A Primer Indianapolis, Indiana June 16, 2010

Similar documents
1/4/2014. Alternative Project Delivery Methods 1. Agenda

DEFINING THE SPECTRUM OF PROJECT DELIVERY OPTIONS AND THEIR IMPLICATIONS FOR YOUR PROJECT 2017 Airport Construction Strategy Summit

Time to Build! What to Expect On Your Upcoming Design and Construction Journey PRESENTED TO

Airport Owners Guide to Project Delivery Systems White Paper Update

LB 889 The Political Subdivisions Construction Alternatives Act

Jim Porter is the Director of Public Works for the County of San Mateo. The Department of Public Works has a staff of over 300 and performs a wide

Choosing a Project Delivery Method. A Design-Build Done Right Primer

Session THREE. Face 2 Face (4 hours) Stage 1 Initial actions & appraisals: Self-directed (6 hours)

Design-Build (DB) and Construction Manager / General Contractor (CMGC)

PROJECT DELIVERY METHODS

WATERTOWN ELEMENTARY SCHOOLS SCHOOL BUILDING COMMITTEE MEETING: OCTOBER 3, 2018

Progressive Design-Build Discussion

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing

Design Process 101. Michael Barnard, AIA, NCARB. animalsheltering.org/expo #AnimalCareExpo. Copyright

DESIGN CONSTRUCTION: PROJECT DELIVERY METHODS (SUPERPOWERS OPTIONAL!) FISHBECK, THOMPSON, CARR & HUBER engineers scientists architects constructors

Construction Project Delivery Methods Overview and Comparison. Operations Division

CMAA Owners Group Construction Delivery Methods

Partnering for Alternative Delivery Projects

Qualifications Based Selection of Contractors

1/12/2015. Collaborative IPD-ish Project Delivery using Design-Build, P3 or CM at-risk: the Einstein Approach

PROGRESSIVE DESIGN-BUILD. Praful M. Kulkarni, AIA Iraj Ghaemi, P.E. J. Brandon Dekker, M.S., DBIA

Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013

APPENDIX D Forms for the Analytical Delivery Decision Approach (Tier 1)

Procurement Documents for Progressive Design-Build Projects

Report on Effectiveness of the Construction Manager at Risk Project Delivery Method

APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1)

ALTERNATE FORMS OF PROJECT DELIVERY

CMAA has met the standards and requirements of the Registered Continuing Education Program. Credit earned on completion of this program will be

Construction Project Delivery Methods

Pioneering Alternative Project Delivery in Ohio

Construction Manager as Constructor (CMc) Manual

Presented By: Jeffrey T. Folden, P.E. Chief, Innovative Contracting Division

ConsensusDocs. Catalog. Updated Docs Inside

Progressive Design Build

Lease-Leaseback Project Delivery Method

Sounds good. What could possibly go wrong? 5/6/2014. Potential Benefits of Design Build. Potential Downsides of Design Build

Project Delivery Systems

AN OWNER S GUIDE TO PROJECT DELIVERY METHODS: CONSTRUCTION MANAGEMENT ASSOCIATION OF AMERICA

Risks Associated with Alternative Delivery Methods. Managing Expectations. Presented by Dan Becker, CCM, PMP, CCE

Project Delivery Selection Matrix If the Project Delivery Approach Fits, Use It

Facility Basics for Bond Project Communications

Construction Documents Education Program

ConsensusDocs. ConsensusDocs CONTRACTS CATALOG. Updated Docs Inside. ou Ah. ead o f the Cur v. e K

Fairfax County Government Construction Management At Risk (CMAR)

Stakeholders and project delivery methods

PROFESSIONAL PRACTICE 544

REQUEST FOR PROPOSALS FOR AN INTEGRATED PROJECT DELIVERY METHOD UTILIZING DESIGN/BUILD GUARANTEED MAXIMUM PRICE (GMP) SERVICES

