Procurement driving better value for money. Guide 3 to Sustainable Procurement. Evaluate and Select Suppliers

Similar documents
Procurement driving better value for money. Guide 6 to Sustainable Procurement. Audit and Improve Supplier

NEW ZEALAND GOVERNMENT PROCUREMENT. New Zealand Government Procurement Business Survey 2016

Constructive Market Engagement

New Zealand Government Procurement Business Survey 2015

Planning Construction Procurement. A guide to health and safety and employment standards at work

NEW ZEALAND GOVERNMENT PROCUREMENT. New Zealand Government Procurement Business Survey A companion report for community service providers

Guidance Document. Guidance on compliance of ISPM 15 marks. 16 May A guidance document issued by the Ministry for Primary Industries

Guidance Note. Effective Consultation for Impact Analysis

NEW ZEALAND GOVERNMENT PROCUREMENT. New Zealand Government Procurement Business Survey 2018

Sustainable Procurement Case Study Natural History Museum

Guidance Document. RMP Template for Farm Dairies Export Eligible Milk. 11 December 2015

MG ALBA PROCUREMENT POLICY AND SCHEME OF TENDERING

Procurement Policy & Procedures

European Maritime and Fisheries Fund Competitive Tendering and Public Procurement. Technical Guidance Notes

2.0 Management of the Commission s Environmental Responsibilities

2017 Four Year Plan Guide

Audit quality. a director s guide. November This handbook offers guidance for. entities about how to improve audit quality

Contract Management arrangements - Procurement Policy update

Audit quality a director s guide

Guidance Document. Guidance for Farm Dairies RMP Template - Domestic Supply. A guidance document issued by the Ministry for Primary Industries

Better Business Cases. Guide to Developing the Strategic Assessment

Procurement Policy. Purchasing guidelines

PROCUREMENT POLICY. Director of Finance Head of Financial Services. The Intranet version of this document is the only version that is maintained.

Environmental & Sustainability Policy

Corporate Procurement Policy

Guidance Document. Guidance for Risk Management Programme (RMP) Template for Dairy Processors. Liquid Milk, Domestic Supply.

Guidance to support delivery of the Living Wage Commitment to Care at Home and Housing Support

PROCUREMENT PROCEDURES

GLASGOW WEST HOUSING ASSOCIATION PROCUREMENT STRATEGY

Procurement strategy and action plan. Published date: 01 May 2018 Next review date: 01 May 2019

Large Goods Vehicle (LGV) Driver Trailblazer Apprenticeship Approach to Assessment

This additional work is carried out by internal auditors, who may be company

Statement of business ethics. (A statement of ethical relationships between the private sector and Council) D10/62448

An Introduction to Milton Keynes Council Procurement

ESOS: The concise guide to achieving compliance. savills.co.uk/energy

Performance audit report. Waste management planning by territorial authorities

Guidance Document. Guidance for Risk Management Programme (RMP) Template for Dairy Processors - Yoghurt Domestic Supply

Effective Date: January, 2007 Last Reviewed Date: September, 2016 Last Revised Date: October, 2016 Next Review Date: April 2018

Sustainable Procurement Policy

Guidance Document. Guidance for Risk Management Programme (RMP) Template for Dairy Processors - Cheese Domestic Supply

Asset Delivery Working together to bring Highways England closer to our customers. Pic to be the same as used on PowerPoint presentations

HOW TO DO BUSINESS WITH BANGOR UNIVERSITY A GUIDE FOR SUPPLIERS

JOB DESCRIPTION SALARY: 36,004

239 Purchasing V4 Current

Commitment to suppliers

Promoting Competition

Procurement Strategy and Action Plan. Financial Year

This document briefly describes when and how a project should undertake the tendering process when making a significant purchase.

Irish PSO Bus Tendering

A simple Procurement Process Flow diagram is shown in Appendix 1 and should be considered when carrying out spend.

ISLE OF MAN GOVERNMENT PROCUREMENT POLICY GD 2017/0026

Procurement Policy. Education is for improving lives and for leaving your community and world better than you found it.

