B512 - GABIONS - OPSS 512

Similar documents
CONSTRUCTION SPECIFICATION FOR INSTALLATION OF GABIONS

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF GABIONS

B701 WATERMAINS- OPSS 701

B441 - WATERMAINS - OPSS GENERAL

902 - EXCAVATION AND BACKFILL FOR STRUCTURES - OPSS Bridges - Working slabs/pads - footings for piers and abutments - wingwalls

B405 - PIPE SUBDRAINS - OPSS 405

406 - PIPE SEWERS - MTC FORM 406

421 - PIPE CULVERTS - OPSS 421 INDEX

Select Subgrade Material, Compacted

B723 ENERGY ATTENUATORS - OPSS 723

Special Provision No. 405F03 March 2005

B STEEL BEAM GUIDE RAIL - OPSS 552

B STEEL BEAM GUIDE RAIL - OPSS 721

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING

410 PIPE SEWERS- OPSS 410

B421-2 PIPE CULVERTS OPSS 421

B410 - PIPE SEWERS - OPSS 410

B410 - PIPE SEWERS OPSS.PROV 410

CONSTRUCTION SPECIFICATION FOR PIPE SUBDRAINS

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING

CONSTRUCTION SPECIFICATION FOR PIPE SUBDRAINS

B421-2 PIPE CULVERTS OPSS 421

B421-2 PIPE CULVERTS OPSS.PROV 421

Construction Specification for Trenching, Backfilling and Compacting

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING AND COMPACTING

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING

B351 - CONCRETE SIDEWALK - OPSS 351

B STEEL BEAM GUIDE RAIL - OPSS 721

FULL-DEPTH RECLAMATION WITH EXPANDED ASPHALT STABILIZATION

Special Provision No. 421F01 April 2006

GABIONS AND REVET MATTRESSES

B STEEL BEAM GUIDE RAIL - OPSS 721

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

B510-5 REMOVAL-PAVEMENT WORK OPSS 510. CDED B Removal CDED B Reclaim Asphalt Pavement

B STEEL BEAM GUIDE RAIL - OPSS.PROV 721

B760 - NOISE BARRIER SYSTEMS OPSS 760

GABIONS - Galvanized

B209 - EMBANKMENTS OVER SWAMPS AND COMPRESSIBLE SOILS - OPSS 209. Excavation method means to remove the swamp material mechanically.

B723 ENERGY ATTENUATORS - OPSS 723

B366 - REPAIRING CONCRETE PAVEMENT AND CONCRETE BASE - OPSS 366

EARTH EXCAVATION (GRADING) - OPSS 206 INDEX

540 - HIGHWAY FENCE - OPSS 540. For full details of fencing Rights-of-Way, the designer is referred to Admin-Property Directive B- 3.

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS IN OPEN CUT

B510-5 REMOVAL-PAVEMENT WORK OPSS 510. CDED B Removal CDED B Reclaim Asphalt Pavement

CONSTRUCTION SPECIFICATION FOR TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES

CONSTRUCTION SPECIFICATION FOR SUPPORT SYSTEMS

Click on image to enlarge.

GABIONS PVC Coated. Product Standard Specifications Installation Instructions Method of Measurement and Payment. Update: May 1999

Special Provision No. 421S01 November 2006

DIVISION 4100 SITEWORK

ITEM 750 ROCK FILTER DAMS

CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES

STANDARD SPECIFICATIONS JULY 2012 S-11 CULVERTS, HEADWALLS AND ROADSIDE DRAINAGE TABLE OF CONTENTS

CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES PRECAST BOX CULVERTS CONSTRUCTION SPECIFICATION

Contract Design, Estimating and Documentation (CDED) Manual REVISION PACKAGE #203

Special Provision No. 399F01 December 2014

CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES

ROAD COMMISSION FOR OAKLAND COUNTY. SPECIAL PROVISION FOR GABION WALL RCOC/DESIGN: AB Page 1 of 8 RCOC12SP706F 10/28/2013

CASE STUDY SERIES #10

MICRO-SURFACING - OPSS 336

CONSTRUCTION SPECIFICATION FOR IN-PLACE FULL DEPTH RECLAMATION OF BITUMINOUS PAVEMENT AND UNDERLYING GRANULAR

304 - SURFACE TREATMENTS - OPSS 304

MOA Project # Golden View Drive Intersection & Safety Upgrades

STANDARD SPECIFICATIONS JANUARY 2015 S-4 GRANULAR BASE and AGGREGATES TABLE OF CONTENTS

MagnumStone Specifications Gravity

Special Provision No. 599S22 March 2018 REQUIREMENTS FOR RETAINED SOIL SYSTEMS (RSS)

