Saldanha Nature Reserve Saldanha Bay Vondeling Island 17 52'0"E 17 54'0"E 17 56'0"E 17 58'0"E 18 0'0"E Big Bay 18 2'0"E Langebaan 18 2'0"E 18 4'0"E Eskom Blouwater Substation 350MW 18 4'0"E 18 6'0"E West Coast National Park 18 6'0"E R27 18 8'0"E 18 8'0"E R45 Study Area BOTS WA NA LIM POPO NA MIBIA NORTH W EST FREE STATE NORTHERN CAPE EASTERN CAPE WESTERN CAPE 0 1 2 3 4 Kilometers TITLE: Ortho Photo Locality Map of Saldhana Bay and the West Coast National Park, Saldhana. Westen Cape CLIENT: DATE: Oct 2015 CHECKED: LB PROJECT: XXXXXX DRAWN: AT APPROVED: MC SCALE: 1 : 120 000 DRAWING: REV: Ortho Locality Map of Shell Main Sail.mxd 0 ERM Building 32, The Woodlands, Woodlands Drive, Woodmead, 2148 Johannesburg, South Africa Tel: +27 11 798 4300 Fax: +27 11 804 2289 Projection: Transverse Mercator, CM 19, Datum: WGS 84 SIZE: Image Source: ESRI World Imagery Layer - DigitalGlobe - 2011 Protected Areas: WDPA Geosites: NGA. Inset: ESRI Data and Maps A4 33 8'0"S 33 6'0"S 33 4'0"S 33 2'0"S 33 0'0"S 32 58'0"S 33 10'0"S 33 8'0"S 33 6'0"S 33 4'0"S 33 2'0"S 33 0'0"S 32 58'0"S C:\Gis Projects\0308613_SHELL_MAIN_SAIL\MAPPING\MXD\Ortho Locality Map of Shell Main Sail.mxd MOZA MBIQUE Background Information Document General Port and Substation Overview FPP Mooring Location General LNG Facilities location It is unlawful for any firm or individual to reproduce copyrighted maps, graphics or drawings, in whole or in part, without permission of the copyright owner, ERM Southern Africa (Pty) Ltd Legend Blouwater Substation FPP Mooring Location General LNG Facilities location Primary Road Secondary Road Tertiary Road Street/Road Track Railway Protected Areas (WDPA) ZIM BAB WE GAUTE NG MPU MA LAN GA SWAZILAND KWAZU LU -N ATAL LE SOT HO SCALE: Department of Energy 8

EIA for a Floating Power Plant and LNG Import Facilities EIA for a Floating Power Plant and LNG Import Facility, Port of Saldanha Registration and Comment Sheet October 2015 Send your queries, comments or suggestions on the proposed project to us. You can email, fax, post or hand them to us. Comments Return this comment sheet to Tougheeda Aspeling of ERM Southern Africa: Tel: 021 681 5400; Fax to email: 086 719 5869 Postnet Suite 90, Private Bag X12, Tokai, 7966 Email: G2Psaldanhabay.eia@erm.com Project Website: www.erm.com/gastopower Please fill-in your contact details below for the stakeholder database. Title and Name: Organisation: Telephone: Cellphone: Position: Email: Postal Address:

Annexure A Examples of Floating Power Plants Example of a Liquid Natural Gas Import facility