A quick guide to. school food procurement

Sample Social Clauses to Encourage Community Benefits from Waste

Procurement manual for activities funded through the National Land Transport Programme

that these standards can only be delivered effectively by devolution of responsibility to the frontline;

Environmental Sustainability Policy

Guidance Document. Animal Products that have Undergone Third Country Processing THIRDCOP.GEN. [Document Date]

UNIVERSITY PROCUREMENT STRATEGY

Planning Construction Procurement. A guide to developing your procurement strategy

Assurance Review Process - Lessons Learned

PROCUREMENT POLICY. Revision Revision Date Owner Reference Comment 00 September 2011

Procurement & Probity Policy (v3.0)

PROCUREMENT AND TENDERING PROCEDURES POLICY 2018

Sustainability Social,Economic and Environmental Responsibility Policy

Best Practices in Public Procurement

Procurement Strategy

Hastings Academies Trust Standard Procurement Procedures

- Details of the item to be procured and whether it is for works, services or goods;

Competitive Tendering & Procurement Policy

WADEBRIDGE SCHOOL PROCUREMENT POLICY

Procurement Policy. November Also available in large print (16pt) and electronic format. Ask Student Services for details.

POSITION DESCRIPTION TEAM LEADER, COMMUNICATIONS, ENGAGEMENT AND COMMUNITY RELATIONS

GREATER SHEPPARTON CITY COUNCIL and GOULBURN VALLEY REGIONAL COLLABORATIVE ALLIANCE

Role of contracts & procurement

Global Procurement: Our Sustainability Policy

Higher Education Procurement Association. Procurement Benefits Reporting Guidance 2016/17 Onwards

Roundtable on. Competition Policy and Public Procurement

Annual Procurement Report 2016/17

Compliance assurance programmes

Assessment Plan Event Assistant

DOING BUSINESS WITH NHS EDUCATION FOR SCOTLAND

GLOSSARY C O N T E N T S PAGE. Group Procurement Strategy

Commissioning Principles and Process Framework

PLEASURES AND PI OF PROCUREMENT

EUROPEAN PARLIAMENT AND COUNCIL

BY LAW 9 CONCERNING PROCUREMENT, SERVICE AND CONSTRUCTION WORK CONTRACTS

MOHAWK VALLEY WATER AUTHORITY PROCUREMENT POLICIES AND PROCEDURES

Towards a more efficient European Procurement Market Response to European Commission Green Paper COM(2011) 15

Integrated information and records systems, processes and practices

Contents Contact details

MSP 50 CONTROL OF CONTRACTORS

Please read this guidance carefully and consider its definitions within the context of your own research proposal.

Experimental monthly filled-job series

Health Procurement Guideline

QUALIFICATIONS WALES STRATEGY 2018 to 2022

Executive Summary. Enhancing support to SMEs - Through better understanding of dual-use aspects of the EDTIB supply chain

Job Description. Compliance Officer Gas and Electrical Grade: Grade 9. Responsible for: None. The Job. Is to:

SUSTAINABLE PROCUREMENT POLICY

UCS PRE-AWARD PROCESS PROJECT DEVELOPMENT CHECKLIST

Transcription:

Procurement driving better value for money Guide 3 to Sustainable Procurement Evaluate and Select Suppliers A guide for agencies July 2010