Construction Manager at Risk Delivery Method

FACILITIES CONFERENCE

FACILITY PROJECT BIDDING OPTIONS OVERVIEW

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices

Design-Build Data Sourcebook

Professional Practice 544

ALTERNATIVE CONTRACTING METHODS

Professional Practice 544

Project Delivery Method

DESIGN-BID-BUILD CONSTRUCTION MANAGER AT RISK DESIGN-BUILD

School Construction: Contract Basics OSBA BONDS, BALLOTS AND BUILDINGS CONFERENCE FEBRUARY 09, 2018

Alternative Project Delivery Methods and Procurement

Different Ways to Contract for Lean Project Delivery. Joel Darrington San Diego COP 3/27/19

Alternate Project Delivery Experience at UOSA and PWCSA

A/E-LED INTEGRATED PROJECT DELIVERY

DTX Project Delivery Methodology and Options. January 9, 2014

Progressive Design-Build

UNIVERSITY OF CALIFORNIA, SAN DIEGO

SCADA System Procurement Alternatives

Alternative Delivery for Municipal Water & Wastewater Projects in 2012

The Owner s Role in Successful Design-Build Project Delivery

Alternative Delivery Methods in the Post-Davis World

EVOLUTION OF DESIGN BUILD IN THE W/WW INDUSTRY

ICOC Procurement Briefing

CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS

Design/Build Institute of America Rocky Mountain Region Water/Wastewater Committee. Project Delivery Selection Approach

Continuing Education Credits

ADDENDUM #2. Design/Build Contractor RFP Bid # for the. Joint-Use 21 st Century Post-Century Education Center.

REQUEST FOR QUALIFICATIONS AND PROPOSALS

INTEGRATED PROJECT DELIVERY IN PUBLIC PROJECTS: LIMITATIONS AND OPPORTUNITY

Finalize Implementation Plan Conduct Introductory Campus Meetings Kickoff Several Comprehensive Projects Secured Program Managers

PROVING OUR PROFESSIONALISM

TOWN OF WINTER PARK REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER / GENERAL CONTRACTOR

Welcome! Achieving Collaborative IPD-ish Delivery with basic D-B, P3 or CM contracts: Yes, there is a way

Successful Use of Progressive Design-Build in California Community Colleges

REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES. For the renovation of existing apartment buildings. August 15, 2016

Audio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program

Job Order Contracting (JOC) ITB JE Overview August 2016

Construction Family of Documents

Strategic Management and Project Selection

AN OVERVIEW OF DESIGN-BUILD. Presented by: David Umstot, PE, CEM Umstot Project and Facilities Solutions, LLC January 20, 2014

Legal Issues Related to Design Build

REQUEST FOR PROPOSALS. Construction Manager CM Services Pre-Construction and Construction Services

SIXTH ANNUAL AIRPORT PROJECT DELIVERY SUMMIT

A , Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

SEPARATED PROJECT DELIVERY SYSTEMS

General Session 2 Procurement Update. #AirportsTechnical

Procurement Guidelines

JOB ORDER CONTRACTING. United Brotherhood of Carpenters and Joiners Interior-Exterior Systems Leadership Conference

WhAt Are my OptIONs?

Integrated Project Delivery (IPD) Across the Spectrum of Delivery Systems Who Owns/Controls the Risk? An Owner s Perspective

Integrated Project Delivery

Transcription:

Alternative Project Delivery Methods A Primer Indianapolis, Indiana June 16, 2010 Michael Kenig, Holder Construction Company, Past chair of AGC of America s s Project Delivery Committee Jayne O Donnell, O General Manager, Turner s s Aviation Division

Overview of this Summit Definitions (Four Stops) Analysis of Options and Issues Identification of Best Practices Looking for Innovation

Industry Convergence Lean/ Economic Pressures You Are Here Building Information Modeling (BIM) Transparency in Public Bidding Labor, Tax and Funding Laws Project Delivery including IPD Threats and Risks Sustainability

Reference Materials Project Delivery Systems for Construction available though Associated General Contractors

