Carmel River Reroute & San Clemente Dam Removal Project (PLN110373) Monterey County Planning Commission Workshop July 25, 2012

Similar documents
MONTEREY PENINSULA WATER MANAGEMENT DISTRICT PROJECT DESCRIPTION FOR SELECTIVE VEGETATION MANAGEMENT AND BANK RESTORATION (RANCHO SAN CARLOS AREA)

Water and Environment. Monterey Peninsula, Carmel Bay and South Monterey Bay Integrated Regional Water Management Draft Plan

NOTICE OF PREPARATION

A Review of the San Clemente Dam Removal & Carmel River Reroute Project

Sacramento Area Flood Control Agency. May State Clearinghouse No Prepared for: Prepared by: Consulting Engineers and Scientists

DECISION MEMO FOR CATEGORICAL EXCLUSION HOLY JIM CREEK CROSSING REPLACEMENT

E. Other Federal Requirements and CEQA Considerations

Notice of Preparation of Environmental Impact Report

Public Notice. Public Notice No. Date: April 8, 2016 CENAP-PL-E Comment Period Closes: May 9, 2016

SECTION 4.0 ALTERNATIVES

WATERSHED MANAGEMENT INITIATIVE: GOALS & IMPLEMENTATION OBJECTIVES, JULY 26, 1999

Accelerating Restoration Projects on Private Lands with the Partners in Restoration (PIR) Permit Coordination Program. Analysis Draft Recommendations

Stream Crossing Reconstruction on the Bog Dam Loop Road (FR15) Scoping Notice. Androscoggin Ranger District

There is a reliable, clean water supply for current and future generations.

PROJECT HIGHLIGHTS,

Responses to Comments from State Agencies

Wapato Access Feasibility Study

Case Studies III: Skokomish River Ecosystem Restoration Washington State

3F. Hydrology and Water Quality

Wood Canyon Emergent Wetland Project. City of Aliso Viejo 12 Journey, Suite 100 Aliso Viejo, CA 92656

Temporary Stream Crossing

Temporary Stream Crossing

Draft Environmental Impact Report

CATEGORY a protection of the natural environment, its ecosystems and biodiversity.

Logan River at Rendezvous Park, Channel and Floodplain Restoration: Crack Willow (Salix fragilis) Issues and Management Strategies

Upper Santa Clara River Watershed Arundo/ Tamarisk Removal Program (SCARP)

APPENDIX N Guidance for Preparing/Reviewing CEQA Initial Studies and Environmental Impact Reports

Programmatic Environmental Compliance and Permitting for Invasive Weed Control and Habitat Restoration Projects. Presented by: Ron Unger

Appendix D - Evaluation of Interim Solutions

RECORD OF DECISION I. INTRODUCTION

David Brockbank, Senior Planner Contra Costa County Department of Conservation and Development 30 Muir Road Martinez, CA, 94553

Removal of the Last Fish Barrier on the Lower Rogue River Shane K. Cline, PE HDR Inc, Portland, OR

1. Red Clover Poco Restoration Project Environmental Permitting

The F.O.R.C.E. The Future Of Redwood Creek Environment

Santa Clara Valley Habitat Plan Regional General Permit #18. Training and Workshop for Co-Permittees April 5, 2016

Chehalis Basin Strategy Programmatic SEPA Draft EIS

LAKE COUNTY STORMWATER MANAGEMENT COMMISSION GENERAL PERMIT NUMBER 3 AUTHORIZING MINOR MAINTENANCE DREDGING ACTIVITIES

Southern California River and Stream Habitats

Public Notice. CENAB-OPR-P P24 (Lime Spring Run)

Local Flood Hazard Mitigation Program. A framework for hazard mitigation in the NYC West of Hudson Water Supply Watersheds

Department of the Army Permit Application

Mixed Conifer Working Group Meeting April 15, 2011 Water and Soil Resource Management Considerations

PUBLIC NOTICE Application for Permit

Public Information Centre September 19 th, 2017

Calleguas Creek Watershed Wetland Restoration Plan. David L. Magney. David Magney Environmental Consulting

LEGAL AUTHORITY AND JURISDICTIONS

Klamath River Renewal Project Dam Removal RFQ Informational Meeting August 29, 2018 Klamath Falls, OR

National Marine Fisheries Service ESA/MSA Restoration Project Consultations. Oregon State Habitat Office Oregon Coast Branch Roseburg, Oregon

Conceptual Design and Feasibility of a Natural Fishway at the Fremont BART Weir, Alameda Creek, California