This guide is part of a series of documents focussed on Integrating Sustainable Procurement into Practice. This material was developed by Sustainable Procurement Limited for the United Nations Marrakech Taskforce for Sustainable Procurement of which the New Zealand government is a member. The series is based around a typical procurement process with a guide for each relevant stage as identified below: Identify need & assess risk Guide 2 Manage the contract & disposal route Guide 7 Audit & improve supplier Guide 6 Identifying sustainable procurement priorities Guide 1 Start Evaluate bids from suppliers & award Guide 5 Evaluate & select suppliers Guide 3 Define the specification & invite bids Guide 4 Please see the separate guidance notes referenced for other stages of the procurement process. First Published July 2010 Government Procurement Development Group Ministry of Economic Development PO Box 1473 Wellington New Zealand http://www.med.govt.nz http://www.procurement.govt.nz Crown Copyright This work is licensed under the Creative Commons Attribution-Noncommercial-Share Alike 3.0 New Zealand License. In essence you are free to copy, distribute and adapt the work noncommercially, as long as you attribute the work to the Crown and abide by the other licence terms. To view a copy of this license, visit http://www.creativecommons.org.nz Please note that no departmental or governmental emblem, logo or Coat of Arms may be used in any way that infringes any provision of the Flags, Emblems, and Names Protection Act 1981. Attribution to the Crown should be in written form and not by reproduction of any such emblem, logo or Coat of Arms.

3 Contents page Background... 4 Introduction... 4 Using risk assessment to inform supplier evaluation and selection... 5 Difference between bid evaluation and supplier selection criteria... 5 Identifying potential areas for supplier evaluation... 5 Use of questionnaires/dialogue... 7 Identifying the key supplier selection criteria... 8 Determine the weighting for sustainability issues... 8 Finalising the supplier selection criteria... 8 Scoring sustainability criteria and determining the suppliers to bid... 8 Summary... 9

4 To what extent does your agency evaluate suppliers about sustainable procurement? Background This guidance document details the key issues involved in evaluating suppliers. In particular, it explains the logic and method of applying sustainability criteria in supplier evaluation. Specifically, it gives guidance concerning how suppliers of different contract categories could be examined, based on their overall sustainability risk profile as follows: Critical contracts - High Value and High Sustainability Risk Secure contracts - Low Value, but High Sustainability Risk Drive contracts - High Value, but Low Sustainability Risk Routine contracts - Low Value and Low Sustainability Risk Whilst referencing inter-linked procurement stages, this guide focuses on developing supplier evaluation criteria to manage sustainability impacts. This is informed by a sustainability risk assessment once the contract need is identified. See Guide 2 Identify Need and Assess Risk. Sustainability risks that are best managed by supplier selection need to be turned into questions and criteria for suppliers to answer. This guide highlights the key issues that need to be considered. Why is this important? Suppliers have to be selected to bid for contracts, the method of this selection needs to be logical and structured to avoid any criticism or implication of impropriety. When practicing sustainable procurement, certain sustainability risks could be managed by the selection of supplier, for example for timber only choosing a supplier who meets a particular sustainable forestry management standard. Alternatively, procurers may choose to invite many suppliers to bid for a contract and put the emphasis on the specification and bid evaluation. There is no right or wrong answer as to which stage of the procurement process these issues are managed. However, if suppliers are being evaluated to determine a bid list then there must be a logical method to determine the selection and this guide illustrates some of the issues involved. How to use this guide The guide is structured by subject, so it can either be read fully in order to obtain a complete overview of the issues in supplier evaluation and selection or the reader can jump to a specific subject area. However, the guide does follow a logical order so it is recommended to start at the beginning and work through to avoid any confusion. Introduction A key procurement decision is the selection of suppliers. Selecting the right suppliers to bid for a contract is a critical stage in the procurement process. Often it is the suppliers who will control and manage the key sustainability impacts in goods (products) or services bought, either directly in their own business activities or through their suppliers along the supply chain. At this stage, procurers are usually evaluating a range of suppliers to determine which have the highest likelihood of meeting their needs. These suppliers are then invited to bid for the contract. This guidance note, highlights the key issues involved in evaluating and selecting suppliers.