Tailored (but dated) Reference Material Joint effort between ACI, ACC and AGC memberships Focused on airport owners Serves as an evolving, collaborative PDS guide Customizes key concepts in AGC PDS textbook

The Four Stops on the Road To Alternative Project Delivery 1. Ability to Use an Alternative Project Delivery 2. Definitions and establishing best options for your airport 3. Selecting best options for specific project needs and goals. 4. Implementing best practices and innovations to deliver the project. Baseline Metrics Lessons

Ability to Use Alternative Delivery Methods Airports have options: Design-Bid Bid-BuildBuild Construction Management at-risk Design /Build And although not yet implemented: FAA s s pilot program for PPP (private public partnerships)

Stop 2: Definitions Management Options Delivery Systems Procurement/Selection Contracting/Payment /Reimbursement

Defining Terms Management Options (in-house or out- sourced) Contracting/ Reimbursement (GMP, cost plus, lump sum, ) Delivery Methods (DBB, CMR, DB, Other) Procurement/Selection (low price/ best value / qualification based)

Defining Terms Management Options Delivery Methods Procurement/Selection Contracting/Payment /Reimbursement

Management Options 1. Use Owner s s Own Staff to manage the project 2. Hire Consultants to Assist in the management (Program Managers, Construction Managers or other staff augmentation)

Management Options vs Delivery Methods Owner & Owner Representatives Management Options: Who oversees the process Designer Builder Design- Bid -Build, Construction Management at-risk, Design/Build Delivery Methods: How design and construction is contracted by the Owner

Defining Terms Management Options Delivery Systems Procurement/ Selection Contracting/Payment /Reimbursement

Contracting/ Reimbursement Defined as: How the Owner wants to pay for the services provided (GMP, Cost plus, negotiated lump sum, lump sum)

Defining Terms Management Options Delivery Methods Procurement/Selection Contracting/Payment /Reimbursement

Phases of Project Development GOAL Traditional Linear Process Planning Design Bid Construction Occupancy Overlapping Phase Process Planning Design Construction Occupancy

Organizational Relationships Based on Delivery Methods How the owner and its consultants interact organizationally

Design-Bid Bid-BuildBuild Owner/ Owner Rep Two Separate Contracts for Design & Construction A / E Responsible for Design General Contractor Responsible for Construction Implementation

Construction Management at-risk Owner/ Owner Rep Two Separate Contracts for Design & Construction (CMR contracted to take cost and schedule risk) A / E Responsible for Design Construction Manager at Risk Responsible for Construction Implementation

Design/Build One Single Contract for Design & Construction Owner Bridging Consultant (optional) Design/Build Entity Responsible for Design and Construction Implementation

Optional Structures for Design/Build Entities Design/Build Entity Types Integrated Firm - All services in-house Contractor Led (design subcontracted) Joint Venture (architect-contractor j.v.) Architect Led (construction subcontracted)

What Characterizes Design-Bid-Build? Defining Characteristics - There are Separate Contracts for Design & Construction Contractor Selection is Based Entirely on Cost And Typically Design Documents are 100% complete

What Characterizes CM At-Risk? Defining Characteristics - There are separate contracts for design & construction Contractor selection is NOT based entirely on cost CMR contracts directly with trades and takes on performance risk (cost and schedule commitments) And Typically though not unique to CMR Schedule allows for overlapping design and construction Owner procures preconstruction services from the CMR Owner expects CMR to provide Guaranteed Maximum Price (GMP) and to commit to delivery schedule

What Characterizes Design/Build? Defining Characteristics - Single Point of Responsibility And Typically Schedule allows for overlapping design and construction Owner procures Preconstruction Services from the CMR Owner expects CMR to provide Guaranteed Maximum Price (GMP) and to commit to delivery schedule

Strengths of Each Delivery Type DBB -100% design complete CM at Risk bring builder in during design to improve design cost and accelerated schedule D/B single point of contact, fastest

Defining Terms Management Options Delivery Methods Procurement/ Selection Contracting/Payment /Reimbursement