CONSTRUCTION SPECIFICATION FOR CLEARING, CLOSE CUT CLEARING, GRUBBING, AND REMOVAL OF SURFACE AND PILED BOULDERS

A.2.a Random Riprap... Table

Construction Specification for General Excavation

Construction Specification for Concrete Unit Pavers

Welded Mesh Gabions and Mattresses River Protection Design Guide Anping County Zhuoda Hardware Mesh Co.,Ltd. Wire Mesh Industrial Zone, Anping

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1

CONSTRUCTION SPECIFICATION FOR IN-PLACE FULL DEPTH RECLAMATION OF BITUMINOUS PAVEMENT AND UNDERLYING GRANULAR

CONSTRUCTION SPECIFICATION FOR PIPE CULVERT INSTALLATION IN OPEN CUT

EXPANDED POLYSTYRENE (EPS GEOFOAM) EMBANKMENT DIVISION 31 EARTHWORK

CHAPTER 200 STORM SEWER CONSTRUCTION STANDARDS

B EARTH GRADING - OPSS.PROV 206

CONSTRUCTION SPECIFICATION FOR CONCRETE UNIT PAVERS

Earth Retaining System

CONSTRUCTION SPECIFICATION FOR IN-PLACE FULL DEPTH RECLAMATION OF BITUMINOUS PAVEMENT AND UNDERLYING GRANULAR

CONSTRUCTION SPECIFICATION FOR TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES

CONSTRUCTION SPECIFICATION FOR PIPE CULVERT INSTALLATION IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

Special Provision No. 799F01 March 2012 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF NOISE BARRIER TABLE OF CONTENTS

CONSTRUCTION SPECIFICATION FOR COMPACTING

Cold In-Place Recycling with Expanded Asphalt B-335 COLD IN-PLACE RECYCLING WITH EXPANDED ASPHALT OPSS 335

Construction Specification for Concrete Curb and Concrete Curb and Gutter

Special Provision No. 599F01 May 2004 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF NOISE BARRIER TABLE OF CONTENTS

CONSTRUCTION SPECIFICATION FOR SITE RESTORATION FOR UNDERGROUND UTILITIES

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS

CONSTRUCTION SPECIFICATION FOR WICK DRAIN INSTALLATION

CONSTRUCTION SPECIFICATION FOR SITE RESTORATION FOLLOWING INSTALLATION OF PIPELINES, UTILITIES, AND ASSOCIATED STRUCTURES

SECTION 303 CULVERTS

Transcription:

B512 - - OPSS 512 512.1 GENERAL Gabions are contained rectangular units made of steel wire mesh and filled with stone. The double twisted wire mesh is galvanized and PVC (polyvinyl chloride) coated. Gabions are flexible and permeable baskets or mats that when combined, may be used for applications ranging from riverbank erosion protection to retaining systems. Gabion baskets are supplied in collapsed form that require site assembly and hand placement of stone (Figure 1). They are manufactured in standard sizes with the following nominal dimensions: Width 0.5m or 1.0m Length 1.5, 2.0, 3.0 or 4.0m Height 0.3, 0.5 or 1.0m Figure 1 - Gabion Basket Gabion baskets stacked vertically are referred to as gabion structures. Gabion mats, generally used as channel lining, are supplied in 30 metre rolls with or without filter cloth. They are manufactured in nominal widths or 2.0 or 3.0 m and standard heights (depths) of 0.23 and 0.30 m. January 2014 Page 1 of 5 B512

512.2 REFERENCES Foundation Investigation and Design Report project specific MTO Drainage Management Manual MTO Retained Soil Systems Guidelines MTO Structural Manual Maccaferri Gabions - Design and Installation Guides 512.3 TENDER ITEMS The tender items associated with the placing of gabions and erection of gabion structures are: Gabions Gabion Structures Not Exceeding 2m Height 512.4 SPECIFICATIONS The installation of gabions is detailed in OPSS 512. The installation of gabion structures is detailed in OPSS 512 amended by special provision. Materials for gabion baskets and mats are specified in OPSS 1430. 512.5 SPECIAL PROVISIONS The designer should refer to Chapter E of this manual to review the special provisions applicable to these tender items. 512.6 STANDARD DRAWINGS There are no Ontario Provincial Standard Drawings for gabions. 512.7 DESIGN The main sources of information are the Regional Geotechnical Section, Regional Environmental Section, Pavements and Foundations Section and the Regional Structural Section. For design application details, see manufacturers' publications. January 2014 Page 2 of 5 B512