5 Using risk assessment to inform supplier evaluation and selection Guide 1 Identifying Sustainable Procurement Priorities details the use of risk assessment to identify and prioritise sustainability impacts and Guide 2 Identify Need and Assess Risk covers in detail the risk assessment process recommended for contracts. It is important that you understand these principles before reviewing the supplier evaluation guidance note further. Difference between bid evaluation and supplier selection criteria The bid evaluation process is distinct and separate from the supplier selection process. The bid evaluation is usually always made on the basis of best Value for Money, this is defined differently by different agencies. The bid evaluation process must provide a fair, transparent and accountable method for evaluating supplier bids on the basis of balancing sustainability and other non-financial factors with cost. This is best applied and demonstrated by the use of a properly constructed bid evaluation model. The bid evaluation process looks forward at the proposals for the specific contract, whereas the supplier selection process looks back at the status and previous performance of the suppliers. Whilst the two processes may cover similar topics, supplier selection and bid evaluation are two quite separate issues. Procurers need to ensure that there is a logical link between supplier selection criteria and bid evaluation criteria. Procurers must not ask the same questions in both stages and the timing of questions needs careful consideration. The supplier evaluation criteria should be considered before making any contact with suppliers about the particular contract. The best time to consider supplier evaluation criteria is during the initial contract risk assessment and to finalise it once the risk assessment is complete. Thereby ensuring that supplier evaluation criteria are founded in risk assessment and are able to be answered by information asked for in any supplier qualification process. Identifying potential areas for supplier evaluation The areas for supplier evaluation are a function of the sustainability risks identified in the contract. When a contract is first being planned risks should be identified and documented. See Guide 2 Identify Need and Assess Risk. Example risks may include: High CO2 emissions due to poor energy efficiency/ travel management Supplier sub-contracts the work to an organisation with poor sustainability credentials Suppliers staff are not properly trained in the sustainability issues associated with this contract Unsustainable materials in the product Employees exploited by supplier Reputation damage to the agency through poor sustainability practices by supplier etc The risks identified then need to be managed. There are five options available: Option 1: Option 2: Option 3: Option 4: Option 5: The risk cannot be managed and is therefore not addressed (these risks need to be closely monitored) The risk is managed by the choice of supplier The risk can be addressed in the specification The supplier needs to provide proposals on their approach, the procurer will then evaluate this in bid evaluation The risk is managed either by targets to be delivered once the contract has been awarded or generally as part of contract management activity Each contract will typically employ a range of these management options. For risks that can only be managed by option 2, (choosing the most sustainable supplier) a supplier selection process

6 will need to be used. The categories used in supplier selection should relate directly back to the risk assessment undertaken at the start of the contract. As highlighted in Guide 4 Define Specification and Invite Bids, sustainability criteria can be applied at all stages of the procurement process. As an example, see below sustainability criteria to manage carbon-dioxide/particulate emissions from travel in a computer services contract. Pay particular attention to the way the criteria become more specific and more dificult between supplier selection and specification. Also note that the bid evaluation criteria highlighted have a direct link to clauses/questions in the specification. Similarly, contract management criteria also link back to both specification and bid evaluation criteria and provide the method by which compliance is monitored and continuous improvement encouraged. Procurers need to think very carefully about the appropriate stage for managing the risks as there are numerous options. Table 1 - Example of possible sustainability criteria to manage Carbon-dioxide/ particulate emissions from travel associated with providing an IT Service Procurement Stage Possible Sustainability Criteria/ Actions Supplier Selection Ensure service provider has a sustainable travel Policy and has experience of sustainable travel planning & control Specification Bid Evaluation Contract management Set a target number of miles to be travelled to support this contract with yr on yr reduction targets, say 4,000 (if it is not feasible supplier will voice concerns in their proposals, negotiate total figure) Supplier to produce a sustainable travel plan to minimise miles travelled by car and plane (should reflect principles below) and reduce carbon emissions from its vehicles Require use of telephone conferencing/ VC conferencing wherever possible, all journeys must have a justification and be reported quarterly for review etc Require train/ public transport where feasible, ask supplier how they will incentivise this with their employees Ban use of domestic flights for journeys that can be undertaken in less than 5 hours by train Proposals to reduce car/plane travel Any proposals to carbon off set travel, by whom and to what level Does the supplier meet the minimum requirements in the specification? Robustness of sustainable travel plan Incentives for low emission vehicles either as lease cars or through mileage rates or other staff incentivisation Targets to reduce car/plane mileage beyond those in the specification % target for carbon off set, value of fund, robustness of carbon off set fund/ mechanism proposed. 100% gets a maximum score. Reduction in miles travelled to deliver and support the contract Reduction in carbon emissions from transport Continuous improvement against the sustainable travel plan, with financial incentives for the supplier % carbon off set against miles travelled against the target agreed Financial penalties for non-essential/ unjustified journeys when phone conferencing/ video conferencing could have been used So by using the risks identified and identifying those that are best managed through the supplier selection process procurers can begin to build a set of supplier selection questions that can be asked of the supplier. It is important that these questions are founded in the risk assessment