Contracting Reimbursement What is The Project Cost? Cost of Construction + Contractor s s Fee & General Conditions + Contingencies /Allowances Total Construction Cost + Professional Services Fees + Design Contingencies + Permitting & Other Soft Costs +Owner Contingency Total Project Budget

Procurement /Selection Types 1. Low Bid Total Construction Cost, is the only selection criteria. (Total Construction weighted 100% ) 2A. Best Value Bid Total Construction Cost is a weighted selection criteria. (Total Construction Cost weighted between 0% & 100% ) 2B. Best Value Fees Fees and/or General Conditions are weighted; but Total Construction Cost is not a weighted selection criteria (Fees weighted between 0% & 100% ) 3. Qualifications Based Selection Price is not a selection criteria. (Price weighted 0% )

Typical Public Owner s Delivery Options SELECTION TYPES Price Definition Designer & Contractor 2 separate contracts Design- Builder 1 combined contract 1. Low Bid Total Construction Cost Professional Services Selected on Price Design/Builder Selected on Price 2A. 2B. Price and other Qualifications Total Construction Cost Fees, General Conditions, Contingencies Etc. Pre Qualified Bid Best Value Proposal Design/Build Pre-Qualified Bid Design/Build Best Value Proposal Qualifications ONLY 3. Based Selection None Professional Services based on Qualifications only Design-Build Services Based on Qualifications only

Examples of Airports Choices SELECTION TYPES Price Definition Designer & Contractor 2 separate contracts Design- Builder 1 combined contract 1. Low Bid Total Construction Cost John Wayne Airport, Washington Dulles - Contractor services Federal Contracts (FAA, DOT, COE)? 2A. 2B. Price and Other Qualifications Total Construction Cost Fees, General Conditions, Contingencies Etc. JetBlue Terminal 5, JFK Airport Most Common -PHX, SEA, FLL, Sacramento Airport* San Francisco Airport Qualifications ONLY 3. Based Selection None John Wayne Airport (PM/CM and A/E services) San Diego Airport

Delivery Methods Selection Options 1. Delivery Method / Selection Types Design-Bid-Build Low Bid Best Value Bid Best Value Fees Qualifications Based Selection (QBS) 2. CM at-risk (aka CM/GC) 3. Design-Build 4. Other

Another Way

Selection Process Summary SELECTION PROCESSES DELIVERY METHOD IFB 1 RFQ 2 RFP 3 Design-Bid-Build Design-Build, 1-Step Design-Build, 2-Step X X Const. Mgr @ Risk JOC, 1-Step JOC, 2-Step X X Notes: 1. Invitation for Bids, low bid process. 2. Request for Qualifications, a qualifications-based selection process with no element of price considered in the first step. 3. Request for Proposals, a process that combines qualifications, technical capabilities, and price in a Best Value process. X Engineering and Architectural Services Department 33 X X X

End of Definitions Next.. we continue to Stop 3 on the Road To Alternative Project Delivery 1. Ability to Use an Alternative Project Delivery 2. Definitions of the each of the Delivery Method Options 3. Selecting the appropriate Project Delivery Method 4. Implementing the chosen Project Delivery Method

Benefits and Results of Alternate Delivery Methods Airport Project Delivery Summit II Chicago, IL May 17, 2007 Wylie Bearup, City Engineer

APDM Project Summary Delivery Methods Total Projects Projects Awarded Projects Completed Contractors Selected Value ($M) Design-Build 29 28 8 23 $436.9 CM @ Risk 147 141 50 65 $2,484.6 Job Order Contracting 59 51 18 99 $212.4 235 220 76 187 $3,133.9 * Cumulative since passage of legislation in 2000 through December 2006 Engineering and Architectural Services Department 36

APDM Benefits Ability to pick Best Qualified contractor Better relationships among all project team members Contractor involvement throughout design phase: more control of budget through design phase true Value Engineering to ensure most costefficient systems enhanced project communications by selecting entire team early more time to plan construction activities better designs through constructability reviews Engineering and Architectural Services Department 37