Gabion baskets may be used for the following installations: Retaining walls Wingwalls Weirs Headwalls Toe walls Channel lining Slope paving Culvert aprons Where gabion installation is of a simple nature, i.e channel lining, slope paving, aprons or weirs, the work under the item "Gabions" is all-inclusive, covering any excavation for gabions and bedding, placement of granular for bedding, use of geotextiles and the installation of the gabion. Geotextile may be used to separate the gabion baskets from the adjacent and underlying earth and/or backfill material, depending on the existing soil conditions and proposed backfill properties. The need for geotextiles should be assessed on a project-specific basis. Where the OPSS 512 requirements for geotextile are not appropriate, the geotextile requirements shall be specified in the Contract Drawings or by Non-Standard Special Provision. When a gabion installation has a retaining function and holds back an embankment, i.e. headwall, wingwall, retaining wall or toe wall, it is described as a gabion structure and the item "Gabion Structures not Exceeding 2m Height" should be used. Height is measured from the base of the gabion structure and includes embedment depth, when applicable. The designer may consult with the Regional Structural Section when designing "Gabion Structures not Exceeding 2m Height". Design checks for bearing, sliding and overturning are required. For work under the item Gabion Structures not Exceeding 2m Height, excavation for structure, granular bedding and backfill, and protection system (if required) are covered by separate tender items. In the case of granular backfill, the tender item would be the appropriate general granular item in the contract. If the Contractor chooses or requires a protection system and the Protection System tender item is not used to cover this in the contract, such protection system shall be according to OPSS 539 and the costs would be included in the Gabion Structures Not Exceeding 2 m Height tender item. At MTO, retaining structures less than 2 m in height are considered landscape walls. For gabion structures exceeding 2 m in height, the MTO Retained Soils Systems process shall be followed. January 2014 Page 3 of 5 B512

512.7.1 Information to be Provided to Bidders The Designer should identify whether protection systems are required. The designer shall consult with the Regional Geotechnical Section to determine whether protection systems are required. If so, a Foundation Investigation Report describing the subsurface conditions in the vicinity of the protection systems should be provided and a separate OPSS 539 Protection System tender item should be included in the contract. 512.8 COMPUTATION The items Gabions and Gabion Structures not Exceeding 2m Height are both Plan Quantity Payment items. The unit of measurement for Gabions and Gabion Structures not Exceeding 2m Height is the cubic metre. The volumes of Gabions and Gabion Structures not Exceeding 2m Height are calculated from the number and dimensions of baskets shown on the design drawings. Excavation for the Gabions item is carried out according to OPSS 206. Excavation for the Gabion Structures not Exceeding 2m Height item is carried out according to OPSS 902. When required, it should include excavation for bedding and frost tapers. The designer is referred to Section B902 of the CDED. 512.9 DOCUMENTATION 512.9.1 Contract Drawings Both new and existing gabions, or gabion structures requiring extension are shown on the plans and profiles of the contract drawings. Typical cross-sections should be included in the contract drawings that show dimensions, any bedding and backfill requirements and excavation limits. Where there is a requirement for a protection system, the line of protection or a protection system shall be shown on the contract drawings depending on the magnitude of the protection required. The actual length and location of the protection system required is the contractor s responsibility. Performance levels should be included on the contract drawings. A separate tender item is provided to cover the protection work. January 2014 Page 4 of 5 B512

Material for bedding and backfill must be identified on the drawings even when it is to be provided under the Earth Excavation (Grading) or Earth Borrow item. The OPSS 1004 gradation of the gabion stone, G-3 or G-10, shall be identified on the drawings. 512.9.2 Quantity Sheets The quantity for each Gabion or Gabion Structure location is shown separately on "Quantities - Miscellaneous 1" sheet. The column total provides the tender quantity. 512.9.3 Documentation Accuracy Stations are recorded to the nearest whole metre. Offsets are recorded to 0.1 of a metre. Quantity entries are recorded to the nearest cubic metre. January 2014 Page 5 of 5 B512