RE: Recommendations for Staged Implementation of Alternative 3a

PRESENTERS. Contact Information: RW Armstrong Union Station, 300 S. Meridian St. Indianapolis, IN

MANZANITA LAKE PLANNING UNIT Willow Creek Watershed

CHAPTER 7. San Dieguito River Flooding Adaptation

Flooding from Butano Creek on Pescadero Road

Public Notice of Application for Permit

Nationwide Permit General Conditions

Terry Benoit 4/1/2009

The Nature Conservancy Cosumnes River Preserve Franklin Boulevard Galt CA 95632

5.2 BIOLOGICAL RESOURCES AND WETLANDS

PUBLIC NOTICE. Section 404 of the Clean Water Act (33 U.S.C. 1344) Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C.

INTRODUCTION AND BACKGROUND

Agency Organization Organization Address Information. Name United States Department of Agriculture

Moonlight Aquatic Organism Passage Project

U.S. ARMY CORPS OF ENGINEERS BUILDING STRONG LOS ANGELES DISTRICT

Projects must fall under one of the nine categories listed in Table 1.

SHORELINE INVENTORY AND RESTORATION PLANNING

Pacheco Reservoir Expansion

Nationwide Permit General Conditions

Appendix Q Conceptual Mitigation Plan for Impacts to Wetlands and Other Waters of the United States

FLOODPLAIN PERMIT APPLICATION SUBMITTAL REQUIREMENTS

CIP-01: Stream Channel Stabilization, Silver Creek

Folsom Dam Water Control Manual Update

STAFF UPDATES FLOOD ZONE 9 ADVISORY BOARD MEETING

COASTAL CONSERVANCY. Staff Recommendation September 22, 2011 GREEN VALLEY CREEK COHO HABITAT ENHANCEMENT DESIGN

Public Notice. Applicant: City of Dallas Project No.: SWF Date: April 18, Name: Chandler Peter Phone Number:

NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT

Proposal for Plumas Watershed Forum. 1. Project Name: Feather River Irrigated Lands Water Quality Improvement Program.

Response: Eastern Shore will require additional permanent easement and temporary workspace (TWS) in the following municipalities:

3.0 CUMULATIVE PROJECTS SCENARIO

Funding And Monitoring. Cobbling it together Focus on watersheds and streams in North Bay

Portland District Regulatory Branch Permit Streamlining for Restoration Projects

DEPARTMENT OF THE ARMY U.S. ARMY CORPS OF ENGINEERS, SACRAMENTO DISTRICT 1325 J STREET SACRAMENTO CA PUBLIC NOTICE

~ate: d~o/~o/h. h ~~~ Date:,;z//o/a?0/6. Managing Water in the West. Upper Sacramento River Anadromous Fish Habitat Restoration Project

Public Notice: Application for Permit

Parks and Open Space 5201 St. Vrain Road Longmont, Colorado Fax:

Prioritizing Local Action. Strengthening the Resilience of the Taunton River Watershed

Boardman River Dams Committee (BRDC) Detailed Analysis of Alternatives

WHETSTONE RIVER RESTORATION PROJECT - ADDENDUM

Notice of Preparation

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR

California WaterFix (Alternative 4A)/Recirculated Environmental Analysis Frequently Asked Questions

Site 18A Culvert Replacement and Fish Passage Enhancement Project

Assessing Habitat in Watersheds. Sabrina Drill UC Cooperative Extension Los Angeles and Ventura

The Los Vaqueros Reservoir Expansion Project

' MY () Interim Risk Reduction Measures Grubbing in Cleared Areas Chena River Lakes Project Fairbanks, Alaska

RINCONADA WATER TREATMENT PLANT RELIABILITY IMPROVEMENT PROJECT Second Addendum to the Final Environmental Impact Report

BAYFRONT CANAL AND ATHERTON CHANNEL PROJECT DESCRIPTION

ESTIMATE OF QUANTITIES

U.S. ARMY CORPS OF ENGINEERS BUILDING STRONG LOS ANGELES DISTRICT

Subject: Notice of Preparation of a Draft Environmental Impact Report

Transcription:

Carmel River Reroute & San Clemente Dam Removal Project (PLN110373) Monterey County Planning Commission Workshop July 25, 2012

URS1 Workshop Agenda 1. Background 2. Project Overview 3. Tree Removals/Mitigation 4. Grading on 25% Slopes 5. Construction Access 6. Parking for Construction Workers 7. Sensitive Habitat 8. Recommendation 9. Applicant s Comments 10. Questions of Staff and Applicant 11. Public Comments 12. Planning Commission Comments Slide 2 of 30