APDM Benefits, con. Better quality from better subcontractors Smoother project close out Better contractor performance for repeat business Reduced completion time with fast tracking and long lead procurement Greater control of subcontractor selection Higher levels of M/W/SBE participation Ability to meet Green Building goals Engineering and Architectural Services Department 38

APDM Research Analyzed 59 completed projects: 33 DBB to serve as baseline 20 completed CM@R projects 6 completed DB projects Analysis compared results in 3 areas: Schedule Growth Cost Growth Delivery Speed Team perceptions: APDM projects on time, with better quality Engineering and Architectural Services Department 39

Schedule Growth 30.0% 25.0% 24.7% 20.0% 15.0% 10.0% 7.0% 5.0% 4.8% 0.0% Design-Bid-Build Design-Build CM@Risk Engineering and Architectural Services Department 40

Cost Growth 16.0% 15.2% 14.0% 12.0% 10.0% 8.0% 6.0% 4.7% 4.0% 2.0% 0.0% 0.7% Design-Bid-Build Design-Build CM@Risk Engineering and Architectural Services Department 41

Construction Speed 2,500 2,000 2,141 SF/month 1,500 1,000 925 1,450 500 0 Design-Bid-Build Design-Build CM@Risk Engineering and Architectural Services Department 42

Conclusion Process is working very well Methods have provided significant benefits to the City City continues to utilize all of the tools in our tool box Engineering and Architectural Services Department 43

6 th Annual FMI/CMAA Survey of Owners

6th Annual FMI/CMAA Survey of Owners

6th Annual FMI/CMAA Survey of Owners

How to Choose the Best Delivery Method Airport Project Delivery Summit II Chicago, IL May 16, 2007 Wylie Bearup, City Engineer, City of Phoenix

NUMERICAL ANALYSIS 1. Select and rank criteria. 2. Rate Delivery Methods ability to deliver criteria. 3. Apply ratings to ranked criteria. 4. Sum scores for each method. 5. Highest scored method selected. Engineering and Architectural Services Department 48

Developing Criteria CRITERIA Low initial design and construction costs High aesthetics of design High quality project Short project schedule High City control of design Low risks to City Non-adversarial relationships Effective coordination of design and construction Maximum flexibility to revise scope Low cost growth Engineering and Architectural Services Department 49

Ranking Criteria CRITERIA RANK Low initial design and construction costs 3.5 High aesthetics of design 10 High quality project 8 Short project schedule 6 High City control of design 9 Low risks to City 1 Non-adversarial relationships 2 Effective coordination of design and construction 7 Maximum flexibility to revise scope 3.5 Low cost growth 5 10 = most important, 1 = least important Engineering and Architectural Services Department 50

Rating Delivery Methods CRITERIA DBB DB CM@R Low initial design and construction costs 1 5 4 High aesthetics of design 5 1 5 High quality project 5 1 5 Short project schedule 1 5 3 High City control of design 5 1 5 Low risks to City 1 5 5 Non-adversarial relationships 1 3 5 Effective coordination of design and construction 1 5 4 Maximum flexibility to revise scope 1 3 5 Low cost growth 1 5 3 5 = best able to deliver, 1 = worst able to deliver Engineering and Architectural Services Department 51

Weighted Criteria CRITERIA DBB DB CM@R Low initial design and construction costs 3.5 17.5 10.5 High aesthetics of design 50 10 50 High quality project 40 8 40 Short project schedule 6 30 18 High City control of design 45 9 45 Low risks to City 1 5 4 Non-adversarial relationships 2 6 8 Effective coordination of design and construction 7 35 28 Maximum Flexibility to revise scope 3.5 10.5 17.5 Low cost growth 5 25 15 TOTAL SCORE 163 156 236 CM@R selected as Best Method Engineering and Architectural Services Department 52