7 process and kept as few and simple as possible. Do not ask questions just for the sake of it or as an endurance test for the supplier. Use of questionnaires/dialogue Many agencies use standard questionnaires to assess suppliers capabilities. Standard questionnaires can be useful, but should only be used where necessary and should be adapted to each contracts need. It is very frustrating for suppliers who have to complete numerous questionnaires if the information provided is not actually used by the buyer. It can often be more productive to write a key set of specific contract questions, see table 2 below. Ideally, buyers should actually discuss the sustainability issues with the supplier either face to face or using telecommunications. A two-way discussion will give the buyer a far greater understanding of the organisations commitment to sustainability and will begin the process of relationship building between the two organisations. Table 2 Example supplier selection questions for computer equipment and service contract Sustainability Issue Organisational commitment to sustainability Sustainable Travel Management Minimised nonrenewable resource use/ wastes from spare parts/ consumables/ packaging Minimised use of any hazardous chemicals Subcontracted employees are not exploited Supplier must comply with sustainability legislation Use of eco-labelled equipment to Minimising consumption Supplier Evaluation question Please provide details (including and targets and achievements) of your organisations sustainability management policy, your organisations top 10 highest sustainability impacts, management system to control sustainability issues. e.g. Environmental Management System (EMS), ISO 14001, Social Accountability SA8000. Please provide relevant sections from your staff travel policy, showing how you minimise environmental impact of your travel. Detail current use of technology to minimise travel to customers e.g. use of Video Conferencing, phone conferencing etc Please provide your sustainable sourcing policy/strategy for hardware, spares and consumables, also include the current % of these items bought and any targets with current level of achievement. Detail your current approach to packaging reduction with any targets and current achievement levels Please detail your current procurement policy to minimise the use of any hazardous substances/ chemicals that may be bought in connection with this contract Please detail how you ensure that your sub-contractors (including those in the developing world) do not exploit their employees and how this is checked/ audited to ensure compliance. Also detail specifically your organisations policy in this regard. Please detail the key sustainability legislation that you believe applies to this contract (including your procurement connected with this contract) and how you will ensure that its requirements are met. Please detail your current approach to the procurement of Eco-labelled hardware/ consumables, also detail which eco-labels you will apply to the selection of specific hardware/ consumables for this contract. Please detail examples of successes in previous contracts where you have reduced consumption of hardware (optimised asset replacement strategy), consumables and spares. Detail previous position, target, approach and achievements. Produced courtesy of the Environment Agency for England and Wales.