Slide 2 URS1 once it is decided, adding the presenter's name would be good and indicate a relative time split for presentation and Q&A URS, 07/17/2012

Background Slide 3 of 30

Background Vicinity Map Slide 4 of 30

Background Site Conditions 1. SC Dam built in 1921 a. 106 feet tall concrete arch dam b. 18.5 miles from Pacific c. Confluence with San Clemente Creek upstream of dam d. Reservoir storage of approximately 1,425 acre-feet 2. Under current conditions a. Reservoir filled with approx. 2.5 million CY of sediment b. Capacity reduced to approx. 70 acre-feet Slide 5 of 30

San Clemente Dam Under Construction

San Clemente Dam - Today

Background Milestone Summary 1. DWR issued a dam safety order in early 1990s 2. DWR released DEIS/R in 2006 3. Final EIR/S certified in 2007 4. Design & permitting is moving forward with cooperative agreement between California American Water (CAW), State Coastal Conservancy (SCC) and National Marine Fisheries Service (NMFS) 5. SCC and NMFS will secure up to $35 million in additional funding 6. Joint Planning Commission/CVLUAC Site Visit - May 23, 2012 7. CVLUAC recommended approval - July 2, 2012 Slide 8 of 30

Project Overview Slide 9 of 30

1. Primary Goals Project Overview Goals & Objectives a. Provide a long-term solution to dam safety issue b. Improve fish passage conditions and provide rearing habitat c. Diminish potential for excessive erosion, undermining, or slope failure, leading to sediment mobilization d. Avoid exacerbating downstream flooding 2. Secondary Goals a. Restore natural character and function of valley bottom b. Shape project components to be as natural as feasible c. Provide long-term sustainable habitat d. Promote more natural sediment transport regime Slide 10 of 30

Project Overview Existing Conditions Slide 11 of 30

Project Overview Proposed Features Upper Carmel River Reach Upper San Clemente Creek Reroute Channel Access Road Design Diversion Dike Combined Flow Reach Sediment Stockpile Area Stabilized Sediment Slope & East Tributary Dam Removal Old Carmel River Dam Removal Slide 12 of 30

Project Overview Pre- and Post- Comparison Proposed Conditions Existing Conditions Slide 13 of 30

URS2 Project Overview OCRD Removal Slide 14 of 30

Slide 14 URS2 URS, 07/17/2012

Tree Removal/Mitigation Slide 15 of 30

Tree Survey Fall 11 Survey 2,490 trees Oak, fir, bay, cottonwood box elder willow sycamore madrone San Clemente Creek Oaks> 6 in Staging Areas Access Road Slide 16 of 30

Tree Removal Design Modifications Avoid: 893 perimeter & 251 access road trees Slide 17 of 30

Tree Mitigation Revegetation Plan Local, native species >14,000 trees >10K riparian Oak mitigation Plant 1,514 coast live oak 3:1 for < 24 diam @ 2 ft 10:1 for > 24 diam Big Sur Land Trust Accumulating funds for Monterey Co. Oak Woodland Conservation Fund (conservation easement) Slide 18 of 30

Existing Site Slopes 25% Slope Map Slide 19 of 22

Construction Access Slide 20 of 30

Construction Access Proposed Access Route Map Slide 21 of 30

Construction Access Jeep Trail/Reservoir Access Road Slide 22 of 30

Construction Access Access Route Alternatives Summary 1. Three initial options: a. San Clemente Drive to the Low Road (Low Road option) NOT FEASIBLE b. San Clemente Drive to the High Road (High Road option) c. Cachagua Road to the Jeep Trail (Jeep Trail option) 2. Alternative Analysis Summary - Compared to the Jeep Trail Option, the High Road option results in approximately: a. 2,800 linear feet of additional road improvement, b. 300 linear feet of additional new road construction, and c. 3 additional new or replacement bridges d. 50% increase in the number of trees impacted e. 4.5 additional acres of new road construction disturbance area 3. Jeep Trail Option selected for Project Slide 23 of 30

Access Route Option Summary

Parking for Construction Workers Access road improvements begin - fall 2012. On-site parking at dam limited to 12 spaces. During initial phase, use existing park and ride lots at: 1) Laureles Grade/Highway 68 (19 spaces); and 2) the Crossroads Shopping Center (33 spaces). Once work starts on dam removal, new temporary park and ride lots will be constructed in Carmel Valley for 80 workers.

Landscape Restoration Plan Riparian: 19.8 acres of riparian vegetation will be planted along reconstructed river. Wetland: 3 acres of wetlands will be restored to achieve a no net loss of wetland and provide habitat for California Red Legged Frog. Upland: Oak woodlands, chaparral and scrub are proposed for upland restoration in appropriate locations.