PROS & CONS ANALYSIS CRITERIA CM@R DBB COMMENTS Contractor Selection Subcontractor Selection Design Input Quality Speed Relationships City selects Best Qualified contractor, based on demonstrated performance. Can select best Civic Plaza constructor in the country. DBB must select low bid, even if no experience or poor past performance. CM@R provides proposed subcontractors to City for approval. City can veto any poor performers or non-local firms. CM@R competes subcontracted work among prequalified, approved subs. DBB, low bid contractor brings own subs, no City control. CM@R selected during design process. Participates in design reviews. Provides true value engineering, constructability reviews. Validates design within budget throughout process. DBB, no design input, no constructor estimate until bid day. CM@R is selected on past performance. Has opportunity to work with designer, understand Owner s quality needs. Able to price construction cost proposal to satisfy quality requirements. Wants to provide high quality for future selections. DBB, quality reduces profit. CM@R can begin work as phases of design are completed; accelerates project. Can plan construction activities during design - site layout, circulation, etc. Is productive from 1st day on site. DBB, cannot start any work until entire design complete. CM@R, entire project team together throughout project. Able to establish relationships, communications processes up front. CM@R selected through professional process, similar to designer. DBB, contractor selected later, after City and designer working together. Engineering and Architectural Services Department 53

Pros & Cons Analysis, con FACTOR CM@R DBB COMMENTS Cost Growth Schedule Growth Initial Cost Cost Certainty Litigation Value CM@R involvement during design improves drawings and specs. More clearly understands design intent, helps eliminate ambiguities and deficiencies. Is motivated to limit change orders for future business. DBB, can exploit design deficiencies, no motivation to reduce. Prior planning during design makes CM@R more efficient, less surprises. Motivated to perform for future business. Paid lump sum for overhead, looses money if project delayed. DBB, negotiates extended General Conditions for changes, covers costs. CM@R requires fee to contractor during design, not required by DBB. CM@R receives construction phase fee, more visible than DBB. Research indicates CM@R can actually save money over project life. City doesn t have sufficient experience to evaluated total cost savings. CM@R gives City Guaranteed Maximum Price, absorbs cost if exceeded. Any savings realized during project returned to City. CM@R involvement during design reduces E&O change orders, cost growth. DBB, final project cost not known until negotiate final change order. Previous litigation used as negative factor in selection process. Improved relationships and communications reduces issues that lead to claims. Desire for repeat business compels CM@R to settle problems early. DBB not concerned about litigation, doesn t impact next low-bid selection. Fees paid to CM@R are investment in the project. Improves relationships, schedule, quality; reduces change orders and litigation. Research indicates CM@R is good value over project life. CM@R selected as Best Method Engineering and Architectural Services Department 54

SUMMARY Have applied Numerical Method on limited projects: Lake Pleasant Water Treatment Plant IGC/TGen Headquarters Convention Center Expansion Typically apply some form of Pros & Cons Analysis Engineering and Architectural Services Department 55

6 th Annual FMI/CMAA Survey of Owners Primary issues surveyed include role of A/E and C, collaboration, commissioning, sustainability, and delivery methods

Need more information?... Contact AGC of America www.agc.org/projectdelivery Mike Stark: starkm@agc.org

RECAP: Defining Terms Management Options (in-house or out- sourced) Contracting/ Reimbursement (GMP, cost plus, lump sum, ) Delivery Methods (DBB, CMR, DB, other) Procurement/Selection (low bid / best value / qualification based)

From this session Management Options Delivery Systems Procurement/Selection Contracting/Payment /Reimbursement Consensus.

Agenda for Remainder of Summit Low Bid vs QBS GMP Contracting Funding Best Practices, a Case Study Design Level of Detail Innovations: BIM, Partnering, IPD

Alternative Delivery Methods, A Primer Michael Kenig, Holder Construction Company Phone: 770-988-3260 E-mail: mkenig@holder.com Jayne O Donnell, O Turner Aviation Phone: 415-705-7901 E-mail: JODonnell@tcco.com

End