8 Identifying the key supplier selection criteria When determining the supplier selection approach it suggested that procurers categorise criteria as follows: Mandatory - Preferred - Leading Mandatory selection criteria which a supplier must meet in order to be on the bid list. If the supplier cannot meet these, it does not necessarily stop them from bidding. However, these issues will inform the basis of the supplier selection criteria. Limit these to as few issues as possible. These issues will really differentiate suppliers and will separate the exceptional suppliers from the ordinary. These issues should have the highest weighting within the supplier selection process. Determine the weighting for sustainability issues The appropriate weighting to sustainability in relation to other criteria, must be established as soon as possible. The final time that this should be set is up to the time that supplier interest closes for the contract. No amendment should be made to the sustainability criteria, ratio, weightings or any part of the supplier evaluation approach once the date for supplier interest has passed. To do so may invite criticism from suppliers and may lead to accusations of in-proper procurement practice. If amendments do not stop after the selection date closes, then an unscrupulous procurer could change the weightings or criteria to favour a particular supplier regardless of how good the supplier actually is. As stated previously, the approach/ weighting used in supplier selection should relate directly to the risks that can only be managed by choosing suppliers that operate in a manner that best manages the issues identified. It is not possible to give precise guidelines for sustainability/ cost ratios/ weightings as contracts and organisations policies vary. Finalising the supplier selection criteria The extent and complexity of the supplier selection criteria selected should reflect the nature of the contract. Procurers should bear in mind that it is better to use fewer, key criteria, rather than a long list, each one of which will carry little individual weight when compared to the total score. In order to clarify suppliers ability to meet sustainability criteria, it can be useful to structure the issues into the form of a questionnaire, using questions drawn from the risk assessment. See table 2 previous. Suppliers should then be assessed on how well they answer the specific supplier selection question you have developed. It should be apparent from the risk assessment, that some sustainability criteria will be more important to a particular contract than others. Criteria that are more important should be given a higher weighting. Thereby increasing the score of more important issues and lessening the influence of lower priority issues. This is explained in more detail below. Scoring sustainability criteria and determining the suppliers to bid The scoring method aims to indicate how well each supplier meets each of the specific sustainability criteria. Care must be taken to differentiate between the sales pitch and the real achievements of suppliers. It is also essential to avoid personal preferences from exerting too strong an influence. Points are awarded to each supplier for each individual sustainability criteria, which are then weighted as appropriate. Weightings may need to be used to ensure high risk criteria are given more importance in the overall score.

9 The total marks available for the assessment are irrelevant, as a mathematically normalised (factored) score should be calculated. For example, if suppliers A, B and C were awarded total sustainability points of 150, 220, and 240 respectively, scores are as follows: Supplier C Highest Score (240) = 100 points Supplier A (150 x 100)/240 = 63 points Supplier B (220 x 100)/240 = 92 points Note: You should only assess a supplier on the information provided. Prior knowledge of the company and we know they have the capability to do this should not really be taken into account. To determine the suppliers who are appropriate to bid for this contract, procurers should select the appropriate number of suppliers in rank order based on the scores calculated. The number of suppliers or the score over which suppliers will be selected to bid, must be pre-determined so as to ensure there are no accusations of in-propriety. So for example, if the supplier selection score was set as a minimum of 70 points, only suppliers C and B would be invited to bid, supplier A would be discounted as they did not meet the minimum score. Summary The definition of supplier evaluation criteria must be founded in the risk assessment process. In essence identifying the sustainability risks that are best managed through the choice of supplier. Sustainability criteria can be applied at any stage of the procurement process from supplier selection, specification, bid evaluation to contract management. This guide primarily focuses on the approach necessary to fairly evaluate suppliers for inclusion on a bid list. Procurers need to consider the risk profile of the contract and set sustainability criteria appropriately. The position with regard to the acceptability of a cost premium to reduce sustainability impacts also needs to be determined. Weightings applied to specific sustainability criteria as well as to the suppliers overall sustainability need to be considered, along side weightings to other non-sustainability related criteria. Finally, consideration needs to be given as to whether there will be a minimum sustainability threshold overall, below which suppliers are rejected from bidding. Procurers must take into account the legal framework in which they operate and ensure that any sustainability criteria they apply can be justified from a legal perspective if challenged. Undertaking supplier evaluation varies from a very simple approach of a few key issues, to a much more detailed approach dealing with numerous non-cost factors. Having a structured and logical supplier evaluation process will ensure that all suppliers are treated fairly and that the most appropriate suppliers are selected. This will ensure that the appropriate level of sustainability is applied, that risks are managed and that the organisation is actually selecting suppliers based on sustainability and risk management principles. Effectively, practicing sustainable procurement.