Sensitive Habitat Mitigation Existing & Proposed Habitat Existing Proposed Slide 28 of 30

Recommendation Staff recommends that the Planning Commission conduct a workshop. Issues the Commission may want to discuss include: Are the proposed tree removals the minimum necessary to implement the project? Is the proposed primary construction access route (i.e., Tassajara Road through Cachagua Road and the Jeep Trail from the southeast) the preferred route? Are there any alternatives that could lessen the construction period impacts, particularly in regard to the road improvements proposed on the construction access routes along Cachagua Road and the Jeep Trail?

Questions? Visit us at: www.sanclementedamremoval.org Slide 30 of 30

Pocket Slides Slide 31 of 22

Project Overview Watershed & River Context 1. Watershed Trends: a. Ecological restoration of Carmel River and streams b. Emphasis on steelhead passage and population 2. Ongoing Projects: a. Carmel River Reroute & San Clemente Dam Removal (CAW) b. Los Padres Dam Downstream Fish Passage Facility (CAW) c. Sleepy Hollow Bridge (MPWMD) d. Lower Carmel River Floodplain Restoration and Enhancement (Big Sur Land Trust) e. Carmel River Lagoon Ecosystem Protection Barrier (Monterey County) Slide 32 of 30

Project Overview Timeline June 2012: RFP out to shortlisted D-B Teams September 2012: D-B Proposals due Begin Access Road Construction December 2012: D-B Team selection March 2013: Execute D-B Agreement D-B begins Diversion Design May 2013: D-B begins Diversion Construction, Geotechnical Investigations, and Site Design 2013 to 2015: Majority of Site Construction 2015 to 2020: D-B Post Construction Phase Slide 33 of 30

Construction Access Access Route Traffic Use 1. Cachagua Road/Jeep Trail a. Buses from Park and Ride (Location TBD) for most workers b. Some personal vehicles c. Construction material in single unit haulers 2. Tassajara Road/Cachagua Road/Jeep Trail a. Construction equipment mobilization b. Any construction material that would not be able negotiate Cachagua Road 3. San Clemente Drive a. Limited personal vehicles b. Limited trucks (1 to 2 ton) Slide 34 of 30

Project Overview CEQA & Permitting Overview CEQA / NEPA (Final EIS/R 2007) SEIR DWR SEIR (OCRD) State Coastal Conservancy Monterey County Combined Development Permit Grading permit Encroachment permit CWA 404 permit USACE ESA 7 Biological Opinions NMFS & FWS NHPA 106 Concurrence SHPO CWA 401 Water Quality Certification RWQCB CWA 404(b)(1) Alternatives Analysis EPA CF&G Code 1600 Lake & Streambed Alteration Agreement CESA 2081 incidental take permit CDFG NPDES SWPPP approval RWQCB Slide 35 of 30

Construction Access Equipment Mobilization Traffic Estimate 1. Heavy Equipment Mobilization a. Extended flatbed to bring in large equipment or crane; Mobile material processing plant. b. Route: Tassajara Road to Cachagua Road to Jeep Trail ONLY 2. Equipment Mobilization Estimates: a. Typically would involve 0-5 round trips per month b. Monthly round trip peaks as follows: i. 1st year of site construction 25 at start of season, 20 at end of season ii. 2nd year of site construction 40 at start of season, 45 at end of season iii. 3rd year of site construction 30 at start of season, 15 at end of season Slide 36 of 30

Construction Access Traffic Safety 1. Traffic Control Plan by Contractor; Approved by County 2. Coordinate with Cachagua Fire District a. 24-hour contact name and number b. Copy of approved Traffic Control Plan c. Updates to traffic estimates (monthly breakdown) 3. Pilot Cars will be required for a. Construction equipment mobilization b. Construction material hauling 4. Flagman required public road construction 5. Signage 6. Adherence to speed limits on all public roads will be emphasized 7. Material hauling will be restricted to: a. 9 am to 3 pm Monday through Friday b. No hauling when school buses are scheduled to run Slide 37 of 30

Construction Access Traffic Daily Average Trips Slide 38 of 30

Construction Access Material Hauling 1. Construction Materials Imported to Site a. Pipe, valves, etc. for diversion b. Aggregate base for access roads c. Imported aggregates for filter materials d. Cement for soil improvement using deep soil mixing (DSM) 2. Construction Materials Removed from Site a. Demolition debris (metal, wood, sheetrock, pipe, etc.); concrete will be buried on site Slide 39 of 30